Special Operations Forces
Army Plans Highly Concurrent Acquisition Strategy for Costly Helicopters Gao ID: NSIAD-90-267 September 28, 1990Pursuant to a congressional request, GAO evaluated cost, schedule, and test plans for the Army's special operations forces (SOF) helicopter program, focusing on: (1) the Army's planned concurrency of developmental and operational testing with actual production; and (2) current cost estimates for the program.
GAO found that: (1) although current acquisition policies and procedures called for developmental and operational testing prior to full-scale production, the Army planned initial production of 22 SOF helicopters concurrent with developmental testing; (2) the Army planned to produce and deliver 53 of the planned 74 SOF aircraft before conducting operational testing; (3) the Army planned to test and field SOF helicopters that did not possess all of the equipment necessary to satisfy operational capability requirements; (4) the Army identified risks involving avionics mission processor development, radar system certification, performance of government-furnished equipment, and retrofit costs, but did not address the risk associated with concurrent production and testing; and (5) program costs could greatly exceed current estimates due to the Army's exclusion of many costs in the estimates, future cost growth, and concurrent testing and production plans.
RecommendationsOur recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director: Team: Phone: