Navy Contracting

Allegations About Trident Submarine Program Matters Gao ID: NSIAD-86-74BR June 13, 1986

In response to a congressional request, GAO reviewed allegations concerning mismanagement and questionable practices in the Trident submarine construction program, specifically: (1) excessive progress payments in submarine construction; (2) advance procurement of long-lead-time material; (3) unwarranted cost escalation on the lead Trident; (4) destruction of Navy records; (5) inappropriate task authorization and funding of engineering services contracts; (6) elimination of a financial monitoring procedure; and (7) violations of standards of conduct.

GAO found that: (1) the contractor inflated contruction progress reports to qualify for more early progress payments; (2) the contractor's budgeting practices raised questions about the accuracy of data and reports it submitted to the Navy; (3) a Navy contracting practice provides, through special clauses in some submarine contracts, additional progress payments, which are normally paid under standard payment clauses; (4) there were increases in funding for advance procurement for long-lead-time material for Trident submarines; (5) a general records disposal effort did not eliminate specified documentation; (6) an increase in escalation authorization in October 1981 for the lead Trident submarine did not result in any additional payment to the contractor; (7) the official who issued the transaction on an engineering services contract had the authority to approve and issue task assignments; (8) the Navy utilizes a contract-required cost report to enable it to financially monitor contract tasking; and (9) the Navy did not violate any laws when it purchased a used boat at fair market value from the contractor.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.