Computers

Information on the Patent and Trademark Office Automation Program Gao ID: IMTEC-86-4FS December 20, 1985

In response to a congressional request, GAO provided information on the Patent and Trademark Office's (PTO) planning, contracting, and scheduling of its patent automation program.

GAO found that: (1) although federal regulations caution against lengthy cost-plus-fixed-fee contracts because they provide minimum incentives for cost control, PTO entered into a $289 million, 18-year, cost-plus-fixed-fee contract to design, develop, implement, and maintain the system; (2) as of December 1985, PTO had procured several hardware components for the system and was developing and testing system software; (3) the system is not operational, but the first evaluation of the system is scheduled for January 1986; (4) PTO did not conduct a space management analysis before it made major acquisition decisions, and potential space problems contributed to the decision to reconfigure the system; (5) problems have been identified with the contractor's accounting systems because they are not in compliance with certain required cost accounting standards; (6) PTO has not elected to establish an on-site team for contract administration and oversight; and (7) the project is more than 1 year behind its original schedule for system development.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.