Coast Guard
Deepwater Program Acquisition Schedule Update Needed
Gao ID: GAO-04-695 June 14, 2004
In 2002, the Coast Guard began its $17 billion, 20-year Integrated Deepwater System acquisition program to replace or modernize its cutters, aircraft, and communications equipment for missions generally beyond 50 miles from shore. During fiscal years 2002-03, Deepwater received about $125 million less than the Coast Guard had planned. In fiscal year 2004, Congress appropriated $668 million, $168 million more than the President's request. GAO has raised concern recently about the Coast Guard's initial management of Deepwater and the potential for escalating costs. GAO was asked to review the status of the program against the initial acquisition schedule and determine the impact of the additional $168 million in fiscal year 2004 funding on this schedule.
The degree to which the Deepwater program is on track with its original 2002 integrated acquisition schedule is difficult to determine because the Coast Guard has not updated the schedule. Coast Guard officials said they have not updated it because of the numerous changes Deepwater experiences every year and the cost, personnel, and time involved. However, in similar acquisitions--those of the Department of Defense (DOD)--cost, schedule, and performance updates are fundamental to congressional oversight. DOD is required to update the schedule at least annually and whenever cost and schedule thresholds are breached. In practice, DOD continually monitors and reports schedules for management on a quarterly basis. Updating the acquisition schedule--including phases such as design and fabrication, interim phase milestones, and critical paths linking assets-- on a more timely basis is imperative so that annual Coast Guard budget submissions can allow Congress to base decisions on accurate information. GAO used available data to develop the current acquisition status for a number of selected Deepwater assets and found that they have experienced delays and are at risk of being delivered later than anticipated. The additional $168 million in fiscal year 2004, while allowing the Coast Guard to conduct a number of Deepwater projects that had been delayed or would not have been funded in fiscal year 2004, will not fully return the program to its original 2002 acquisition schedule. Reasons include: all work originally planned for fiscal year 2004 was not funded and some will have to be delayed to fiscal year 2005; delivery of some assets has fallen so far behind schedule that ensuring their original delivery dates is impossible; and nonfunding reasons have caused delays, such as greater than expected hull corrosion of patrol boats delaying length extension upgrades.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-04-695, Coast Guard: Deepwater Program Acquisition Schedule Update Needed
This is the accessible text file for GAO report number GAO-04-695
entitled 'Coast Guard: Deepwater Program Acquisition Schedule Update
Needed' which was released on June 29, 2004.
This text file was formatted by the U.S. General Accounting Office
(GAO) to be accessible to users with visual impairments, as part of a
longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Chairmen, Subcommittees on Homeland Security, Committees
on Appropriations, House of Representatives and U.S. Senate:
United States General Accounting Office:
GAO:
June 2004:
Coast Guard:
Deepwater Program Acquisition Schedule Update Needed:
GAO-04-695:
GAO Highlights:
Highlights of GAO-04-695, a report to the Chairmen, Subcommittees on
Homeland Security, Committees on Appropriations, House of
Representatives and U.S. Senate
Why GAO Did This Study:
In 2002, the Coast Guard began its $17 billion, 20-year Integrated
Deepwater System acquisition program to replace or modernize its
cutters, aircraft, and communications equipment for missions generally
beyond 50 miles from shore. During fiscal years 2002-03, Deepwater
received about $125 million less than the Coast Guard had planned. In
fiscal year 2004, Congress appropriated $668 million, $168 million more
than the President‘s request.
GAO has raised concern recently about the Coast Guard‘s initial
management of Deepwater and the potential for escalating costs. GAO was
asked to review the status of the program against the initial
acquisition schedule and determine the impact of the additional $168
million in fiscal year 2004 funding on this schedule.
What GAO Found:
The degree to which the Deepwater program is on track with its original
2002 integrated acquisition schedule is difficult to determine because
the Coast Guard has not updated the schedule. Coast Guard officials
said they have not updated it because of the numerous changes Deepwater
experiences every year and the cost, personnel, and time involved.
However, in similar acquisitions”those of the Department of Defense
(DOD)”cost, schedule, and performance updates are fundamental to
congressional oversight. DOD is required to update the schedule at
least annually and whenever cost and schedule thresholds are breached.
In practice, DOD continually monitors and reports schedules for
management on a quarterly basis. Updating the acquisition schedule”
including phases such as design and fabrication, interim phase
milestones, and critical paths linking assets”on a more timely basis is
imperative so that annual Coast Guard budget submissions can allow
Congress to base decisions on accurate information.
GAO used available data to develop the current acquisition status for a
number of selected Deepwater assets and found that they have
experienced delays and are at risk of being delivered later than
anticipated.
GAO analysis of current acquisition of selected Deepwater assets:
[See PDF for image]
[End of figure]
The additional $168 million in fiscal year 2004, while allowing the
Coast Guard to conduct a number of Deepwater projects that had been
delayed or would not have been funded in fiscal year 2004, will not
fully return the program to its original 2002 acquisition schedule.
Reasons include: all work originally planned for fiscal year 2004 was
not funded and some will have to be delayed to fiscal year 2005;
delivery of some assets has fallen so far behind schedule that ensuring
their original delivery dates is impossible; and nonfunding reasons
have caused delays, such as greater than expected hull corrosion of
patrol boats delaying length extension upgrades.
What GAO Recommends:
GAO recommends the Coast Guard update the original 2002 Deepwater
acquisition schedule in time to support the fiscal year 2006 Deepwater
budget submission to the Department of Homeland Security and Congress
and at least once a year thereafter to support each budget submission.
The updated schedule should include the current status of asset
acquisition phases, interim phase milestones, and the critical paths
linking assets. In written comments, the Coast Guard generally
concurred with GAO‘s findings and recommendation.
www.gao.gov/cgi-bin/getrpt?GAO-04-695.
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Margaret Wrightson at
(415) 904-2200 or wrightsonm@gao.gov.
[End of section]
Contents:
Letter:
Background:
Results:
Conclusions:
Recommendation for Executive Action:
Agency Comments:
Appendix I: Briefing Slides:
Appendix II: Coast Guard's Comments:
Abbreviations:
C4ISR: Command, Control, Communications and Computers, Intelligence,
Surveillance, and Reconnaissance:
Deepwater: Integrated Deepwater Systems program:
DHS: Department of Homeland Security:
DOD: Department of Defense:
EVMS: Earned Value Management System:
GAO: General Accounting Office:
ICGS: Integrated Coast Guard Systems, LLC:
IMS: Integrated Master Schedule:
MPA: Maritime Patrol Aircraft:
OPC: Offshore Patrol Cutter:
UAV: Unmanned Air Vehicle:
United States General Accounting Office:
Washington, DC 20548:
June 14, 2004:
The Honorable of Thad Cochran:
Chairman, Subcommittee on Homeland Security:
Committee on Appropriations:
United States Senate:
The Honorable Harold Rogers:
Chairman, Subcommittee on Homeland Security:
Committee on Appropriations:
House of Representatives:
In 2002, the Coast Guard began the acquisition phase of the largest and
most complex procurement in its history, the Integrated Deepwater
System program (Deepwater). Under this program, the Coast Guard will
replace or modernize its cutters, aircraft, and communications
equipment used for missions generally beyond 50 miles from shore but
which may start at ports, waterways, and coasts and extend seaward to
wherever the Coast Guard is required to take appropriate action. In
developing the program, the Coast Guard chose a contracting approach
that relies heavily on a "systems integrator"--a contractor that will
translate the Coast Guard's mission requirements into specific
acquisitions and upgrades. This contracting approach also relies
heavily on a steady, predictable funding stream throughout the
program's anticipated 20-year acquisition span[Footnote 1]. When the
program began, we expressed concern that, given this approach's
particularly heavy dependence on funding at planned levels, the Coast
Guard risked schedule slippages and cost escalation if program funding
fell short of planned funding amount[Footnote 2]s. During the program's
first 2 years (fiscal years 2002-03), the total amount of funding
available was nearly $125 million less than the amount the Coast Guard
had planned and $32 million less than the President's request. The
Congress then increased the Deepwater appropriation for fiscal year
2004 to about $668 million, or about $86 million more than the agency's
original plan for that year and $168 million more than the President's
request.
You asked us to assess the Deepwater program's status in light of this
increased funding. We focused our work on (1) reviewing the status of
the program against the initial acquisition schedule and (2)
determining the impact of the additional $168 million in fiscal year
2004 funding on returning the program to this schedule. You also asked
us to provide information on the Coast Guard's status in revising
Deepwater's mission to meet increased homeland security requirements
and the amount of assistance the Department of Defense (DOD) has
provided for Deepwater from fiscal years 2002 to 2004. On March 12,
2004, we briefed your offices on the preliminary results of our work to
date. This report and the briefing slides in appendix I provide our
final results.
Our work for this report involved reviewing and analyzing a variety of
documents and interviewing officials from the headquarters of the Coast
Guard and Integrated Coast Guard Systems, LLC, (ICGS). To determine the
status of Deepwater's acquisition schedule for selected assets, we
analyzed (1) the delivery task orders and their associated statements
of work for individual Deepwater assets to establish what work was
started, when it was started, and the period of performance for that
work, and (2) the monthly assessment reports of Deepwater program
managers on the performance of executing the delivery task orders. We
compared these start and end dates of the delivery task orders with the
acquisition schedule laid out in the original June 2002 Integrated
Deepwater System Implementation Plan, which covers the first 5 years of
the program. To determine the specific assets that were originally
planned to have been funded by fiscal year 2004 but were not, we
compared the Coast Guard's original plan listing the work scheduled to
begin (contract line item numbers) for each fiscal year with the work
that was actually begun (the delivery task orders that were issued for
those line items). We interviewed Coast Guard and ICGS officials about
the reliability of the data in the Integrated Master Schedule (IMS)
management tool. On the basis of those discussions, we determined that
the data within IMS were not reliable enough for use in our report. To
determine the amount of funding support DOD provided to the Deepwater
program from fiscal years 2002 to 2004, we interviewed officials and
analyzed documents from the Navy. We also interviewed officials from
other DOD components; however, they all referred us back to the Navy.
We conducted our work from January through June 2004 and did our work
in accordance with generally accepted government auditing standards.
Background:
In June 2002, the Coast Guard awarded a contract to ICGS to begin the
acquisition phase of the Deepwater program. Rather than using the
traditional approach of replacing classes of ships or aircraft through
a series of individual acquisitions, the Coast Guard chose to employ a
"system of systems" acquisition strategy that would replace its aging
assets of ships, aircraft, and communication capabilities with a
single, integrated package of new or modernized assets and
capabilities. The focus of the program is not just on new ships and
aircraft, but rather on an integrated approach to modernizing existing
or "legacy" assets while transitioning to newer, more capable assets,
with improved command, control, communications and computers,
intelligence, surveillance, and reconnaissance (C4ISR) capabilities.
At full implementation, the Deepwater program will replace the Coast
Guard's entire fleet of current deepwater surface and air assets,
comprising three classes of new cutters and their associated small
boats, a new fixed-wing manned aircraft fleet, a combination of new and
upgraded helicopters, and both cutter-based and land-based unmanned air
vehicles (UAVs). In addition, all of these assets will be linked with
state-of-the-art C4ISR capabilities and computers and will be supported
by an integrated logistics management system.
ICGS, a business entity jointly owned by Northrop Grumman and Lockheed
Martin, acts as the system integrator to develop and deliver the
Deepwater program. They are the two first-tier subcontractors for the
program and either provides Deepwater assets themselves or award
second-tier subcontracts for the assets. The Coast Guard's contract
with ICGS has a 5-year base period with five additional 5-year options.
The Coast Guard is scheduled to decide on whether to extend ICGS's
contract by June 2006, which is 1 year prior to the end of the first 5-
year contract term. Although ICGS is responsible for designing,
constructing, deploying, supporting, and integrating Deepwater assets,
the Coast Guard maintains responsibility for oversight and overall
management of the program. To help fulfill this responsibility, the
Coast Guard uses several management tools to track progress in the
program, such as monthly status reports called quad reports, a
performance-based management tool called the Earned Value Management
System (EVMS), and a schedule management system called IMS. The quad
reports are monthly summaries of the work performed on the various
deepwater assets and were developed to give managers a monthly progress
report on the performance of the program in such areas as cost,
schedule, and contract administration. EVMS is used to track cost and
schedule for certain delivery orders that have been placed to manage
the risk of the major assets and activities. IMS is a three-tiered,
calendar-based schedule used to track the completion of tasks and
milestones of the individual Deepwater delivery task orders. However,
data reliability with IMS has been an area of concern for the Coast
Guard, and it is currently working with a private contractor and ICGS
to address these concerns. Currently, the Coast Guard only maintains
the lowest and most detailed level of IMS with monthly updates. These
updates reflect the status of active contracts of individual assets and
feed into EVMS's monthly cost performance reports of those individual
contracts, which allow program management to monitor the cost,
schedule, and technical performance of ongoing work at these lowest and
most detailed levels.
In recent months, we have issued two reports that have raised concern
about the Coast Guard's initial management of the Deepwater program and
the potential for escalating costs. In March 2004,[Footnote 3] we
reported that key components needed to manage the Deepwater program and
oversee the system integrator's performance have not been effectively
implemented. We recommended that the Secretary of Homeland Security
direct the Commandant of the Coast Guard to take a number of actions to
improve Deepwater program management and contractor oversight. In April
2004,[Footnote 4] we testified that the most significant challenge the
Coast Guard faces as it moves forward in the Deepwater program is
keeping the program on schedule and within planned budget estimates. We
noted that the Coast Guard was at risk of having to expend funds to
repair deteriorating legacy assets that otherwise had been planned for
Deepwater modernization initiatives, which could potentially further
delay the program and increase total program costs. We noted further
that the Coast Guard's current estimate for completing the acquisition
program within the 20-year schedule has risen to $17.2 billion, an
increase of $2.2 billion over the original $15 billion
estimate.[Footnote 5]
Results:
The degree to which the Deepwater program is on track with regard to
its original 2002 acquisition schedule is difficult to determine,
because the Coast Guard has not maintained and updated the acquisition
schedule. The original acquisition schedule included acquisition phases
(such as concept technology and design, system development and
demonstration, and fabrication), interim phase milestones (such as
preliminary and critical design reviews, installation, and testing),
and the critical paths integrating the delivery of individual
components to particular assets. However, while the Coast Guard has
what is called an integrated master schedule, it currently uses it only
at the lowest and most detailed levels and have not updated it to
demonstrate whether individual components and assets are being
integrated and delivered on schedule and in the critical sequence.
There are a number of reasons why tracking the current integrated
schedule on a major government investment or acquisition is important,
but two stand out. First, our work has shown that it is important to
identify potential risks in major acquisitions as early as possible so
problems can be avoided or minimized. The ability to achieve scheduled
events is a key indicator of risk. Second, cost, schedule, and
performance are fundamental to the Congress's oversight of major
acquisitions. In fact, by law, DOD's major defense acquisition programs
have to report cost, schedule, and performance updates to the Congress
at least annually and whenever cost and schedule thresholds are
breached. In practice, schedules on DOD's major defense acquisitions
are continually monitored and reported to management on a quarterly
basis.
While Coast Guard officials indicated that the management tools they
use are sufficient for tracking delivery dates throughout the
acquisition, we found that these tools could not provide a ready and
reliable picture of the current integrated Deepwater acquisition
schedule. For example, IMS has had problems with data reliability and
the monthly status reports, while assessing the progress of individual
assets, do not translate those individual assessments into an overall
integrated Deepwater acquisition schedule. In fact, the February 2004
status report noted that because there was no accurate overall
integrated schedule for the command and control design phase, the
linkages with the development of other assets were largely unknown.
Although maintaining a current integrated schedule is a best practice
for ensuring adequate contract oversight and management and is a
requirement for DOD acquisitions, Coast Guard officials said they have
not done so because of the numerous changes the Deepwater Program
experiences every year and because of the cost, personnel, and time
involved in crafting a revised master plan with the systems integrator
on an annual basis. The officials said they have not planned to update
the original acquisition schedule until just prior to deciding whether
to extend the award of the next 5-year Deepwater contract in 2007.
However, we have found that in acquisitions of similar scope--and in
particular, acquisitions made by DOD--maintaining a current schedule is
a fundamental practice that the department considers necessary.
While the Coast Guard could not provide us with an updated integrated
schedule, we developed the current acquisition status of a number of
selected Deepwater assets from documents provided by the Coast Guard.
Our analysis indicates that several Deepwater assets and capabilities
have experienced delays and are at risk of being delivered later than
anticipated in the original implementation plan. For example, the
delivery of the first two maritime patrol aircraft is behind schedule
by about 1 year, and the delivery and integration of the vertical-take-
off-and-land unmanned air vehicle to the first national security cutter
has been delayed 18 months.
The $168 million appropriated in fiscal year 2004 for the Deepwater
program above the President's request of $500 million will allow the
Coast Guard to conduct a number of projects that had been delayed or
would not have been funded in fiscal year 2004, but it will not fully
return the program to its original 2002 acquisition schedule. Our
analysis indicates there are several reasons for this result. First,
even with the additional amount, the program still had a cumulative
funding shortfall of $39 million through fiscal year 2004, as compared
to the Coast Guard's planned funding amount. Second, because part of
the additional $168 million was needed to start work delayed from
fiscal year 2003, it did not provide enough funding for the delayed
work and for all the work that the Coast Guard had originally planned
for fiscal year 2004. As a result, some of this work will have to be
delayed to fiscal year 2005. Third, the delivery of some assets has
fallen so far behind schedule that it is impossible to ensure their
delivery according to the original 2002 implementation schedule by
simply providing more money. For example, according to the 2002
implementation schedule, nine maritime patrol aircraft were to be
delivered by the end of 2005; according to the current contract, none
will be delivered in 2005 and two will be delivered by the end of 2006.
Similarly, the original schedule called for completing 18 123-foot
patrol boat conversions by the end of 2005; according to the current
contract, 8 will be completed by the end of 2005.[Footnote 6] Fourth,
the acquisition of some assets has been delayed for reasons other than
funding. For example, greater than anticipated hull corrosion in the
110 ft. patrol boats has delayed the conversion of those into 123
footers and delays in the availability of faster satellite service for
legacy cutters has delayed the delivery of those upgraded legacy
cutters. Finally, in keeping with appropriations conference committee
directives for how the additional amount was to be spent, part of the
additional funding went for design of the offshore patrol cutter, work
that, under the original schedule, would not begin for another 6 to 8
years. This work may speed up acquisition of these assets, but they
were not on the original schedule this early in the program.
The Coast Guard is currently revising Deepwater's mission needs
statement in response to increased homeland security requirements
resulting from the terrorist attacks of September 11, 2001. According
to the Coast Guard, in May 2004 it submitted the revised statement to
the Department of Homeland Security's (DHS) Joint Requirements Council,
which conditionally accepted it until the Deepwater contractor, ICGS,
completes a new estimate of the costs needed to acquire the necessary
functional capabilities resulting from the revised mission needs
statement. The council further directed the Coast Guard to complete the
new cost estimate in order to brief the DHS Investment Review Board in
October 2004. Acting as an agent of the DHS, the board will approve any
increases in the Deepwater total ownership cost associated with the
revised mission needs statement and any growth in the Deepwater budget.
Specifications for some specific Deepwater assets--most notably the
National Security Cutter--will be changed in light of the Coast Guard's
added homeland security responsibilities. Coast Guard officials said
the main impact of the revision would be to close the gaps in Deepwater
asset capabilities created by the expansion of Coast Guard mission
requirement after September 11.[Footnote 7]
Regarding DOD's assistance to the Coast Guard for Deepwater, the Navy
budgeted $25 million for the Deepwater program in fiscal years 2002-04,
mainly to help outfit the National Security Cutter. The Navy budgeted
these funds to provide capabilities and equipment it regarded as
important for the Coast Guard to have for potential national defense
missions that would be carried out in conjunction with Navy
operations.[Footnote 8]
Conclusions:
The 2002 Deepwater acquisition schedule showed not only the individual
planned phases and interim milestones for designing, testing, and
fabricating assets but also the integrated schedules of critical
linkages between assets. The absence of an up-to-date integrated
acquisition schedule for the Deepwater program is a concern, because it
is a symptom of the larger issues we reported in March 2004 that are
related to whether this complicated acquisition is being adequately
managed and whether the government's interests are being properly
safeguarded. Since the inception of the unique contracting approach to
this project, we have pointed out that it poses risks, in that it would
be expensive to alter and, because of the unique "systems integrator"
approach, does not operate like a conventional acquisition. The recent
disclosure that, just 3 years into the acquisition, costs have risen by
$2.2 billion points to the need for a clear understanding of what
assets are being acquired, when they are being acquired, and at what
cost. This lack of such a current schedule lessens the Coast Guard's
ability to monitor the contractor's performance and to take early
action on potential risks before they become problems later in the
program.
The Coast Guard has so far maintained that it is not worth the time and
cost involved to update the acquisition schedule until just before the
award of the next 5-year Deepwater contract, but we disagree. We
recognize that there are costs involved with keeping an acquisition
schedule updated. However, for Department of Defense acquisitions of
such scope, maintaining a current schedule is a fundamental and
necessary practice. Deepwater remains a program in transition, in that
the Coast Guard is currently revising the program's mission
requirements to include increased homeland security requirements. The
major modifications that may result to key assets make keeping the
program on track that much harder. As evolving mission requirements are
translated into decisions about what assets are needed and what
capabilities they will need to have, it becomes even more imperative
that Coast Guard officials update the acquisition schedule on a more
timely basis, so that budget submissions by the Coast Guard can allow
DHS and Congress to base decisions on accurate information.
Recommendation for Executive Action:
We recommend that the Secretary of Homeland Security direct the
Commandant of the Coast Guard to update the original 2002 Deepwater
acquisition schedule in time to support the fiscal year 2006 Deepwater
budget submission to DHS and Congress and at least once a year
thereafter to support each budget submission. The updated schedule
should include the current status of asset acquisition phases (such as
concept technology and design, system development and demonstration,
and fabrication), interim phase milestones (such as preliminary and
critical design reviews, installation, and testing), and the critical
paths linking the delivery of individual components to particular
assets.
Agency Comments:
We provided a draft of this report to DHS and the Coast Guard for their
review and comment. In written comments, which are reproduced in
appendix II, the Coast Guard generally concurred with the findings and
recommendations in the report. The Coast Guard also provided technical
comments, which we incorporated as appropriate.
The Coast Guard, however, did not concur with three areas of
discussion. First, the Coast Guard said that our draft report did not
accurately portray its current acquisition tools and disagreed with our
determination that data within one of those tools, the IMS, was not
reliable enough for use in our report. As we noted in the report, at
the time of our review Coast Guard officials expressed concerns about
the reliability of IMS data, such as out-dated data and less than
adequate data input and adjustment, and told us that they had hired a
consultant to address those concerns. For that reason and with Coast
Guard and ICGS agreement on our methodology, we based our analysis on
the same source documents the Coast Guard uses as inputs to IMS's
lowest, most detailed level. The Coast Guard stated in its written
comments that while not in the form of an acquisition schedule, IMS's
lower level data are reliable. According to its written comments, the
Coast Guard is making improvements in updating IMS at all levels.
Second, the Coast Guard said that we did not highlight that delays in
the delivery schedule have been caused by a lack of funding and the
subsequent need to sustain legacy assets rather than a lack of
acquisition schedule updates. The scope of our review was to determine
the impact of the additional $168 million in fiscal year 2004 on
returning Deepwater to its original 2002 schedule, not to determine
effects of receiving appropriations that were less than requested in
previous years. However, in explaining why the $168 million will not
return the Deepwater to its original schedule, we did note that part of
the $168 million was needed to start work delayed from fiscal year
2003, and that the acquisition of some assets had been delayed due to
greater than anticipated hull corrosion in legacy 110-foot patrol boats
causing the delay in converting them to 123-footers.
Finally, we did not intend to imply that the lack of acquisition
schedule updates caused delays in delivery schedule. However, we
continue to believe that not updating an integrated schedule to show
the acquisition linkages between critical assets is a management
concern. We believe in the importance of updating acquisition schedules
at least annually not only as a best practice for managing and
overseeing a complex integrated acquisition such as Deepwater but also
as a up-to-date source of information on which DHS and the Congress can
base annual budget decisions.
As agreed with your office, unless you publicly announce its contents
earlier, we plan no further distribution of this report until 15 days
from its issue date. At that time, we will send copies of this report
to the Secretary of Homeland Security, the Commandant of the Coast
Guard, appropriate congressional committees, and other interested
parties. The report will also be available at no charge on GAO's Web
site at http://www.gao.gov. If you or your staffs have any questions
about this report, please contact me at (415) 904-2200 or by email at
wrightsonm@gao.gov, or Steve Calvo, Assistant Director, at (206) 287-
4839 or by email at calvos@gao.gov. Other key contributors to this
report were Shawn Arbogast, Leo Barbour, David Best, Michele Fejfar,
Paul Francis, Sam Hinojosa, David Hooper, Michele Mackin, and Stan
Stenersen.
Margaret T. Wrightson:
Director, Homeland Security and Justice Issues:
[End of section]
Appendix I: Briefing Slides:
[See PDF for image]
[End of figure]
[End of section]
Appendix II: Coast Guard's Comments:
U.S. Department of Homeland Security:
United States Coast Guard:
Commandant
2100 Second Street SW
Washington, DC 20593
Staff Symbol: CG-8
Phone: 202-267-2405
Fax: 202-267-4850:
3800:
27 May 2004:
Mr. Steven Calvo:
U.S. General Accounting Office
441 G Street, NW
Washington, DC 20548:
Dear Mr. Calvo,
This letter is the Coast Guard and Department of Homeland Security
response to the draft June 2004 audit of the Coast Guard entitled
"Deepwater Program Acquisition Schedule Update Needed." The Coast Guard
and the Department concur generally with the findings and
recommendation of the report.
Over the last six months, the Coast Guard has engaged with your staff
to help address the questions of the Committee on Appropriations,
Subcommittee on Homeland Security, concerning the Integrated Deepwater
System. We welcome your observations and recommendations as an
independent review of the program, and I appreciate the opportunity to
respond to the draft report. The Coast Guard has already provided your
staff with detailed observations, and I wish to review additional key
points in the draft report at this time.
As I noted above, the Coast Guard and the Department concur generally
with the findings and recommendation of the draft audit. However, there
are two specific areas of discussion with which we do not concur.
First, the draft audit report fails to accurately portray the existing
acquisition schedule tools currently in use. Second, the draft audit
report fails to highlight the fact that delays in the delivery schedule
have been caused by a lack of funding and the subsequent need to
sustain legacy assets rather than a lack of acquisition schedule
updates.
The Coast Guard currently uses a multi-tiered Integrated Master
Schedule (IMS) to oversee the Deepwater acquisition. The top-level plan
in the IMS that tracks the full period of performance of the
acquisition contract is Implementation Plan. Development of this plan
is complex and costly, and, as noted in the report, the Coast Guard
previously planned to do, at a minimum, one full update of this
Implementation Plan every contract term. Following the draft audit
report's guidance, the Coast Guard will now revise the Implementation
Plan by the end of 2004.
The IMS supplements the Implementation Plan with additional levels of
detail and adds definition and structure to it. The Coast Guard
Acknowledges that the IMS has not been completely updated in its
entirety (all periods of the three tiers) on a monthly basis. But
significant improvements have been made. The near-term periods of all
three tiers are now updated on a monthly basis. Necessary horizontal
linkages across Delivery Task Orders (DTOs) and across the air,
surface, logistics, and C4ISR domains have been validated. Tiers 1 and
2 levels are now being reviewed on a monthly basis by the schedulers
and planners in each of the major program areas with the first complete
review planned for the end of May 2004.
Even before the GAO input, the Tier 3 IMS (the lowest, most detailed
level of the IMS and considered to be the most important tool) has been
consistently updated monthly over the last
year. These monthly updates reflect the status of active DTOs fed into
the Earned Value Management System's (EVMS) monthly Cost Performance
Reports (CPRs).
Monthly CPRs give program management more than adequate insight into
the cost, schedule, and technical performance variances associated with
ongoing work. CPRs are the singularly most important tool for program
management since the information for the various DTOs captured at those
levels provides the essential data to manage the contract.
For these and other reasons, I do not concur with the statement that
"the data within the IMS was not reliable enough for use in our
report." There was sufficient data within the IMS, it simply wasn't in
the form of an acquisition schedule. The GAO audit team's analysis was
based on a comparison of the proposed June 2002 Implementation Plan
with the Tier 3 IMS data, the statements of work for the active CLINs,
and the monthly QUAD status reports. The audit team, like Deepwater
program management, was able to use IMS to determine the status of
assets, unfortunately the lack of an updated acquisition schedule,
similar to what the team had used in auditing DoD's major defense
acquisition programs, lead to conclusions such as, "(w)hile the Coast
Guard could not provide us with an updated integrated schedule, we
developed the current acquisition status of a number of key Deepwater
assets from documents provided by the Coast Guard." The Coast Guard
provided relevant IMS data, it was just at a lower tier than
anticipated.
Overall, there is full agreement with the report's determination that
the $168 million appropriated in fiscal year 2004 for the Deepwater
program above the President's request of $500 million does not fully
return the program to its original 2002 Implementation Plan Schedule
nor to its planned funding levels. As noted in the report, this delay
in asset delivery is due to lack of funding and other legacy
sustainment problems such as responding to the extensive deterioration
of 110' hulls and the need for immediate re-engining of HH-65s.
The draft report should highlight the impact of funding shortfalls on
delays in asset delivery. For example, the graph on page 23 should
explain that the reason for asset delivery delays was a lack of funds
in the first two years of contract execution. Any program that receives
approximately $125 million less than the $918 million planned, which is
a 13.6 percent decrease for the first two years, will have delays.
This view is supported by the April 17, 2004, GAO testimony before the
Senate Subcommittee on Oceans Fisheries, and Coast Guard, Committee on
Commerce, Science, and Transportation. "In a 2001 report," GAO
reported, "we expressed concern that the Coast Guard risked slippages
and cost escalation if project funding fell short of planned funding
levels. Now, very early in the program our concerns are being realized.
Program funding in the first 2 years was less than the agency planned
by about $125 million. This resulted in delays in the scheduled
delivery of key Deepwater assets, such as the maritime patrol
aircraft."
Even with the Congressional increase of $168 million in the third year
of the program, cumulative funding was still approximately $40 million
less than planned. When a program is underfunded, schedule delays are
unavoidable. This is not a unique risk to Deepwater, but a universal
risk to any major program in that all major programs plan their Master
Schedule based on a projected funding level. If the funding received is
less than the funding planned, schedule slippage will result.
Additionally, if a substantial amount of the shortfall is made up in
the third year and then an assessment is made right at the start of the
third year, there will still be delays. These slippages
have no relationship to updating the schedule. These delays would exist
whether or not the schedule was updated. The updated schedule would
have still shown the same delays that the GAO report displayed on page
23.
Given the above information, the Coast Guard does not concur with the
audit report's conclusion that the absence of an updated integrated
schedule is a symptom of the management concerns GAO reported in March
2004. Contrary to the implications of the draft report's language, the
Coast Guard is effectively tracking cost, schedule, and performance,
and identifying potential risks by maintaining existing management and
tracking tools such as the Earned Value Management System (EVMS) and
the Monthly Quad Charts. Just as defense acquisitions report quarterly
to DoD management, the Coast Guard reports this information quarterly
to DHS.
As we continue to work together, our agencies will achieve greater
mutual understanding of this dynamic and challenging acquisition
program. To further that understanding, I also would like to clarify
one aspect of the Coast Guard's Deepwater missions and the program's
history. While it is accurate to state that the Coast Guard's Deepwater
missions generally occur beyond 50 miles from shore, it is important to
recognize that these missions, so critical to America's homeland
security, start at America's ports, waterways, and coasts and extend
seaward to wherever the Coast Guard is required to take appropriate
action. Deepwater's more capable, sustainable, interoperable, and
flexible platforms and systems will contribute significantly. to the
Coast Guard's ability to address and defeat maritime security threats
closer to our shores and in our ports. These missions are characterized
as requiring powerful C4ISR capabilities, extended on-scene presence,
any mission using Coast Guard aviation assets, or significant
prosecution power.
The Coast Guard has incorporated recommendations made by previous
reviews of the Deepwater Program by GAO and the Department of Homeland
Security. I thank you for your detailed analysis and observations and
appreciate the opportunity to share our lessons learned, successes, and
growing pains in an open environment as we continue to embrace the
tenets of a successful learning organization. I look forward to
continued positive dialog with you and your staff as we work to improve
the management of the Deepwater program during the coming years. You
have our commitment to engage in continuous improvement.
Signed by:
ART S. HOROWITZ:
Deputy Assistant:
Commandant For Planning, Resources, and Procurement:
FOOTNOTES
[1] The Deepwater program is scheduled to last for 30 years, the assets
are expected to be delivered in the first 20 years, and the contractor
is to be retained an additional 10 years to continue implementing the
program.
[2] See U.S. General Accounting Office, Coast Guard: Progress Being
Made on Deepwater Project, but Risks Remain, GAO-01-564 (Washington,
D.C.: May 2, 2001).
[3] See U.S. General Accounting Office, Contract Management: Coast
Guard's Deepwater Program Needs Increased Attention to Management and
Contractor Oversight, GAO-04-380 (Washington, D.C.: Mar. 9, 2004).
[4] See U.S. General Accounting Office, Coast Guard: Key Management and
Budget Challenges for Fiscal Year 2005 and Beyond, GAO-04-636T
(Washington, D.C.: Apr. 7, 2004).
[5] These amounts are in nominal (current-year) dollars.
[6] The conversion is to extend the 110-foot patrol boats by 13 feet to
incorporate a stern ramp.
[7] An April 2004 RAND Corporation study concluded that the Coast Guard
will need twice the number of cutters and 50 percent more aircraft to
meet new national security requirements. U.S. Coast Guard's Deepwater
Force Modernization Plan: Can it Be Accelerated? Will Meet Changing
Security Needs?, The Rand Corporation, Santa Monica, Calif., April
2004.
[8] Through a 1987 agreement, the Navy provides to the Coast Guard all
Navy-owned, military readiness equipment and associated support
materials that the Navy deems necessary to enable the Coast Guard to
carry out assigned missions while operating with the Navy. Upon
declaration of war, or when the President directs, the Coast Guard
operates as a service of the Navy and is subject to the orders of the
Secretary of the Navy.
GAO's Mission:
The General Accounting Office, the investigative arm of Congress,
exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. General Accounting Office
441 G Street NW,
Room LM Washington,
D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.
General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.
20548: