Second GAO Report on Need for Better Control Over Government-Furnished Material Provided to Defense Overhaul and Repair Contractors

Gao ID: PSAD-76-78 March 8, 1976

Air Force overhaul and repair contractors are given about $200 million of government material every year. The Air Force, however, does not have the necessary records to hold the contractors accountable for this material.

As long ago as 1970, GAO recommended improvements in the management of government materials given to contractors. The military services agreed and said corrective action was being taken. An internal Department of Defense (DOD) audit report, February 1974, stated little, if any, management attention was being paid to the control of government-furnished material in contractors' plants. One case involved an apparent misuse of government-furnished material valued at about $2.5 million. Good business practice dictates that when custody of property is transferred from one supplier to another, an audit trail of what was transferred must be kept by the supplier to provide accountability. Accountability for government-furnished material within the Air Force includes such weaknesses as incomplete estimates of materials to be used, limited knowledge of materials ordered and received by contractors, and inadequate checks of whether materials are used for proper purposes.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: No director on record Team: No team on record Phone: No phone on record


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.