Cost Increases and Schedule Delays in the Air Force's Titan IV Program Gao ID: NSIAD-90-113 May 3, 1990

Pursuant to a congressional request, GAO reviewed the Air Force Titan IV program's contract status, cost growth, and schedule estimates.

GAO found that: (1) between March 1988 and October 1989, Titan IV program costs increased by $1.9 billion; (2) the Air Force planned to use 21 of the 55 launch vehicles procured through fiscal year (FY) 1995; (3) the Air Force funded most Titan IV research and development and launch facilities; (4) the cost overrun on the Titan IV contract was $209 million as of July 1989, which was primarily due to production and engineering problems; (5) the Air Force postponed 6 of the 10 launches planned for FY 1989 and FY 1990 because of launch site preparation delays and payload rescheduling; and (6) the completion dates for 3 Titan IV facilities slipped up to 20 months.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.