Delivery Problems With Inertial Measurement Units Gao ID: NSIAD-88-74BR December 18, 1987

In response to a congressional request, GAO provided information on the Air Force's acquisition of inertial measurement units (IMU), a major component of the Peacekeeper missile guidance and control system.

GAO found that: (1) the IMU manufacturer did not timely deliver the units, resulting in a 4.5-month delay in the deployment schedule; (2) although the manufacturer expects to be back on schedule by April 1988, the Air Force believes that October is a more realistic date; (3) changes in the production date from 1983 to 1984 without any changes in the operational capability date caused delays; and (4) as of September 30, 1987, only 18 of the 28 Peacekeeper missiles available for operations were on alert because of shortages of IMU. GAO also found that: (1) the Air Force relaxed its acquisition procedures in order to accommodate the manufacturer's inability to effectively manage its manufacturing process; (2) 17 test flights for IMU accuracy and reliability had better-than-anticipated results; and (3) the Air Force will absorb about $17 million of an estimated $24.4 million in total contract costs because of delivery delays.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.