2000 Census

Coverage Measurement Programs' Results, Costs, and Lessons Learned Gao ID: GAO-03-287 January 29, 2003

To help measure the quality of the 2000 Census and to possibly adjust for any errors, the U.S. Census Bureau (Bureau) conducted the Accuracy and Coverage Evaluation (A.C.E.) program. However, after obligating around $207 million for A.C.E. and its predecessor program, Integrated Coverage Measurement (I.C.M.), from fiscal years 1996 through 2001, the Bureau did not use either program to adjust the census numbers. Concerned about the amount of money the Bureau spent on I.C.M. and A.C.E. programs and what was produced in return, the subcommittee asked us to review the objectives and results of the programs, the costs of consultants, and how best to track future coverage measurement activities.

The two programs the Bureau employed to measure the quality of the 2000 Census population data did not meet their objectives. The A.C.E. program achieved results other than those laid out in the Bureau's formal objectives that highlight important lessons learned. They include (1) developing a coverage measurement methodology that is both operationally and technically feasible, (2) determining the level of geography at which coverage measurement is intended, (3) keeping stakeholders, particularly Congress, informed of the Bureau's plans, and (4) adequately testing coverage measurement methodologies. It will be important for the Bureau to consider these as its current plans for the 2010 Census include coverage evaluation to measure the accuracy of the census but not necessarily to adjust the results. Of the roughly $207 million the Bureau obligated for I.C.M./A.C.E. programs from fiscal years 1996 through 2001, we identified about $22.3 million that was obligated for contracts involving over 170 vendors. We could not identify any obligations prior to 1996 in part because the Bureau included them with its general research and development efforts and did not assign the I.C.M./A.C.E. operations unique project codes in its financial management system. To track these costs in the future, it will be important for the Bureau to (1) have a financial management system that has specific project codes to capture coverage measurement costs, (2) establish the project codes as early in the planning process as possible, and (3) monitor the usage of the codes to ensure that they are properly charged.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


GAO-03-287, 2000 Census: Coverage Measurement Programs' Results, Costs, and Lessons Learned This is the accessible text file for GAO report number GAO-03-287 entitled '2000 Census: Coverage Measurement Programs‘ Results, Costs, and Lessons Learned' which was released on January 29, 2003. This text file was formatted by the U.S. General Accounting Office (GAO) to be accessible to users with visual impairments, as part of a longer term project to improve GAO products‘ accessibility. Every attempt has been made to maintain the structural and data integrity of the original printed product. Accessibility features, such as text descriptions of tables, consecutively numbered footnotes placed at the end of the file, and the text of agency comment letters, are provided but may not exactly duplicate the presentation or format of the printed version. The portable document format (PDF) file is an exact electronic replica of the printed version. We welcome your feedback. Please E-mail your comments regarding the contents or accessibility features of this document to Webmaster@gao.gov. Report to the Chairman, Subcommittee on Civil Service, Census, and Agency Organization, Committee on Government Reform, House of Representatives: January 2003: 2000 Census: Coverage Measurement Programs‘ Results, Costs, and Lessons Learned: GAO-03-287: GAO Highlights: Highlights of GAO-03-287, a report to Chairman, Subcommittee on Civil Service, Census, and Agency Organization, Committee on Government Reform, House of Representatives 2000 CENSUS Coverage Measurement Programs‘ Results, Costs, and Lessons Learned Why GAO Did This Study: To help measure the quality of the 2000 Census and to possibly adjust for any errors, the U.S. Census Bureau (Bureau) conducted the Accuracy and Coverage Evaluation (A.C.E.) program. However, after obligating around $207 million for A.C.E. and its predecessor program, Integrated Coverage Measurement (I.C.M.), from fiscal years 1996 through 2001, the Bureau did not use either program to adjust the census numbers. Concerned about the amount of money the Bureau spent on I.C.M. and A.C.E. programs and what was produced in return, the subcommittee asked us to review the objectives and results of the programs, the costs of consultants, and how best to track future coverage measurement activities. What GAO found: As shown below, the two programs the Bureau employed to measure the quality of the 2000 Census population data did not meet their objectives. Coverage Measurement Programs Did Not Achieve Objectives Program/objectives. [See PDF for Image] [End of Figure] The A.C.E. program achieved results other than those laid out in the Bureau‘s formal objectives that highlight important lessons learned. They include (1) developing a coverage measurement methodology that is both operationally and technically feasible, (2) determining the level of geography at which coverage measurement is intended, (3) keeping stakeholders, particularly Congress, informed of the Bureau‘s plans, and (4) adequately testing coverage measurement methodologies. It will be important for the Bureau to consider these as its current plans for the 2010 Census include coverage evaluation to measure the accuracy of the census but not necessarily to adjust the results. Of the roughly $207 million the Bureau obligated for I.C.M./A.C.E. programs from fiscal years 1996 through 2001, we identified about $22.3 million that was obligated for contracts involving over 170 vendors. We could not identify any obligations prior to 1996 in part because the Bureau included them with its general research and development efforts and did not assign the I.C.M./A.C.E. operations unique project codes in its financial management system. To track these costs in the future, it will be important for the Bureau to (1) have a financial management system that has specific project codes to capture coverage measurement costs, (2) establish the project codes as early in the planning process as possible, and (3) monitor the usage of the codes to ensure that they are properly charged. What GAO Recommends: The Secretary of Commerce should direct the Bureau to (1) work with Congress and other stakeholders and soon decide on whether and how coverage measurement will be used in 2010, (2) adopt lessons learned from its 2000 Census experience, and (3) ensure that its financial management systems can capture and report program activities early and that projects‘ costs are monitored. The Bureau agreed with our recommendations but noted that for the 2000 Census, it followed the steps we identified as lessons learned. It also took exception to how we presented our conclusions concerning its ability to properly classify certain costs. To view the full report, including the scope and methodology, click on the link above. For more information, contact Patricia A. Dalton at (202) 512-6806 or daltonp@gao.gov Contents: Letter: Results in Brief: Background: Scope and Methodology: Coverage Measurement Programs for the 2000 Census Did Not Meet Bureau Objectives: I.C.M./A.C.E. Contractor Costs Are Not Complete: Tracking Future Coverage Measurement Costs: Conclusions: Recommendations for Executive Action: Agency Comments and Our Evaluation: Appendix: Appendix I: Comments from the Department of Commerce: Related GAO Products: Tables : Table 1: Coverage Measurement Programs Did Not Achieve Objectives: Table 2: Census 2000 I.C.M./A.C.E. Contractor Costs for Fiscal Years 1996 through 2001 (Dollars in thousands): Letter January 29, 2003: The Honorable Dave Weldon, M.D. Chairman Subcommittee on Civil Service, Census, and Agency Organization Committee on Government Reform House of Representatives: Dear Mr. Chairman: To assess the quality of population data for the 2000 Census and to possibly adjust for any errors, the U.S. Census Bureau (Bureau) conducted the Accuracy and Coverage Evaluation (A.C.E.) program. The A.C.E. program was first included in Bureau program documents in November 1998 and funded for fiscal years 2000 through 2002 with proposed funding through December 31, 2002. Its predecessor, Integrated Coverage Measurement (I.C.M.), began in May 1995 and was funded by the Bureau for fiscal years 1996 through 1999. The Bureau obligated about $207 million to both programs from fiscal years 1996 through 2001,[Footnote 1] which was about 3 percent of the $6.5 billion total estimated cost of the 2000 Census. However, neither program was used to adjust the 2000 Census population count. Concerned about the amount of money the Bureau spent on both programs as well as what was received in return for its investment, you and former Vice Chairman Dan Miller asked us to examine (1) the Bureau‘s objectives for the I.C.M./A.C.E. programs and the extent to which those objectives were met, (2) the cost of consultants and technical studies, and (3) ways to track the costs of coverage measurement activities in future censuses. This report responds to that request. In October 2002, we issued a report that provides additional information on the cost of the I.C.M./A.C.E. programs.[Footnote 2] Both reports are part of our ongoing series on the results of the 2000 Census and the lessons learned for planning a more cost-effective census in 2010. (See the Related GAO Products section at the end of this report for the assessments issued to date.): Results in Brief: The coverage measurement programs the Census Bureau planned for the 2000 Census--I.C.M. and its successor, A.C.E.--did not meet their intended objectives. Although the Bureau designed I.C.M. to measure census coverage; generate data for apportionment, redistricting, and federal programs using statistical sampling and estimation; and produce a ’one-number“ census based on statistical sampling and estimation, the Bureau abandoned the program following a Supreme Court ruling that the Census Act prohibited the use of statistical sampling to generate population data for reapportioning the House of Representatives.[Footnote 3] Because its replacement--A.C.E.--did not provide a reliable measure of census accuracy in time to meet legally mandated deadlines for releasing redistricting data, the Bureau decided against using it to adjust the census data for nonapportionment purposes. The difficulties the Bureau encountered in trying to implement I.C.M. and A.C.E. underscore the importance of (1) developing a coverage measurement methodology that is both technically and operationally feasible, (2) determining the level of geography at which coverage measurement is intended, (3) keeping stakeholders, particularly Congress, informed of the Bureau‘s plans, and (4) adequate testing. It will be important for the Bureau to address these lessons learned as its planning efforts for the 2010 Census continue. Those plans currently call for a coverage measurement program to evaluate the accuracy of the census, whereas the issue of whether coverage measurement will be used to adjust the numbers has not yet been resolved. Concerning the cost of contracts, including the consultants and technical studies related to the I.C.M./A.C.E. programs, we identified about $22.3 million of obligated amounts for over 170 vendors for fiscal year 1996 through fiscal year 2001 from unaudited Bureau financial management reports. This amount does not represent the complete contract costs for the I.C.M./A.C.E. programs for three reasons. First, the Bureau considered costs from earlier years to be part of its general research and development efforts and did not assign unique project codes to identify I.C.M./A.C.E. programs and related costs in its financial management system. Second, although $182,000 of fiscal year 1996 obligated costs were identified in the Bureau‘s financial management systems as contract costs for an I.C.M. special test, the Bureau did not consider these costs as part of the I.C.M./A.C.E. programs and classified these costs as general research. We disagreed with the Bureau on this point and have included this amount in our report as part of the I.C.M./A.C.E. contract costs that we could identify from Bureau records. Finally, certain costs, such as program evaluations, were Bureau-wide in nature, and the portion attributable to I.C.M./A.C.E could not be separated out. The Bureau‘s ability to track future costs of coverage measurement activities is primarily dependent on its ability to (1) ensure that its financial management system accurately and completely captures the accounting and reporting of project codes, (2) design its project codes to capture coverage measurement activities as early in the planning process as possible, even though the activities‘ names may change as the programs evolve, and (3) correctly charge the project codes established. Although the Bureau has never used the results of its coverage measurement programs to adjust census numbers, we believe that an evaluation of the accuracy of the census is essential given the importance of the data, the need to know the nature of any errors, and the cost of the census overall. Whether the results of the evaluation should be used to adjust the census is still an open question, the answer to which should involve discussions between the Bureau, Congress, and other stakeholders, and be based on detailed data and a convincing demonstration of the feasibility of the Bureau‘s proposed approach. Regardless of the outcome of the decision, it is critical that it be made soon so that the Bureau can proceed with its planning. The longer the Bureau goes without a firm decision on the role of coverage measurement, the greater the risk of wasted resources and disappointing results. In light of the challenges facing the Bureau as it prepares for the next decennial census in 2010, we recommend that the Secretary of Commerce direct the U.S. Census Bureau to: * in conjunction with Congress and other stakeholders, decide soon on whether and how coverage measurement will be used in the 2010 Census; * consider incorporating lessons learned from its coverage measurement experience during the 2000 Census, such as (1) demonstrating both the operational and technical feasibility of its coverage measurement methods, (2) determining the level of geography at which coverage can be reliably measured, (3) keeping Congress and other stakeholders informed of its plans, and (4) adequately testing coverage measurement prior to full implementation; and: * ensure that the Bureau‘s financial management systems can capture and report program activities early in the decennial process and that project costs are monitored for accuracy and completeness. The Secretary of Commerce forwarded written comments from the Bureau of the Census on a draft of this report (see app. I). The Bureau agreed with our recommendations noting that they were important steps that should be followed in the development of a coverage measurement methodology for the 2010 Census. However, the Bureau maintained that most of these steps such as keeping Congress and other stakeholders informed of its plans were followed for the 2000 Census. We disagree because, as noted in the report, the lack of information contributed to stakeholders‘ skepticism surrounding the Bureau‘s plans. The Bureau also took exception to the way we presented our conclusions concerning its ability to properly classify certain costs associated with the development of the Bureau‘s coverage measurement programs. Our perspective on the Bureau‘s position is detailed in the ’Agency Comments and Our Evaluation“ section at the end of this report. Background: The Bureau puts forth tremendous effort to conduct a complete and accurate count of the nation‘s population. However, some degree of error in the form of persons missed or counted more than once is inevitable because of limitations in census-taking methods. Because census results are used, among other purposes, to apportion Congress, redraw congressional districts, and allocate federal aid to state and local governments, the size and demographic composition of these coverage errors have become increasingly sensitive since the Bureau was first able to generate detailed data on them during the 1980 Census. However, the Bureau has never used the results of its coverage measurements to correct estimated coverage errors. The Bureau first attempted to measure the accuracy of the census in the 1940s when it compared the census numbers to birth and death certificates and other administrative data using a procedure called demographic analysis. Modern coverage measurement began with the 1980 Census when the Bureau compared census figures to the results of an independent sample survey of the population. Using statistical methods, the Bureau generated detailed measures of the differences among undercounts of particular ethnic, racial, and other groups. In the months that followed, many lawsuits were filed, most contending that the results of the 1980 coverage measurement should have been used to adjust the census. However, the Bureau designed the evaluation to measure errors, not to correct the census results, and the Director of the Census Bureau decided against adopting the adjusted numbers, as they were deemed flawed due to missing and inaccurate data. The quality of the coverage measurement data improved for the 1990 Census, and the Bureau recommended statistically adjusting the results. However, the Secretary of Commerce determined that the evidence to support an adjustment was inconclusive and decided not to adjust the 1990 Census. The adjustment decision was complicated by the fact that the 1990 Census figures had already been released when the coverage measurement results became available in the spring of 1991. The Secretary of Commerce was concerned that two sets of numbers--the actual census results and the adjusted figures--could create confusion and might allow political considerations to play a part in choosing between sets of numbers when the outcome of the choices, such as congressional apportionment, could be known in advance of a decision. Scope and Methodology: To determine the objectives of 2000 Census I.C.M./A.C.E. programs and their results, we reviewed Bureau and other documents that included Federal Register notices; Census Operational Plans; reports to Congress; internal memorandums; research and feasibility studies; and reports of the Executive Steering Committee for Accuracy and Coverage Policy (ESCAP) I and II, which assessed the results of the A.C.E. program and recommended how they should be used. To determine costs for consultants and technical studies for 2000 Census I.C.M./A.C.E. programs, we focused on object class code 25 from the financial management reports to obtain contract data. With Bureau assistance, we identified I.C.M./A.C.E. project accounts and analyzed amounts by fiscal year using the financial management reports generated by the Department of Commerce‘s Administrative Management System (CAMS). We reviewed and analyzed obligated and expended data for all coverage measurement programs that existed during the 2000 Census for fiscal years 1991 to 2003. We did not audit financial data provided by the Bureau. To determine ways to track future costs, we reviewed current Bureau financial management reports and considered established standards of accounting, auditing, and internal controls. In addition, we met with key Bureau officials to discuss the results of our analysis and obtain their observations and perspectives. The limitations we encountered in the scope of our work on this assignment are as follows. * We were unable to determine the complete contractual and technical studies costs of the I.C.M./A.C.E. programs because the Bureau considered any I.C.M./A.C.E.-related costs from fiscal years 1991 through 1995 as part of its general research and development programs and thus did not separately track these costs. Although some costs were tracked in fiscal year 1996, the Bureau still considered these costs as research and development and did not include these costs as I.C.M./ A.C.E. program costs. * We were unable to identify I.C.M./A.C.E. portions of costs from projects that covered the entire census, such as the 2000 Census Evaluation program. * We did not evaluate the propriety of contracts for I.C.M./A.C.E. programs. Our work was performed in Washington, D.C., and at U.S. Census Bureau headquarters in Suitland, Maryland, from June 2002 through October 2002 in accordance with generally accepted government auditing standards. On January 7, 2003, the Secretary of Commerce provided written comments on a draft of this report. We address these comments in the ’Agency Comments and Our Evaluation“ section, and have reprinted them in appendix I. Coverage Measurement Programs for the 2000 Census Did Not Meet Bureau Objectives: In planning the 2000 Census, the Bureau developed a new coverage measurement program, I.C.M., that was designed to address the major shortcomings of the 1990 coverage measurement program. However, as shown in table 1, much like similar programs in earlier censuses, the Bureau did not use I.C.M. and its successor program, A.C.E., to adjust the census because of legal challenges, technical obstacles, and the inability to resolve uncertainties in the data in time to meet the deadlines for releasing the data. Table 1: Coverage Measurement Programs Did Not Achieve Objectives: [See PDF] [End of Figure] Source: GAO. Note: This table reflects GAO‘s analysis of U.S. Census Bureau data. [End of table] The Bureau Canceled I.C.M. in Response to a Supreme Court Ruling: In designing I.C.M., the Bureau‘s goal was to produce a single, consolidated count or ’one-number“ census and thus avoid the controversy of having two sets of census results as occurred during the 1990 Census. Thus, as shown in table 1, the objectives of I.C.M. were to (1) measure census coverage, (2) generate, using statistical sampling and estimation methods, the detailed data required for apportionment, congressional redistricting, and federal program purposes, and (3) produce a one-number census. The Bureau‘s plans for I.C.M. emerged in response to the unsatisfactory results of the 1990 Census. Although the 1990 headcount was, at that time, the most costly in U.S. history, it produced data that were less accurate than those from the 1980 Census. The disappointing outcome was due in large part to the Bureau‘s efforts to count housing units that did not mail back their census questionnaires. The operation, known as nonresponse follow-up, where enumerators visited and collected information from each nonresponding housing unit, proved to be costly and error-prone when a higher-than-expected workload and a shortage of enumerators caused the operation to fall behind schedule. The final stages of nonresponse follow-up were particularly problematic. Indeed, while enumerators finished 90 percent of the follow-up workload within 8 weeks (2 weeks behind schedule), it took another 6 weeks to resolve the remaining 10 percent. Moreover, in trying to complete the last portion of nonresponse follow-up cases, the Bureau accepted less complete responses and information from nonhousehold members such as neighbors, which may have reduced the quality of the data. In the years following the 1990 Census, Congress, the Bureau, several organizations, and GAO, concluded that fundamental design changes were needed to reduce census costs and improve the quality of the data. In response, the Bureau reengineered a number of operations for the 2000 Census. For example, to save time and reduce its nonresponse follow-up workload, the Bureau planned to enumerate a sample of the last remaining portion of nonresponse follow-up cases instead of visiting every nonresponding household as it had done in previous censuses. To adjust for enumeration errors, the Bureau developed I.C.M., which was intended to reconcile the original census figures with data obtained from a separate, independent count of a sample of 750,000 housing units using a statistical process called Dual System Estimation. The Bureau believed that this approach offered the best combination of reduced costs, improved accuracy expected at various geographic levels, and operational feasibility. However, concerned about the legality of the Bureau‘s planned use of sampling and estimation, members of Congress challenged the Bureau‘s use of I.C.M. in court. In January 1999, the Supreme Court ruled that the Census Act[Footnote 4] prohibited the use of statistical sampling to generate population data for reapportioning the House of Representatives.[Footnote 5] A.C.E. Did Not Meet Bureau Objectives: Following the Supreme Court ruling, the Bureau planned to produce apportionment numbers using traditional census-taking methods, and provide statistically adjusted numbers for nonapportionment uses of the data such as congressional redistricting and allocating federal funds. The Bureau initiated the A.C.E. program, which was designed to take a national sample of approximately 300,000 housing units to evaluate coverage errors among different population groups and statistically correct for them. Thus, as shown in table 1, the Bureau‘s objectives for A.C.E. were to (1) measure how many people were missed in the census and how many were erroneously included and (2) produce the detailed data required in time for redistricting and federal program purposes. However, while the Bureau generally conducted A.C.E. in accordance with its plans,[Footnote 6] the Bureau later determined that the A.C.E. results did not provide a reliable measure of census accuracy and could not be used to adjust the nonapportionment census data. The first decision against A.C.E. occurred in March 2001, when the Acting Director of the Census Bureau recommended to the Secretary of Commerce that the unadjusted census data be used for redistricting purposes. He cited as a primary reason an apparent inconsistency between the population growth over the prior decade, as implied by A.C.E. results, and demographic analysis, which estimated the population using birth, death, and other administrative records. The inconsistency raised the possibility of an unidentified error in either the A.C.E. or census numbers. He reported that the inconsistency could not be resolved prior to April 1, 2001, the legally mandated deadline for releasing redistricting data.[Footnote 7] The second decision against A.C.E. came in October 2001 when, based on a large body of additional research, ESCAP decided against adjusting census data for allocating federal aid and other purposes, because A.C.E. failed to identify a significant number of people erroneously included in the census, and other remaining uncertainties. According to Bureau officials, it might be possible to use adjusted data to produce intercensal population estimates for federal programs that require this information; however, the Bureau would need to revise the A.C.E. results before any use of the data could be considered. The Bureau‘s Experience in Implementing Coverage Measurement Programs Highlights Important Lessons Learned: Although I.C.M. and A.C.E. did not meet their formal objectives, they did produce a body of important lessons learned. As the Bureau‘s current approach for the 2010 Census includes coverage measurement to assess the accuracy of the census (but not necessarily to adjust the numbers themselves), it will be important for the Bureau to consider these lessons as its planning efforts continue. The lessons include (1) developing a coverage measurement methodology that is both technically and operationally feasible, (2) determining the level of geography at which coverage measurement is intended, (3) keeping stakeholders, particularly Congress, informed of the Bureau‘s plans, and (4) adequately testing the eventual coverage measurement program. 1. A.C.E. demonstrated operational, but not technical feasibility. According to Bureau officials, an important result of the A.C.E. program was that it demonstrated, from an operational perspective only, the feasibility of conducting a large independent field check on the quality of the census. The Bureau canvassed the entire A.C.E. sample area to develop an address list, collected census response data for persons living in the sample areas on census day, and conducted an operation to try and match A.C.E. respondents to census respondents, all independent of the regular census operations and within required time frames. Our separate reviews of two of these operations--interviewing respondents and matching A.C.E. and census data--while raising questions about the impact on final A.C.E. results due to apparently small operational deviations, also concluded that the Bureau implemented those two operations largely as planned.[Footnote 8] Nevertheless, while the Bureau demonstrated that it could execute A.C.E. field operations using available resources within required time frames, as the Bureau has noted, feasibility also consists of a technical component--that is, whether the A.C.E. methodology would improve the accuracy of the census. Although the Bureau clearly stated in its justification for A.C.E. that the effort would make the census more accurate, as noted earlier, because of unresolved data discrepancies, its experience in 2000 proved otherwise. Moreover, according to the Bureau, because the A.C.E. was designed to correct a census with a net coverage error similar to that observed in previous censuses, the Bureau commented that applying the methodology to the historically low levels of net error observed in the 2000 Census represented a unique and unanticipated challenge for A.C.E. Thus, it will be important for the Bureau to refine its coverage measurement methodology to ensure that it is technically feasible. 2. The level of geography at which the Bureau can successfully measure coverage is unclear. Since the October 2001 decision to not rely on adjusted census data for nonapportionment and nonredistricting purposes, Bureau officials have told us that they now doubt whether census data can reliably be improved down to the level of geography for which A.C.E. was intended to improve the accuracy--the census tract level (neighborhoods that typically contain around 1,700 housing units and 4,000 people). The Bureau‘s current position differs from that taken in 2000, when it reported to Congress that it expected accuracy at the tract level to be improved, on average, by A.C.E. statistically adjusting numbers at an even lower level of geography--the census block level.[Footnote 9] Uncertainty in the level of geography at which accuracy is to be measured or improved can affect the overall design of coverage measurement, as well as its technical feasibility. Therefore, it will be important for the Bureau to determine the level of geography at which it intends to measure accuracy as it decides the role and design of future coverage measurement programs. 3. Keeping stakeholders informed is essential. Throughout the 1990s, Congress and other stakeholders, including GAO, expressed concerns about the Bureau‘s planned use of sampling and statistical estimation procedures to adjust the census. A key cause of this skepticism was the Bureau‘s failure to provide sufficiently detailed data on the effects that I.C.M. would have at different levels of geographic detail. Information was also lacking on the various design alternatives being considered, their likely implications, and the basis for certain decisions. As a result, it was difficult for Congress and other stakeholders to support the Bureau‘s coverage measurement initiatives. For example, on September 24, 1996, the House Committee on Government Reform and Oversight issued a report that criticized the Bureau‘s initiatives for sampling and statistical estimation. Among other things, the Committee found that the Bureau had not clarified issues of accuracy, particularly for small geographic areas, raised by the sampling initiative. Congress‘s perspective on the process was later reflected in its enactment of legislation in 1997 that included provisions requiring the Department of Commerce to provide Congress with comprehensive information on its planned use of statistical estimation within 30 days.[Footnote 10] 4. Adequate testing of coverage measurement methodologies is critical. Although the Bureau conducted a dress rehearsal for the census in three locations across the country that was intended to demonstrate the overall design of the census, the 1998 operation did not reveal the problems that the Bureau encountered in dealing with the discrepancies between the 2000 A.C.E. results and its benchmarks. According to Bureau officials, this was partly because the sites were not representative of the nation at large. Additionally, as a result of a compromise between Congress and the administration to simultaneously prepare for a nonsampling census, the I.C.M. was tested at only two of the three dress rehearsal sites--an urban area and an Indian reservation--but was not tested in a rural location as was originally planned. An earlier test in 1995 was also not comprehensive in that it did not test a sampling operation designed to help determine whether nonresponse follow-up of the magnitude projected by the Bureau‘s current plan could be completed in time for the I.C.M to be done on schedule. I.C.M./A.C.E. Contractor Costs Are Not Complete: From fiscal year 1996 through fiscal year 2001, the Bureau obligated about $207 million for I.C.M./A.C.E. activities.[Footnote 11] As shown in table 2, of that $207 million, we identified about $22.3 million (11 percent) in obligated amounts for contracts involving more than 170 vendors. These contracts were primarily for technical advisory and assistant services, computer systems support, and training. Table 2: Census 2000 I.C.M./A.C.E. Contractor Costs for Fiscal Years 1996 through 2001 (Dollars in thousands): Project description: A.C.E. coverage management; FY96: 0; FY97: 0 ; FY98: 0; FY99: 0; FY00: $1,458; FY01: 0; Total: $1,458. Project description: A.C.E. operations; FY96: 0; FY97: 0; FY98: 0; FY99: 0; FY00: 249; FY01: ($2); Total: 247. Project description: I.C.M. collection; FY96: 0; FY97: 0; FY98: $201; FY99: $41; FY00: 6,272; FY01: 467; Total: 6,981. Project description: Framework 3 total; FY96: 0 ; FY97: 0; FY98: 201; FY99: 41; FY00: 7,979; FY01: 465; Total: 8,686. Project description: I.C.M. procedures and training; FY96: 0; FY97: $249; FY98: 594; FY99: 1,065; FY00: 1,766; FY01: 814; Total: 4,488. Project description: I.C.M. processing; FY96: 0; FY97: 0; FY98: 0; FY99: 2,412; FY00: 287; FY01: 574; Total: 3,273. Project description: Framework 5 total; FY96: 0; FY97: 249; FY98: 594; FY99: 3,477; FY00: 2,053; FY01: 1,388; Total: 7,761. Project description: I.C.M. dress rehearsal; FY96: 0; FY97: 0; FY98: 502; FY99: 20; FY00: 0; FY01: (10); Total: 512. Project description: I.C.M. special test; FY96: $182; FY97: 628; FY98: 0; FY99: 0; FY00: 0; FY01: 0; Total: 810. Project description: I.C.M. coverage measurement; FY96: 0; FY97: 409; FY98: 1,257; FY99: 1,991; FY00: (130); FY01: 999; Total: 4,526. Project description: Framework 6 total; FY96: 182; FY97: 1,037; FY98: 1,759; FY99: 2,011; FY00: (130); FY01: 989; Total: 5,848. Project description: Total; FY96: $182; FY97: $1,286; FY98: $2,554; FY99: $5,529; FY00: $9,902; FY01: $2,842; Total: $22,295. Source: GAO. Note: This table reflects GAO‘s analysis of U.S. Census Bureau financial management reports. [End of table] Although the Bureau tracked some costs of contracts for the I.C.M./ A.C.E. programs, we found that the $22.3 million did not represent the complete contractor costs of the programs because of the following three factors. * First, the Bureau only tracked the contractor costs associated with conducting the I.C.M./A.C.E. programs, which covers the period from fiscal year 1997 through 2003. Although life cycle costs for the 2000 Census cover a 13-year period from fiscal years 1991 through 2003, senior Bureau officials said that the I.C.M./A.C.E. program was not viable for implementation until fiscal year 1997. Therefore, the Bureau considered contractor costs from earlier years as part of its general research and development programs, and the Bureau did not assign unique project codes to identify I.C.M./A.C.E. programs and related costs in its financial management system. * Second, although $182,000 of fiscal year 1996 obligated contractor costs were identifiable in the Bureau‘s financial management system as an I.C.M. special test, the Bureau did not consider these costs as part of the I.C.M./A.C.E. programs. Instead, these costs were considered general research and development. However, because the Bureau separately identified these costs as I.C.M. program contractor costs, we have included the $182,000 as part of the I.C.M./A.C.E. program contractor costs in this report. * Finally, we were unable to identify the I.C.M./A.C.E. portions of costs that were part of other programs. For example, in late fiscal year 2000 and after, the Bureau did not separate A.C.E. evaluations from its other 2000 Census evaluations in its financial management systems. Bureau officials stated that the contracts for evaluations included overall 2000 Census and A.C.E. evaluations, and did not have a separate code identifying A.C.E. costs. Tracking Future Coverage Measurement Costs: During the 2000 Census, the Bureau, its auditors, and GAO, found extensive weaknesses in the Bureau‘s financial management system, the components of which include hardware, software, and associated personnel. The weaknesses included difficulties in providing reliable and timely financial information to manage current government operations and preparing financial statements and other reports. Together, they affected the completeness, accuracy, and timeliness of data needed for informed management decisions and effective oversight. In light of these weaknesses, the Bureau‘s ability to track future costs of coverage measurement activities will largely depend on three factors. * First, a sound financial management system is critical. As discussed in our December 2001 report, the Bureau‘s core financial management system, CAMS, had persistent internal control weaknesses in fiscal year 2000.[Footnote 12] In its latest financial report, the Bureau indicated that these weaknesses have continued through fiscal year 2001.[Footnote 13] The Bureau expects to issue its fiscal year 2002 financial report shortly. * Second, it would be important to set up project codes to capture coverage measurement activities as early in the planning process as possible. The Bureau did not set up a specific project code to identify I.C.M. program costs until 1996 because, according to Bureau officials, the I.C.M. program was not viable until 1997 and all costs up to this point were considered general research. * Finally, it would be important for Bureau personnel to correctly charge the project codes established for the coverage measurement program activities. During the 2000 Census, for example, while the Bureau established a project code and a budget for the remote Alaska enumeration, the project costs were erroneously charged to and commingled with a project code for enumerating special populations. As a result, the actual costs for remote Alaska enumeration were reported by the Bureau‘s financial management system as zero and are unknown, while enumerating special population costs are overstated. Conclusions: The Bureau‘s 2000 Census coverage measurement programs did not achieve their primary objectives of measuring the accuracy of the census and adjusting the results because of legal challenges, technical hurdles, and questionable data. However, beyond these formal objectives, there emerged several important lessons learned that Bureau managers should consider because current plans for the 2010 Census include coverage measurement. At the same time, it will also be important for the Bureau to be capable of fully tracking the money it spends on coverage measurement and other census activities so that Congress and other stakeholders can hold the Bureau accountable for achieving intended results. Although the Bureau has never used the results of its coverage measurement programs to adjust census numbers, we believe that an evaluation of the accuracy and completeness of the census is critical given the many uses of census data, the importance of identifying the magnitude and characteristics of any under-and overcounts, and the cost of the census overall. Less clear is whether the results of the coverage measurement should be used to adjust the census. Any Bureau decisions on this matter should involve close consultation with Congress and other stakeholders, and be based on detailed data and a convincing demonstration of the feasibility of the Bureau‘s proposed approach. Whatever the decision, it is imperative that it be made soon so that the Bureau can design appropriate procedures and concentrate on the business of counting the nation‘s population. The longer the 2010 planning process proceeds without a firm decision on the role of coverage measurement, the greater the risk of wasted resources and disappointing results. Recommendations for Executive Action: To help ensure that any future coverage measurement efforts achieve their intended objectives and costs can be properly tracked, we recommend that the Secretary of Commerce direct the Bureau to: * in conjunction with Congress and other stakeholders, come to a decision soon on whether and how coverage measurement will be used in the 2010 Census; * consider incorporating lessons learned from its coverage measurement experience during the 2000 Census, such as (1) demonstrating both the operational and technical feasibility of its coverage measurement methods, (2) determining the level of geography at which coverage can be reliably measured, (3) keeping Congress and other stakeholders informed of its plans, and (4) adequately testing coverage measurement prior to full implementation; and: * ensure that the Bureau‘s financial management systems can capture and report program activities early in the decennial process and ensure that project costs are monitored for accuracy and completeness. Agency Comments and Our Evaluation: The Secretary of Commerce forwarded written comments from the Census Bureau on a draft of this report, which are reprinted in appendix I. The Bureau agreed with our recommendations highlighting the steps that should be followed in the development of a coverage measurement methodology for the 2010 Census and acknowledged their importance. However, the Bureau maintained that it followed most of these steps for the 2000 Census including (1) keeping stakeholders, particularly Congress, informed of the Bureau‘s plans, (2) determining the level of geography at which coverage measurement is intended, and (3) adequately testing coverage measurement methodologies. The Bureau also maintained that throughout the 1990s, it had an open and transparent process for implementing the coverage measurement program, including the levels of geography to which its results would be applied. We disagree. As we stated in our report, the Bureau‘s failure to provide important information was a key cause of congressional skepticism over the Bureau‘s coverage measurement plans. In fact, Congress was so concerned about the lack of comprehensive information on the Bureau‘s proposed approach that in July 1997, it passed a law that included provisions requiring the Department of Commerce to provide detailed data on the Bureau‘s planned use of statistical estimation within 30 days.[Footnote 14] We revised the report to include this, and provide other examples to further support our position that the Bureau‘s I.C.M. and A.C.E. planning and development processes were less than fully open and transparent. The Bureau also commented that each major component of the I.C.M./ A.C.E. program underwent ’rigorous“ testing in the middle of the decade as well as during the dress rehearsal for the 2000 Census held in 1998. We believe this overstates what actually occurred. As we noted in the report, the dress rehearsal failed to detect the problems that A.C.E. encountered during the 2000 Census because the sites were not representative of the nation. Additionally, because of an agreement between Congress and the administration to simultaneously prepare for a census that did not include sampling, the I.C.M. was only tested at two of the three dress rehearsal sites--an urban area and an Indian reservation--but was not tested in a rural location as was originally planned. We made this and other revisions to strengthen our point. Because the A.C.E. was designed to correct a census with a net coverage error similar to that observed in previous censuses, the Bureau commented that applying the methodology to the historically low levels of net error observed in the 2000 Census represented a unique and unexpected challenge for A.C.E. We revised the report to reflect this additional context. The Bureau took exception to the way we presented our conclusions concerning its ability to properly classify certain costs associated with the development of the Bureau‘s coverage measurement programs. The Bureau noted that it decided not to separately track coverage measurement development costs in 1994, because there was no internal or external request for a separate cost accounting of the program. Our report does not make interpretive conclusions or qualitative judgments about which coverage measurement program costs the Bureau decided to track. Instead, the report (1) points out that we could not identify all of the contractor costs associated with the I.C.M./A.C.E. programs because of the three factors described in the report, and (2) underscores the importance of a sound financial management system for tracking, planning, and development costs for the 2010 Census. We are sending copies of this report to other interested congressional committees, the Secretary of Commerce, and the Director of the U.S. Census Bureau. Copies will be made available to others upon request. This report will also be available at no charge on GAO‘s home page at http://www.gao.gov. Please contact Patricia A. Dalton on (202) 512-6806 or by E-mail at daltonp@gao.gov if you have any questions. Other key contributors to this report were Robert Goldenkoff, Roger Stoltz, Carolyn Samuels, Cindy Brown-Barnes, Ty Mitchell, and Linda Brigham. Sincerely yours, Patricia A. Dalton Director, Strategic Issues: Signed by Patricia A. Dalton: McCoy Williams Director Financial Management and Assurance: Signed by McCoy Williams: [End of section] Appendixes: Appendix I: Comments from the Department of Commerce: THE SECRETARY OF COMMERCE Washington D.C. 20230: JAN 7 2003: Ms. Patricia A Dalton Director: Strategic Issues: United States General Accounting Office Washington, DC 20548: Dear Ms. Dalton: The Department of Commerce appreciates the opportunity to comment on the General Accounting Office (GAO) draft document entitled 2000 Census: Coverage Measurement Programs‘ Results, Costs and Lessons Learned (GAO-03-287)_ The Department‘s comments on this report are enclosed. Sincerely, Donald L. Evans: Signed by Donald L. Evans: Enclosure: Comments from the U.S. Department of Commerce U.S. Census Bureau: U.S. General Accounting Office draft report entitled 2000 Census: Coverage Measurement Programs‘ Results, Costs, and Lessons Learned: Comments on the Teat of the Report: In its analysis of the coverage measurement program implemented by the U.S. Census Bureau during Census 2000, the General Accounting Office {GAO) reaches conclusions that undcrscore the importance of finalizing the census design early in the decade, continuing to refine coverage measurement methodology based on lessons learned from Census 2000, and thoroughly testing coverage measurement operations prior to implementing them in 2010. We take exception with the way in which these conclusions are presented Moreover, the GAO asserts that the Census Bureau did not maintain a financial accounting system that could properly classify certain costs attributable to the development of the integrated Coverage Measurement (ICM)/Accuracy and Coverage Evaluation (A.C.E.) programs. We fundamentally disagree with this assertion, as we stressed in our response to the GAO‘s earlier discussion of this issue (see GAO-03-41). The GAO states that the Census Bureau did not adequately account for the costs of the ICM/A.C.E. program. This conclusion was correct only at the beginning of the Census 2000 cycle. At the beginning of each census, we identify the specific activities for which we think costs should be separately tracked. The decision not to separately track coverage measurement development costs was made in 1994, when there was no internal or extetnal request for a separate cost accounting of this program. The GAO‘s suggestion after Census 2000 that we should have separately tracked coverage measurement activities early in the census cycle is far different from the implication that we had no system in place for tracking those costs. The Census Bureau plans to track coverage measurement expenditures earlier in the 2010 census cycle and, in fact, will be happy to begin tracking costs in whatever additional categories the GAO identifies. (2) The GAO also identifies a series of ’lessons learned“ from Census 2000 that include the following: ’keeping stakeholders, particularly Congress, informed of the Bureau‘s plans“ ’determining the level of geography at which coverage measurement is intended“ ’adequately testing coverage measurement methodologies‘*: It is worth underscoring that each of these steps was taken during Census 2000. Throughout the census, and in the years leading up to it, the Census Bureau was unwavering in its maintenance of an open and transparent process for implementing the coverage measurement program, including the levels of geography to which its remits: See the one-page overview ar the beginning of the report and the ’Results in Brief“ section of the text. would be applied, in the face of unprecedented scrutiny from census stakeholders. Moreover, each major component of the ICM/A.C.E. program underwent rigorous testing in the middle of the decade and in the dress rehearsal conducted in 1998. Finally, while shortcomings in the data from the A.C.E. prevented their use for improving the counts from Census 2000, as originally intended, the A.C.E. itself was designed to correct a census with a net coverage error based on the level of error observed in previous decennial censuses. Applying the dual system estimation methodology central to the A.C.E. to improve upon a level of net coverage error at the historically low levels observed in Census 2000 represented a unique and unexpected challenge for this program. This new circumstance will be taken into consideration as coverage measurement methodologies are developed for the 2010 census. In short, the GAO has identified important steps that should be followed in the development of a coverage measurement methodology for the 2010 census. It is important to stress, however, that most of these steps were followed in Census 2000, as well. [End of Section] Related GAO Products: 2000 Census: Complete Costs of Coverage Evaluation Programs Are Not Available. GAO-03-41. Washington, D.C.: October 31, 2002. 2000 Census: Lessons Learned for Planning a More Cost-Effective 2010 Census. GAO-03-40. Washington, D.C.: October 31, 2002. 2000 Census: Refinements to Full Count Review Program Could Improve Future Data Quality. GAO-02-562. Washington, D.C.: July 3, 2002. 2000 Census: Coverage Evaluation Matching Implemented as Planned, but Census Bureau Should Evaluate Lessons Learned. GAO-02-297. Washington, D.C.: March 14, 2002. 2000 Census: Best Practices and Lessons Learned for More Cost-Effective Nonresponse Follow-up. GAO-02-196. Washington, D.C.: February 11, 2002. 2000 Census: Coverage Evaluation Interviewing Overcame Challenges, but Further Research Needed. GAO-02-26. Washington, D.C.: December 31, 2001. 2000 Census: Analysis of Fiscal Year 2000 Budget and Internal Control Weaknesses at the U.S. Census Bureau. GAO-02-30. Washington, D.C.: December 28, 2001. 2000 Census: Significant Increase in Cost Per Housing Unit Compared to 1990 Census. GAO-02-31. Washington, D.C.: December 11, 2001. 2000 Census: Better Productivity Data Needed for Future Planning and Budgeting. GAO-02-4. Washington, D.C.: October 4, 2001. 2000 Census: Review of Partnership Program Highlights Best Practices for Future Operations. GAO-01-579. Washington, D.C.: August 20, 2001. Decennial Censuses: Historical Data on Enumerator Productivity Are Limited. GAO-01-208R. Washington, D.C.: January 5, 2001. 2000 Census: Information on Short-and Long-Form Response Rates. GAO/ GGD-00-127R. Washington, D.C.: June 7, 2000. FOOTNOTES [1] At the time of our report, obligated costs after fiscal year 2001 were not final. [2] U.S. General Accounting Office, 2000 Census: Complete Costs of Coverage Evaluation Programs Are Not Available, GAO-03-41 (Washington, D.C.: Oct. 31, 2002). [3] Department of Commerce v. United States House of Representatives, 525 U.S. 316 (1999). [4] 13 U.S.C. 195. [5] Department of Commerce v. United States House of Representatives 525, U.S. 316 (1999). [6] See, for example, U.S. General Accounting Office, 2000 Census: Coverage Evaluation Interviewing Overcame Challenges, but Further Research Needed, GAO-02-26 (Washington, D.C.: Dec. 31, 2001), and 2000 Census: Coverage Evaluation Matching Implemented as Planned, but Census Bureau Should Evaluate Lessons Learned, GAO-02-297 (Washington, D.C.: Mar. 14, 2002). [7] March 1, 2001, Memorandum to Secretary Donald Evans from Acting Director William Barron, Jr. (ESCAP I decision memo.) [8] See GAO-02-26 and GAO-02-297. [9] U.S. Census Bureau, ’Report to Congress--The Plan for Census 2000,“ 44-46 and Accuracy and Coverage Evaluation--Statement on the Feasibility of Using Statistical Methods to Improve the Accuracy of the Census 2000 (June 2000), 19, fn. 19. [10] Pub. L. 105-18, Title VIII, June 12, 1997. [11] At the time of our report, obligated costs after fiscal year 2001 were not final. [12] U.S. General Accounting Office, 2000 Census: Analysis of Fiscal Year 2000 Budget and Internal Control Weaknesses at the U.S. Census Bureau, GAO-02-30 (Washington, D.C.: Dec. 28, 2001). [13] U.S. Census Bureau, 2001 Financial Report (Suitland, Md.: May 2002). [14] Pub. L. 105-18, Title VIII, June 12, 1997. GAO‘s Mission: The General Accounting Office, the investigative arm of Congress, exists to support Congress in meeting its constitutional responsibilities and to help improve the performance and accountability of the federal government for the American people. GAO examines the use of public funds; evaluates federal programs and policies; and provides analyses, recommendations, and other assistance to help Congress make informed oversight, policy, and funding decisions. GAO‘s commitment to good government is reflected in its core values of accountability, integrity, and reliability. Obtaining Copies of GAO Reports and Testimony: The fastest and easiest way to obtain copies of GAO documents at no cost is through the Internet. GAO‘s Web site ( www.gao.gov ) contains abstracts and full-text files of current reports and testimony and an expanding archive of older products. The Web site features a search engine to help you locate documents using key words and phrases. You can print these documents in their entirety, including charts and other graphics. Each day, GAO issues a list of newly released reports, testimony, and correspondence. GAO posts this list, known as ’Today‘s Reports,“ on its Web site daily. The list contains links to the full-text document files. To have GAO e-mail this list to you every afternoon, go to www.gao.gov and select ’Subscribe to daily E-mail alert for newly released products“ under the GAO Reports heading. Order by Mail or Phone: The first copy of each printed report is free. Additional copies are $2 each. A check or money order should be made out to the Superintendent of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or more copies mailed to a single address are discounted 25 percent. Orders should be sent to: U.S. General Accounting Office 441 G Street NW, Room LM Washington, D.C. 20548: To order by Phone: Voice: (202) 512-6000: TDD: (202) 512-2537: Fax: (202) 512-6061: To Report Fraud, Waste, and Abuse in Federal Programs: Contact: Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov Automated answering system: (800) 424-5454 or (202) 512-7470: Public Affairs: Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S. General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C. 20548:

The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.