The Consolidated Space Operations Center Is Not Supported by Adequate Defense Department Planning
Gao ID: B-205335 March 22, 1982In response to a congressional request, GAO evaluated the Department of Defense's (DOD) comments on a prior GAO report. The comments were included in the report unevaluated because they were received after the 30-day period allowed for agency response, and the GAO reporting deadline precluded a detailed evaluation of the comments in the report.
DOD agreed with the facts which GAO found during its review of the Consolidated Space Operations Center siting decision. However, DOD disagreed with the GAO interpretation of the findings and the recommendations based thereon.