Tactical Aircraft

DOD Should Reconsider Decision to Increase F/A-22 Production Rates While Development Risks Continue Gao ID: GAO-03-431 March 14, 2003

The Air Force is developing the F/A-22 aircraft to fly at higher speeds for longer distances, be less detectable, and improve the pilot's awareness of the surrounding situation. The F/A-22 will replace the Air Force's existing fleet of F-15 aircraft. Over the past several years the program has experienced significant cost overruns and schedule delays. Congress mandated that GAO assess the development program and determine whether the Air Force is meeting key performance, schedule, and cost goals. GAO also assessed the implications of the progress of the development program on production.

The F/A-22 development program did not meet key performance, schedule, and cost goals in fiscal year 2002, and delays in the flight test program have led to an increase in the development cost estimate of $876 million. In response to this increase, DOD restructured the development program and reduced production aircraft by 27. If additional delays occur, further changes may be required. The program also continues to address technical problems that have limited the performance of test aircraft, including violent movement or "buffeting" of the vertical fins, overheating in portions of the aircraft, weakening of materials in the horizontal tail, and instability of avionics software. Air Force officials cannot predict when they will resolve these problems. These technical problems, along with the late delivery of aircraft to the flight test center, have delayed the development program. Based on F/A-22 flight test accomplishment data and current flight test plans, we believe that operational testing will likely be delayed several months beyond the planned August 2003 start date. The F/A-22 program is in its final stages of development, and low-rate initial production has begun. Since fiscal year 1997, funds have been appropriated to acquire production aircraft, and the F/A-22 acquisition plan calls for steadily increasing annual production rates. However, GAO considers the Air Force's acquisition strategy at high risk for increases in production costs. In past reports, GAO has reported that acquiring aircraft while significant technical challenges remain does not allow for adequate testing of the aircraft. The uncertainties regarding performance capabilities of the F/A-22 aircraft and its development schedule will persist until technical problems have been addressed, including testing of modifications or fixes necessary to potentially alleviate these problems. In light of those uncertainties, steadily increasing annual production rates could result in the Air Force having to modify a larger quantity of aircraft after they are built.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.