Incentive Contracts

Examination of Fixed-Price Incentive Contracts Gao ID: NSIAD-88-36BR November 3, 1987

In response to a congressional request, GAO examined the federal government's practice of using fixed-price incentive (FPI) contracts to share cost risks with its contractors, to determine its cost-effectiveness.

GAO reviewed 573 FPI contracts at 6 Department of Defense (DOD) purchasing offices and found that: (1) DOD had given final pricing to 62 contracts; (2) of the 62 contracts, 2 achieved the target price, 33 overran the target price, and 27 underran the target price; and (3) none of the 6 purchasing offices exceeded their cumulative target price by more than 1.76 percent. GAO also found that: (1) there was no relationship between the cost-sharing ratio and achievement of a contract's target price; (2) although the FPI contracts did not always achieve the desired goal, they enabled the government to share financial risks with contractors and limited its financial liability; (2) government contractors often refuse to accept firm-fixed-price contracts because of the associated risks; and (3) the government would have to use cost-type contracts if it could not partially share risk through FPI contracts.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.