F-22 Aircraft

Progress in Achieving Engineering and Manufacturing Development Goals Gao ID: NSIAD-98-67 March 10, 1998

Schedule delays in the engineering and manufacturing development of the advanced F-22 aircraft, including problems in delivering the plane's wings and fuselage, have prompted the Air Force to reconsider the program's cost. The National Defense Authorization Act for Fiscal Year 1988 imposed cost limitations of $18.6 billion on the F-22 engineering and manufacturing development program and $43.4 billion on the production program. In addition, testing delays have limited the amount of information available to support the Air Force's plans to begin production of the F-22 in 1999. GAO summarized this report in testimony before Congress; see: F-22 Aircraft: Progress of the Engineering and Manufacturing Development Program, by Louis J. Rodrigues, Director of Defense Acquisition Issues, before the Subcommittee on AirLand Forces, Senate Committee on Armed Services. GAO/T-NSIAD-98-137, Mar. 25 (seven pages).

GAO noted that: (1) the Air Force's estimate to complete F-22 EMD is $18.884 billion, $55 million less than the EMD cost limitation that will be adjusted to $18.939 billion; (2) however, the F-22 EMD program is not meeting schedule goals established in response to the Joint Estimating Team review; (3) the first flight of the F-22 was about 3 months late, issues have emerged concerning production and delivery of wings and fuselages for the EMD aircraft, and test schedules have consequently been delayed; (4) Lockheed Martin has indicated that negotiated costs should not be exceeded because of these issues; (5) the Air Force, however, is further assessing the impact of these issues on EMD cost, the schedule upon which test data is produced, and the schedule upon which the EMD program is to be completed; (6) the Air Force expects to complete this assessment at the end of February 1998; (7) the Air Force is estimating that the F-22 will meet or exceed its performance goals; (8) however, less flight test data have been accumulated through January 1998 than were expected because the beginning of the flight test program was delayed from May 1997 to September 1997 and flight tests have been suspended to accomplish planned ground tests and minor structural additions to the airframe; (9) flight testing will not resume until April 1998; and (10) delayed tests reduce the amount of actual F-22 performance information that will be available to support Air Force plans to begin production in fiscal year 1999.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.