Cost and Savings Estimates the Air Force Used To Decide Against Relocating the Electromagnetic Compatibility Analysis Center From Annapolis, Maryland, to Duluth, Minnesota

Gao ID: PLRD-83-48 March 9, 1983

In response to a congressional request, GAO reviewed the cost and savings estimates used by the Air Force to decide against relocating the Electromagnetic Compatibility Analysis Center from Government-owned and leased space in Annapolis, Maryland, to Government-owned space at the Duluth International Airport, Minnesota.

The Air Force estimated in September 1980 that relocation would, over a 10-year period, cost $11 million more than leaving the Center in Annapolis. In September 1981, the Air Force revised this estimate to $5 million over a 10-year period. GAO estimated that relocation would increase cost to the Government, over the next 15 years, between $4.3 million and $7 million, depending upon the number of personnel that would relocate. The GAO estimate of relocation costs and the Air Force's estimates differ because: (1) GAO used 1982 cost data whereas the Air Force used 1979 cost data; (2) GAO projected costs over 15 years whereas the Air Force projected costs over 10 years; (3) GAO used a 13.26-percent discount factor to compute the present value of total costs whereas the Air Force used a 10-percent factor; and (4) GAO computed higher or lower estimates for some cost items. GAO believes that the decision not to relocate was, from a cost standpoint, appropriate.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.