Chemical Weapons
Destruction Schedule Delays and Cost Growth Continue to Challenge Program Management
Gao ID: GAO-04-634T April 1, 2004
Since its inception in 1985, the Chemical Demilitarization (Chem-Demil) Program has been charged with destroying the nation's large chemical weapons stockpile of over 31,000 tons of agent. The program started destroying the stockpile in 1990. As of March 2004, the program had destroyed over 27 percent of the stockpile. The program has recently reorganized into the Chemical Materials Agency (CMA) to manage seven of the nine sites. There are five sites using incineration to destroy the agent and two bulk agent only sites using neutralization. The Assembled Chemical Weapons Alternatives (ACWA) Program, in the Department of Defense (DOD), manages two sites using neutralization to destroy agent in weapons. This testimony updates GAO's September 2003 report and October 2003 testimony. As requested, it focuses on the following issues: (1) changes in the status of schedule milestones and costs at the sites, (2) recent developments that impact the Chemical Weapons Convention (CWC) deadlines, (3) the challenges associated with managing the program, and (4) an update on the status of the Chemical Stockpile Emergency Preparedness Program (CSEPP).
Since GAO testified in October 2003, the Chem-Demil Program continues to fall behind its schedule milestones, which were last extended in 2001. In the last 6 months, very little agent has been destroyed. While one site has closed, no new sites have started destroying agent (two were scheduled to start by March 2004). The delays stem from incidents during operations, environmental permitting issues, concerns about emergency preparedness, and unfunded requirements. If these delays persist, GAO continues to believe that program costs will rise substantially higher than the October 2003 estimate of more than $25 billion. These rising costs have led to the need to reallocate funds within the program's fiscal year 2005 budget. Due to schedule delays, the United States will not meet the CWC April 2004 deadline to destroy 45 percent of the stockpile. Although it has received an extension for this task to December 2007, it is questionable if the program will meet this deadline. DOD has said it will ask for an extension of the final deadline to destroy 100 percent of the stockpile beyond 2007. Unless the program resolves the problems causing program delays, the United States risks not meeting this deadline, if extended. One positive development in the program is that the leadership has been stabilized for over a year since the program was reorganized. However, several long-standing organizational and strategic planning issues remain. One problem is that the program's new management structure is complex, with multiple lines of authority within the Army and the separation of ACWA from the rest of the program. These complexities raise concerns about the roles and responsibilities of the different parts of the program. Program officials also told us that they are developing strategic and risk mitigation plans, as GAO recommended. Since GAO testified in October, there continues to be improvement in the preparation of state and local communities to respond to chemical emergencies. As of January 2004, 6 of 10 states near the stockpiles report they are fully prepared. This is a marked improvement from the status we reported in 2001 when three states reported they were far from being prepared. However, CSEPP costs continue to rise because some states have expanded their preparedness requests beyond their approved budgets.
GAO-04-634T, Chemical Weapons: Destruction Schedule Delays and Cost Growth Continue to Challenge Program Management
This is the accessible text file for GAO report number GAO-04-634T
entitled 'Chemical Weapons: Destruction Schedule Delays and Cost Growth
Continue to Challenge Program Management' which was released on April
01, 2004.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Terrorism, Unconventional Threats and
Capabilities, Committee on Armed Services, House of Representatives:
United States General Accounting Office:
GAO:
For Release on Delivery Expected at 10:00 a.m. EST:
Thursday, April 1, 2004:
Chemical Weapons:
Destruction Schedule Delays and Cost Growth Continue to Challenge
Program Management:
Statement of Raymond J Decker, Director, Defense Capabilities and
Management:
GAO-04-634T:
GAO Highlights:
Highlights of GAO-04-634T, testimony to the Subcommittee on Terrorism,
Unconventional Threats and Capabilities, Committee on Armed Services,
House of Representatives
Why GAO Did This Study:
Since its inception in 1985, the Chemical Demilitarization (Chem Demil)
Program has been charged with destroying the nation‘s large chemical
weapons stockpile of over 31,000 tons of agent. The program started
destroying the stockpile in 1990. As of March 2004, the program had
destroyed over 27 percent of the stockpile. The program has recently
reorganized into the Chemical Materials Agency (CMA) to manage seven of
the nine sites. There are five sites using incineration to destroy the
agent and two bulk agent only sites using neutralization. The Assembled
Chemical Weapons Alternatives (ACWA) Program, in the Department of
Defense (DOD), manages two sites using neutralization to destroy agent
in weapons.
This testimony updates GAO‘s September 2003 report and October 2003
testimony. As requested, it focuses on the following issues: (1)
changes in the status of schedule milestones and costs at the sites,
(2) recent developments that impact the Chemical Weapons Convention
(CWC) deadlines, (3) the challenges associated with managing the
program, and (4) an update on the status of the Chemical Stockpile
Emergency Preparedness Program (CSEPP).
What GAO Found:
Since GAO testified in October 2003, the Chem-Demil Program continues
to fall behind its schedule milestones, which were last extended in
2001. In the last 6 months, very little agent has been destroyed. While
one site has closed, no new sites have started destroying agent (two
were scheduled to start by March 2004). The delays stem from incidents
during operations, environmental permitting issues, concerns about
emergency preparedness, and unfunded requirements. If these delays
persist, GAO continues to believe that program costs will rise
substantially higher than the October 2003 estimate of more than $25
billion. These rising costs have led to the need to reallocate funds
within the program‘s fiscal year 2005 budget.
Due to schedule delays, the United States will not meet the CWC April
2004 deadline to destroy 45 percent of the stockpile. Although it has
received an extension for this task to December 2007, it is
questionable if the program will meet this deadline. DOD has said it
will ask for an extension of the final deadline to destroy 100 percent
of the stockpile beyond 2007. Unless the program resolves the problems
causing program delays, the United States risks not meeting this
deadline, if extended.
One positive development in the program is that the leadership has been
stabilized for over a year since the program was reorganized. However,
several long-standing organizational and strategic planning issues
remain. One problem is that the program's new management structure is
complex, with multiple lines of authority within the Army and the
separation of ACWA from the rest of the program. These complexities
raise concerns about the roles and responsibilities of the different
parts of the program. Program officials also told us that they are
developing strategic and risk mitigation plans, as GAO recommended.
Since GAO testified in October, there continues to be improvement in
the preparation of state and local communities to respond to chemical
emergencies. As of January 2004, 6 of 10 states near the stockpiles
report they are fully prepared. This is a marked improvement from the
status we reported in 2001 when three states reported they were far
from being prepared. However, CSEPP costs continue to rise because some
states have expanded their preparedness requests beyond their approved
budgets.
www.gao.gov/cgi-bin/getrpt?GAO-04-634T.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Raymond J. Decker at
(202) 512-6020 or deckerrj@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
I appreciate the opportunity to participate in this hearing today on
the Department of Defense's (DOD) Chemical Demilitarization (Chem-
Demil) Program. Since its inception in 1985, this program has been
charged with destroying the nation's large chemical weapons stockpile,
second only to Russia's in terms of its size. After years of planning
and building new facilities, the program started destroying the
stockpile in 1990. Since 1990, we have issued more than 25 reports on
the Chem-Demil Program. Nearly half of the reviews have raised
questions about the program's growing costs, its inability to meet its
schedule milestones, and its management weaknesses.
As you requested, my statement updates GAO's testimony from October
2003 and focuses on the following issues: (1) changes in the status of
schedule milestones and costs at the sites, (2) recent developments
that impact the Chemical Weapons Convention (CWC) deadlines, (3) the
challenges associated with managing the program, and (4) an update on
the status of the Chemical Stockpile Emergency Preparedness Program
(CSEPP).
As of March 2004, the Chem-Demil Program had destroyed an estimated
8,691 tons (27.6 percent) of the total 31,500 tons of the original
agent stockpile stored at nine sites in the United States and the
Pacific Ocean at Johnston Atoll. Since our testimony in October 2003,
the program has destroyed very little additional agent (about 1.5
percent). Of the four sites that have begun agent destruction
operations, Johnston Atoll has destroyed its entire stockpile and is
closed; Tooele, Utah, has reduced its stockpile by about 47.1 percent;
Anniston, Alabama, has destroyed 5.1 percent of its stockpile; and
Aberdeen, Maryland, has destroyed 7.9 percent of its stockpile. Current
schedule estimates show that the Army will not complete destruction of
the entire stockpile until after the year 2012.
For this testimony, we conducted work that included discussions with
officials from DOD, the Army, and FEMA. We also drew on the work we
conducted for our September 2003 report[Footnote 1] and October 2003
testimony.[Footnote 2] We performed our work in March 2004 in
accordance with generally accepted government auditing standards.
Summary:
In summary, we found the following:
* Since we testified in October 2003, the Chem-Demil Program continues
to fall behind its schedule milestones, which were extended in 2001.
These schedule delays led to increased program costs and very little
agent destruction over the last 6 months. We testified that four
incineration sites and one bulk agent site would miss their scheduled
milestones. However, since then, one of the incineration sites has
closed and an additional bulk agent site has missed its scheduled
milestone, resulting in five sites remaining behind approved
destruction schedules. The remaining three sites--two Assembled
Chemical Weapons Alternatives (ACWA) sites and one incineration site
have not yet missed schedule milestones, but they too have experienced
delays. The delays stem from ongoing incidents during operations,
environmental permitting issues, concerns about emergency
preparedness, and unfunded requirements. If these delays persist, we
continue to believe that program costs will rise substantially higher
than the October 2003 estimate of more than $25 billion. These rising
costs have led to the need to reallocate funds within the program's
fiscal year 2005 budget.
* Because of schedule delays, the United States will not meet CWC's
April 2004 deadline to destroy 45 percent of the chemical stockpile.
The United States asked the governing body of the convention for and
received an extension for this deadline to December 2007. Although it
has received an extension for this task, it is questionable if the
program will meet this deadline. Moreover, DOD has said it will ask for
an extension of the final deadline to destroy 100 percent of the
stockpile beyond 2007. Unless the Chem-Demil Program is able to resolve
the problems that have caused schedule delays to destroy the stockpile,
the United States also risks not meeting CWC's deadline to destroy the
entire stockpile, if extended to 2012.[Footnote 3]
* We previously testified that despite efforts to improve the
management and reorganize the Chem-Demil Program, the program has
suffered from several long-standing and unresolved management,
organizational, and strategic planning issues. Recently, under the new
organization, the leadership of the program has stabilized. However,
the program's complex management structure, with multiple lines of
authority within the Army and the separation of program components
between the Army and DOD, raises concerns about the roles and
responsibilities of the different parts of the program. For example,
DOD manages two of the program's nine sites separately from the Army's
management of the other sites. In addition, the absence of an
overarching, comprehensive management strategy has resulted in a
program without a clear road map to closely guide and integrate all of
its activities and monitor its performance. Neither DOD nor the Army
has adopted a comprehensive risk management approach that could help
mitigate potential problems that affect program schedules, costs, and
safety by anticipating problems and developing proactive plans. Program
officials also told us that they are developing strategic and risk
mitigation plans, as we have recommended.
* Since our October 2003 testimony, states and communities have
continued to improve their emergency preparedness to respond to
chemical incidents. Based on the states' self-assessments and FEMA's
reviews, 6 of the 10 states near the eight storage sites are fully
prepared and the remaining 4 are close to being fully prepared. In
addition, in response to recommendations in our 2001 report,[Footnote
4] FEMA and the Army have implemented a number of actions to improve
technical assistance and guidance, training, and compliance measures to
assess preparedness. However, despite these accomplishments, CSEPP
costs continue to rise because some state and local communities have
expanded their emergency preparedness requests beyond their approved
budgets. The requests for fiscal years 2004 and 2005 exceeded approved
budgets by a total of $88 million. In a few communities, these requests
have grown as the sites have moved closer to the agent operations
phase. These unfunded requirements have caused further delays in
overall program operations because funds have to be diverted from other
sites approved budgets to pay for these communities' requirements. To
date, CSEPP has spent a total of $723 million in local communities.
Most Sites Will Miss Schedule Milestones Due to Programís Inability to
Anticipate and Influence†Issues:
Since our October 2003 testimony, the Chem-Demil Program continues to
struggle to meet its schedule milestones and remain within its cost
estimates. These schedule delays led to increased program costs and
very little agent has been destroyed over the last 6 months. We
testified then that most incineration sites would miss their scheduled
milestones established in 2001. At that time Anniston, Umatilla, and
Pine Bluff had missed their 2001 milestones to begin agent destruction
operations and Johnston Atoll had missed its milestone for shutting
down the facility. However, since then, three of these sites have
experienced further delays. Table 1 shows the delays at Umatilla, Pine
Bluff, and Johnston Atoll incineration sites since October 2003. The
delays stem from incidents during operations, environmental permitting
issues, emergency preparedness, and unfunded requirements. If these
delays persist, we continue to believe that program costs will rise
substantially higher than the October 2003 estimate of more than $25
billion. These rising costs have led to the need to reallocate funds
within the program's fiscal year 2005 budget.
Table 1: Delays in Meeting Schedule Milestones, by Incineration Site:
Site: Umatilla;
Next schedule milestone: Operations;
October 2003 estimate to begin next milestone: Mar. 2004;
Current estimates to begin next phase[A]: July 2004;
Difference between 2003 status and current estimate (no. of months):
+4.
Site: Pine Bluff;
Next schedule milestone: Operations;
October 2003 estimate to begin next milestone: Apr. 2004;
Current estimates to begin next phase[A]: July 2004;
Difference between 2003 status and current estimate (no. of months):
+3.
Site: Johnston Atoll;
Next schedule milestone: End of closure;
October 2003 estimate to begin next milestone: Nov. 2003;
Current estimates to begin next phase[A]: Dec. 2003;
Difference between 2003 status and current estimate (no. of months):
+1.
Sources: DOD and the U.S. Army.
[A] Actual date that Johnston Atoll closed and program manager's
official estimates for Pine Bluff and Umatilla to start operations.
[End of table]
As of March 2004, the two bulk-agent only sites, Aberdeen and Newport,
have experienced delays and Aberdeen has missed its scheduled milestone
for draining the agent from the ton containers. In 2002, DOD approved
using an accelerated method that was expected to increase the rate of
destruction at these two sites. The Army estimated that this process
would reduce the scheduled end of operations at both sites by 5 years,
from 2008 to 2003 at Aberdeen and from 2009 to 2004 at Newport.
However, Aberdeen has encountered unanticipated problems with the
processing of the mustard agent in the ton containers and has extended
its planned completion date from October 2003 to December of 2004. The
program has exceeded the 6-month period it estimated would be needed
for accelerated destruction of the agent. Additionally, the site has
only drained 152 of the 1,817-ton containers as of March 2004. Even if
finished by December 2004, this time frame only covers the first stage
of the operation to remove the mustard agent from the containers. An
added problem, the hardening and congealing of residual agent in the
ton containers, will require a second stage of operation to remove the
residual agent. In addition, Newport has faced construction delays and
community resistance to offsite treatment of waste byproducts. As a
result of these delays, Newport extended its planned start date for
agent operations twice: first from October 2003 to February 2004, and
again to August 2004. However, the current plan to ship the waste to a
treatment facility in New Jersey from Indiana has not been finalized
and faces opposition from residents, workers, and environmental groups.
DOD has not programmed funds to treat the waste on-site or to store it
there until a disposal location has been finalized.
At the two ACWA sites, Pueblo, Colorado, and Blue Grass, Kentucky, DOD
directed that they pursue accelerated destruction methods. According to
program officials, the initial accelerated approaches proposed by the
contractors exceeded DOD programmed funding and have to be reevaluated.
Until the plans are approved, final schedule milestones cannot be set.
This means both projects have been delayed while additional design work
is completed.
These delays and schedule extensions[Footnote 5] have contributed
directly to program cost growth, according to program officials. As a
result, DOD's total program cost estimate grew from $15 billion to
$24 billion between 1998 and 2001. (See fig. 1.) Because of delays
encountered since the 2001 revisions, the Army is now in the process of
developing new milestones that will extend beyond those adopted in
2001. According to a DOD official, the program will use events that
have occurred since 2001 in presenting new cost estimates to DOD for
preparation of the fiscal year 2006 budget submission. Program
officials told us that they estimate new costs had increased by
$1.4 billion as of October 2003, and this estimate is certainly going
to rise further, given the information we obtained on schedule delays
from fiscal year 2005 budget documents and from program officials.
Figure 1: Comparison of 1998, 2001, and 2003 Cumulative Program
Cost Estimates:
[See PDF for image]
[End of figure]
As an example of the impact schedule delays have on the program, DOD's
fiscal year 2005 budget request includes a realignment of $147 million
from the ACWA program to the rest of the program. Additional
requirements have been identified that will likely delay the schedule
further if future realignments are necessary.
Schedule Delays Required CWC Extension of Deadlines:
Although the United States met the first two chemical weapons treaty
deadlines, the continuing delays in the schedule jeopardize its ability
to meet the final two deadlines. (See table 2.) The program will not
meet the April 2004 CWC deadline to destroy 45 percent of the
stockpile. Although it has received an extension for this task to
December 2007, it is questionable if the program will meet this
deadline. Unless the Chem-Demil Program is able to resolve the problems
that have caused schedule delays to destroy the stockpile, the United
States will likely risk not meeting the deadline, if extended to 2012,
to eliminate 100 percent of the stockpile.
Table 2: CWC Deadlines:
Required percentage of agent destroyed: 1;
Deadlines for destruction: April 29, 2000;
Date United States met deadline: September 1997.
Required percentage of agent destroyed: 20;
Deadlines for destruction: April 29, 2002;
Date United States met deadline: July 2001.
Required percentage of agent destroyed: 45;
Deadlines for destruction: April 29, 2004;
Date United States met deadline: Will not meet.
Required percentage of agent destroyed: 100;
Deadlines for destruction: April 29, 2007;
Date United States met deadline: Will not meet.
Sources: CWC and U.S. Army.
[End of table]
Long-standing Management and Strategic Planning Weaknesses Hamper
Program Progress:
Despite recent efforts to improve the management and change the
organization of the Chem-Demil Program, the program continues to falter
because several long-standing management, organizational, and
strategic planning weaknesses remain unresolved. While the program has
lacked sustained leadership in the recent past, this situation has
stabilized. However, the program's complex structure, with its many
lines of authority within the Army and between the Army and DOD, raises
questions about the roles and responsibilities of its various offices.
In addition, the program lacks strategic and risk management plans to
guide and integrate its activities.
Program Management Structure Remains Complex:
Although the program has experienced turbulence in key leadership
positions in the recent past, the current leadership has been in place
for more than a year, and these leaders have a substantial history of
involvement with the program. The new leadership team is clarifying its
roles, responsibilities, decision-making authority, and
accountability.
However, despite the recent reorganization, this change has not
streamlined the program's complex organization, as we documented in our
2003 report.[Footnote 6] The establishment of the Chemical Materials
Agency (CMA) in January 2003 has left the Director reporting to two
different senior Army organizations. The reorganization has also
divided the responsibility for various program phases between two
offices within CMA. One organization, the Program Manager for the
Elimination of Chemical Weapons, will manage the first three phases
(design, construction, and systemization) for each site, and a newly
created organization, the Director of Operations, will manage the final
two phases (operations and closure). Moreover, the reorganization did
not address the relationship between the Assembled Chemical Weapons
Alternatives (ACWA) program and the Army's CMA since DOD manages ACWA
separately from the Army, as congressionally directed.
Program Lacks Strategic and Risk Management Plans:
In response to our recommendations in our September 2003 report,
according to DOD officials, the Army is developing a strategic plan to
address the goals, objectives, and performance measures of the program.
DOD says it is now in the process of developing a risk management plan.
In the past, because the program had used a crisis management approach,
it was forced to react to, rather than control issues. We believe a
risk management approach would allow DOD and the Army to proactively
anticipate and address potential problems that could adversely affect
program schedule, costs, and safety.
Emergency Preparedness Program Is Improving, but Costs Are Rising:
FEMA and the Army continue to provide assistance to state and local
communities to improve their emergency preparedness. Since our October
2003 testimony, states and communities have continued to improve their
emergency preparedness to respond to chemical incidents. Additionally,
FEMA has provided software and training to state and local communities
to help them simplify development of CSEPP financial reporting
documents. FEMA also has published a Recovery Workbook.[Footnote 7] The
workbook fills a void in state and local guidance for emergency
responders to follow in the event of a chemical emergency. FEMA also
expanded its capability assessment readiness tool to assist local
communities in quantifying benchmark scores. In January 2004, FEMA
reported to Congress that these achievements have aided CSEPP
communities in reaching 95 percent of their benchmark compliance. Six
of 10 states near the eight storage sites reported that they are fully
prepared and the remaining 4 reported being close to fully prepared.
Despite these accomplishments, CSEPP costs continue to rise because,
according to Army and FEMA officials, some state and local communities
continue to identify additional emergency requirements that exceed
DOD's programmed funding. This situation occurs because of the open
interpretation of "maximum protection" concept that governs CSEPP.
These unfunded requests have two effects. First, they cause the
benchmarks showing how prepared each community is to change from fully
compliant to not compliant from year to year. Second, they cause funds
to be transferred from destruction activities to CSEPP and result in
further delays in the destruction schedule. Army and FEMA officials
explain that the states often identify and expand their requirements,
especially as destruction facilities move closer to the start of the
operations phase. For example, the states of Colorado, Alabama, and
Oregon have requested additional funds for infrastructure support,
including roads and bridges that exceed their CSEPP budgets. These
requests follow a pattern that occurred at Anniston in 2001 when it
received $40.5 million for additional CSEPP items. Currently, the
communities around the Umatilla facility are demanding that substantial
additional funding be provided as the onset of operations comes closer.
Programwide, new requirements continue to exceed approved CSEPP funding
levels. FEMA has little control over the additional funding requests
made by the states. As of October 2003, FEMA had identified total $88
million in unfunded CSEPP requirements for fiscal years 2004 and 2005.
As of fiscal year 2004, the total cost for CSEPP has risen to $723.1
million. Funding for individual states ranges from $9.7 million to
$259.6 million for the period of 1989 to 2004. (See table 3.):
Table 3: CSEPP Funding by State, Fiscal Years 1989-2004:
State: Alabama; Fiscal years 1989-2004: $259,612,223;
Percent of total spending: 35.9.
State: Arkansas; Fiscal years 1989-2004: 80,311,665;
Percent of total spending: 11.1.
State: Colorado; Fiscal years 1989-2004: 30,233,930;
Percent of total spending: 4.2.
State: Illinois; Fiscal years 1989-2004: 9,724,039;
Percent of total spending: 1.3.
State: Indiana; Fiscal years 1989-2004: 46,201,152;
Percent of total spending: 6.4.
State: Kentucky; Fiscal years 1989-2004: 60,055,596;
Percent of total spending: 8.3.
State: Maryland; Fiscal years 1989-2004: 30,472,755;
Percent of total spending: 4.2.
State: Oregon; Fiscal years 1989-2004: 93,484,394;
Percent of total spending: 12.9.
State: Utah; Fiscal years 1989-2004: 74,596,336;
Percent of total spending: 10.3.
State: Washington; Fiscal years 1989-2004: 38,388,929;
Percent of total spending: 5.3.
Total; Fiscal years 1989-2004: $723,071,019;
Percent of total spending: 100.0.
Source: FEMA data. The Army and FEMA have recently recognized the
Confederated Tribes of the Umatilla Indian Reservation as a separate
funding entity. The confederated tribes have received $2.5 million to
date.
[End of table]
Mr. Chairman, this concludes my statement. I would be pleased to
respond to any questions that you or Members of the Subcommittee may
have.
Contacts and Acknowledgments For future questions regarding this
testimony, please contact me at (202) 512-6020. Individuals making key
contributions to this testimony include Donald Snyder, Rodell Anderson,
Bonita Oden, John Buehler, Nancy Benco, Rick Yeh, Susan Mason, and Mike
Zola.
FOOTNOTES
[1] U.S. General Accounting Office, Chemical Weapons: Sustained
Leadership, Along with Key Strategic Management Tools, Is Needed to
Guide DOD's Destruction Program, GAO-03-1031 (Washington, D.C.: Sept.
5, 2003).
[2] U.S. General Accounting Office, Chemical Weapons: Better Management
Tools Needed to Guide DOD's Stockpile Destruction Program, GAO-04-221T
(Washington, D.C.: Oct. 30, 2003).
[3] The CWC allows extensions of up to 5 years to the 2007 deadline.
[4] Chemical Weapons: FEMA and Army Must Be Proactive in Preparing
States for Emergencies, GAO-01-850 (Washington, D.C.: Aug. 13, 2001).
[5] Schedule extensions or slippages are caused primarily by actual
destruction rates being lower than planned.
[6] GAO-03-1031.
[7] U.S. General Accounting Office, Chemical Weapons: FEMA and Army
Must Be Proactive in Preparing States for Emergencies, GAO-01-850
(Washington, D.C.: Aug. 13, 2001). Recovery plans refer to support
activities that occur following a chemical event. The primary purpose
is to protect the public health and safety while returning the
community to normal conditions.