Navy Shipbuilding

Cost and Schedule Problems on the DDG-51 AEGIS Destroyer Program Gao ID: T-NSIAD-90-14 January 24, 1990

GAO discussed the cost and schedule status of the DDG-51 class Arleigh Burke guided missile destroyer. GAO found that: (1) the contractor for the lead ship encountered design and construction problems which resulted in contract requirements changes and substantial cost increases, and delayed the expected delivery schedule by 17 months; (2) although the contractor estimated that about 50 percent of the lead ship was completed, it still had to install, integrate, and test the combat system and other technical components; (3) because the Navy has already awarded contracts for the seven follow ships, it could have as many as 17 ships under construction before delivery of the lead ship; (4) the Navy expected the design costs to more than double from the original contract costs of $111 million, to $247 million, and construction costs to grow more than 60 percent, from $157 million to $253 million; (5) the Navy modified the contract to resolve outstanding contractual issues, which could increase Navy compensation as much as $71.7 million and eliminate the contractor's projected losses; and (6) the modification could establish an inappropriate precedent, since many of the Navy's fixed-price-incentive shipbuilding contracts experienced cost overruns. GAO believes that the Department of Defense should either provide assurances on the development and affordability of the DDG-51 program or delay award of the additional follow ships.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.