Geostationary Operational Environmental Satellites
Progress Has Been Made, but Improvements Are Needed to Effectively Manage Risks
Gao ID: GAO-08-18 October 23, 2007
The Department of Commerce's National Oceanic and Atmospheric Administration (NOAA), with the aid of the National Aeronautics and Space Administration (NASA), plans to procure the next generation of geostationary operational environmental satellites, called the Geostationary Operational Environmental Satellites-R series (GOES-R). This series is considered critical to the United States' ability to maintain the continuity of data required for weather forecasting through the year 2028. GAO was asked to (1) assess the status and plans for GOES-R, and (2) evaluate whether NOAA is adequately mitigating key technical and programmatic risks. To do so, GAO analyzed contractor and program data and interviewed officials from NOAA and NASA.
NOAA has made progress in planning its GOES-R procurement--which is estimated to cost $7 billion and scheduled to have the first satellite ready for launch in 2014--but cost and schedules are likely to grow. Specifically, the agency completed preliminary design studies of GOES-R and recently decided to separate the space and ground elements of the program into two separate development contracts. However, this change in the GOES-R acquisition strategy has delayed a decision to proceed with the acquisition. Further, independent estimates are higher than the program's current cost estimate and convey a low level of confidence in the program's schedule. Independent studies show that the estimated program could cost about $2 billion more, and the first satellite launch could be delayed by 2 years. As NOAA works to reconcile the independent estimate with its own program office estimate, costs are likely to grow and schedules are likely to be delayed. To address cost, schedule, and technical risks, the GOES-R program has established a risk management program and has taken steps to mitigate selected risks. For example, as of July 2007, the program office identified the lack of an integrated master schedule to be its highest priority risk and established plans to bring this risk to closure. However, more remains to be done to fully address GOES-R risks. Specifically, the program has multiple risk watchlists that are not always consistent and key risks are missing from the watchlists, including risks associated with unfilled executive positions, limitations in NOAA's insight into NASA's deliverables, and insufficient funds for unexpected costs--called management reserves. As a result, the GOES-R program is at risk that problems will not be identified or mitigated in a timely manner and could lead to program cost overruns and schedule delays.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-08-18, Geostationary Operational Environmental Satellites: Progress Has Been Made, but Improvements Are Needed to Effectively Manage Risks
This is the accessible text file for GAO report number GAO-08-18
entitled 'Geostationary Operational Environmental Satellites: Progress
Has Been Made, but Improvements Are Needed to Effectively Manage Risks'
which was released on October 23, 2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
United States Government Accountability Office:
GAO:
October 2007:
Geostationary Operational Environmental Satellites:
Progress Has Been Made, but Improvements Are Needed to Effectively
Manage Risks:
GAO-08-18:
GAO Highlights:
Highlights of GAO-08-18, a report to congressional requesters.
Why GAO Did This Study:
The Department of Commerce‘s National Oceanic and Atmospheric
Administration (NOAA), with the aid of the National Aeronautics and
Space Administration (NASA), plans to procure the next generation of
geostationary operational environmental satellites, called the
Geostationary Operational Environmental Satellites-R series (GOES-R).
This series is considered critical to the United States‘ ability to
maintain the continuity of data required for weather forecasting
through the year 2028.
GAO was asked to (1) assess the status and plans for GOES-R, and (2)
evaluate whether NOAA is adequately mitigating key technical and
programmatic risks. To do so, GAO analyzed contractor and program data
and interviewed officials from NOAA and NASA.
What GAO Found:
NOAA has made progress in planning its GOES-R procurement”which is
estimated to cost $7 billion and scheduled to have the first satellite
ready for launch in 2014”but cost and schedules are likely to grow.
Specifically, the agency completed preliminary design studies of GOES-R
and recently decided to separate the space and ground elements of the
program into two separate development contracts. However, this change
in the GOES-R acquisition strategy has delayed a decision to proceed
with the acquisition. Further, independent estimates are higher than
the program‘s current cost estimate and convey a low level of
confidence in the program‘s schedule. Independent studies show that the
estimated program could cost about $2 billion more, and the first
satellite launch could be delayed by 2 years. As NOAA works to
reconcile the independent estimate with its own program office
estimate, costs are likely to grow and schedules are likely to be
delayed.
To address cost, schedule, and technical risks, the GOES-R program has
established a risk management program and has taken steps to mitigate
selected risks. For example, as of July 2007, the program office
identified the lack of an integrated master schedule to be its highest
priority risk and established plans to bring this risk to closure.
However, more remains to be done to fully address GOES-R risks.
Specifically, the program has multiple risk watchlists that are not
always consistent and key risks are missing from the watchlists,
including risks associated with unfilled executive positions,
limitations in NOAA‘s insight into NASA‘s deliverables, and
insufficient funds for unexpected costs”called management reserves (see
table for more details). As a result, the GOES-R program is at risk
that problems will not be identified or mitigated in a timely manner
and could lead to program cost overruns and schedule delays.
Description of Key Risks Missing from GOES-R Risk Lists:
Key Risk: Unfilled GOES-R executive leadership positions; Description:
Two senior GOES-R program positions”the system program director and
deputy system program director”are currently filled by NASA and NOAA
personnel in an acting capacity until they can be permanently filled by
NOAA. The agency reported that it plans to fill the deputy system
program director role in the near future, but noted that it could take
more than 6 months to fill the system program director role.
Key Risk: Limitations in NOAA‘s insight into NASA‘s deliverables;
Description: The established NOAA/NASA interagency agreements do not
contain provisions that enable NOAA to ensure that monthly contractor
data and reports, submitted by NASA, are reliable and that they
accurately depict contractor performance.
Key Risk: Insufficient management reserve (for unexpected costs) held
by the program and a critical instrument contractor; Description: As of
May 2007, the contractor for a critical instrument”the Advanced
Baseline Imager”had less than 1 percent of funding in reserve to cover
unexpected costs associated with the 40 percent of work left to be
completed. In addition, as a result of addressing issues on the
Advanced Baseline Imager in March 2007, the reserve funding for the
overall GOES-R program dropped below 25 percent”a level that NOAA
reported it intended to establish as a lesson learned from other
satellite acquisitions. As of July 2007, the reserve level was at about
15 percent.
Source: GAO.
What GAO Recommends:
GAO is making recommendations to the Secretary of Commerce to ensure
that the GOES-R program effectively manages and mitigates risks. The
Secretary agreed with GAO‘s recommendations to use a program level risk
list and to add selected risks to its list, but disagreed that NOAA has
insufficient insight into NASA‘s contracts. The Secretary cited an
unparalleled transparency between the two agencies. However, NOAA has
not demonstrated that it has validated NASA‘s contractor performance
and GAO remains concerned that NOAA lacks the capability to oversee
this key aspect of the program.
To view the full product, including the scope and methodology, click on
[hyperlink, http://www.GAO-08-18]. For more information, contact David
A. Powner at (202) 512-9286 or pownerd@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
GOES-R Preliminary Design Studies Are Completed, but Key Program
Changes Have Been Made and Cost and Schedule Estimates Are Likely to
Grow:
NOAA is Taking Steps to Address Key Risks, but More Remains to Be Done:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: Comments from the Department of Commerce:
Appendix III: GAO Contact and Staff Acknowledgments:
Tables:
Table 1: Summary of the Procurement History of GOES:
Table 2: Summary of Key GOES-R System Improvements:
Table 3: Originally Planned GOES-R Series Instruments, as of August
2006:
Table 4: Key Changes to the GOES-R Program:
Table 5: Status of GOES-R and Component Contracts, as of July 2007:
Table 6: GOES-R Program Launch Schedule, as of July 2007:
Figures:
Figure 1: Approximate GOES Geographic Coverage:
Figure 2: Generic GOES Data Relay Pattern:
Figure 3: GOES-R Program Office Structure and Staffing:
Figure 4: Top Program Risks as Identified by the GOES-R Program Office,
as of July 2007:
Figure 5: Risks Identified by the GOES-R Flight Project Office, as of
July 2007:
Figure 6: Risks Identified by the GOES-R Operations Project Office, as
of July 2007:
Figure 7: Examples of Inconsistencies among GOES-R Risk Watchlists, as
of July 2007:
Abbreviations:
ABI: Advanced Baseline Imager:
EXIS: Extreme Ultraviolet and X-Ray Irradiance Suite:
GLM: Geostationary Lightning Mapper:
GOES-R: Geostationary Operational Environmental Satellites - R Series:
HES: Hyperspectral Environmental Suite:
NASA: National Aeronautics and Space Administration:
NESDIS: National Environmental Satellite Data and Information Service:
NOAA: National Oceanic and Atmospheric Administration:
SEISS: Space Environmental In-Situ Suite:
SIS: Solar Imaging Suite:
SUVI: Solar Ultra Violet Imager:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
October 23, 2007:
The Honorable Nick Lampson:
Chairman:
The Honorable Bob Inglis:
Ranking Member:
Subcommittee on Energy and Environment:
Committee on Science and Technology:
House of Representatives:
The Honorable Brad Miller:
Chairman:
The Honorable James F. Sensenbrenner, Jr.:
Ranking Member:
Subcommittee on Investigations and Oversight:
Committee on Science and Technology:
House of Representatives:
Operational geostationary environmental satellites play a critical role
in our nation's weather forecasting. These satellites--which are
managed by the National Oceanic and Atmospheric Administration (NOAA)-
-provide critical information on atmospheric, oceanic, climatic, and
solar conditions that help meteorologists observe and predict global
and local weather events. They also provide a means to identify severe
storm conditions, such as hurricanes and tornadoes, and to track the
movement and intensity of these storms once they develop.
NOAA, with the aid of the National Aeronautics and Space Administration
(NASA), is planning to procure the next generation of geostationary
satellites, called the Geostationary Operational Environmental
Satellites-R series (GOES-R). The GOES-R series is to replace the
current series of satellites which will likely begin to reach the end
of their useful lives in approximately 2014. This new series is
expected to mark the first major technological advance in GOES
instrumentation since 1994. It is also considered critical to the
United States' ability to maintain the continuity of data required for
weather forecasting through the year 2028.
This report responds to your request that we review NOAA's management
of the GOES-R program. Specifically, we were asked to (1) assess the
status and revised plans for the GOES-R procurement, and (2) evaluate
whether NOAA is adequately mitigating key technical and programmatic
risks facing the GOES-R program.
To assess GOES-R status and revised plans, we reviewed program
documents on the revised acquisition strategy, system requirements, and
cost estimates, and interviewed officials from NOAA, NASA, and the
contractor for a critical GOES-R instrument. To evaluate whether NOAA
is adequately mitigating key technical and programmatic risks, we
analyzed risk management plans and also met with internal technical
experts to determine the key risks that could negatively affect the
program's ability to acquire the GOES-R system. We also interviewed
agency officials to evaluate the adequacy of NOAA's mitigation efforts.
We conducted our work at NOAA and NASA offices in the Washington, D.C.,
metropolitan area and at ITT Corporation in Fort Wayne, Indiana. We
performed our work from April 2007 to September 2007, in accordance
with generally accepted government auditing standards. Appendix I
contains further details on our objectives, scope, and methodology.
Results in Brief:
NOAA has made progress on its GOES-R procurement--which is estimated to
cost $7 billion and scheduled to have the first satellite ready for
launch in 2014--but costs and schedules are likely to grow.
Specifically, NOAA completed preliminary design studies of its GOES-R
acquisition and planned to make a decision to proceed to development
and production in September 2007. In addition, the agency recently
decided to separate the space and ground elements of the program into
two separate contracts, to be managed by NASA and NOAA, respectively.
However, this change in the GOES-R acquisition strategy has delayed the
decision to proceed with the acquisition. Further, independent
estimates are higher than the program's current cost estimate and
convey a low level of confidence in the program's schedule. Independent
studies show that the estimated program could cost about $2 billion
more, and the first satellite launch could be delayed by 2 years. As
NOAA works to reconcile the independent estimate with its own program
office estimate, costs are likely to grow and schedules are likely to
be delayed. In commenting on a draft of this report, NOAA officials
stated that while their reconciliation process is still ongoing, the
revised cost estimate will likely be $1 billion more than the current
$7 billion and the first satellite launch will likely be delayed 1 year
from 2014, rather than 2 years.
To address cost, schedule, and technical risks, the GOES-R program has
established a risk management program and has taken steps to identify
and mitigate selected risks. For example, as of July 2007, the program
office identified the lack of an integrated master schedule as its
highest priority risk. It also identified other risks including
technical challenges affecting the development of a critical instrument
and the development of requirements between the space and ground
segments. The program has also established plans for bringing these
risks to closure. However, more remains to be done to fully address
risks. Specifically, the program has multiple risk watchlists that are
not always consistent. Further, key risks are missing from the risk
lists, including risks associated with unfilled executive positions,
limitations in NOAA's insight into NASA's deliverables, and
insufficient funds for unexpected costs (called management reserve). As
a result, the program is at risk that problems will not be identified
or mitigated in a timely manner and could lead to program cost overruns
and schedule delays.
We are making recommendations to the Secretary of Commerce to direct
the Undersecretary of Commerce for Oceans and Atmosphere to ensure that
the GOES-R program office manages, mitigates, and reports on risks
using a more comprehensive program-level risk list. In written comments
on a draft of this report, the Secretary agreed with our
recommendations to use a program level risk list and to add selected
risks to its list, but disagreed that NOAA has insufficient insight
into NASA's contracts. The Secretary cited an unparalleled transparency
between the two agencies. However, NOAA has not demonstrated that it
has validated NASA's contractor performance and we remain concerned
that NOAA lacks the capability to oversee this important aspect of the
program. Given the past problems NOAA had in obtaining insight into
NASA's contracts and the importance of this interagency relationship to
the success of the GOES-R program, we believe that this issue should be
managed and monitored as a risk. The Department also suggested
technical comments which we incorporated as appropriate.
Background:
Since the 1960s, geostationary and polar-orbiting environmental
satellites have been used by the United States to provide
meteorological data for weather observation, research, and forecasting.
NOAA's National Environmental Satellite Data and Information Service
(NESDIS) is responsible for managing the civilian geostationary and
polar-orbiting satellite systems as two separate programs, called GOES
and the Polar Operational Environmental Satellites, respectively.
Unlike polar-orbiting satellites, which constantly circle the earth in
a relatively low polar orbit, geostationary satellites can maintain a
constant view of the earth from a high orbit of about 22,300 miles in
space. NOAA operates GOES as a two-satellite system that is primarily
focused on the United States (see fig. 1). These satellites are
uniquely positioned to provide timely environmental data to
meteorologists and their audiences on the earth's atmosphere, its
surface, cloud cover, and the space environment. They also observe the
development of hazardous weather, such as hurricanes and severe
thunderstorms, and track their movement and intensity to reduce or
avoid major losses of property and life. Furthermore, the satellites'
ability to provide broad, continuously updated coverage of atmospheric
conditions over land and oceans is important to NOAA's weather
forecasting operations.
Figure 1: Approximate GOES Geographic Coverage:
[See PDF for image]
This figure is a world map depicting the geographical coverage of GOES-
11 and GOES-12.
Sources: NOAA (data), MapArt (map).
[End of figure]
To provide continuous satellite coverage, NOAA acquires several
satellites at a time as part of a series and launches new satellites
every few years. Three satellites--GOES-11, GOES-12, and GOES-13--are
currently in orbit. Both GOES-11 and GOES-12 are operational
satellites, while GOES-13 is in an on-orbit storage mode. It is a
backup for the other two satellites should they experience any
degradation in service. The others in the series, GOES-O and GOES-P,
are planned for launch over the next few years.[Footnote 1] NOAA is
also planning the next generation of satellites, known as the GOES-R
series, which are planned for launch beginning in 2014.
Each of the operational geostationary satellites continuously transmits
raw environmental data to NOAA ground stations. The data are processed
at these ground stations and transmitted back to the satellite for
broadcast to primary weather services and the global research community
here in the United States and abroad. Raw and processed data are also
distributed to users via ground stations through other communication
channels, such as dedicated private communication lines and the
Internet. Figure 2 depicts a generic data relay pattern from the
geostationary satellites to the ground stations and commercial
terminals.
Figure 2: Generic GOES Data Relay Pattern:
[See PDF for image]
This figure is a depiction of the generic GOES data relay pattern. The
depiction indicates that data is relayed in the following manner:
* GOES satellite: raw environmental data sent to ground station;
* Ground station: processed environmental data sent back to GOES;
* GOES satellite: processed environmental data broadcast to users.
Also depicted is a communications link between the ground station and
users.
Source: GAO analysis of NOAA data.
[End of figure]
A Brief History of Prior GOES Series:
To date, NOAA has procured three series of GOES satellites and is in
the planning stages to acquire a fourth one (see table 1).
Table 1: Summary of the Procurement History of GOES:
Series name: Original GOES[B];
Procurement duration[A]: 1970-1987;
Satellites: 1, 2, 3, 4, 5, 6, 7.
Series name: GOES I-M;
Procurement duration[A]: 1985-2001;
Satellites: 8, 9, 10, 11, 12.
Series name: GOES-N;
Procurement duration[A]: 1998-2011;
Satellites: 13, O, P, Q[C].
Series name: GOES-R;
Procurement duration[A]: 2007-2016;
Satellites: R, S.
Source: GAO analysis of NOAA data.
[A] Duration includes time from contract award to final satellite
launch.
[B] The procurement of these satellites consisted of four separate
contracts for (1) two early prototype satellites and GOES-1, (2) GOES-
2 and -3, (3) GOES-4 through -6, and (4) GOES-G (failed on launch) and
GOES-7.
[C] NOAA decided not to exercise the option for this satellite.
[End of table]
Original GOES Satellites:
In 1970, NOAA initiated its original GOES program based on experimental
geostationary satellites developed by NASA. While these satellites
operated effectively for many years, they had technical limitations.
For example, this series of satellites was "spin-stabilized," meaning
that the satellites slowly spun while in orbit to maintain a stable
position with respect to the earth. As a result, the satellite viewed
the earth only about 5 percent of the time and had to collect data very
slowly, capturing one narrow band of data each time its field of view
swung past the earth. A complete set of sounding data[Footnote 2] for
GOES-4 through GOES-7 took 2 to 3 hours to collect.
GOES I-M Series:
In 1985, NOAA and NASA began to procure a new generation of GOES,
called the GOES I-M series, based on a set of requirements developed by
NOAA's National Weather Service, NESDIS, and NASA, among others. GOES I-
M consisted of five satellites, GOES-8 through GOES-12, and was a
significant improvement in technology from the original satellites. For
example, GOES I-M was "body-stabilized," meaning that the satellite
held a fixed position in orbit relative to the earth, thereby allowing
for continuous meteorological observations. Instead of maintaining
stability by spinning, the satellite would preserve its fixed position
by continuously making small adjustments in the rotation of internal
momentum wheels or by firing small thrusters to compensate for drift.
This and other enhancements meant that the GOES I-M satellites would be
able to collect significantly better quality data more quickly than the
older series of satellites.
GOES-N Series:
In 1998, NOAA began the procurement of satellites to follow GOES I-M,
called the GOES-N series. This series used existing technologies for
the instruments and added system upgrades, including an improved power
subsystem and enhanced satellite pointing accuracy. Furthermore, these
satellites were designed to operate longer than their predecessors.
This series originally consisted of four satellites--GOES-N through
GOES-Q. However, the option for the GOES-Q satellite was canceled based
on NOAA's assessment that it would not need the final satellite to
continue weather coverage. In particular, the agency found that the
satellites already in operation were lasting longer than expected and
that the first satellite in the next series could be available to back
up the last of the GOES-N satellites. As noted earlier, the first GOES-
N series satellite--GOES-13--was launched in May 2006. The GOES-O and
GOES-P satellites are currently in production and are expected to be
launched in July 2008 and July 2011, respectively.
Planned GOES-R Series:
NOAA is currently planning to procure the next series of GOES
satellites--called the GOES-R series--which is intended to provide the
first major technological advance in instrumentation since the launch
of the first satellite of the GOES I-M series in 1994.[Footnote 3] The
original plans for this series included four satellites--GOES-R through
GOES-U. However, in September 2006, NOAA reduced the scope of the
program to consist of a minimum of two satellites and removed a
technically complex instrument because it was estimated that program
costs could almost double the original cost estimate.
GOES-R Program--An Overview:
NOAA plans for the GOES-R program to improve on the technology of prior
series, in terms of both system and instrument improvements. The system
improvements are expected to fulfill more demanding user requirements
and to provide more rapid information updates. Table 2 highlights key
system-related improvements GOES-R is expected to make to the
geostationary satellite program.
Table 2: Summary of Key GOES-R System Improvements:
Key feature: Total number of products;
GOES-N (current): 41;
GOES-R: ~68-120.
Key feature: Downlink rate of raw data collected by instruments (from
satellite to ground stations);
GOES-N (current): 2.6 Mbps;
GOES-R: 70 Mbps.
Key feature: Broadcast rate of processed GOES data (from satellite to
users);
GOES-N (current): 2.1 Mbps;
GOES-R: 40 Mbps.
Key feature: Raw data storage (the length of time that raw data will be
stored at ground stations);
GOES-N (current): 0 days;
GOES-R: 3 days.
Source: GAO analysis of NOAA data.
[End of table]
In addition to the system improvements, the instruments on the GOES-R
series are expected to significantly increase the clarity and precision
of the observed environmental data. NOAA originally planned to acquire
six different types of instruments. Furthermore, two of these
instruments--the Advanced Baseline Imager and the Hyperspectral
Environmental Suite--were considered to be the most critical because
they would provide data for key weather products. Table 3 summarizes
the originally planned instruments and their expected capabilities.
Table 3: Originally Planned GOES-R Series Instruments, as of August
2006:
Planned instrument: Advanced Baseline Imager (ABI);
Description: Expected to provide variable area imagery and radiometric
information of the earth's surface, atmosphere, and cloud cover. Key
features include;
* monitoring and tracking severe weather;
* providing images of clouds to support forecasts, and;
* providing higher resolution, faster coverage, and broader coverage
simultaneously.
Planned instrument: Hyperspectral Environmental Suite (HES)[A];
Description: Expected to provide information about the earth's surface
to aid in the prediction of weather and climate monitoring. Key
features include;
* providing atmospheric moisture and temperature profiles to support
forecasts and climate monitoring;
* monitoring coastal regions for ecosystem health, water quality,
coastal erosion, and harmful algal blooms, and;
* providing higher resolution and faster coverage.
Planned instrument: Geostationary Lightning Mapper (GLM);
Description: Expected to continuously monitor lightning activity over
the United States and provide a more complete dataset than previously
possible. Key features include;
* detecting lightning strikes as an indicator of severe storms and;
* providing a new capability to GOES that only previously existed on
polar satellites.
Planned instrument: Magnetometer;
Description: Expected to provide information on the general level of
geomagnetic activity, monitor current systems in space, and permit
detection of magnetopause crossings, sudden storm commencements, and
substorms.
Planned instrument: Space Environmental In-Situ Suite (SEISS);
Description: Expected to provide information on space weather to aid in
the prediction of particle precipitation, which causes disturbance and
disruption of radio communications and navigation systems. Key features
include;
* measuring magnetic fields and charged particles;
* providing improved heavy ion detection, adding low energy electrons
and protons, and;
* enabling early warnings for satellite and power grid operation,
telecom services, astronauts, and airlines.
Planned instrument: Solar Imaging Suite (SIS)[B];
Description: Expected to provide coverage of the entire dynamic range
of solar X-ray features, from coronal holes to X-class flares, as well
as estimate the measure of temperature and emissions. Key features
include;
* providing images of the sun and measuring solar output to monitor
solar storms and;
* providing improved imager capability.
Source: GAO analysis of NOAA data.
[A] HES was canceled in September 2006.
[B] SIS development work was divided into two separate acquisitions,
the Solar Ultra Violet Imager (SUVI) and the Extreme Ultraviolet and X-
Ray Irradiance Suite (EXIS).
[End of table]
More recently, however, NOAA reduced the scope of the GOES-R program
because of expectations of higher costs. In May 2006, the program
office projected that total costs, which were originally estimated to
be $6.2 billion, could reach $11.4 billion. We reported that this led
NOAA to reduce the scope and technical complexity of the baseline
program.[Footnote 4] Specifically, in September 2006, NOAA reduced the
minimum number of satellites from four to two, canceled plans for
developing the Hyperspectral Environmental Suite, and estimated the
revised program would cost $7 billion. Table 4 provides a summary of
the timeline and scope of these key changes.
Table 4: Key Changes to the GOES-R Program:
Number of satellites;
Baseline program, as of August 2006: 4;
Program with reduced scope, as of September 2006: 2.
Planned instruments;
Baseline program, as of August 2006: 2 critical instruments and 4
noncritical instruments or instrument suites;
* Critical instruments:
- Advanced Baseline Imager;
- Hyperspectral Environmental Suite;
* Noncritical instruments/suites:
- Geostationary Lightning Mapper;
- Magnetometer;
- Space Environmental In-Situ Suite;
- Solar Imaging Suite;
Program with reduced scope, as of September 2006:
1 critical instrument and 4 noncritical instruments or instrument
suites;
* Critical instrument:
- Advanced Baseline Imager;
* Noncritical instruments/suites:
- Geostationary Lightning Mapper;
- Magnetometer;
- Space Environmental In-Situ Suite;
- Two components of the former Solar Imaging Suite (the Solar Ultra
Violet Imager and Extreme Ultraviolet and X-Ray Irradiance Suite).
Life-cycle cost estimate (in then year dollars);
Baseline program, as of August 2006: $6.2 - 11.4 billion;
Program with reduced scope, as of September 2006: $7 billion.
End of operations and maintenance;
Baseline program, as of August 2006: 2028;
Program with reduced scope, as of September 2006: 2028[A].
Source: GAO analysis of NOAA data.
[A] All satellites are expected to have a 15-year lifespan (5 years in
on-orbit storage plus 10 years in operation).
[End of table]
In our September 2006 report, we made a number of recommendations to
improve the agency's ability to effectively manage GOES-R based on
lessons learned from other satellite procurements. In particular, we
recommended that NOAA establish a process for objectively evaluating
and reconciling government and independent cost estimates once the
scope of the program was finalized. We also recommended that the agency
perform a comprehensive review of the Advanced Baseline Imager to
determine the level of technical maturity achieved prior to moving the
instrument into production and to seek assistance in determining the
appropriate levels of resources needed at the program office to
adequately track and oversee the contractor's earned value management
data.[Footnote 5] The agency agreed with our recommendations and has
completed a comprehensive review of the Advanced Baseline Imager.
Actions on other recommendations are under way. For example, NOAA has
established a team to conduct a line-by-line reconciliation of the
government and independent cost estimates. Additionally, NOAA plans to
have four earned value specialists on staff by the end of 2007 and has
requested that NASA determine the appropriate level of resources needed
to perform its earned value management functions.
GOES-R Program Office Structure:
NOAA is solely responsible for GOES-R program funding and overall
mission success. However, since it relies on NASA's acquisition
experience and technical expertise to help ensure the success of its
programs, NOAA implemented an integrated program management structure
with NASA for the GOES-R program (see fig. 3). Within the program
office, there are two project offices that manage key components of the
GOES-R system. These are called the flight and operations project
offices. The flight project office oversees the spacecraft,
instruments, and launch services. The operations project office
oversees the ground elements and on-orbit operations of the satellites.
The project manager for the flight project office and the deputy
project manager for operations project office are designated to be
filled with NASA personnel. Additionally, NOAA has located the program
office at NASA's Goddard Space Flight Center.
Figure 3: GOES-R Program Office Structure and Staffing:
[See PDF for image]
This figure is an organizational chart depicting the GOES-R Program
Office structure and staffing, with connecting lines indicating
"reports to" and "communicates with" status.
From bottom to top, the structure is depicted as follows:
Flight Project: Project Manager: NASA; Deputy: NOAA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
Operations Project: Project Manager: NOAA; Deputy: NASA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
Program Mission Assurance: Lead: NASA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
Contracts: Lead: NOAA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
Program Control: Lead: NOAA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
Program Systems Engineering: Lead: NASA;
Reports to: GOES-R Program; System Program Director: NOAA; Deputy
System Program Director: NOAA; Assistant System Program Director: NASA.
GOES-R Program; System Program Director: NOAA; Deputy System Program
Director: NOAA; Assistant System Program Director: NASA;
Reports to: NESDIS.
GOES-R Program; System Program Director: NOAA; Deputy System Program
Director: NOAA; Assistant System Program Director: NASA;
Communicates with: Goddard Space Flight Center Management Council;
GOES-R Program; System Program Director: NOAA; Deputy System Program
Director: NOAA; Assistant System Program Director: NASA;
Communicates with: Program Scientist: NOAA.
Program Scientist: NOAA.
Reports to: NESDIS.
NESDIS:
Reports to: NOAA.
NESDIS:
Communicates with: Goddard Space Flight Center Management Council;
Communicates with: NOAA Program Management Council.
NOAA:
Reports to: Commerce.
NOAA:
Communicates with: NOAA Program Management Council.
Goddard Space Flight Center Management Council:
Reports to: NASA.
The top level of the organization chart includes both Commerce and
NASA.
Source: NOAA.
[End of figure]
Planned GOES-R Acquisition Strategy:
NOAA's acquisition strategy was to award contracts for the preliminary
design of the GOES-R system to several vendors who would subsequently
compete for the contract to be the single prime contractor responsible
for overall system development and production. As such, in October
2005, NOAA awarded contracts for the preliminary design of the overall
GOES-R system to three vendors.[Footnote 6]
In addition, to reduce the risks associated with developing technically
advanced instruments, NASA awarded contracts for the preliminary
designs for five of the originally planned instruments. NASA expected
to subsequently award development contracts for these instruments and
to eventually turn them over to the prime contractor responsible for
the overall GOES-R program.
GOES-R Preliminary Design Studies Are Completed, but Key Program
Changes Have Been Made and Cost and Schedule Estimates Are Likely to
Grow:
NOAA has completed preliminary design studies of its GOES-R
procurement. In addition, the agency recently decided to separate the
space and ground elements of the program into two separate contracts to
be managed by NASA and NOAA, respectively. However, this change has
delayed a key decision to proceed with the acquisition, which was
planned for September 2007. Further, independent estimates are higher
than the program's current $7 billion cost estimate and convey a low
level of confidence in the program's schedule for launching the first
satellite by 2014. As NOAA works to reconcile the independent estimate
with its own program office estimate, costs are likely to grow and
schedules are likely to be delayed.
Progress Has Been Made on GOES-R Procurement Activities:
NOAA and NASA have made progress on GOES-R. The program office has
completed preliminary design studies of the overall GOES-R system and
has initiated development work on most of the planned instruments.
Specifically, the NOAA-issued contracts for the preliminary design of
the overall GOES-R system to three vendors have ended, and the designs
have been completed.
In addition, after completing preliminary designs on five of the
originally planned instruments, NASA awarded development contracts for
three of them.[Footnote 7] Further, the most critical of these
instruments--the Advanced Baseline Imager--has completed a major
development milestone. In February 2007, it passed a critical design
review gate and NASA approved the contractor to begin production of a
prototype model. See table 5 for the summary of the contracts on GOES-
R and its component instruments.
Table 5: Status of GOES-R and Component Contracts, as of July 2007:
GOES-R component: Overall program;
Contract scope: preliminary design;
Contractor: Boeing, Lockheed Martin, Northrop Grumman;
Status: completed.
GOES-R component: Overall program;
Contract scope: development and production;
Contractor: to be determined;
Status: contract award is pending.
GOES-R component: ABI instrument;
Contract scope: preliminary design;
Contractor: Ball, ITT Corp., Raytheon;
Status: completed.
GOES-R component: ABI instrument;
Contract scope: development and production;
Contractor: ITT Corp.;
Status: under way.
GOES-R component: HES instrument;
Contract scope: preliminary design;
Contractor: BAE Systems, Ball, ITT Corp.;
Status: completed.
GOES-R component: HES instrument;
Contract scope: development and production;
Contractor: [Empty];
Status: canceled.
GOES-R component: SEISS instrument;
Contract scope: preliminary design;
Contractor: Assurance Technology Corp., Lockheed Martin;
Status: completed.
GOES-R component: SEISS instrument;
Contract scope: development and production;
Contractor: Assurance Technology Corp.;
Status: under way.
GOES-R component: SIS instruments (consisting of SUVI and EXIS);
Contract scope: preliminary design;
Contractor: Lockheed Martin;
Status: completed.
GOES-R component: SIS instruments (consisting of SUVI and EXIS);
Contract scope: development and production;
Contractor: SUVI: Lockheed Martin; EXIS: Laboratory for Atmospheric and
Space Physics;
Status: under way.
GOES-R component: GLM instrument;
Contract scope: preliminary design;
Contractor: Ball, ITT Corp., Lockheed Martin;
Status: completed.
GOES-R component: GLM instrument;
Contract scope: development and production;
Contractor: to be determined;
Status: contract award is pending.
Source: GAO analysis of NOAA and NASA data.
[End of table]
NOAA Revised its Acquisition Strategy:
NOAA recently made a number of key changes in how it plans to acquire
the GOES-R system. Originally, NOAA planned to award and manage a
single prime contract for the acquisition and operation of the
integrated system. However, an independent review team assessed the
program and found that this approach was risky.[Footnote 8] It
recommended that NOAA split the acquisition effort into two separate
contracts for the space and ground segments and have NASA manage the
space segment. The independent review team concluded that there was
less risk in continuing with this approach than there would be if NOAA
took on a new and expanded role.
In March 2007, Commerce approved NOAA's decision to implement these
recommendations. The agency revised its acquisition strategy to include
two separate contracts--the space segment and the ground segment. The
two contracts are expected to be awarded in May 2008 and August 2008,
respectively. The space segment is to be managed by a NASA-led flight
project office. As such, NASA is to be responsible for awarding and
managing the space segment contract, delivering the flight-ready
instruments to the space segment contractor for integration onto the
satellites, and overseeing the systems engineering and integration.
NOAA is to be responsible for the ground segment contract, which is to
be managed by the NOAA-led operations project office.
The revised acquisition strategy has delayed NOAA's plans to complete a
key decision milestone on whether to proceed with GOES-R development
and production in September 2007. Once this decision is made, the final
requests for proposals on the system segments are to be released. The
agency could not provide a timeframe for when this key decision
milestone would take place.
GOES-R Cost Estimates Are Likely to Grow and Schedule Estimates Are
Likely to Slip:
NOAA's current estimate that the life cycle cost of the GOES-R program
would be $7 billion is likely to grow, and its estimate that the first
satellite would be launched in December 2014 is likely to slip.
Consistent with best practices in cost estimating, in May 2007, NOAA
had two different cost estimates completed for the current GOES-R
program--one by its program office and one by an independent cost
estimating firm. The program office estimated with 80 percent
confidence that the program would cost $6.9 billion. The independent
estimating firm estimated with 80 percent confidence that the program
would cost $9.3 billion.
A comparison of the two cost models shows that the independent
estimator has about a 20 percent level of confidence that the program
can be completed for $6.9 billion. Further, the independent estimator
concluded that the program office estimate significantly understated
the risk of cost overruns. Other major differences between the two
estimates are contained in government costs and in the space and ground
segments. In commenting on a draft of this report, NOAA officials noted
that one of the differences between the estimates is the inflation
rate. The independent estimator assumed a higher inflation rate than
the rate that NOAA and NASA typically use. NOAA officials noted that if
the independent estimate was adjusted to NOAA's inflation rate, the
program's cost estimate with 80 percent confidence would be $8.7
billion. However, we believe that the value of an independent estimate
is that it does not necessarily use the same assumptions as the program
office. By offering alternative assumptions, the independent estimate
provides valuable information for government officials to consider when
revising program cost estimates.
Program officials are reconciling the two different cost estimates and
plan to establish a new program cost estimate to be released in
conjunction with the President's fiscal year 2009 budget in February
2008. Program officials were unable to provide us information on the
reconciled estimate until it is released. Nonetheless, the revised cost
estimate will likely be $1 billion more than the current $7 billion.
Regarding schedule, NOAA's current plan to launch the first GOES-R
series satellite in December 2014 could be delayed. This schedule was
driven by a requirement that the satellites be available to back up the
last remaining GOES satellites (GOES-O and GOES-P) should anything go
wrong during the planned launches of these satellites (see table 6).
However, as part of its cost estimate, the independent estimator
performed a schedule risk analysis. The independent estimator
determined that there was less than a 50 percent chance that the first
satellite would be ready for launch by December 2014 and that a later
date would be more realistic. The estimator determined that it had 50
percent confidence that the first satellite would launch by October
2015 and 80 percent confidence that the satellite would launch by March
2017. A delay of this magnitude could affect the continuity of GOES
data should the agency experience problems with the predecessor
satellites.
Table 6: GOES-R Program Launch Schedule, as of July 2007:
Milestone: GOES-O launch[A];
Planned date: April 2008.
Milestone: GOES-P launch[A];
Planned date: April 2009.
Milestone: GOES-R satellite available for launch;
Planned date: Dec. 2014.
Milestone: GOES-S satellite available for launch;
Planned date: April 2016.
Source: NOAA.
[A] GOES-O and GOES-P are not part of the GOES-R series program. Their
launch dates are provided because of their relevance to the GOES-R
series satellite schedules.
[End of table]
NOAA is Taking Steps to Address Key Risks, but More Remains to Be Done:
To address cost, schedule, and technical risks, the GOES-R program
established a risk management program and has taken steps to identify
and mitigate selected risks. However, more remains to be done to fully
address a comprehensive set of risks. Specifically, the program has
multiple risk watchlists and they are not always consistent. Further,
key risks are missing from the risk lists, including risks associated
with unfilled executive positions, limitations in NOAA's insight into
NASA's deliverables, and insufficient funding for unexpected costs
(called management reserve) on a critical sensor. As a result, the GOES-
R program is at increased risk that problems will not be identified or
mitigated in a timely manner and that they could lead to program cost
overruns and schedule delays.
GOES-R Has a Risk Management Program and Is Taking Measures to Address
Selected Risks:
The GOES-R program office established a risk management program and is
tracking and mitigating selected risks. Risk management is a leading
management practice that is widely recognized as a key component of a
sound system development approach. An effective risk management
approach typically includes identifying, prioritizing, and mitigating
risks, and escalating key risks to the attention of senior management.
In accordance with leading management practices, the GOES-R program
identifies risks, assigns a severity rating to risks, tracks these
risks in a database, plans response strategies for each risk in the
database, and reviews and evaluates these risks during monthly program
risk management board meetings. Programwide and project-specific risks
are managed by different offices. The program office identifies and
tracks programwide risks--those that affect the overall GOES-R program.
NASA's flight project office and NOAA's operations project office
manage risks affecting their respective aspects of the
program.[Footnote 9] Further, the program office briefs senior
executives on top program and project risks on a monthly basis.
GOES-R Program Office Identified and Is Working to Mitigate Programwide
Risks:
As of July 2007, the program office identified three program risks
affecting the overall GOES-R program (see fig. 4). These risks include
the development of the integrated master schedule, the ability to
secure authorization to use a key frequency band to meet the space-to-
ground communication data link requirements for the GOES-R system, and
the final approval of the GOES-R mission requirements from the NOAA
Deputy Undersecretary.
Figure 4: Top Program Risks as Identified by the GOES-R Program Office,
as of July 2007:
[See PDF for image]
This figure is an illustration of risk on a matrix. The vertical axis
of the matrix represents probability of occurrence from low to high.
The horizontal axis of the matrix represents potential severity of
consequence from low to high. The matrix is five blocks high and five
blocks wide. The following data is depicted on the matrix:
Integrated program master schedule:
medium risk (fourth block for potential severity of consequence; second
block for probability of occurrence).
X-band allocation and license:
low risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
GOES-R level 1 requirements:
low risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
Source: NOAA.
[End of figure]
NOAA is working to mitigate and close program risks that it is
tracking. For example, the program office recently closed the risk
associated with GOES-R requirements because it had sufficiently defined
and obtained approval of these requirements. As another example, the
program office considers the lack of an integrated master schedule to
be its highest priority risk. Program officials reported that
completion of the integrated master schedule is driven by the
completion of the intermediate schedules for the ground segment and the
space-to-ground interdependencies. Key program staff members, including
a resident scheduler, meet on a weekly basis to resolve outstanding
design issues and hone these schedules. Program officials reported that
the intermediate schedules are near completion and that they plan to
have the integrated master schedule completed in Fall 2007. They expect
to remove this issue from the risk watchlist at that time.
NASA Identified Flight Segment Risks and Is Working to Mitigate Them:
As of July 2007, the NASA flight project office identified four risks
affecting instrument development, all of which are classified as medium
risk (see fig. 5). The top three risks pertain to the advanced imaging
instrument, ABI--including issues on timely and quality subcontractor
delivery of a critical part, stray light negatively impacting the
performance of the optical system, and meeting specified performance
requirements on image navigation and registration. The fourth priority
risk pertains to the improvement of subcontractor quality assurance on
a key sensor for the Space Environmental In-Situ Suite.
Figure 5: Risks Identified by the GOES-R Flight Project Office, as of
July 2007:
[See PDF for image]
This figure is an illustration of risk on a matrix. The vertical axis
of the matrix represents probability of occurrence from low to high.
The horizontal axis of the matrix represents potential severity of
consequence from low to high. The matrix is five blocks high and five
blocks wide. The following data is depicted on the matrix:
Manufacture of visible-near infrared module (for ABI):
medium risk (fourth block for potential severity of consequence; second
block for probability of occurrence).
ABI stray light:
medium risk (fourth block for potential severity of consequence; second
block for probability of occurrence).
ABI image navigation and registration performance:
medium risk (fourth block for potential severity of consequence; second
block for probability of occurrence).
Quality assurance for the Space Environmental In-Situ Suite:
medium risk (second block for potential severity of consequence; third
block for probability of occurrence).
Source: NOAA.
[End of figure]
NASA is working to mitigate the flight segment risks that it is
tracking. For example, the ABI contractor, among other things, plans to
complete a key simulation review before the end of the year (called the
structural thermal optical performance analysis) to evaluate whether
the instrument can meet its expected performance parameters for image
navigation and registration. NASA also recently conducted a vendor
facility assessment of the SEISS subcontractor to determine whether
adequate quality assurance improvements had been made to be compliant
with contract requirements. These actions are expected to help mitigate
the risk.
NOAA Identified Risks in its Operations Segment and Is Working to
Mitigate Them:
As of July 2007, the NOAA operations project office identified five
risks impacting the management and development of the ground system and
operations, including one that is identified as a medium risk (see fig.
6). These risks include, among other things, inadequate definition of
flight and operations project interdependencies, algorithm development
responsibilities, and the adequate definition of coordination
requirements between the space and ground segments to ensure that the
two requests for proposals are consistent.
Figure 6: Risks Identified by the GOES-R Operations Project Office, as
of July 2007:
[See PDF for image]
This figure is an illustration of risk on a matrix. The vertical axis
of the matrix represents probability of occurrence from low to high.
The horizontal axis of the matrix represents potential severity of
consequence from low to high. The matrix is five blocks high and five
blocks wide. The following data is depicted on the matrix:
Flight-ops project acquisition and operations schedule
interdependencies:
medium risk (fourth block for potential severity of consequence; third
block for probability of occurrence).
Frequency interference (L-Band and X-Band):
medium risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
Algorithm development responsibilities:
medium risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
GOES-R rebroadcast L-Band dual pole space to ground link:
medium risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
Space to ground coordination:
medium risk (fourth block for potential severity of consequence; first
block for probability of occurrence).
Source: NOAA.
[End of figure]
NOAA is working to mitigate the ground system and operations risks that
it is tracking. For example, for the highest priority risk regarding
schedule interdependencies, key staff from both the flight and
operations projects meet weekly in order to identify and synchronize
project schedules. The project office expects to close this risk in
Fall 2007.
Multiple Watchlists Are Not Consistent, Making it Difficult to
Prioritize and Manage Risks:
While GOES-R has implemented a risk management process, its multiple
risk watchlists are not consistent in areas where there are
interdependencies between the lists, which makes it difficult to
effectively prioritize and manage risks at the appropriate
organizational levels. Sound risk management practices call for having
a consistent prioritization approach and for significant problems to be
elevated from the component level to the program level. This is because
an issue affecting a critical component could have severe programmatic
implications and should be identified, tracked, and overseen at the
program level. In addition, program executives should be briefed
regularly on the status of key risks.
However, on the GOES-R program, the risks identified on the multiple
risk lists are inconsistent in areas where there are interdependencies
between the lists. These interdependencies include situations where a
risk is raised by one project office and affects the other project
office, but is not identified by the other project office or elevated
to the program level risk list. They also include situations where a
risk identified by a project office has programwide implications, but
is not elevated to the program level risk list. For example, the
operations project office identified schedule interdependencies between
the flight and operations project offices as a medium criticality risk,
but neither the flight project office nor the program identified this
risk even though it is relevant to both. As another example, the
operations project office identified the ground procurement schedule as
a major issue in its briefing to senior management, but this risk was
not identified on its own or on the programwide risk lists.
In addition, while the three offices brief senior management about
their key risks on a monthly basis, selected risks may not be
accurately depicted in these briefings because of the inconsistencies
among the risk watchlists. For example, both the flight and operations
project offices identified technical development issues as minor to
moderate risk areas, but the program office did not identify this item
as a risk and, when it briefed senior management, it noted that
technical development was in good shape. Figure 7 depicts examples of
inconsistencies among risk lists and briefings to senior management.
The lack of consistency in managing risks in areas where there are
interdependencies makes it difficult to ensure that all identified
risks are appropriately prioritized and managed. This situation hampers
the program office's ability to identify and mitigate risks early on
and to anticipate and manage the impact of risks on other areas of the
program.
Figure 7: Examples of Inconsistencies among GOES-R Risk Watchlists, as
of July 2007:
[See PDF for image]
Program Office's risk list:
Risk: Schedule interdependencies between the flight and operations
segments: not identified as a risk;
Risk: Ground procurement schedule: not identified as a risk;
Risk: Technical development issues: not identified as a risk.
Flight Project Office's risk list:
Risk: Schedule interdependencies between the flight and operations
segments: not identified as a risk;
Risk: Ground procurement schedule: not applicable-is an operations
project office issue;
Risk: Technical development issues: 3 technical risks listed as medium
criticality.
Operations Project Office's risk list:
Risk: Schedule interdependencies between the flight and operations
segments: listed as medium criticality;
Risk: Ground procurement schedule: not identified as a risk;
Risk: Technical development issues: 1 technical risk listed as medium
criticality.
Briefing to senior executive council:
Risk: Schedule interdependencies between the flight and operations
segments: not identified as a risk;
Risk: Ground procurement schedule: identified as having major issues
(high risk);
Risk: Technical development issues: Program Office identified risk area
as in good shape (low risk);
* Flight Project identified risk area as having moderate issues (medium
risk);
* Operations Project identified risk area as having minor issues
(medium risk).
Source: GAO analysis of NASA and NOAA data.
[End of figure]
Important GOES-R Management Risks Are Missing from the Program
Watchlist:
To be effective, a risk management program should have a comprehensive
list of risks. However, several key risks that impact the GOES-R
procurement and merit agency attention are not identified in the
program's risk lists. These risks include (1) key leadership positions
that need to be filled, (2) NOAA's limited insight into NASA's
deliverables, and (3) insufficient management reserves (held by the
program and a key instrument contractor). At the conclusion of our
review, program officials stated that they are aware of these issues
and working to monitor them or address them, as warranted.
Nevertheless, until these and other programwide risks are identified
and addressed as part of a comprehensive risk management program, there
is increased likelihood that issues will be overlooked that could
affect the acquisition of the GOES-R system.
Key GOES-R Leadership Positions Need to be Filled:
The two senior GOES-R program positions--the system program director
and deputy system program director--are currently filled by NASA and
NOAA personnel in an acting capacity until they can be permanently
filled by NOAA. In addition, the acting system program director is not
able to work full time in this role because she is also on a special
assignment as the NESDIS Deputy Assistant Administrator for Systems.
NOAA reported that it plans to fill the deputy system program director
role in the near future, but noted that it could take more than 6
months to fill the system program director role. Given the approach of
the development phase of the GOES-R acquisition and the competing
priorities of the acting system program director, it is especially
important that these key leadership positions be filled quickly. At the
conclusion of our review, agency officials stated that they are aware
of this issue and working to fill the positions, but they did not
believe the issue warranted inclusion on the program level risk watch
list. However, without the senior level attention inherent in a sound
risk management program, it is not clear that NOAA is sufficiently
focused on the importance of establishing knowledgeable and committed
program executives, or in moving quickly to fill these critical
positions.
NOAA's Insight into NASA's Program Elements Is Limited:
NOAA's March 2007 decision to adopt an acquisition management approach
similar to prior GOES procurements could make the agency vulnerable to
repeating some of the problems experienced in the past. In particular,
our work on the GOES I-M series found that NOAA did not have the
ability to make quick decisions on problems because portions of the
procurement were managed by NASA.[Footnote 10] In fact, NOAA officials
originally intended to depart from this approach as a lesson they
learned from the GOES I-M acquisition, because it limited the agency's
insight and management involvement in the procurement of major elements
of the system.
The established NOAA/NASA interagency agreements require NASA to submit
monthly contractor cost performance reports to NOAA and to alert NOAA
should cost and schedule performance drop below certain thresholds.
NASA is currently submitting the required reports and has alerted NOAA
on major cost and schedule changes. However, these interagency
agreements do not contain provisions that enable NOAA to ensure that
the data and reports are reliable and that they accurately depict
contractor performance. To do so would entail NOAA having the ability
and means to question and validate data, such as by having direct
access to the contractor.
NASA and NOAA officials reported that the two agencies are working
together with an unparalleled level of transparency and noted that NOAA
program staff have access to contractor data and can bring any
questions with the data to the relevant NASA staff. However, they
acknowledged that this process is not documented and were not able to
demonstrate that NOAA staff had questioned contract data and that NASA
had facilitated obtaining answers to the questions. By not identifying
and mitigating this risk on its program risk list, NOAA increases the
likelihood that the GOES-R program will repeat the management and
contractor shortfalls that plagued past GOES procurements.
Recent Changes on a Key Instrument Have Reduced Program Management
Reserve Funds and Limited Contractor Reserve Funds Leave GOES-R
Vulnerable to Future Cost Increases:
A recent modification to the critical ABI instrument contract increased
its cost, thereby reducing the amount of management reserve funds held
by the program office for unexpected expenses. In September 2006, we
reported that ABI was experiencing technical challenges, resulting in
cost and schedule overruns. Since then, the contractor continued
missing cost and schedule targets--a trend that continued until
February 2007. At that time, NASA modified the contract to implement a
revised baseline cost and schedule. The added cost of this modification
was funded using management reserve funds held by the GOES-R program
office.[Footnote 11] As a result, the amount of reserve held by the
program office dropped below 25 percent--a level that NOAA reported it
intended to establish as a lesson learned from other satellite
acquisitions. As of July 2007, the program's reserve level was at about
15 percent. Program officials stated that their revised goal is to
maintain between 10 and 15 percent in reserve at the program level.
While maintaining a 10 to 15 percent management reserve is on par with
other major satellite acquisitions, the depletion of management
reserves this early in the GOES-R acquisition raises concerns that
there will be insufficient reserves during the challenging development,
integration, and testing phases to come.
In addition, the contractor for the ABI instrument has a very low level
of reserve funding for unexpected costs, which means that any
unexpected problems will likely lead to cost growth on the overall GOES-
R program. As of May 2007, the contractor was holding less than 1
percent of funding in reserve to cover unexpected costs associated with
the 40 percent of work left to be completed. As such, there is a risk
that the new baseline could fail due to inadequate reserves to finish
the program. This would likely have a diminishing effect on the reserve
held by the GOES-R flight project and the program office to cover the
costs of a second revised baseline plan. Our prior work on system
acquisitions has shown inadequate reserves to be an indicator of poor
management performance that could lead to cost overruns.[Footnote 12]
Considering that GOES-R has not yet entered the development and
production phase, it will be critical for NOAA's senior executive
management to aggressively manage this risk. By not identifying,
mitigating, and tracking this risk in a programwide risk list, the GOES-
R program runs an increased risk that unanticipated issues on the ABI
instrument will lead to programwide cost overruns and schedule delays.
Conclusions:
Over the last year, NOAA has completed preliminary design studies of
its GOES-R system and has made a number of key changes to the program.
Current program plans call for a two-satellite program--estimated to
cost about $7 billion--with launch of the first satellite in December
2014. However, independent studies show that the program's cost could
increase by about $2 billion more and the first launch could be delayed
by at least 2 years.
NOAA has taken steps to identify and address key risks but more could
be done to effectively manage risks from a programwide perspective. In
particular, the program has multiple risk watchlists that are not
consistent in areas where there are interdependencies and key risks
have not been elevated for programwide attention. Also, several risks
that warrant NOAA's attention have not been placed on any watchlist.
Specifically, the top two leadership positions are only temporarily
filled; NOAA does not have the ability and means to obtain insight into
NASA contracts in order to validate contractor performance data; and
insufficient management reserves to handle unexpected problems on a
critical instrument and at the program level are likely to affect
overall program costs when any unexpected problems arise. Until NOAA
manages and addresses a comprehensive set of program risks, the
agency's ability to effectively manage the GOES-R acquisition will be
significantly weakened and could lead to substantial program overruns
and delays.
Recommendations for Executive Action:
To improve NOAA's ability to effectively manage the procurement of the
GOES-R system, we recommend that the Secretary of Commerce direct the
Undersecretary of Commerce for Oceans and Atmosphere to take the
following two actions:
* Ensure that the GOES-R program office manages, mitigates, and reports
on risks using a program-level risk list that is reconciled with and
includes risks from its flight and operations project offices that
could impact the overall program.
* Include the following risks on the programwide risk list, develop
plans to mitigate them, and report to senior executives on progress in
mitigating them:
- unfilled or temporary GOES-R program leadership positions;
- insufficient program insight on NASA contract performance, and;
- insufficient management reserve on the critical Advanced Baseline
Imager instrument and at the GOES-R program level.
Agency Comments and Our Evaluation:
The Department of Commerce provided written comments on a draft of this
report (see app. II). In the department's response, the Secretary of
Commerce agreed with our recommendations to use a program level risk
list and to add selected risks to its list. The department reported
that NOAA has established a consolidated programwide risk list that is
to be used to evaluate risks during monthly internal and external
reviews. Further, NOAA acknowledges the risks associated with unfilled
leadership positions and insufficient management reserves and is
working to mitigate these risks. However, the department disagreed with
our recommendation to manage and mitigate the risk that NOAA has
insufficient insight into NASA's contracts. The department cited an
unparalleled level of transparency between the two agencies and listed
multiple regular meetings that the two agencies hold to ensure close
coordination. While an improved working relationship between the two
agencies is critical, NOAA has not provided any evidence that it has
been able to effectively question and validate data on NASA's
contractor performance. Given the past problems that NOAA experienced
in obtaining insight into NASA's contracts and the importance of this
interagency relationship to the success of the GOES-R program, we
believe that this issue should be managed and monitored as a risk.
NOAA also requested that we acknowledge its effort to reconcile its
program estimate with the independent estimate and reflect a 20 percent
possibility that the program could cost $1 billion more than the
current estimate of $7 billion, rather than $2 billion more. We
acknowledge this in our report, however, the reconciliation effort is
not complete and NOAA did not provide us with a reconciled estimate.
In addition, NOAA provided detailed comments on its cost estimates,
which are bulleted below and include our response.
* NOAA asserts that the independent cost estimate of $9.3 billion at
the 80 percent level could only be realized in an extreme situation;
and that based on its own cost model, there is a 20 percent probability
this extreme situation will occur. The independent estimator's $9.3
billion figure is not an extreme situation. Rather, it is at the 80
percent level, meaning that there is a 20 percent chance that the cost
could be even higher.
* NOAA expressed concern with our use of preliminary independent cost
estimates and schedule projections that are more conservative than the
current independent analyses indicate. However, NOAA did not provide us
its current independent analyses. Further, these current independent
analyses were developed through NOAA's negotiations with the
independent estimator to modify selected assumptions. We believe that
such negotiations could reduce the independence of the estimate and, in
turn, diminish its value as a conservative view by experts outside the
program office.
* NOAA commented that its reconciled cost estimate is within 4 percent
of the independent estimate's mean (50 percent) value, and that this
difference is well within a standard margin of error for cost estimates
at this phase of the program. While we are not prescribing a specific
level of risk that NOAA should assume, it should be noted that at the
50 percent confidence level, there is a 50 percent chance of being
under or over budget. Throughout our report, we have chosen to report
the independent estimate at the 80 percent confidence level.
* NOAA also commented that the schedule difference between the
independent estimate and the program estimate is currently 11 months
and that the program estimate is considered reasonable by the
independent estimator. However, the agency compared its projected
launch date (December 2014) to the independent estimator's projected
launch at 50 percent confidence (October 2015), instead of at its 80
percent confidence (March 2017). As such, our report accurately depicts
the results of this analysis at the 80 percent confidence level.
In the department's comments, NOAA also disagreed that the ABI
instrument contractor's low level of management reserve would likely
lead to cost growth on the overall GOES-R program. In particular, it
noted that the flight project office is expected to maintain a reserve
of 20 percent of the "cost to go" (the remaining funds) of the overall
space segment, which includes ABI. NOAA stated that, as of August 2007,
this reserve was at 20 percent. However, with the contractor's
management reserve at 1 percent and 40 percent of work remaining, we
continue to believe that ABI's situation will likely result in the
early depletion of reserves for the overall program. Furthermore, since
ABI is the first major initiative in this program and much remains to
be done, it is important to ensure that sufficient management reserve
is conserved for other key components as the program enters the
development phase.
The Department also suggested technical comments which we incorporated
as appropriate.
We will be sending copies of this report to interested congressional
committees, the Secretary of Commerce, the Administrator of NASA, the
Director of the Office of Management and Budget, and other interested
parties. In addition, this report will be available at no charge on our
Web site at [hyperlink, http://www.gao.gov].
If you have any questions on matters discussed in this report, please
contact me at (202) 512-9286 or by e-mail at pownerd@gao.gov. Contact
points for our Offices of Congressional Relations and Public Affairs
may be found on the last page of this report. GAO staff who made major
contributions to this report are listed in appendix III.
Signed by:
David A. Powner:
Director:
Information Technology Management Issues:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
Our objectives were to assess the status and revised plans for the
Geostationary Operational Environmental Satellites-R series (GOES-R)
procurement and to evaluate whether the National Oceanic and
Atmospheric Administration (NOAA) is adequately mitigating key
technical and programmatic risks facing the GOES-R program.
To assess the status and the revised plans for the GOES-R procurement,
we evaluated various programmatic and technical plans, management
reports, and other program documentation. We reviewed the acquisition
strategy, cost estimates performed by the program office and an
independent estimator, planned system requirements, and monthly
executive-level management briefings. We also analyzed earned value
management data obtained from a key instrument contractor to assess
performance against cost and schedule targets. Furthermore, we
interviewed agency officials from NOAA, the National Aeronautics and
Space Administration (NASA), and ITT Corporation to determine key dates
for future GOES-R acquisition efforts and milestones and progress made
on current instrument development efforts.
To evaluate whether NOAA is adequately mitigating key technical and
programmatic risks facing the GOES-R program, we analyzed relevant cost
reports and risk management plans to identify key risks that could
negatively affect the program's ability to acquire the GOES-R system
and the mitigation plans for these risks. We also met with technical
experts in system acquisitions and relied on our past body of work on
other major satellite acquisitions (such as the previous GOES series
and the National Polar-orbiting Operational Environmental Satellite
System programs) to identify other key risks. We applied lessons
learned and also interviewed agency officials to evaluate the adequacy
of NOAA's mitigation efforts.
We conducted our work at NOAA and NASA offices in the Washington, D.C.,
metropolitan area and at ITT Corporation (the contractor for the most
critical GOES-R instrument) in Fort Wayne, Indiana. We performed our
work from April 2007 to September 2007, in accordance with generally
accepted government auditing standards.
[End of section]
Appendix II: Comments from the Department of Commerce:
The Secretary Of Commerce:
Washington, D.C. 20230:
October 4, 2007:
Mr. David A. Powner:
Director:
Information Technology Management Issues:
U.S. Government Accountability Office:
441 G Street, NW:
Washington, D.C. 20548:
Dear Mr. Powner:
Thank you for the opportunity to review and comment on the Government
Accountability Office's draft report entitled Geostationary Operational
Environmental Satellites: Progress Has Been Made, but Improvements Are
Needed to Effectively Manage Risks (GAO-08-18). On behalf of the
Department of Commerce, I enclose the National Oceanic and Atmospheric
Administration's comments to the draft report.
Signed by:
Carlos M. Gutierrez:
Enclosure
[End of letter]
Enclosure:
Department of Commerce:
National Oceanic and Atmospheric Administration:
Comments on the Draft GAO Report Entitled "Geostationary Operational
Environmental Satellites: Progress Has Been Made, but Improvements Are
Needed to Effectively Manage Risks"
(GAO-08-18/October 2007):
General Comments:
The Department of Commerce's National Oceanic and Atmospheric
Administration (NOAA) appreciates the opportunity to review this report
on Geostationary Operational Environmental Satellites, specifically the
R-series (GOES-R). The report does a thorough job assessing the overall
status of the GOES-R program. However, NOAA is concerned with GAO's use
of preliminary independent cost estimates and schedule projections that
are more conservative than the current independent analyses indicate.
NOAA has been actively reconciling its Program Office Estimate (POE)
with the Independent Cost Estimate (ICE) to ensure both are using
similar assumptions in their projections. One significant assumption
involves estimated future inflation rates. By using standard NASA and
DoD inflation indices, the ICE reduces to $600 million but still
regards higher inflation as a potential risk. In addition, the GOES-R
Program Office has added management reserve to its POE for space
segment and operations activities. As a result, the independent cost
estimator has noted (1) the reconciled program office estimate is
within 4 percent of the independent estimate's mean value, which is the
expected value of the cost projection and (2) this difference is well
within a standard margin of error for cost estimates at this phase of
the program.
The most conservative estimates at the 80 percent confidence intervals
bring the POE within 12 percent of the ICE, or $1.032 billion below the
ICE. In addition, the schedule delta between the ICE and the POE is
currently 11 months and considered by the independent estimator to be
reasonable and within the ability of schedule models to predict.
Therefore, NOAA requests that the GAO acknowledge NOAA's reconciliation
efforts and revise its cost and schedule statements in the report to
reflect the 20 percent possibility that in the extremes, the program
could cost $1 billion more rather than $2 billion, and that the first
satellite launch could be delayed by one year rather than two.
NOAA Response to GAO Recommendations
The draft GAO report states, "To improve NOAA's ability to effectively
manage the procurement of the GOES-R system, we recommend that the
Secretary of Commerce direct the Under Secretary of Commerce for Oceans
and Atmosphere to take the following two actions."
Recommendation 1: "Ensure that the GOES-R program office manages,
mitigates, and reports on risks using a program-level risk list that is
reconciled with and includes risks from its flight and operational
project offices that could impact the overall program."
NOAA Response: NOAA agrees with this recommendation. In order to
manage, mitigate and report on risks, the GOES-R Program Office will
maintain a consolidated program-wide risk list and will use this list
in internal and external reviews of the program.
NOAA has taken the following steps to address this recommendation:
* The System Engineering and Integration Division of the GOES-R Program
Office maintains the program-wide risk list.
* The GOES-R System Program Director (SPD) reviews all risks during
monthly reviews of the flight and ground projects.
* The GOES-R SPD briefs the NOAA Program Management Council (PMC)
monthly on risks that warrant senior level review and guidance.
Recommendation 2: "Include the following risks on the programwide risk
list, develop plans to mitigate them, and report to the senior
executives on progress in mitigating them:
* unfilled or temporary GOES-R program leadership positions;
* insufficient program insight on National Aeronautics and Space
Administration (NASA) contract performance, and;
* insufficient management reserve on the critical Advanced Baseline
Imager instrument and at the GOES-R program level."
NOAA Response: NOAA partially agrees with this recommendation. We agree
that the unfilled leadership positions and the insufficiency of
management reserves are significant risks. However, NOAA does not
concur that it has insufficient program oversight on NASA's contract
performance.
First, NOAA is aggressively seeking to fill the three top GOES-R
leadership positions.
* The former GOES-R SPD announced on July 6, 2007, that he would be
retiring. NOAA's National Environmental Satellite, Data, and
Information Service immediately appointed the Deputy Assistant
Administrator for Systems, an individual with extensive GOES-R
experience, as Acting SPD and began the recruitment process for a new
SPD. NOAA advertised this position beginning on August 1, 2007, with
closure on September 17, 2007, and plans to select the new SPD within
weeks.
* The Deputy SPD position became vacant in April 2007. NOAA immediately
appointed a senior headquarters staff advisor, with extensive GOES-R
experience, as Acting Deputy SPD. NOAA advertised the position in May
and June 2007. No selection was made; therefore, the position has been
re-advertised.
* The Assistant SPD position became vacant in May 2007. Following a
competitive selection process, the new Assistant SPD reported on
September 4, 2007.
The tracking and reporting of all GOES-R personnel actions is a major
focus area during the monthly program reviews by the NOAA Program
Management Council. The GOES-R program tracks personnel actions through
all steps of the recruitment process: initiation of the recruitment
package through the vacancy posting, certificate issuance, job
interviews, and the employee reporting on-board.
Second, NOAA agrees that management reserves should be a watch item on
the program-wide risk list. The GOES-R program has adopted the strategy
below for managing its reserves. This strategy has been successful for
other programs.
* In accordance with standard NASA practice, the GOES-R program
maintains reserves at the program and project levels – not at the
individual instrument level. Each project has its own reserve funds and
the SPD hold additional reserves. There is no management reserve
funding specifically assigned to the Advanced Baseline Imager (ABI).
The government-held ABI management reserve is contained within the
overall Flight Project and GOES-R program reserves.
* The GOES-R Flight Project Manager's strategy for instrument
development is to aggressively manage instrument costs and minimize the
allocation of reserves to the instrument contractors until the need
arises. This philosophy calls for tight management and oversight by the
Flight Project Manager with re-baselining as necessary to allocate
management reserves to the contracts. This process ensures the project
is actively involved in cost oversight and contractors do not expend
management reserves without the necessary government oversight. When
the instrument contractors experience problems causing their costs to
exceed their contract values, the GOES-R program has budgeted adequate
reserves to meet the development challenges.
Given this management approach, NOAA disagrees with GAO's finding that
"the contractor for the ABI instrument has a very low level of reserve
funding for unexpected costs, which means that any unexpected problems
will likely lead to cost growth on the overall GOES-R program." The
reserve posture of ABI has to be evaluated in its larger context: the
Flight Project is expected to maintain a 20 percent reserve on the
"cost to go" of the overall GOES-R space segment, which includes ABI,
and to report variances against that reserve. As of August 2007, the
project reserve was at 20 percent.
Third, NOAA does not agree with the statement that "insufficient
program insight on NASA contract performance" exists.
* For previous GOES programs, NOAA maintained a small liaison office,
but did not engage in the day-to-day oversight of NASA contract
management. NOAA learned some useful lessons from not having sufficient
insight into the performance of NASA's contractors. Unlike those
earlier management arrangements, the GOES-R program is now managed by a
joint NOAA-NASA Program Office with NOAA and NASA personnel working
side-by-side at all levels of the organization, giving NOAA
unprecedented insight into NASA's contracts.
* The NASA-led Flight Project, which is responsible for the spacecraft
and instrument contracts, undergoes four formal reviews each month, all
of which address contractor performance:
1. NOAA's Program Status Review (PSR) – The SPD conducts an in-depth
PSR, which is open to all GOES-R program and project staff. The PSR
objectives include a review of all spacecraft and instrument risks,
issues, status, resources, and mission assurance items.
2. NASA's Goddard Space Flight Center (GSFC) Program and Projects
Directorate Monthly Status Review (MSR) – The SPD or Deputy SPD attends
these meetings.
3. NASA's GSFC PMC MSR – The SPD is a member of the GSFC PMC for the
GOES-R portion of the meeting.
4. NOAA's PMC – The SPD, the Flight Project Manager, and the Ground
Project Manager each present information to NOAA leadership on all GOES-
R program contracts, their financial performance, risks and issues.
Senior NASA officials participate in the NOAA PMC to provide immediate
responses to any concerns raised by the NOAA leadership.
* In addition to the formal reviews, there are regular and frequent
interactions between the co-located NOAA-led Program Office and the
NASA-led Flight Project, including weekly senior management team
meetings and weekly risk meetings. The GOES-R Budget Officer, a NOAA
official, and his staff provide regular oversight of Earned Value
Management on the NASA acquisition and operation contracts. Ad hoc
meetings on numerous topics are facilitated by the two staffs being co-
located in the same suite of offices at GSFC.
There is unprecedented transparency between NOAA and NASA for GOES-R,
as documented in the NOAA-NASA Memorandum of Understanding dated June
15, 2007. Daily interactions between the NOAA and NASA staffs occur
with a free exchange of information enabling the NOAA-led Program
Office to carry out its management and oversight responsibilities.
[End of section]
Appendix III: GAO Contact and Staff Acknowledgments:
GAO Contact:
David A. Powner, (202) 512-9286 or pownerd@gao.gov:
Staff Acknowledgments:
In addition to the contact named above, Colleen Phillips (Assistant
Director), Carol Cha, Neil Doherty, Nancy Glover, Mustafa Hassan, Karen
Richey, and Teresa Smith made key contributions to this report.
(310840):
[End of section]
Footnotes:
[1] Satellites in a series are identified by letters of the alphabet
when they are on the ground and by numbers once they are in orbit.
[2] Sounding data is information on the vertical structure of
temperature and water vapor.
[3] The instruments were based on 1980s technology.
[4] GAO, Geostationary Operational Environmental Satellites: Additional
Action Needed to Incorporate Lessons Learned from Other Satellite
Programs, GAO-06-1129T (Washington, D.C.: Sept. 29, 2006) and
Geostationary Operational Environmental Satellites: Steps Remain in
Incorporating Lessons Learned from Other Satellite Programs, GAO-06-993
(Washington, D.C.: Sept. 6, 2006).
[5] Earned value management is a method that compares the value of work
accomplished during a given period with that of the work expected in
that period.
[6] These were called Program Definition and Risk Reduction contracts.
[7] NASA has not yet issued a development contract for the
Geostationary Lightning Mapper. This contract is expected to be awarded
at the end of October 2007.
[8] This independent review team, comprised of former senior industry
and government space acquisition experts, was hired by NOAA to assess
the adequacy of the GOES-R program's management approach, acquisition
strategy, and resource availability, among other things.
[9] NASA's GOES-R flight project office is responsible for the
spacecraft, instruments, and launch services. NOAA's GOES-R operations
project office is responsible for the ground elements and on-orbit
operations of the satellites.
[10] GAO-06-993.
[11] This reserve is intended to cover expected costs above those
projected by the contractor and unexpected costs in solving problems
during a system development program.
[12] GAO-06-993.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation, and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, DC 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, DC 20548:
Public Affairs:
Susan Becker, Acting Manager, BeckerS@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, DC 20548: