Missile Development

Advanced Medium Range Air-to-Air Missile (AMRAAM) Certification Issues Gao ID: NSIAD-86-124BR July 9, 1986

In response to a congressional request, GAO reviewed the status of the Advanced Medium Range Air-to-Air Missile program (AMRAAM) as it relates to the certification requirements of the Defense Authorization Act.

GAO found that: (1) although the AMRAAM program manager and the Air Force stated that the design was complete, based on the critical design review, they subsequently made a number of design changes; (2) a more reliable indicator of design completion would have been the functional configuration audit; (3) some proposed engineering changes and existing design deviations could adversely affect missile performance, but they do not require certification; (4) potential schedule slippages in the development and testing of the cost-reduction changes could delay incorporating these changes into planned production lots; (5) the contract has not yet exceeded its cost ceiling, but the program manager believes that the ceiling will restrain and delay development testing; (6) the $5.2 billion production cost estimate does not appear conservative and reasonable as a ceiling over the next 10 years; and (7) although it is too early to assess missile performance, by 1988 the scheduled tests should provide a basis to judge whether AMRAAM is in accordance with development specifications.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.