Contract Pricing

Overpriced B-52 Bomber Avionics Subcontract Gao ID: NSIAD-88-38 November 30, 1987

GAO reviewed an Air Force subcontractor's pricing practices for the Offensive Avionics System/Cruise Missile Integration Program to determine whether it provided the prime contractor with accurate and complete cost data as required by the Truth in Negotiations Act.

GAO found that: (1) the subcontractor did not provide the prime contractor with accurate and complete data, which caused the prime contractor to overstate its contract costs by about $644,601; (2) the subcontractor did not inform the prime contractor of its plan to purchase certain items from another vendor at a reduced price; (3) the subcontractor failed to inform the prime contractor of its decision to purchase about 50 percent of the parts it had planned to make; (4) although the purchase order prices on the parts were significantly lower than its proposed prices, the subcontractor did not reduce its original price; and (5) although the subcontractor did not admit any liability for the overpricing, it agreed to repay any overdue amount.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.