In response to a congressional request, GAO reviewed the Department of the Interior's outer continental shelf (OCS) environmental studies program to determine: (1) whether contractors timely delivered environmental studies in relation to originally scheduled due dates and planned lease uses; (2) the level of user satisfaction with the studies and how Interior's Minerals Management Service (MMS) used them for OCS decisionmaking; and (3) whether MMS and the National Oceanic and Atmospheric Administration (NOAA) could use Alaska program resources more efficiently.

GAO found that: (1) although MMS and NOAA received most draft and final studies after their originally scheduled due dates, most of the studies were in time for planned lease sale uses; (2) most of the program studies users were satisfied with the studies' usefulness, timeliness, and quality, but some groups reported that they received half of the studies too late to provide input to MMS on lease sale decisions; and (3) recent declines in program funding for Alaska and in the number of studies contracts, as well as duplication of administrative functions by MMS and NOAA, reduced program efficiency.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone: