Military Airlift

C-17 Faces Schedule, Cost, and Performance Challenges Gao ID: NSIAD-89-195 August 18, 1989

GAO evaluated the Air Force's progress in meeting the C-17 aircraft program's schedule, cost, and performance goals.

GAO found that: (1) reduced funding in fiscal years 1986 and 1987 delayed the aircraft's fabrication and assembly by 9 months and its first flight until August 1990; (2) the Air Force may not meet the test flight date because the assembly schedule has a high degree of risk, projected late deliveries of tooling and parts could delay assembly, and subcontractor development of key avionics systems is behind schedule; (3) current program acquisition cost estimates have increased $3 billion over the original $34.5 billion and do not include $437 million for the defense systems the Air Force planned to develop; (4) although the Air Force requested funding through 1993 so it could conduct an interim review after initial flight tests, it only received funding for low-rate production through 1991; (5) although the contractor projected that the aircraft would meet approved requirements, the aircraft's projected weight had already increased to the maximum allowable to meet current payload and range requirements; (6) the Air Force planned to install defense systems to detect and counter combat threats, and to conduct live-fire tests on a representative section of the aircraft's wing to determine its vulnerability to combat damage; and (7) due to continuing problems in the contractor's ability to effectively address existing assembly and avionics development problems, the Air Force extended the planned first flight to December 1990.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.