Weapons Production
Impacts of Production Rate Changes on Aircraft Unit Costs Gao ID: NSIAD-91-12 December 18, 1990Pursuant to a congressional request, GAO reviewed the sensitivity of estimated procurement costs for military aircraft to reductions in the quantity of aircraft purchased.
GAO found that: (1) aircraft procurement unit costs generally increased as their procurement rates decreased, but some mature Air Force and Navy procurement programs did not show a significant unit cost increase compared to other aircraft programs; (2) contractors reported that the procurement unit cost was especially sensitive to sudden unanticipated changes in production rates; (3) unit costs were less sensitive when the military planned rate reductions and reduced such fixed costs as overhead and facilities; and (4) contractors needed sufficient advance notice of procurement rate decreases, so that they could eliminate unnecessary facility, overhead, and other costs before the production rate decreases began.