Military Airlift

Selected Events in the Development of the C-17 Gao ID: NSIAD-92-181FS May 4, 1992

This report provides information on the financing of the Air Force's C-17 aircraft, which is being developed by the McDonnell Douglas Corporation. GAO discusses (1) progress payments, (2) the change in accounting treatment of engineering costs, (3) the decision to split the government's contractual acceptance of the development test aircraft into two separate events, (4) reductions to the aircraft's performance specifications, and (5) the status of claims filed by McDonnell Douglas. GAO provides a chronology of the events from June 1990 through September 1991.

GAO found that: (1) since November 1990, increases in the cost estimate for completion of the development contract have resulted in substantially lower monthly progress payments to the contractor, but other events have increased the contractor's cash flow; (2) the contractor changed its accounting treatment of engineering charges, which resulted in $172 million being available for fiscal year 1991 progress payments; (3) a contract modification split the government's acceptance test aircraft into two events and resulted in the contractor receiving a payment 9 months earlier than previously agreed; (4) reductions to the aircraft performance specifications will affect the contractor's financial condition because compliance with the reduced specifications should be achievable at a lower cost; (5) claims against the government could also affect the contractor's financial status; (6) in 1990 and 1991, the contractor filed seven claims totalling $108 million relating to the C-17 Program; (7) two of those claims were denied, and five are awaiting a final Air Force decision; and (8) in 1992, $237 million in claims have been filed and are under review.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.