Trident II Proceeding Toward Deployment Gao ID: NSIAD-89-40 November 21, 1988

Pursuant to a congressional request, GAO reviewed the acquisition status of the Navy's Trident II system.

GAO found that the: (1) Trident II system development is on schedule; (2) Navy will need to continue testing the system after the December 1989 initial operational capability date to obtain sufficient data to verify missile performance; (3) Department of Defense's December 31, 1987, estimated program cost was $51.3 billion, which included costs for research, development, and procurement of 843 missiles, procurement of 11 Trident II submarines, and general support facilities; (4) Navy believes that it will complete construction at the Naval Submarine Base at Kings Bay, Georgia, in time to support critical 1989 program milestones; (5) dredging of waterways required for the Trident II submarine is nearly complete; (6) Navy plans to conduct two missile launches from a Trident II submarine before submarine deployment; and (7) Navy must meet several major milestones before December 1989, including land-based and at-sea missile launch tests. GAO estimated total life-cycle acquisition, operations, and support costs for the system at $155 billion.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.