Pursuant to a congressional request, GAO reviewed the Department of Agriculture's (USDA) Agricultural Stabilization and Conservation Service's (ASCS) two major information resources management projects, focusing on: (1) the costs and schedule delays for the Grain Inventory Management System (GIMS) and Processed Commodity Inventory Management System (PCIMS); and (2) how ASCS monitored and managed disk capacity to determine upgrades for minicomputers in its county offices.

GAO found that: (1) current cost estimates for the two commodity inventory systems amounted to approximately $62 million, almost nine times the initial estimate of $7 million; (2) ASCS misjudgment of user requirements resulted in its underestimation of both systems' size and scope; (3) the lack of management control over system design changes resulted in increased system complexity and the automation of unnecessary functions with no cost-saving potential; (4) poor contract management, interagency coordination, and some external factors contributed to system development problems; (5) since weaknesses existed in ASCS county office minicomputer disk capacity management, the ASCS request for $258 million for future disk capacity requirements is based on current inefficient disk use; and (6) ASCS lacked reliable information to justify its request for interim computer equipment upgrades.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.