Status of the Army's M687 Binary Program Gao ID: NSIAD-90-295 September 28, 1990

Pursuant to a legislative requirement, GAO assessed an Army contractor's ability to eliminate its delivery backlog of M-20 and M-21 canister components for the M687 binary chemical projectile by October 1, 1990.

GAO found that the: (1) Army recognized that the contractor could not complete deliveries by October 1, 1990 for the fiscal year (FY) 1988 program; (2) contractor expected to complete deliveries for the 1988 program by the end of November 1990; (3) United States' agreement with the Soviet Union to halt production of chemical weapons made the FY 1989 program the last procurement program for M687 projectiles; (4) Army did not expect to finish construction of a new chemical production plant scheduled for completion in October 1989 until October 1990; and (5) Army might not be able to use the new facility due to difficulties in obtaining chemicals needed for production.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.