Oregon Inlet Jetty Project

Environmental and Economic Concerns Need to Be Resolved Gao ID: GAO-02-803 September 30, 2002

Oregon Inlet is the primary route to the ocean for hundreds of commercial and recreational fishing vessels operating in the Outer Banks region of North Carolina. However, the inlet experiences more high winds, strong tides, and shifting sand than any other inlet on the coast of the United States. This high-energy environment often creates sand bars and large breaking waves at the inlet's entrance to the ocean, commonly known as the ocean bar. These conditions, especially when combined with the severe storms that frequent the area, can swamp a boat or run it aground, imperiling both life and property. During the past 19 years, the Army Corps of Engineers has had difficulty maintaining the ocean bar navigation channel at Oregon Inlet at its authorized 14-foot depth. Specifically, from 1983 through 1994, the Corps spent on average $4.1 million per year dredging the channel, but was only able to maintain the authorized 14-foot depth on average 23 percent of the time. After 1994, the Corps spent an average of $2 million per year, but the percentage of time the channel depth was maintained at its authorized depth declined to 15 percent. The Corps' most recent economic analysis of the proposed Oregon Inlet jetty project, issued in 2001, has several limitations, and as a result, does not provide a reliable basis for deciding whether to proceed with the project. Of the eight completed jetty projects constructed similarly to the proposed Oregon Inlet jetty project, two are generally performing as planned. Of the six other similar projects, three have required more dredging and higher maintenance costs than expected, and two have had their weirs closed. In designing the proposed Oregon Inlet jetty project, the Corps' Wilmington District Office applied lessons learned from the construction of similar jetty projects and from internal Corps guidance. Both the Department of Commerce and the Department of the Interior support the goal of providing a safe navigation channel through Oregon Inlet for commercial and recreational fishing vessels. However, both departments support a dredging-only approach to achieve that goal in an environmentally acceptable manner.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.