Strategic Defense Initiative

Need to Examine Concurrency in Development of Brilliant Pebbles Gao ID: NSIAD-91-154 March 27, 1991

Pursuant to a congressional request, GAO provided information on the Strategic Defense Initiative Organization's (SDIO) program for developing Brilliant Pebbles, the space-based weapons system for the Phase I Strategic Defense System.

GAO found that: (1) the SDIO full-scale development program was highly concurrent with the Department of Energy's (DOE) Lawrence Livermore National Laboratory (LLNL) test program; (2) the concurrency would result in SDIO paying contractors to improve a design concept before LLNL fully demonstrated that the concept worked; (3) the primary objective of the LLNL test program was to demonstrate the technical feasibility of the space-based weapons system before making a full-scale development and deployment decision; (4) the first flight test did not achieve all its objectives due to a mechanical failure, resulting in a 10-month delay of the test schedule; (5) the current test schedule could not be compressed any further, and if delayed another 4 months, would not be completed by the summer 1993 deadline; (6) the cost estimate for a Phase I Strategic Defense System decreased from $69.1 billion to $55.3 billion due to substituting the new space-based system for the dated space-based interceptor; and (7) a matter for congressional consideration included in the classified report may no longer be relevant, due to the revised schedule.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.