Tactical Aircraft
DOD Needs to Better Inform Congress about Implications of Continuing F/A-22 Cost Growth
Gao ID: GAO-03-280 February 28, 2003
In 1991, the Air Force began developing the F/A-22 aircraft with advanced features to make it less detectable to adversaries and capable of high speeds for long distances. After a history of program cost increases, Congress limited the cost of F/A-22 production to $37.5 billion in 1997. Congress has remained interested in the potential cost of production. As requested, we (1) identified the latest production cost estimate and assessed the planned offsets from cost reduction plans, (2) identified areas where additional cost growth is likely to occur, and (3) determined the extent that DOD has informed Congress about production costs.
The Department of Defense (DOD) has identified about $18 billion in estimated production cost growth over the last 6 years. Even though the Air Force has designed cost reduction plans to offset a significant amount of this estimated cost growth, DOD still estimates that the cost of production will exceed the cost limit established by Congress in 1997. Furthermore, the Air Force has not fully funded certain cost reduction plans called production improvement programs (PIPs), and as a result, these PIPs may not achieve their estimated $3.7 billion in offsets to cost growth. In addition to the cost growth estimated by DOD, GAO identified areas where, in the future, F/A-22 production cost growth is likely to occur. First, the Office of the Secretary of Defense's current production cost estimate does not include about $1.3 billion in costs that should be considered in future cost estimates. Second, schedule delays in developmental testing could delay the start of a multiyear contract designed to control costs. These delays could also result in additional costs owing to the expiration of an Air Force agreement with the contractor designed to help control production costs in fiscal year 2005. Last, other risk factors may increase future production costs, including the dependency of certain cost reduction plans on the availability of funding and a reduction in funding for support costs. DOD has not fully informed Congress (1) about what the total cost of the production program could be if cost reduction plans do not offset cost growth as planned or (2) about the aircraft quantity that can be procured within the production cost limit. If the cost limit is maintained and estimated production costs continue to rise, the Air Force will likely have to procure fewer F/A-22s.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-03-280, Tactical Aircraft: DOD Needs to Better Inform Congress about Implications of Continuing F/A-22 Cost Growth
This is the accessible text file for GAO report number GAO-03-280
entitled 'Tactical Aircraft: DOD Needs to Better Inform Congress about
Implications of Continuing F/A-22 Cost Growth' which was released on
March 13, 2003.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products‘ accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
Report to the Honorable John F. Tierney, House of Representatives:
United States General Accounting Office:
GAO:
February 2003:
TACTICAL AIRCRAFT:
DOD Needs to Better Inform Congress about Implications of Continuing F/
A-22 Cost Growth:
F/A-22F-22 Aircraft:
GAO-03-280:
GAO Highlights:
Highlights of GAO-03-280, a report to Representative John F. Tierney
Why GAO Did This Study:
In 1991, the Air Force began developing the F/A-22 aircraft with
advanced features to make it less detectable to adversaries and capable
of high speeds for long distances. After a history of program cost
increases, Congress limited the cost of F/A-22 production to $37.5
billion in 1997. Congress has remained interested in the potential cost
of production. As requested, we (1) identified the latest production
cost estimate and assessed the planned offsets from cost reduction
plans, (2) identified areas where additional cost growth is likely to
occur, and (3) determined the extent that DOD has informed Congress
about production costs.
What GAO Found:
The Department of Defense (DOD) has identified about $18 billion in
estimated production cost growth over the last 6 years. Even though
the Air Force has designed cost reduction plans to offset a
significant amount of this estimated cost growth, DOD still
estimates that the cost of production will exceed the cost limit
established by Congress in 1997. Furthermore, the Air Force has not
fully funded certain cost reduction plans called production
improvement programs (PIPs), and as a result, these PIPs may not
achieve their estimated $3.7 billion in offsets to cost growth.
In addition to the cost growth estimated by DOD, GAO identified
areas where, in the future, F/A-22 production cost growth is likely
to occur. First, the Office of the Secretary of Defense‘s current
production cost estimate does not include about $1.3 billion in
costs that should be considered in future cost estimates. Second,
schedule delays in developmental testing could delay the start of
a multiyear contract designed to control costs. These delays could
also result in additional costs owing to the expiration of an Air
Force agreement with the contractor designed to help control
production costs in fiscal year 2005. Last, other risk factors may
increase future production costs, including the dependency of
certain cost reduction plans on the availability of funding and a
reduction in funding for support costs.
DOD has not fully informed Congress (1) about what the total cost
of the production program could be if cost reduction plans do not
offset cost growth as planned or (2) about the aircraft quantity
that can be procured within the production cost limit. If the cost
limit is maintained and estimated production costs continue to rise,
the Air Force will likely have to procure fewer F/A-22s.
What GAO Recommends:
GAO recommends that the Air Force fund production improvement
programs at the planned level to maximize its potential for cost
reductions. To help ensure proper congressional oversight, GAO
recommends that DOD provide Congress with documentation (1) showing
that the Air Force is funding production improvement programs as
planned and (2) reflecting the potential cost of production if
offsets are not achieved as planned and the aircraft quantity that
can be procured with the cost limit.
DOD did not concur with GAO‘s recommendations. GAO believes that
DOD‘s position lessens the opportunity to create greater production
efficiencies and better inform Congress.
www.gao.gov/cgi-bin/getrpt?GAO-03-280.
To view the full report, including the scope
and methodology, click on the link above.
www.gao.gov/cgi-bin/getrpt?GAO-03-280.
To view the full report, including the scope
and methodology, click on the link above.
For more information, contact Allen Li at (202) 512-4841.
Contents:
Letter:
Results in Brief:
Background:
DOD‘s F/A-22 Estimated Production Costs Exceed Cost Limitation:
Estimated Production Costs Are Likely to Increase:
DOD Has Not Fully Informed Congress about Potential Impact of Reduced
Offsets to Estimated Cost Growth:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Scope and Methodology:
Appendix I: Comments from the Department of Defense:
Appendix II: Amounts Associated with Cost Reduction Plan Categories:
Appendix III: F/A-22 Estimated Production Cost Growth in 1997:
Appendix IV: Cost Reduction Plan Categories and Planned Offsets
to Estimated Cost Growth:
Appendix V: Estimated F/A-22 Production Cost Growth in 2001:
Appendix VI: Estimated Cost Reduction Plan Offsets for Future
Production
Lot Contracts:
Appendix VII: GAO Staff Acknowledgments:
Related GAO Products:
Tables:
Table 1: Comparison of Planned versus Implemented Cost Reduction Plan
Offsets for Awarded Production Contracts:
Table 2: F/A-22‘s Production Cost Growth Not Included in OSD‘s Latest
Estimate:
Table 3: Current Amounts Associated with Cost Reduction
Plan Categories:
Figures:
Figure 1: Planned versus Actual F/A-22 Production Improvement Program
Investment for Production Lots 1 and 2:
Figure 2: Planned Offsets to Cost Growth from Investing in and
Implementing Production Improvement Programs:
Abbreviations:
DAB: Defense Acquisition Board
DOD: Department of Defense
GAO: General Accounting Office
OSD: Office of the Secretary of Defense
PIPs: production improvement programs:
This is a work of the U.S. Government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. It may contain
copyrighted graphics, images or other materials. Permission from the
copyright holder may be necessary should you wish to reproduce
copyrighted materials separately from GAO‘s product.
United States General Accounting Office:
Washington, DC 20548:
February 28, 2003:
The Honorable John F. Tierney
House of Representatives:
Dear Mr. Tierney:
The Air Force is developing the F/A-22 aircraft[Footnote 1] with
advanced features designed to allow it to be less detectable to
adversaries, capable of high speeds for long ranges, and able to
provide the pilot with improved awareness of the surrounding
situation.[Footnote 2] Development of the aircraft, which started in
1991, is expected to be completed in early 2004. The Air Force approved
the start of low-rate production in August 2001.
Congress established a production cost limitation in the National
Defense Authorization Act for Fiscal Year 1998[Footnote 3] following a
history of program cost increases. The limitation, which allows for
inflation adjustments, is currently $37.5 billion.[Footnote 4] The act
does not specify the total number of aircraft to be procured for this
amount. During a high-level review by the Department of Defense‘s (DOD)
Defense Acquisition Board[Footnote 5] in August 2001, the Department of
Defense estimated that production program costs would be
$43 billion[Footnote 6] and therefore exceed the production cost limit
of $37.5 billion.
As requested, we reviewed the Air Force‘s F/A-22 production program and
the service‘s efforts to offset estimated production cost growth
through various cost reduction plans. Specifically, we (1) identified
the F/A-22‘s latest production cost estimate acknowledged by DOD,
including an assessment of the planned offsets from cost reduction
plans; (2) identified areas where additional cost growth is likely to
occur; and (3) determined the extent to which DOD has informed Congress
about the effect of not achieving cost reduction plans, particularly on
the number of aircraft that can be procured within the existing
production cost limit.
Results in Brief:
DOD has identified about $18 billion in estimated production cost
growth over the last 6 years. Even though the Air Force has designed
cost reduction plans to offset a significant amount of this estimated
cost growth, DOD still estimates that the cost of production will
exceed the cost limit of $37.5 billion established by Congress in 1997.
In addition, the Air Force has not fully funded certain cost reduction
plans; therefore, these plans may not achieve their planned offsets to
cost growth. For example, the Air Force has not been able to fully fund
improvements to production processes. As a result, the Air Force may
not be able to achieve the planned $3.7 billion in offsets from
improvements to production processes.
In addition to the cost growth estimated by DOD, we identified areas
where F/A-22 production cost growth is likely to occur in the future.
First, the current Office of the Secretary of Defense‘s production cost
estimate does not include about $1.3 billion in costs that should be
considered in future cost estimates. Second, schedule delays in
developmental testing could delay the award of a multiyear contract
designed to help control production costs. As a result of schedule
delays, the Air Force has already delayed the effective date of this
contract to fiscal year 2006. Consequently, the aircraft planned for
fiscal year 2005 will not be included in any agreements with the
contractor designed to help control production costs. Last, several
risk factors may increase future production costs, including the
dependency of certain cost reduction plans on the availability of
funding and a reduction in funding for support costs.
DOD has not fully informed Congress about the potential cost of the
production program if cost reduction plans do not offset cost growth as
planned. Moreover, DOD has not informed Congress about the quantity of
aircraft that can be procured within the existing production cost
limit. If the production cost limit is maintained and estimated
production costs continue to rise, the Air Force will likely have to
procure fewer than the 276 planned F/A-22s.
We are providing recommendations aimed at improving the Air Force‘s
implementation of cost reduction plans and enhancing congressional
oversight of the F/A-22 program. In written comments on a draft of this
report, DOD stated that it did not concur with our recommendations.
Background:
The F/A-22 is an air superiority[Footnote 7] aircraft with advanced
features to make it less detectable to adversaries (stealth
characteristics) and capable of high speeds for long ranges. It is
being developed under contracts with Lockheed Martin Corporation for
the aircraft and Pratt & Whitney Corporation for the engine.
Because of potential cost increases, the Air Force established a team-
-the Joint Estimating Team--to review the total estimated cost of the
F/A-22 program in 1996. This team reported that the cost of the F/A-22
production program could grow by $13.1 billion from the amount planned.
In response to identified cost growth, Congress, in the National
Defense Authorization Act for Fiscal Year 1998 established cost limits
for the development and production phases of the F/A-22 program. The
current production cost limit is $37.5 billion.
In August 2001, during a review by DOD‘s Defense Acquisition Board
(DAB), DOD estimated that the production program would cost
$43 billion, or $5.4 billion more than the production cost limit.
However, the two major parties involved in DAB, the Office of the
Secretary of Defense (OSD) and the Air Force, disagreed over how many
aircraft could be purchased for $43 billion. OSD believed that only 297
aircraft could be purchased for $43 billion while the Air Force
believed 333 aircraft could be purchased for the same amount. DOD
informed Congress of these divergent viewpoints in September 2001. The
F/A-22 President‘s Budget for fiscal year 2004 would transfer
$876 million in production funding and reduce the number of aircraft
to 276 to help fund estimated cost increases in development. As a
result, the current production cost estimate is $42.2 billion, an
amount that still exceeds the cost limit of $37.5 billion.
To fully offset the $13.1 billion in estimated cost growth, the Air
Force and contractors designed cost reduction plans. Since 1997, the
Air Force has been identifying and implementing these plans. (See
appendix IV for a list of the major categories of cost reduction plans
designed to offset the cost growth estimated in 1997.) A direct
relationship cannot be established between the cost reduction plans and
specific areas of cost growth. The reason is that the plans generally
offset cost growth in broad areas by enhancing production technology,
improving manufacturing techniques, and improving
acquisition practices.
F/A-22 cost reduction plans are categorized as either ’implemented“ or
’not yet implemented.“ The Air Force‘s and contractors‘ criteria for
determining if a cost reduction plan is implemented include whether:
* the contractor has submitted a firm, fixed price proposal that
recognizes the impact of the cost reduction;
* the impact of the reduction has been reflected in a current contract
price or negotiated in an agreement; or:
* the contractor has reduced the number of hours allocated to a task.
Currently, $14 billion in cost reduction plans is considered
’implemented.“:
Cost reduction plans are categorized as ’not yet implemented“ if the
plans are well defined but none of the criteria listed above are met.
Table 3 in appendix II shows the amounts the Air Force currently
considers ’implemented“ and ’not yet implemented.“:
DOD‘s F/A-22 Estimated Production Costs Exceed Cost Limitation:
Over the last 6 years, $17.7 billion in estimated production cost
growth has been identified during the course of two program reviews. As
a result, the estimated cost of the production program currently
exceeds the congressional cost limit despite the establishment of cost
reduction plans designed to offset a significant amount of this
estimated cost growth. The effectiveness of these cost reduction plans
has varied.
DOD‘s Estimates of Production Costs Have Risen:
During a review in 1997, the Air Force estimated cost growth of
$13.1 billion.[Footnote 8] The major contributing factors to this cost
growth were inflation, increased estimates of labor costs and materials
associated with the airframe and engine, and engineering changes to the
airframe and engine. These factors made up about 75 percent of the cost
growth identified in 1997. (See appendix III for a complete list of
cost growth categories identified in 1997.):
In August 2001, DOD estimated an additional $5.4 billion in cost growth
for the production of the F/A-22, bringing total estimated production
costs to $43 billion.[Footnote 9] The major contributing factors to
this cost growth were again due to increased labor costs and airframe
and engine costs. These factors totaled almost 70 percent of the cost
growth. According to program officials, major contractors‘ and
suppliers‘ inability to achieve the expected reductions in labor costs
throughout the building of the development and early production
aircraft has been the primary reason for estimating this additional
cost growth. (See appendix VI for a complete list of the categories and
sources of cost growth identified in 2001.):
Cost Reduction Plans Achieve Varied Results:
The effectiveness of cost reduction plans has varied. The Air Force
was able to implement cost reduction plans and offset cost growth in
the first four production lot contracts awarded.[Footnote 10] Air Force
projections for cost reduction plans show that expected offsets are
also planned for the future production lot contracts to enable the
production program to be completed within the current production cost
estimate. However, the Air Force has not fully funded production
improvement programs (PIPs), which are designed to offset cost growth
by improving production processes. Consequently, planned offsets may
not be achieved in the amount expected.
Implemented Cost Reduction Plans Are Offsetting Cost Growth:
The Air Force was able to implement cost reduction plans and offset
cost growth in the first four production contracts awarded. The total
offsets for these contracts slightly exceeded earlier projections by
about $0.5 million. Table 1 compares previous planned offsets with
implemented cost reduction plan offsets in the first four production
contracts.
Table 1: Comparison of Planned versus Implemented Cost Reduction Plan
Offsets for Awarded Production Contracts:
Dollars in millions.
Fiscal year 1999 (2 aircraft); Planned
offsets: $199.0; Implemented
offsets: $200.5; Difference: $1.5.
Fiscal year 2000 (6 aircraft); Planned
offsets: 329.3; Implemented
offsets: 336.4; Difference: 7.1.
Fiscal year 2001 (10 aircraft); Planned
offsets: 580.2; Implemented
offsets: 611.1; Difference: 30.9.
Fiscal year 2002 (13 aircraft); Planned
offsets: 827.2; Implemented
offsets: 788.2; Difference: (39.0).
Total; Planned
offsets: $1,935.7; Implemented
offsets: $1,936.2; Difference: $0.5.
Source: U.S. Air Force.
[End of table]
Cost reduction plans exist but have not yet been implemented for
subsequent production lots planned for fiscal years 2003 through 2010
because contracts for these production lots have not yet been awarded.
If implemented successfully, the Air Force expects these cost reduction
plans to achieve billions of dollars in offsets to estimated cost
growth and allow the production program to be completed within the
current production cost estimate of $43 billion.[Footnote 11] However,
as we noted earlier in this report, this amount exceeds the
congressionally imposed production cost limit of $37.5 billion.
Not Fully Funding Production Improvement Programs May Reduce Expected
Offsets:
A production improvement program is a type of cost reduction
plan whereby the government must make an initial investment to realize
savings. The earlier the Air Force implements PIPs, the greater the
impact on the cost of production. Examples of PIPs previously
implemented by the Air Force include manufacturing process improvements
for avionics, improvements in the fabrication and assembly processes
for the airframe, and the redesign of several components to enable
lower production costs.
The Air Force reduced the funding available for investment in PIPs
because of cost growth in production lots 1 and 2.[Footnote 12] The Air
Force subsequently used funding that it planned to invest in PIPs to
cover the cost growth in production lots 1 and 2. As a result, there
has not been as much funding available for investment in these PIPs as
planned. Figure 1 shows that funding was reduced $61 million in fiscal
year 2001 and $26 million in fiscal year 2002.
Figure 1: Planned versus Actual F/A-22 Production Improvement Program
Investment for Production Lots 1 and 2:
[See PDF for image]
[End of figure]
It is unlikely that the Air Force will achieve the estimated
$3.7 billion in cost growth offsets from the implementation of these
PIPs if investment continues to be less than planned. Figure 2 shows
the remaining planned investment in PIPs through fiscal year 2006 and
the $3.7 billion in estimated cost growth that can potentially be
offset through fiscal year 2010 if the Air Force invests as planned in
these PIPs.
Figure 2: Planned Offsets to Cost Growth from Investing in and
Implementing Production Improvement Programs:
[See PDF for image]
[End of figure]
In the past, Congress has been concerned about the Air Force‘s practice
of requesting fiscal year funding for these PIPs but then using part of
that funding for F/A-22 airframe cost increases. Recently, Congress
directed the Air Force to submit a request if it plans to use PIP funds
for an alternate purpose.
Estimated Production Costs Are Likely to Increase:
We found indications that, in the future, F/A-22 production costs are
likely to increase more than the latest $5.4 billion in cost growth
recently estimated by the Air Force and OSD. First, the current OSD
production estimate does not include all costs. Second, schedule delays
in developmental testing could delay the start of a multiyear contract
designed to help control production costs. Third, as a result of
schedule delays that have already occurred, the Air Force has already
delayed the awarding of this contract to fiscal year 2006. As a
consequence, the aircraft planned for fiscal year 2005 are not
currently included in any agreements with the contractor that are
designed to help control production costs. Last, we found several risk
factors that may increase future production costs, including the
dependency of certain cost reduction plans on congressional action and
a reduction in funding for support costs.
Current OSD Production Cost Estimate Does Not Include All Costs:
OSD‘s latest cost estimate does not include costs identified by the
Air Force during the development of the Air Force‘s current F/A-22
acquisition plan. The Air Force developed this acquisition plan after
OSD completed its estimate. Table 2 shows some areas of additional
costs that the Air Force believes the program will incur.
Table 2: F/A-22‘s Production Cost Growth Not Included in OSD‘s Latest
Estimate:
Dollars in millions.
Reason for cost growth: Delayed award of multiyear contract; Cost
growth: $390.
Reason for cost growth: Inflation increases because new acquisition
plan delays some early
aircraft purchases; Cost growth:
350.
Reason for cost growth: Decreased savings expected from Joint Strike
Fighter program[A]; Cost
growth: 300.
Reason for cost growth: Change in avionics subcontractor; Cost growth:
250.
Total; Cost growth: $1,290.
Source: GAO‘s analysis of Air Force and OSD Cost Analysis Improvement
Group data.
[A] Resulting from changes in the prime contractor‘s accounting system
and the calculation of overhead costs.
[End of table]
According to an OSD official, these additional costs should be
considered in any future OSD production cost estimate, which would
increase OSD‘s estimate by $1.29 billion.
Additional Program Delays May Further Delay Multiyear Procurement:
If the F/A-22‘s developmental testing program experiences additional
delays, there is a greater risk that operational testing, full-rate
production, and multiyear procurement will be delayed as a result.
Delays in production and multiyear procurement would likely increase
production costs. The Air Force has not addressed ongoing problems with
the developmental testing and therefore remains at high risk for
further schedule delays.
For example, in March 2002, we reported that the Air Force‘s plan to
complete the developmental airframe testing necessary for the start of
operational testing was at high risk because (1) the planned number of
test objectives per flight-hour was not being achieved and (2) most of
the planned flight-test program was essentially being performed by only
one test aircraft rather than the three originally planned.[Footnote
13] Air Force officials told us they understood that completing the
tests as scheduled with only one development test aircraft was high
risk. As a result of this strategy, in late 2001, the Air Force delayed
the F/A-22‘s schedule, including the start of a multiyear contract
designed to save production costs.
Acquisition Plan Contains Gap in Methods to Control Costs:
The cost of the fiscal year 2005 production lot could increase because
it is currently not included in plans to help control production costs.
In late 1996, as part of a major program review, the Air Force and
major F/A-22 contractors entered into a Target Price Curve agreement
designed to help reduce production costs and ensure production
affordability. The agreement established production cost goals for the
first five production lots (fiscal years 1999-2003) and provided the
contractors with incentives if they achieved these cost goals.
Previously, the Air Force planned to transition directly to multiyear
procurement starting with the next production lot. However, since the
Air Force delayed the start of multiyear procurement from fiscal year
2004 to fiscal 2006, fiscal 2005 is now not covered by either the
agreement with the contractor or the planned multiyear procurement
contract. Therefore, there is less assurance that the cost of the
fiscal year 2005 production lot will match the current estimate for
this production lot. If a method to help control costs is not
implemented for the fiscal year 2005 production lot, the cost of this
production lot could increase more than expected.
Other Factors Could Increase Future Production Costs:
We found several additional risk factors that may increase production
costs in the future. As we have also previously reported, the Air Force
is depending on both multiyear procurement and the Joint Strike
Fighter initiatives to achieve offsets to estimated cost
growth.[Footnote 14] Multiyear procurement, because of the cost
reductions available through long-term commitments such as a 5-year
contract, make it possible for the contractors and subcontractors to
charge lower prices for the aircraft being procured. Joint Strike
Fighter-related savings are planned because the Air Force plans to use
many of the same contractors and subcontractors as with the Joint
Strike Fighter in the F/A-22 program, thereby lowering overhead rates
and increasing buying power.
Even though the Air Force is depending on both the multiyear
procurement and Joint Strike Fighter initiatives to achieve offsets to
estimated cost growth, approval to proceed with multiyear procurement
is determined from the availability of funding.[Footnote 15] Thus, if
entry into a multiyear procurement contract does not occur as planned,
offsets from the implementation of multiyear procurement cannot be
achieved. Similarly, the success of the Joint Strike Fighter cost
reduction plan is dependent on the schedule of the Joint Strike Fighter
program and the quantity of the aircraft procured, which are determined
by Congress and OSD. In an earlier report, we cautioned that if the
Joint Strike Fighter program were not approved or were delayed, then
the F/A-22 production program would not achieve the estimated cost
reductions.[Footnote 16]
Furthermore, the Air Force reduced estimated funding for F/A-22 support
costs by $1.8 billion in its latest production cost estimate. Support
costs are for such items as spare components for the aircraft and
engines, spare engines, and equipment used to support and maintain
aircraft. F/A-22 program officials explained that the latest support
costs estimate is a detailed, requirements-based estimate that is more
accurate than previous estimates, but they could not provide us with
the detailed rationale for this new estimate. At the same time, we also
observed that the Air Force added about $1.8 billion to the estimated
production costs associated with the aircraft and engine. If it is
determined the F/A-22 program will require the same level of support
cost funding identified by the Defense Acquisition Board‘s review, the
production cost estimate will increase.
DOD Has Not Fully Informed Congress about Potential Impact of Reduced
Offsets to Estimated Cost Growth:
DOD has not fully informed Congress about specifics related to the
total cost of the F/A-22 production program or the quantity of aircraft
that can be purchased within the cost limitation. DOD uses selected
acquisition reports and the President‘s budget submissions to inform
Congress about weapon systems programs.[Footnote 17] Since 1999,
neither the F/A-22 selected acquisition reports nor the President‘s
annual budget submissions to Congress have included details about the
amount of cost reduction plans identified to offset cost growth. More
importantly, these documents have not included the potential cost of
the F/A-22 production program if cost reduction plans do not offset
cost growth as planned. From 1996 to 1998, selected acquisition reports
did inform Congress about the potential cost of production if cost
reduction plans did not offset cost growth as planned. If cost growth
is not offset as planned, the cost of F/A-22 production could be
several billion dollars higher than currently estimated.
Furthermore, recent documentation, including the latest selected
acquisition report (December 2001) and Fiscal Year 2003 President‘s
Budget submission have also not provided Congress with information
about the quantity of aircraft DOD believes can be procured under the
existing production cost limitation. Even though the production cost
limitation remains, as adjusted, at $37.5 billion, the official
documentation provided to Congress to date has not provided the number
of aircraft that can be purchased for this amount. Even at the higher
cost estimate of $43 billion,[Footnote 18] OSD and the Air Force have
not been able to agree on the aircraft quantity that can be purchased.
In July 2001, we projected that the Air Force would have to buy 85
fewer F/A-22s rather than the 333 that it planned to buy to stay within
the cost limit.[Footnote 19]
Conclusions:
Despite the success of early cost reduction plans, we identified
estimated cost growth beyond the amounts recognized by the Air Force
and DOD. Therefore, it is important for the Air Force to take advantage
of every opportunity to offset cost growth. PIPs can be an important
mechanism for offsetting this cost growth. However, the Air Force is
not investing funding as planned in F/A-22 PIPs designed to offset
estimated cost growth. The failure to invest in PIPs at the planned
level will likely not allow estimated cost growth to be offset as
planned and therefore may affect the quantity of aircraft that can be
acquired.
The F/A-22 production program has experienced a number of schedule
delays and problems that have increased the estimated costs of a
program that already requires a significant investment. DOD has not
fully informed Congress about the amount of cost reduction plans
identified to offset cost growth, the potential cost of production if
cost reduction plans are not as effective as planned, or the quantity
of aircraft that can be produced within the production cost limit.
Congress would be able to utilize this information to help exercise
proper program oversight.
Recommendations for Executive Action:
For the Air Force to achieve planned offsets to estimated cost growth,
we recommend that the Secretary of the Air Force make the funding of
PIPs at the planned level a priority.
To ensure proper congressional oversight of the F/A-22 program, we
also recommend that the Secretary of Defense provide Congress with
documentation:
* showing that funding for PIPs is being invested at the planned level
each fiscal year, and if not, explaining the reasons why and the
potential consequences of not fully investing and potentially not
offsetting cost growth as planned;
* reflecting the potential cost of F/A-22 production if cost reduction
plans do not offset cost growth as planned; and:
* reflecting the quantity of aircraft DOD believes can be procured with
the existing production cost limit.
Agency Comments and Our Evaluation:
In written comments on a draft of this report, DOD stated that it did
not concur with either of our recommendations. Regarding our first
recommendation on making investments in PIPs a priority, DOD said
that while it believes that PIP investments in general are a good idea,
the Department intends to implement PIPs on a case-by-case basis, using
expected return-on-investment criteria. DOD also commented that our
report does not provide evidence that investments in PIPs reduce costs.
Our recommendation that the Air Force make the funding of PIPs at
the planned level a priority is based on evidence from both the
Air Force and OSD that investment in PIPs at the planned level will
generate a significant return-on-investment. In addition, during the
course of our review, Air Force officials told us they planned to make
up for not fully investing in PIPs during the last 2 fiscal years by
investing more in subsequent years in order to achieve the planned
savings. The Air Force‘s plan appears to recognize that it has moved
beyond a case-by-case approach. Our recommendation would support such a
plan. Finally, the reluctance to embrace PIPs in DOD‘s comments appears
to be contrary to the position taken within the Department. The
potential benefits of investing in PIPs continue to be highlighted in
high-level F/A-22 meetings[Footnote 20] and correspondence to Congress.
A September 2001 letter to Congress from the Under Secretary of Defense
for Acquisition, Technology and Logistics estimates that the quantity
of F/A-22 aircraft will need to be reduced, but more aircraft can be
procured if cost reduction plans (which include PIPs) prove more
successful than OSD‘s estimates. We believe our recommendation to make
the funding of PIPs at the planned level a priority puts DOD in a
better position to enhance the affordability of the F/A-22. Conversely,
by not funding PIPs at the planned level, DOD may lose opportunities to
create greater production efficiencies and as a result, have to acquire
fewer aircraft.
Regarding our second recommendation related to providing documentation
to Congress on cost reduction plans, the implications of not investing
in PIPs as planned, and the aircraft quantities that can be acquired
within the existing production cost limit, DOD stated that our
recommendation is inconsistent with its decision to use a ’buy-to-
budget“ approach for the F/A-22 (buying the highest quantity of
aircraft possible each year on the basis of appropriated funding each
year). DOD also stated that providing this information to Congress
would not provide a reliable projection of the number of aircraft
possible because (1) there are other factors that affect cost and (2)
the projected savings are uncertain and may not materialize as the
estimator expects.
We continue to believe that the Secretary of Defense should provide
Congress with this documentation. As we have discussed in this and
several earlier reports,[Footnote 21] we agree that there are indeed
many factors that can cause F/A-22 production costs to rise. And, as we
have also noted, projected offsets generated by PIPs and other cost
reduction plans are uncertain and may not all materialize, even if
investments are made as planned. Shifts in these realities are frequent
and create a constantly changing picture of F/A-22 production costs,
offsets, and aircraft quantities. This is particularly the case when
PIP investments are not made as planned. Hence, it is important that
updated and accurate information be regularly and routinely made
available to Congress as the picture changes. DOD‘s argument that it is
implementing a ’buy-to-budget“ approach makes our recommendation more
compelling because aircraft quantities planned each fiscal year can
change in the few months between when fiscal year funding is
appropriated and when a production contract is negotiated with the
prime contractor and awarded. Providing visibility to the projection of
how many aircraft can be acquired within the cost limitation would
enhance program oversight.
DOD has several extant reporting options that can be used to provide
this information. A new report is not required. For example, DOD could
return to its former practice of using annual selected acquisition
reports to inform Congress about the potential cost of production if
cost reduction plans do not offset cost growth as planned. This
information was included in these reports from 1996 to 1998. In
addition, the President‘s Budget submission could be used as a vehicle
to provide Congress with updated information about the quantity of
aircraft DOD believes can be acquired under the existing production
cost limitation. Finally, requests to reprogram PIP investment funds
could be expanded to include this information along with justification
for PIP reprogramming.
Scope and Methodology:
To identify the F/A-22 production cost growth, we examined documents
related to the Joint Estimating Team‘s review completed in January 1997
and received clarification on some review conclusions from the F/A-22
program office. We also reviewed documentation and discussed with
program officials the results of the 2001 F/A-22 Defense Acquisition
Board‘s review that estimated $5.4 billion more in production cost
growth.
To evaluate the planned effectiveness of cost reduction plans designed
to offset production cost growth, we assessed the reliability of a
contractor‘s and the Air Force‘s database on cost reduction plans to
ensure that the data were complete, sufficient, and relevant to our
work. We reviewed information from this database on implemented and not
yet implemented cost reduction plans. We compared estimated cost
reduction plan offsets from fiscal years 2000 and 2002 to determine
current versus planned estimated offsets for F/A-22 production lots. We
also analyzed cost information from the Air Force to determine the
amount of planned and actual funding invested in PIPs designed to
offset estimated cost growth by improving production processes.
To identify areas where additional production cost growth has occurred
and may occur, we reviewed several aspects of the F/A-22 program that
were likely to contribute to future cost growth. We examined previous
and current OSD and Air Force production cost estimates, expected
delays in the F/A-22 program‘s completion of operational testing,
aircraft unit price estimates and controls, and funding for support
costs.
To evaluate the degree to which DOD has informed Congress about the
potential cost of F/A-22 production, we examined the content of recent
official documentation (selected acquisition reports and President‘s
budgets) provided to Congress and compared them with required content
and content that would be expected considering the congressionally
imposed F/A-22 production cost limitation.
In performing our work, we obtained information or interviewed
officials from the Office of the Secretary of Defense, Washington D.C.;
the F/A-22 Program Office, Wright-Patterson Air Force Base, Ohio; and
the Defense Contract Management Agency, Marietta, Georgia. We performed
our work from March 2002 through February 2003 in accordance with
generally accepted government auditing standards.
As agreed with your office, unless you publicly announce the contents
of this report earlier, we plan no further distribution of it until 30
days from the date of this report. At that time, we will send copies to
interested congressional committees; the Secretary of Defense; the
Secretary of the Air Force; and the Director, Office of Management and
Budget. We will also make copies available to others upon request. In
addition, the report will be available at no charge on the GAO Web site
at http://www.gao.gov.
Please contact me at (202) 512-4841 or Catherine Baltzell at (202) 512-
8001 if you or your staff have any questions concerning this report.
Major contributors to this report are listed in appendix VII.
Sincerely yours,
Allen Li
Director
Acquisition and Sourcing Management:
Signed by Allen Li:
[End of section]
Appendix I: Comments from the Department of Defense:
ACQUISITION, TECHNOLOGY AND LOGISTICS:
OFFICE OF THE UNDER SECRETARY OF DEFENSE:
3000 DEFENSE PENTAGON WASHINGTON, DC 20301-3000:
24 JAN 2003
Mr. Allen Li:
Director, Acquisition and Sourcing Management U.S. General Accounting
Office:
441 G Street, NW Washington, D.C. 20548:
Dear Mr. Li:
This is the Department of Defense‘s (DoD) response to the General
Accounting Office‘s Draft Report, GAO-03-280, ’TACTICAL AIRCRAFT: F/A-
22 Production Cost Growth Continues Despite Some Effective Offsetting
Efforts,“ Dated December 13, 2002 (GAO Code 120128). The Department
appreciates the opportunity to comment on the draft report.
The Under Secretary of Defense (Acquisition, Technology and Logistics)
has targeted, and continues to address, cost control as a key oversight
issue on the F/A-22 program. The GAO‘s report, however, fails to
provide credible evidence that investments in Production Improvement
Programs (PIPS) reduce costs. The Department intends to implement PIPS
on a case-by-case basis, using expected return-on-investment criteria,
rather than using a generalized formula that is not sufficient across
the wide range of projects.
The GAO‘s report makes two recommendations. The Department does not
concur with Recommendation 1 which requires the Secretary of the Air
Force to make funding of the PIPs at the planned level a priority,
because there is no evidence to support this recommendation, and its
implementation, therefore, would not be prudent. Recommendation 2
requires the Secretary of Defense to provide documentation to Congress
concerning investment in PIPs, and the consequences of any decision not
to invest in PIPs. The Department does not concur with this
recommendation because it would require the Secretary to submit
redundant reports, since justification already is required as a part of
a request to reprogram funds designated for PIPs.
The Department believes that focusing F/A-22 program cost management on
the PIPs is too narrow. The absence of a measurable, direct cause-and-
effect relationship between the PIP investments and production costs
does not support the GAO‘s recommendations.
Detailed comments regarding the recommendation are enclosed. The
Department is prepared to discuss these comments with you in more
detail should you desire.
Sincerely,
Glenn F. Lamartin, Director:
Strategic and Tactical Systems:
Enclosure:
GENERAL ACCOUNTING OFFICE DRAFT REPORT Dated December 13, 2002 (GAO-03-
280/GAO Code 120128):
’TACTICAL AIRCRAFT: F/A-22 Production Cost Growth Continues Despite
Some Effective Offsetting Efforts“:
DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS:
RECOMMENDATION 1: The GAO recommended that the Secretary of the Air
Force make the funding of production improvement plans (PIPs) at the
planned level a priority. (Draft Report/p. 19):
DOD RESPONSE: Non Concur. The Department believes that there is no
evidence to support this recommendation. The future PIP-related cost
savings of $3.7 billion appear to be based on a 15:1 return on
investment (from the data presented in Figure 2, page 11). The specific
source of these data is not provided. We believe that the PIP
investments in general are a good idea, and they should be funded based
upon expected return-on-investment criteria.
RECOMMENDATION 2: The GAO recommended that the Secretary of Defense
provide documentation to Congress a) showing that funding for PIPS is
being invested at the planned level each fiscal year, and if not,
provide an explanation to Congress on the reasons why and the potential
consequences, and b) reflecting both the potential cost of F/A-22
production if cost reduction plans do not offset cost growth as planned
and the quantity of aircraft DOD believes can be procured with the
existing production cost limit. (Draft Report/p. 19):
DOD RESPONSE: Non Concur. Part (a) of the recommendation would create
redundant reporting requirements, given that the conferees from the
appropriations committees, in the conference report regarding the
Department of Defense Appropriations Act, 2003, directed the Air Force
to submit a request for reprogramming to use PIP funds for alternate
purposes (page 12 of the draft report). That request must include a
justification for the Air force‘s decision not to use these funds for
investments in PIPs. There is no reason that the Air Force and the
Secretary of Defense should provide reports that contain essentially
identical information. Part (b) of the recommendation is inconsistent
with the Department‘s August 2001 decision to approve a ’buy-to-budget“
approach for F/A-22, and reflects the GAO‘s failure to recognize that
other factors can cause costs to rise. Any report would, of necessity,
be based on either the Air Force‘s or the contractor‘s projection of
savings. However, this estimate would not provide a reliable
projection of the number of aircraft possible because (a) there
are other factors that impact cost such as: prime labor and materials
costs, supplier pricing strategies, economic order quantities, and
uncertainty of the F/A-22 development program, and (b) the projected
savings are uncertain and may not materialize as the estimator
expects.
[End of section]
Appendix II: Amounts Associated with Cost Reduction Plan Categories:
F/A-22 cost reduction plans are categorized as either ’implemented“
or ’not yet implemented.“ The Air Force and contractors‘ criteria for
determining if a cost reduction plan is implemented include (1) whether
the contractor has submitted a firm-fixed price proposal that
recognizes the impact of the cost reduction, (2) whether the impact of
the reduction has been reflected in a current contract price or
negotiated in an agreement, or (3) whether the contractor has reduced
the number of hours allocated to a task.
Cost reduction plans are categorized as ’not yet implemented“ if the
plans are well defined but none of the criteria listed above are met.
Table 3: Current Amounts Associated with Cost Reduction
Plan Categories:
Dollars in billions.
Cost reduction plan category: Implemented; Amount: $14.0.
Cost reduction plan category: Not yet implemented; Amount: 13.3.
Total; Amount: $27.3.
Source: U.S. Air Force.
[End of table]
[End of section]
Appendix III: F/A-22 Estimated Production Cost Growth in 1997:
Dollars in billions.
Category of cost growth: Inflation; Source of cost growth: Inflation;
Cost growth: $5.8; Cost growth as a percentage: 43.3.
Category of cost growth: Airframe labor and materials; Source of cost
growth: Increased estimates of the cost of labor and materials; Cost
growth: 2.4; Cost growth as a percentage: 17.9.
Category of cost growth: All categories; Source of cost growth:
Increase in fee provided to contractor; Cost growth: 1.1; Cost growth
as a percentage: 8.2.
Category of cost growth: Airframe and engine; Source of cost growth:
Engineering changes to airframe and engine; Cost growth: 1.8; Cost
growth as a percentage: 13.4.
Category of cost growth: Analysis and integration of components and
training; Source of cost growth: Increased costs associated with
analysis and integration of aircraft components; Cost growth:
0.6; Cost growth as a percentage: 4.5.
Category of cost growth: Defensive countermeasure and a classified
program; Source of cost growth: Funding for defensive countermeasures
and a classified program; Cost growth: 0.6; Cost growth as a
percentage: 4.5.
Category of cost growth: Equipment provided to contractor by the
government and equipment used to support the aircraft; Source of cost
growth: Increased costs of equipment; Cost growth: 0.4; Cost growth
as a percentage: 3.0.
Category of cost growth: Avionics; Source of cost growth: Increased
cost associated with buying large quantities of parts that industry
may not continue to produce; Cost growth: 0.3; Cost growth as a
percentage: 2.2.
Category of cost growth: Aircraft utilities and subsystems; Source of
cost growth: Increased estimate of the cost to produce aircraft
utilities and subsystems; Cost growth: 0.2; Cost growth
as a percentage: 1.5.
Category of cost growth: Contractor costs; Source of cost growth:
Increased estimate of the cost of contractor support; Cost growth:
0.1; Cost growth as a percentage: 0.7.
Category of cost growth: Mission support requirements; Source of
cost growth: Increased estimate for mission support requirements;
Cost growth: 0.1; Cost growth as a percentage: 0.7.
Total cost growth (aircraft): Engine and materials; Source of cost
growth: Not purchasing a training engine and outsourcing a wiring
harness; Cost growth: (0.2); Cost growth as a percentage: [Empty].
Net cost growth[A]; Source of cost growth: [Empty]; Cost growth:
$13.1[B]; Cost growth as a percentage: [Empty].
Source: U.S. Air Force.
[A] Based on a plan to procure 438 aircraft.
[B] Does not add because of rounding.
[End of table]
[End of section]
Appendix IV: Cost Reduction Plan Categories and Planned Offsets
to Estimated Cost Growth:
Dollars in billions.
Cost production plan category: Lean manufacturing--Improving
manufacturing processes and
incorporating new technology; Planned offsets to estimated cost
growth: Dollar amount: $9.1; Planned offsets to estimated cost
growth: Percentage: 33.7.
Cost production plan category: Production improvement programs--
Improving production processes; Planned offsets to estimated cost
growth: Dollar amount: 8.4; Planned offsets to estimated cost
growth: Percentage: 30.8.
Cost production plan category: Acquisition reform--Applying
performance-based contracting practices;
Planned offsets to estimated cost growth: Dollar amount: 0.5;
Planned offsets to estimated cost growth: Percentage: 2.9.
Cost production plan category: Material efficiencies--Improving
material procurement strategies;
Planned offsets to estimated cost growth: Dollar amount: 1.0;
Planned offsets to estimated cost growth: Percentage: 3.7.
Cost production plan category: Diminishing manufacturing
sources--Resolving obsolescence and diminishing sources issues;
Planned offsets to estimated cost growth: Dollar amount: 1.5;
Planned offsets to estimated cost growth:
Percentage: 5.5.
Cost production plan category: Production support--Defer or avoid
government investment in depot
maintenance capability; Planned offsets to estimated cost growth:
Dollar amount: 3.0; Planned offsets to estimated cost growth:
Percentage: 11.0.
Cost production plan category: Multiyear procurement--Award a
production contract for multiple years;
Planned offsets to estimated cost growth: Dollar amount: 2.2;
Planned
offsets to estimated cost growth: Percentage: 8.1.
Cost production plan category: Joint Strike Fighter--Manufacturing
Joint Strike Fighter and F/A-22
components in the same plants; Planned offsets to estimated cost
growth: Dollar amount: 1.1; Planned offsets to estimated cost
growth:
Percentage: 4.0.
Cost production plan category: Strategic sourcing--Procurement
initiatives to identify suppliers to reduce costs; Planned offsets
to estimated cost growth: Dollar amount: 0.3; Planned offsets to
estimated cost growth: Percentage: [Empty].
Cost production plan category: Additional learning--Various methods
and process improvements; Planned offsets to estimated cost growth:
Dollar amount: 0.1; Planned offsets to estimated cost growth:
Percentage: [Empty].
Total; Planned offsets to estimated cost growth: Dollar amount:
$27.3[A]; Planned offsets to estimated cost growth: Percentage:
100[A].
Source: U.S. Air Force.
[A] Does not add because of rounding.
[End of table]
[End of section]
Appendix V: Estimated F/A-22 Production Cost Growth in 2001:
Dollars in billions.
Airframe and engine; Source of cost growth: Increased estimated labor
costs of prime contractors and subcontractors; Cost
growth: $4.60; Cost growth as a percentage: 69.
Inflation; Source of cost growth: Adjustments for inflation; Cost
growth: 0.95; Cost growth as a percentage: 14.
Risk; Source of cost growth: Increased estimate for risk; Cost
growth: 0.50; Cost growth as a percentage: 8.
Avionics; Source of cost growth: Change in contractor required revised
cost estimate; Cost growth: 0.25; Cost growth as a percentage: 4.
Tools to produce airframe and engine; Source of cost growth: Increase
in production rate required more tooling; Cost growth: 0.20;
Cost growth as a percentage: 3.
Other government costs; Source of cost growth: Production of pilot
helmet designed to help fire short-range missiles more effectively;
Cost growth: 0.14; Cost growth as a percentage: 2.
Total cost growth; Source of cost growth: [Empty]; Cost
growth: $6.64; Cost growth as a percentage: 100.
Spare parts; Source of cost growth: Reassessment of quantity of spare
parts needed; Cost growth: (0.80)[A]; Cost growth as a
percentage: [Empty].
Production rate savings; Source of cost growth: Lowered production rate
charges by using new accounting system; Cost growth:
(0.30)[A]; Cost growth as a percentage: [Empty].
Cost reduction plans; Source of cost growth: Change is estimated offset
amount; Cost growth: (0.13)[A]; Cost growth as a percentage: [Empty].
Net cost growth; Source of cost growth: [Empty]; Cost
growth: $5.40[B]; Cost growth as a
percentage: [Empty].
Source: U.S. Air Force.
[A] Expected offsets to estimated cost growth.
[B] DOES NOT ADD BECAUSE OF ROUNDING] .
[End of table]
[End of section]
Appendix VI: Estimated Cost Reduction Plan Offsets for Future
Production
Lot Contracts:
Dollars in billions.
Lot 3 (fiscal year 2003); Estimated offsets: $1.1.
Lot 4 (fiscal year 2004); Estimated offsets: 1.5.
Lot 5 (fiscal year 2005); Estimated offsets: 1.9.
Lot 6 (fiscal year 2006); Estimated offsets: 2.5.
Lot 7 (fiscal year 2007); Estimated offsets: 2.9.
Lot 8 (fiscal year 2008); Estimated offsets: 2.8.
Lot 9 (fiscal year 2009); Estimated offsets: 2.8.
Lot 10 (fiscal year 2010); Estimated offsets: 1.7.
Total; Estimated offsets: $17.2.
Source: U.S. Air Force.
[End of table]
[End of section]
Appendix VII: GAO Staff Acknowledgments:
Acknowledgments:
Catherine Baltzell, Marvin Bonner, Edward Browning, Gary Middleton,
Sameena Nooruddin, Robert Pelletier, and Don M. Springman made key
contributions to this report.
[End of section]
Related GAO Products:
Tactical Aircraft: F-22 Delays Indicate Initial Production Rates Should
Be Lower to Reduce Risks. GAO-02-298. Washington, D.C.: March 5, 2002.
Tactical Aircraft: Continuing Difficulty Keeping F-22 Production Costs
within the Congressional Limitation. GAO-01-782. Washington, D.C.:
July 16, 2001.
Tactical Aircraft: F-22 Development and Testing Delays Indicate Need
for Low-Rate Production. GAO-01-310. Washington, D.C.: March 15, 2001.
Defense Acquisitions: Recent F-22 Production Cost Estimates
Exceeded Congressional Limitation. GAO/NSIAD-00-178. Washington, D.C.:
August 15, 2000.
Defense Acquisitions: Use of Cost Reduction Plans in Estimating
F-22 Total Production Costs. GAO/T-NSIAD-00-200. Washington, D.C.:
June 15, 2000.
Budget Issues: Budgetary Implications of Selected GAO Work for
Fiscal Year 2001. GAO/OCG-00-8. Washington, D.C.: March 31, 2000.
F-22 Aircraft: Development Cost Goal Achievable If Major Problems Are
Avoided. GAO/NSIAD-00-68. Washington, D.C.: March 14, 2000.
Defense Acquisitions: Progress in Meeting F-22 Cost and Schedule Goals.
GAO/T-NSIAD-00-58. Washington, D.C.: December 7, 1999.
Fiscal Year 2000 Budget: DOD‘s Procurement and RDT&E Programs. GAO/
NSIAD-99-233R. Washington D.C.: September 23, 1999.
Budget Issues: Budgetary Implications of Selected GAO Work for
Fiscal Year 2000. GAO/OCG-99-26. Washington, D.C.: April 16, 1999.
Defense Acquisitions: Progress of the F-22 and F/A-18E/F Engineering
and Manufacturing Development Programs. GAO/T-NSIAD-99-113.
Washington, D.C.: March 17, 1999.
F-22 Aircraft: Issues in Achieving Engineering and Manufacturing
Development Goals. GAO/NSIAD-99-55. Washington, D.C.: March 15, 1999.
F-22 Aircraft: Progress of the Engineering and Manufacturing
Development Program. GAO/T-NSIAD-98-137. Washington D.C.:
March 25, 1998.
F-22 Aircraft: Progress in Achieving Engineering and Manufacturing
Development Goals. GAO/NSIAD-98-67. Washington, D.C.: March 10, 1998.
Tactical Aircraft: Restructuring of the Air Force F-22 Fighter Program.
GAO/NSIAD-97-156. Washington, D.C.: June 4, 1997.
Defense Aircraft Investments: Major Program Commitments Based on
Optimistic Budget Projections. GAO/T-NSIAD-97-103. Washington, D.C.:
March 5, 1997.
F-22 Restructuring. GAO/NSIAD-97-100BR. Washington, D.C.:
February 28, 1997.
Tactical Aircraft: Concurrency in Development and Production of F-22
Aircraft Should Be Reduced. GAO/NSIAD-95-59. Washington, D.C.:
April 19, 1995.
Tactical Aircraft: F-15 Replacement Issues. GAO/T-NSIAD-94-176.
Washington, D.C.: May 5, 1994.
Tactical Aircraft: F-15 Replacement Is Premature as Currently Planned.
GAO/NSIAD-94-118. Washington, D.C.: March 25, 1994.
FOOTNOTES
[1] ’F/A“ stands for fighter/attack aircraft. The Air Force changed the
designation from F-22 to F/A-22 in September 2002 to reflect the
aircraft‘s air-to-surface attack capability.
[2] These features are expected to permit the F/A-22 to penetrate
adversary airspace, operate with limited interference, and destroy
targets on the ground as well as in the air.
[3] Section 217, P.L.105-85, Nov. 18, 1997.
[4] The cost limitation, before adjustment under the act‘s provisions,
was $43.4 billion. The cost limitation does not include $1.575 billion
associated with six aircraft labeled Production Representative Test
Vehicles, which are excluded from the production cost limitation. Those
aircraft are funded mostly with appropriations for research,
development, test and evaluation as approved by Congress.
[5] A DOD senior-level forum for advising the Under Secretary of
Defense (Acquisition, Technology and Logistics) on critical decisions
concerning major weapon systems programs.
[6] The F/A-22 President‘s Budget for fiscal year 2004 would transfer
$876 million in production funding to help fund estimated cost
increases in development. As a result, the current production cost
estimate is $42.2 billion, an amount that still exceeds the cost limit
of $37.5 billion.
[7] ’Air superiority“ is the degree of air dominance that allows the
conduct of operations by land, sea, and air forces without prohibitive
interference by enemy aircraft.
[8] P.L.105-85, Nov. 18, 1997. The cost limit is adjusted for inflation
and for compliance with changes in federal, state, and local laws.
[9] Based on a plan to procure 438 aircraft.
[10] The F/A-22 President‘s Budget for fiscal year 2004 would transfer
$876 million in production funding to help fund estimated cost
increases in development. As a result, the current production cost
estimate is $42.2 billion.
[11] These four production lots include: Production Representative Test
Vehicle lot 1--fiscal year 1999, Production Representative Test
Vehicle lot 2--fiscal year 2000, lot 1--fiscal year 2001, and lot 2--
fiscal year 2002. Future production lots are planned annually from
fiscal year 2003 to fiscal year 2011.
[12] The F/A-22 President‘s Budget for fiscal year 2004 would transfer
$876 million in production funding to help fund estimated cost
increases in development. As a result, the current production cost
estimate is $42.2 billion.
[13] Production lot 1 was awarded in fiscal year 2001, and production
lot 2 was awarded in fiscal year 2002.
[14] See U.S. General Accounting Office, Tactical Aircraft: F-22 Delays
Indicate Initial Production Rates Should Be Lower to Reduce Risks, GAO-
02-298 (Washington, D.C.: Mar. 5, 2002).
[15] See U.S. General Accounting Office, Defense Acquisitions: Recent
F-22 Production Cost Estimates Exceeded Congressional Limitation, GAO/
NSIAD-00-178 (Washington, D.C.: Aug. 15, 2000).
[16] Under 10 U.S.C. 2306b, a multiyear contract must meet specific
criteria and be approved by Congress. The criteria must include the
following: (1) the contract must result in substantial savings compared
with the awarding of annual contracts, (2) the item being bought must
have a stable design and not have excessive technical risks, and
(3) the estimated cost of the system and the estimated cost avoidance
from the multiyear procurement are to be realistic.
[17] See GAO/NSIAD-00-178.
[18] The U.S. Code (10 U.S.C. Sec. 2432) requires DOD-selected
acquisition reports to report the status of all the costs of
production, and the President‘s budgets are meant to do the same on an
annual basis.
[19] The F/A-22 President‘s Budget for fiscal year 2004 would transfer
$876 million in production funding to help fund estimated cost
increases in development. As a result, the current production cost
estimate is $42.2 billion, an amount that still exceeds the cost limit
of $37.5 billion.
[20] See U.S. General Accounting Office, Tactical Aircraft: Continuing
Difficulty Keeping F-22 Production Costs Within the Congressional
Limitation, GAO-01-782 (Washington D.C.: July 16, 2001).
[21] PIPs were highlighted in the most recent F/A-22 Defense
Acquisition Board meeting involving both Air Force and OSD officials.
[22] See U.S. General Accounting Office, Tactical Aircraft: Continuing
Difficulty Keeping F-22 Production Costs Within the Congressional Cost
Limitation. GAO-01-782 (Washington D.C.: July 16, 2001), and Defense
Acquisitions: Recent F-22 Production Cost Estimates Exceeded
Congressional Limitation, GAO/NSIAD-00-178 (Washington D.C.:
Aug. 15, 2000).
GAO‘s Mission:
The General Accounting Office, the investigative arm of Congress,
exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO‘s commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO‘s Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as ’Today‘s Reports,“ on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select ’Subscribe to daily E-mail alert for newly
released products“ under the GAO Reports heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. General Accounting Office
441 G Street NW,
Room LM Washington,
D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.
General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.
20548: