Joint Strike Fighter Acquisition

Development Schedule Should Be Changed to Reduce Risks Gao ID: T-NSIAD-00-132 March 16, 2000

The Defense Department (DOD) has made the Joint Strike Fighter program a leading example of military acquisition reform. A key concept is to demonstrate, before moving into the engineering and manufacturing phase, that critical technologies, processes, and system characteristics are able to produce an affordable family of strike aircraft--one that meets all participants' needs. Once a weapons system enters the development phase, a large, fixed investment has already been made and any significant changes at that point will have a ripple effect on cost and schedule. Although GAO is encouraged by the design of the acquisition strategy for the Joint Strike Fighter, GAO has concerns about its implementation. GAO's biggest concern is that critical technologies are projected to be at low levels of technical maturity when the engineering and manufacturing development contract is scheduled to be awarded. Also, when the competing contractors experienced design problems and cost overruns, DOD restructured the program in a way that will provide less information than originally planned before selecting between the two competing contractors' proposals. GAO believes that program managers should continue to focus on risk-reduction efforts by maturing critical technologies before entering engineering and manufacturing development and be allowed to do so without the penalty of withdrawal of funding support.

GAO noted that: (1) the Joint Strike Fighter acquisition strategy is designed to meet affordability goals by reducing program risk before proceeding into the engineering and manufacturing development phase; (2) the acquisition strategy is designed to ensure a better match between the maturity of key technologies and the aircraft's requirements; (3) matching the requirements and the maturity of technology when a program enters engineering and manufacturing development (development phase) is a critical determinant of a program's success; (4) once the development phase begins, a large, fixed investment in the form of human capital, facilities, and materials is sunk into the program and any significant changes will have a large, rippling effect on schedule and cost; (5) beginning the development phase when critical technologies are at a low level of maturity serves to significantly increase program risk and the likelihood of schedule delays, which in turn result in increased program costs; (6) while GAO was encouraged by the design of the Joint Strike Fighter acquisition strategy, GAO has some concerns about its implementation; (7) GAO's biggest concern is that critical technologies are projected to be at low levels of technical maturity when the engineering and manufacturing development contract is scheduled to be awarded; (8) in addition, when the competing contractors experienced design problems and cost overruns, the Department of Defense (DOD) restructured the program in a manner that will provide less information than originally planned prior to selecting between the two competing contractor proposals; and (9) GAO believes that to demonstrate DOD's commitment to acquisition reform, follow best commercial practices, and reduce the risk of future cost growth, the Joint Strike Fighter program office should continue to focus on risk-reduction efforts by maturing critical technologies prior to entering engineering and manufacturing development, and be allowed to do so without the penalty of withdrawal of funding support.



The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.