Contract Pricing
GBU-15 Bomb Components Overpricing Gao ID: NSIAD-89-10 November 2, 1988GAO reviewed an Air Force procurement for components for the GBU-15 Modular Guided Weapon System, to determine whether the contractor complied with the Truth in Negotiations Act and provided accurate, complete, and current cost data.
GAO found that the contractor: (1) did not disclose accurate, complete, and current pricing information for seven materiel items, resulting in contract overpricing of $1,008,854; (2) allegedly orally disclosed lower vendor prices for three materiel items, but could not provide any supporting evidence; (3) agreed that it did not disclose lower available prices for three other materiel items, but did not believe that the nondisclosure resulted in contract overpricing; and (4) agreed that the contract was overpriced for the remaining item.
RecommendationsOur recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director: Team: Phone: