Defense Acquisition

Examination of MLRS Terminal Guidance Warhead Program Gao ID: NSIAD-91-144 March 28, 1991

GAO reviewed the requirements, schedule, performance, and cost of the Army's Multiple Launch Rocket System (MLRS) Terminal Guidance Warhead (TGW) program.

GAO found that: (1) MLRS TGW had been in development for more than 6 years, and cost about $530 million; (2) the U.S. share of the project was $230 million and the European countries' share was $300 million; (3) early in development, the program experienced serious schedule slippages and technical difficulties; (4) the Army has not finalized its statement of required operational capabilities, but has tested system components separately, and a full system demonstration is underway; (5) test results to date have not been sufficient to lower previous overall assessments of medium technical risk in the program; (6) successful testing of integrated system hardware is scheduled for between late 1991 and late 1992; (7) the Army estimated the total U.S. acquisition cost at $7 billion, although the Department of Defense believed that there were considerable uncertainties in the estimate; (8) program costs could become even more uncertain due to changes in quantity requirements, production line and economic adjustment decisions, and the configuration required to accomodate a longer range delivery vehicle; (9) if the Army decided to use the MLRS TGW submunition in a longer range delivery vehicle rather than in the basic MLRS rocket, development of MLRS TGW would no longer be necessary; and (10) the technical risks and cost uncertainties raise serious funding questions.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.