The Air Force's C-5B Should Cost Study

Gao ID: T-NSIAD-87-1 December 3, 1986

GAO testified on the Air Force's should-cost study on the final option for 21 C-5B aircraft under a fixed-price contract, specifically: (1) the events which led to the Air Force's decision to conduct a cost study; and (2) the methodology upon which the Air Force based the study. GAO found that the Air Force: (1) was concerned that the contractor might substantially underrun the expected costs of producing the C-5B aircraft and achieve a profit rate higher than the 15 percent which the Air Force had negotiated; (2) inserted a profit-sharing clause into the contract to reduce any profit over 17 percent, instead of renegotiating the contract; (3) notified the contractor that it should submit a new proposal, on which the Air Force would perform a cost study to determine if the price of the fiscal year (FY) 1987 option was fair and reasonable; and (4) conducted the study in order to establish a negotiating position if it decided not to exercise the FY 1987 option under contract terms that existed at that time. GAO also found that the should-cost study: (1) evaluated the contractor's proposal in sufficient detail for the Air Force to decide whether it should exercise the option; (2) performed a cost analysis of subcontract costs; and (3) did not identify uneconomical, inefficient, or outdated practices in the contractor's management and operations, since there was not enough time to implement any recommended changes.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.