Tactical Aircraft
F/A-22 and JSF Acquisition Plans and Implications for Tactical Aircraft Modernization
Gao ID: GAO-05-519T April 6, 2005
The F/A-22 Raptor and Joint Strike Fighter (JSF)--two of the Department of Defense's (DOD) major tactical aircraft fighter programs--are intended to replace aging tactical fighter aircraft with highly advanced, stealthy aircraft. The two programs combined have a potential future investment of more than $240 billion. This testimony highlights key concerns in the F/A-22 and JSF programs and discusses the implications on DOD's overall investment strategy for modernizing its tactical fixed-wing aircraft. Last month, GAO issued comprehensive reports on the numerous setbacks these programs have experienced since they were initiated and their effect on the F/A- 22 and JSF business cases.
Significant changes in the F/A-22 program have severely weakened its original business case. Since the F/A-22 program began in 1986, new threats emerged and mission requirements changed; to keep the F/A-22 viable, the Air Force has planned for large investments in new capabilities. Significant delays and cost increases have affected affordability, reducing planned deliveries from 750 F/A-22 aircraft to fewer than 180. The recent budget decision to terminate procurement of the F/A-22 after fiscal year 2008 and the prospect of additional funding cuts also have significant implications for the program's viability and modernization efforts. JSF's original business case, established when the program began in 1996, is unexecutable. The cost estimate to develop the aircraft has increased 80 percent, operational capability has been pushed out 2 years, and expected acquisition quantities have been cut by 535 aircraft. The JSF program is approaching key investment decisions that will greatly influence the efficiency of the remaining funding--more than 90 percent of the $245 billion estimated total program costs. This sizable investment greatly raises the stakes to meet future promises. While DOD has been working to resolve early design and performance problems, continuing program uncertainties suggest DOD could use more time to gain knowledge before it commits to a new business case and moves forward. To reduce the risk of further cost and schedule growth, any new business case must include an acquisition strategy that adopts an evolutionary, knowledge-based approach to product development. Currently, the JSF program plans to make key production decisions before critical knowledge is captured. Taken together, these issues have broader implications for the DOD tactical fixed-wing aircraft modernization program, raising questions as to whether overarching goals to reduce average aircraft age and ownership costs while maintaining the force structure are now achievable. The 2005 Quadrennial Defense Review provides an opportunity for DOD to assess needs and plans and to weigh options for accomplishing its tactical aircraft goals.
GAO-05-519T, Tactical Aircraft: F/A-22 and JSF Acquisition Plans and Implications for Tactical Aircraft Modernization
This is the accessible text file for GAO report number GAO-05-519T
entitled 'Tactical Aircraft: F/A-22 and JSF Acquisition Plans and
Implications for Tactical Aircraft Modernization' which was released on
April 6, 2005.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on AirLand, Committee on Armed Services, U.S.
Senate:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 2:30 p.m. EDT:
Wednesday, April 6, 2005:
Tactical Aircraft:
F/A-22 and JSF Acquisition Plans and Implications for Tactical Aircraft
Modernization:
Statement of Michael Sullivan, Director:
Acquisition and Sourcing Management Issues:
GAO-05-519T:
GAO Highlights:
Highlights of GAO-05-519T, a testimony before the Subcommittee on
AirLand, Committee on Armed Services, U.S. Senate:
Why GAO Did This Study:
The F/A-22 Raptor and Joint Strike Fighter (JSF)”two of the Department
of Defense‘s (DOD) major tactical aircraft fighter programs”are
intended to replace aging tactical fighter aircraft with highly
advanced, stealthy aircraft. The two programs combined have a potential
future investment of more than $240 billion.
This testimony highlights key concerns in the F/A-22 and JSF programs
and discusses the implications on DOD‘s overall investment strategy for
modernizing its tactical fixed-wing aircraft. Last month, GAO issued
comprehensive reports on the numerous setbacks these programs have
experienced since they were initiated and their effect on the F/A-22
and JSF business cases.
What GAO Found:
Significant changes in the F/A-22 program have severely weakened its
original business case. Since the F/A-22 program began in 1986, new
threats emerged and mission requirements changed; to keep the F/A-22
viable, the Air Force has planned for large investments in new
capabilities. Significant delays and cost increases have affected
affordability, reducing planned deliveries from 750 F/A-22 aircraft to
fewer than 180. The recent budget decision to terminate procurement of
the F/A-22 after fiscal year 2008 and the prospect of additional
funding cuts also have significant implications for the program‘s
viability and modernization efforts.
JSF‘s original business case, established when the program began in
1996, is unexecutable. The cost estimate to develop the aircraft has
increased 80 percent, operational capability has been pushed out 2
years, and expected acquisition quantities have been cut by 535
aircraft. The JSF program is approaching key investment decisions that
will greatly influence the efficiency of the remaining funding”more
than 90 percent of the $245 billion estimated total program costs. This
sizable investment greatly raises the stakes to meet future promises.
While DOD has been working to resolve early design and performance
problems, continuing program uncertainties suggest DOD could use more
time to gain knowledge before it commits to a new business case and
moves forward. To reduce the risk of further cost and schedule growth,
any new business case must include an acquisition strategy that adopts
an evolutionary, knowledge-based approach to product development.
Currently, the JSF program plans to make key production decisions
before critical knowledge is captured.
JSF Program‘s Annual Funding Requirements from 2005 to 2027:
[See PDF for image]
[End of figure]
Taken together, these issues have broader implications for the DOD
tactical fixed-wing aircraft modernization program, raising questions
as to whether overarching goals to reduce average aircraft age and
ownership costs while maintaining the force structure are now
achievable. The 2005 Quadrennial Defense Review provides an opportunity
for DOD to assess needs and plans and to weigh options for
accomplishing its tactical aircraft goals.
What GAO Recommends:
GAO made recommendations in two reports issued in March 2005. For the
F/A-22 program, GAO reiterated and expanded upon its 2004
recommendation for DOD to establish a new business case”one that
justifies the continued expenditure of funds on the F/A-22. For the JSF
program, GAO recommended that”before the program moves forward”DOD
establish an executable business case that is consistent with best
practices and DOD policy regarding knowledge-based, evolutionary
acquisitions.
www.gao.gov/cgi-bin/getrpt?GAO-05-519T
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Michael J. Sullivan at
(202) 512-4841 or sullivanm@gao.gov.
[End of section]
Mr. Chairman and members of the subcommittee:
I am pleased to be here today to participate in the Subcommittee's
hearing on the status of two of the Department of Defense's (DOD) major
tactical aircraft fighter programs, the F/A-22 Raptor and the F-35,
also known as the Joint Strike Fighter (JSF).[Footnote 1] Both programs
are intended to replace aging tactical fighter aircraft with highly
advanced, stealthy aircraft. These two programs represent a potential
future investment for DOD of about $240 billion to modernize tactical
fixed-wing aircraft.
My statement today will highlight key concerns in the F/A-22 and JSF
programs. Our work has shown that because of the significant changes in
the F/A-22 development and procurement programs and the key investment
decisions remaining, a new business case is needed to justify aircraft
quantities and investments in new capabilities. Changes in the JSF
program and DOD's intent to begin producing aircraft with at least 6
years of development remaining suggest that the JSF does not yet have
the knowledge to justify future investments. In addition to
highlighting specific F/A-22 and JSF program issues, I will discuss the
implications these development programs have on DOD's overall
investment strategy for modernizing the tactical fixed-wing aircraft.
My statement is primarily based on our recent reports on the F/A-22 and
JSF programs.[Footnote 2] We performed the work associated with this
statement in accordance with generally accepted government auditing
standards.
Summary:
The F/A-22 has been in development for 19 years, and cost increases and
delays have created affordability concerns that reduced the number of
aircraft planned for acquisition. A changing world environment and
threats over this time frame have compelled the Air Force to plan for
large investments in new capabilities to keep the F/A-22 viable.
Termination of F/A-22 procurement after fiscal year 2008 has also
placed modernization plans in doubt. The original business case
elements--needs and resources---set at the outset of the program are no
longer valid, and a new business case is needed to justify future
investments for aircraft quantities and modernization efforts. The F/A-
22's acquisition approach was not knowledge-based or evolutionary. It
attempted to develop revolutionary capability in a single step, causing
significant technology and design uncertainties and, eventually,
significant cost overruns and schedule delays. Lessons from the F/A-22
program can be applied to the JSF program to improve on its outcomes.
While relatively early in its acquisition program, the JSF program has
experienced design and weight problems that, if not solved, will affect
aircraft performance. These problems have led to increased development
and procurement costs and schedule delays so far. In addition, the
program's customers are still not sure how many aircraft they will
need. The combination of cost overruns and quantity reductions has
already diluted DOD's buying power and made the original JSF business
case unexecutable. Given continuing program uncertainties, DOD could
use more time right now to gain knowledge before it commits to a new
business case for its substantial remaining investments. The JSF's
current acquisition strategy does not embrace evolutionary, knowledge-
based techniques intended to reduce risks. Key decisions, like the
planned 2007 production decision, are expected to occur before critical
knowledge is captured. Time taken now to gain knowledge will avoid
placing sizable investments in production capabilities at risk to
expensive changes.
Taken together, the current status and continuing risk in these two
programs have broader implications to the DOD tactical fixed-wing
aircraft modernization program, raising questions as to whether its
overarching goals are now achievable. Decreases in quantities alone--
about 30 percent since original plans--raise questions about how well
the aircraft will complement our tactical air forces in the future.
Background:
The F/A-22 aircraft program is acquiring the Air Force's next
generation, multimission fighter for about $63.8 billion.[Footnote 3]
The continued need for the F/A-22, its increasing costs, and the
quantities required to perform its mission have been the subject of a
continuing debate within DOD and Congress. Supporters cite the F/A-22's
advanced features--stealth, supercruise speed, maneuverability, and
integrated avionics--as integral to the Air Force's Global Strike
initiative and for maintaining air superiority over potential future
adversaries for years to come.[Footnote 4] Critics, on the other hand,
argue that the Soviet threat the F/A-22 was originally designed to
counter no longer exists and that its remaining budget dollars could
better be invested in enhancing current air assets and acquiring new
and more transformational capabilities that will allow it to meet
evolving threats. The debate continues as a December 2004 budget
decision by the Office of the Secretary of Defense (OSD) reduced F/A-22
funding and the number of aircraft to be acquired. A full-rate
production decision is expected in early April, but the Air Force
already has 98 aircraft on contract.[Footnote 5]
The JSF program is DOD's most costly aircraft acquisition program. The
program's goals are to develop and field more than 2,400 stealthy
strike fighter aircraft for the Navy, Air Force, and Marine Corps and
potentially several hundred more aircraft for U.S. allies.
International participation in the development of this system is a
vital part of the acquisition strategy. The JSF is intended to provide
greater capability and to replace DOD's aging fighter and attack
aircraft. DOD estimates that the total cost to develop and procure its
fleet of aircraft will reach $245 billion, with total costs to maintain
and operate the JSF adding another $344 billion over its life cycle.
Since the program began in November 1996, it has experienced technical
challenges that have resulted in significant cost increases and
schedule overruns. During most of 2004, the program worked to
understand and define current development risks in order to prepare
more accurate cost and delivery estimates to support development and
production investment decisions planned over the next 2 years.
A key to successful acquisition programs is the development of a
business case that should match requirements with resources--proven
technologies, sufficient engineering capabilities, time, and funding--
-when undertaking a new product development. First, the user's needs
must be accurately defined, alternative approaches to satisfying these
needs must be properly analyzed, and quantities needed for the chosen
system must be well understood. The developed product must be
producible at a cost that matches the users' expectations and budgetary
resources. Finally, the developer must have the resources to design and
deliver the product with the features that the customer wants and to
deliver it when it is needed. If the financial, material, and
intellectual resources to develop the product are not available, a
program incurs substantial risk in moving forward.
A New Business Case Is Needed to Justify Continued Investment in the F/
A-22 Program:
Since its inception in 1986, the F/A-22 aircraft program has
encountered numerous and continuing management and technical
challenges. Changing threats, missions, and requirements have severely
weakened the original business case. Program milestones have slipped
substantially; development costs have more than doubled; and a
modernization program was added. The recent budget decision to
terminate procurement after fiscal year 2008, the prospect of
additional cuts because of ceilings on program cost, and upcoming
defense reviews have significant implications for the program's
viability and the future of modernization efforts.
In March 2004, we reported that the significant changes in the F/A-22's
cost, quantity, capabilities, and mission and the persistent problems
and delays in its development and testing schedules called for a new
business case to justify the continued need for the F/A-22.[Footnote 6]
We recommended that OSD direct the Air Force to consider alternatives
and examine the constraints of future defense spending. In subsequent
testimony, we reiterated this position, stating that competing
priorities--both internal and external to DOD's budget--require a sound
and sustainable business case for DOD's acquisition programs based on
comprehensive needs assessments and a thorough analysis of available
resources.[Footnote 7] In response to our recommendation, DOD stated
its routine budgeting processes annually addressed business case issues
on the F/A-22. We disagreed, as we do not think those processes provide
the breadth or depth of analysis needed to develop a comprehensive new
business case.
Problems in the F/A-22 Program Strain Future Viability:
When initiated, the F/A-22 acquisition program planned to complete
development in 1995, achieve initial operational capability by March
1996, and ultimately procure 750 aircraft. The Air Force currently
plans to complete system development in 2005, achieve initial
operational capability by December 2005, and procure 178 aircraft.
Amidst concerns about escalating costs and schedule, the Congress
placed cost limitations on both development and production budgets in
1997,[Footnote 8] later removing the development cost cap.[Footnote 9]
According to the Air Force, the current production cost cap is $37.3
billion. Affordability concerns have, in part, led to the steady
decrease in procurement quantities. Two major reviews of defense force
structure and acquisition plans--the 1993 Bottom-Up Review and the 1997
Quadrennial Defense Review (QDR)--significantly reduced F/A-22
quantities. OSD's "buy to budget" acquisition strategy essentially
placed a ceiling on total program costs resulting in reducing
quantities, and in December 2004, Program Budget Decision 753 reduced
F/A-22 funding by $10.5 billion, further reducing in all likelihood
procurement quantities from 275 to 178 aircraft.[Footnote 10] The
December 2004 budget decision also ended procurement in fiscal year
2008, instead of fiscal year 2011.
Decreased procurement quantities, along with increased development and
production costs and increased costs to modernize and enhance
capability, have led to rising acquisition unit costs. Figure 1
illustrates the downward trend in procurement quantities and the upward
trend in program acquisition unit costs.[Footnote 11]
Figure 1: Quantity and Program Acquisition Unit Cost of F/A-22s:
[See PDF for image]
[End of figure]
In arguing for reversal of the December 2004 budget decision to stop
procurement of the F/A-22 in 2008, Air Force officials noted that the
decision obviates production economies and efficiencies that the Air
Force expected to achieve through a multiyear procurement contract that
was to begin in fiscal year 2008. Officials also stated that cutting
production quantities from the final years of the program limits
expected savings in annual unit procurement costs. As with many DOD
acquisitions, Air Force program officials had assumed in future budgets
that the costs for buying F/A-22s would decrease as a result of
manufacturing efficiencies, reduced fixed costs, productivity projects,
and more economical buying quantities. For example, the average unit
flyaway cost for the F/A-22 in 2003 was about $178 million, while the
unit flyaway costs for future annual buys were projected before the
budget decision to decrease to $127 million, $111 million, and $108
million in fiscal years 2007, 2008, and 2009 respectively.[Footnote 12]
Now that the program will be truncated in 2008, the less expensive
aircraft in 2009 and beyond will not be bought and unit costs are now
projected at $135 million in 2007 and $149 million in 2008 (increases
associated with close-out of production).
The F/A-22 program changes have also resulted in schedule delays for
completing development testing, operational testing, and, consequently,
the full-rate production decision. That decision is currently expected
later this month but could slip again given the unsettled environment.
One critical input to the decision is the report by the Office of the
Director of Operational Test and Evaluation to the Congress and defense
leadership on the adequacy and results of the recently completed
initial operational test and evaluation.[Footnote 13] In addition, the
F/A-22 program must demonstrate it satisfies criteria established by
the Defense Acquisition Board in November 2004, which include
delivering a fully resourced plan for follow-on testing to correct
deficiencies identified in initial operational testing and evaluation,
achieving design stability of the avionics software, demonstrating
mature manufacturing processes, and validating technical order
data.[Footnote 14]
Final reports detailing the results from initial operational testing
and evaluation were not available for our review, but Air Force test
officials told us that testing showed the F/A-22 was "overwhelmingly
effective" as an air superiority fighter and that its supporting
systems were "potentially suitable" pending the correction of
identified deficiencies. Operational testing of the limited ground
attack capability in the current design was not conducted but is
scheduled during follow-on testing planned to start in July
2005.[Footnote 15] Air Force officials believe that test results
support approval of full-rate production. They also believe that
deficiencies identified in aircraft reliability and maintainability
(including maintaining low observable characteristics) and in the
integrated diagnostic systems are readily correctible and the aircraft
should meet the needs of the warfighter by the scheduled initial
operational capability date in December 2005. However, whether the Air
Force can accomplish all of this by December 2005 remains to be seen.
Future of Modernization Plans in Doubt:
Originally, the F/A-22 was intended to replace the F-15 and achieve air-
to-air superiority to counter large numbers of advanced Soviet fighters
in conventional warfare. However, over the 19 years that the aircraft
has been in development, the projected Cold War threats never
materialized and new threats emerged, changing tactical fighter
requirements and operational war plans. The Air Force now plans to
implement a Global Strike concept of operations by developing a robust
air-to-ground attack capability to allow the aircraft to counter a
greater variety of targets, such as surface-to-air missiles systems,
that pose a significant threat to U.S. aircraft. It also plans to equip
most of the F/A-22 fleet with improved capabilities to satisfy expanded
warfighter requirements and to take on new missions, including
intelligence data gathering and the suppression of enemy air defenses
and interdiction.
To implement its Global Strike concept, the Air Force established a
time-phased modernization program. Table 1 shows how the Air Force
intended to integrate new capabilities incrementally before the
December 2004 budget decision reduced quantities by 96 aircraft. At the
time of our review, officials were still determining the impacts of the
budget decision on the modernization program content and quantities.
Table 1: Planned Modernization Enhancements for the F/A-22 Program:
[See PDF for image]
Sources: Air Force and Office of Secretary of Defense.
[A] Global Strike Enhanced includes two increments of capability, with
the first increment incorporated in fiscal year 2009 and the second in
2011.
[B] The Air Force planned to have three configurations (called blocks)
that included specific enhancements developed in the modernization
program.
[C] This quantity included in Global Strike Full amount. Total 128
aircraft planned for block 40.
[End of table]
In March 2003, OSD's Cost Analysis Improvement Group (CAIG) estimated
that the Air Force would need $11.7 billion for the planned
modernization programs through fiscal year 2018.[Footnote 16] The Air
Force's latest estimate includes about $4.1 billion through fiscal year
2011 for the first two modernization increments (blocks 20 and 30) and
about $1.3 billion through fiscal year 2011 for the latter two
increments (block 40). The Air Force will continue to manage blocks 20
and 30 as part of the F/A-22 acquisition program. To manage block 40
efforts, OSD has directed the Air Force to establish a separate
modernization program.[Footnote 17] Future modernization costs beyond
2011 have not been fully definitized and are subject to change. The
modernization program manager projected annual funding of $700 to $750
million would be needed for the currently planned modernization program
after 2011.
The December 2004 budget decision places much of the modernization
program in doubt, particularly the latter stages. This is because that
decision terminated F/A-22 procurement after fiscal year 2008 and many
of these new and advanced capabilities had been planned for aircraft
that now will not be bought. Therefore, if the budget cut is sustained,
the modernization program as currently planned is largely obsolete and
some funding for advanced capabilities planned to be incorporated after
fiscal year 2008 could be available for other uses. At the time of our
review, Air Force officials were still restructuring the modernization
program in response to the budget decision, including revising the
desired mix of capabilities and the number of aircraft in each
configuration. With the reduced quantity, they are considering having
only two configurations, with the second incorporating some
enhancements originally planned for the third configuration.
The budget decision causes a ripple effect on other resource plans tied
to the modernization. For example, it brings into question the need for
(1) upgrades to the computer architecture and processors estimated to
cost between $400 million and $500 million; (2) upgrades to government
laboratory and test range infrastructure like software avionics
integration labs, flying test beds, and test ranges estimated to cost
about $1.8 billion; and (3) changes in other activities supporting
modernization enhancements in the production line, retrofit of
aircraft, and establishing depot maintenance support estimated at more
than $1.6 billion.
New JSF Business Case and Acquisition Strategy Is Critical for Program
Success:
Unlike the F/A-22 program, which is near the end of development, the
JSF program is approaching key investment decisions that will greatly
influence the efficiency of the remaining funding--over 90 percent of
the $245 billion estimated total program costs--and determine the risk
DOD is willing to accept. DOD has not been able to deliver on its
initial promise, and the sizable investment greatly raises the stakes
to meet future promises. Given continuing program uncertainties, DOD
could use more time to gain knowledge before it commits to a new
business case and moves forward. Any new business case must be
accompanied by an acquisition strategy that adopts an evolutionary
approach to product development--one that enables knowledge-based
decisions to maximize the return on remaining dollars--as dictated by
best practices.
DOD Needs More Time to Develop a New JSF Business Case:
Increased program costs, delayed schedules, and reduced quantities have
diluted DOD's buying power and made the original JSF business case
unexecutable. Program instability at this time makes the development of
a new and viable business case difficult to prepare. The cost estimate
to fully develop the JSF has increased by more than 80 percent.
Development costs were originally estimated at roughly $25 billion. By
the 2001 system development decision, these costs increased almost $10
billion, and by 2004, costs increased an additional $10 billion,
pushing total development cost estimates to nearly $45 billion. Current
estimates for the program acquisition unit cost are about $100 million,
a 23 percent increase since 2001. Ongoing OSD cost reviews could result
in further increases to the estimated program cost. At the same time,
procurement quantities have been reduced by 535 aircraft and the
delivery of operational aircraft has been delayed. Figure 2 shows how
costs, quantities, and schedules have changed since first estimates
based on data as of January 2005.
Figure 2: Measures of JSF Cost and Schedule Changes:
[See PDF for image]
[End of figure]
Ongoing program uncertainties--including uncertainties about the
aircraft's design and procurement quantities--make it difficult to
understand what capabilities can be delivered with future investments.
For example, DOD has been working over the past year to restructure the
JSF program to accommodate changes in the aircraft's design; until this
restructuring is completed, it will be difficult to accurately estimate
program costs. The need for design changes largely resulted from the
increased weight of the short takeoff and vertical landing variant and
the impact it was having on key performance parameters. The other JSF
variants' designs were affected as well. The program plans to have a
more comprehensive cost estimate in the spring of 2005. However, a
detailed assessment has not been conducted to determine the impact that
the restructured program will have on meeting performance
specifications. Until the detailed design efforts are complete--after
the critical design review in February 2006--the program will have
difficulty assessing the impact of the design changes on performance.
While the program office anticipates that recent design changes will
allow the aircraft to meet key performance parameters, it will not know
with certainty if the weight problems have been resolved until after
the plane is manufactured and weighed in mid-2007.
Program officials are also examining ways to reduce program
requirements while keeping cost and schedules constant. Design and
software teams have found greater complexity and less efficiency as
they develop the 17 million lines of software needed for the system.
Program analysis indicated that some aircraft capabilities will have to
be deferred to stay within cost and schedule constraints. As a result,
the program office is working with the warfighters to determine what
capabilities could be deferred to later in the development program or
to follow-on development efforts while still meeting the warfighter's
basic needs. It may be some time before DOD knows when and what
capabilities it will be able to deliver. The content and schedule of
the planned 7-year, 10,000-hour flight test program is also being
examined. According to the program office, the test program was already
considered aggressive, and recent program changes have only increased
the risks of completing it on time.
Finally, uncertainty about the number and mix of variants the services
plan to purchase will also affect JSF's acquisition plans. While the
Air Force has announced its intention to acquire the short takeoff and
vertical-landing variant, it has yet to announce when or how many it
expects to buy or how this purchase will affect the quantity of the
conventional takeoff and landing variant it plans to buy. The number
and mix of JSF variants that the Navy and Marine Corps intend to
purchase--and their related procurement costs--also remain
undetermined. Foreign partners have expressed intent to buy about 700
aircraft between 2012 and 2015, but no formal agreements have been
signed at this time. The 2005 Quadrennial Defense Review--an
examination of U.S. defense needs--could also affect the procurement
quantities and schedule. In developing a reliable business case,
knowing the quantities to be purchased is equally as important as other
elements. Without knowing types and quantities the program manager
cannot accurately estimate costs or plan for production.
Timely Capture of Product Knowledge Needed to Support Future Business
Decisions:
In recent years, DOD has revised its weapons acquisition policy to
support an evolutionary, knowledge-based strategy based on best
practices--key to executing a future business case and making more
informed business decisions.[Footnote 18] With an evolutionary
acquisition approach, new products are developed in increments based on
available resources. Design elements that are not currently achievable
are planned for and managed as separate acquisitions in future
generations of the product with separate milestones, costs, and
schedules. While JSF's acquisition strategy calls for initially
delivering a small number of aircraft with limited capabilities, the
program has committed to deliver the full capability by the end of
system development and demonstration in 2013 within an established cost
and schedule for a single increment, contrary to an evolutionary
approach.
In addition, JSF's planned approach will not capture adequate knowledge
about technologies, design, and manufacturing processes for investment
decisions at key investment junctures. Our past work has shown that to
ensure successful program outcomes, a high level of demonstrated
knowledge must be attained at three key junctures for each increment in
the program. Table 2 compares best practice and JSF knowledge
expectations at each critical point.
Table 2: Knowledge Attainment on JSF Program at Critical Junctures:
Knowledge point 1: Best practice: Should be achieved at development
start;
Knowledge point 2: Best practice: Should be achieved by the design
review;
Knowledge point 3: Best practice: Should be achieved by the start of
production.
Knowledge point 1: Separate technology and product development, deliver
mature technology, and have preliminary design based on systems
engineering principles;
Knowledge point 2: Completion of 90 percent of engineering drawing
packages for structures and systems, critical design review completed,
and design prototyped;
Knowledge point 3: 100 percent of critical manufacturing processes
under statistical control, demonstration of a fully integrated product
in its operational environment to show it will work as intended, and
reliability goals demonstrated.
Best practice: JSF practice;
Knowledge point 1: Knowledge point 1 was not attained at milestone B in
2001;
Knowledge point 2: Knowledge point 2 will not be attained by design
review in 2006 under current plan;
Knowledge point 3: Knowledge point 3 will not be attained by start of
production in 2007 under current plan.
Knowledge point 1: Failed to separate technology and product
development. Critical technologies not mature and sound preliminary
design not established. Several technologies not expected to be mature
until after production begins;
Knowledge point 2: The program estimates 35 percent of the engineering
drawing packages are expected to be released at the critical design
reviews. Also, prototype testing will not be done prior to the design
review. The design will not be stable until after production begins;
Knowledge point 3: Program does not expect to demonstrate that the
critical processes are under statistical control until 2009. Program
expects to demonstrate that a fully integrated aircraft will work as
intended and meets reliability goals in 2010-2012 timeframe.
Source: GAO data and analysis of DOD data:
[End of table]
As shown in table 2, the JSF program will lack critical production
knowledge when it plans to enter low-rate initial production in 2007.
The department has included about $152.4 million in its fiscal year
2006 budget request to begin long lead funding for low-rate initial
production. This production decision is critical, and the knowledge
required to be captured by knowledge point 3 in our best practice model
should be achieved before this critical juncture is reached. If
production begins without knowledge that the design is mature, critical
manufacturing processes are under control, and reliability is
demonstrated, costly changes to the design and manufacturing processes
can occur, driving up costs and delaying delivery of the needed
capability to the warfighter. The size of the potential risk is
illustrated in the production ramp-up and investments planned after
this decision is made. Between 2007 (the start of low-rate production)
and 2013 (the scheduled start of full-rate production) DOD plans to buy
nearly 500 JSF aircraft--20 percent of its planned total buys--at a
cost of roughly $50 billion. Under the program's preliminary plan, DOD
expects to increase low-rate production from 5 aircraft a year to 143
aircraft a year, significantly increasing the financial investment
after production begins.[Footnote 19] Between 2007 and 2009, the
program plans to increase low-rate production spending from about $100
million a month to more than $500 million a month, and before
development has ended and an integrated aircraft has undergone
operational evaluations, DOD expects to spend nearly $1 billion a month.
To achieve its production rate, the program will invest significantly
in tooling, facilities, and personnel. According to contractor
officials, an additional $1.2 billion in tooling alone would be needed
to ramp up the production rate to 143 aircraft a year. Over half of
this increase would be needed by 2009--more than 2 years before
operational flight testing begins. Figure 3 shows the planned
production ramp up, along with the concurrently planned development
program for the JSF.
Figure 3: Overlap of JSF Low-Rate Production and System Development and
Demonstration Activities (Includes U.S. and U.K. Quantities):
[See PDF for image]
[End of figure]
Following are examples of technology, design, and production knowledge
that should be but will not be captured when the low-rate production
decision is scheduled to be made.
* Only one of JSF's eight critical technologies is expected to be
demonstrated in an operational environment by the 2007 production
decision.
* Only about 40 percent of the 17 million lines of code needed for the
system's software will have been released, and complex software needed
to integrate the advanced mission systems is not scheduled for release
until about 2010--3 years after JSF is scheduled to enter production.
Further, most structural fatigue testing and radar cross section
testing of full-up test articles are not planned to be completed until
2010.
* The program will not demonstrate that critical manufacturing
processes are in statistical control, and flight testing of a fully
configured and integrated JSF (with critical mission systems and
prognostics technologies) is not scheduled until 2011.
Further, because of the risk created by the extreme overlap of
development and production, the program office plans to place initial
production orders on a cost reimbursement contract, placing a higher
cost risk burden on the government than is normal. These contracts
provide for payment of allowable incurred costs, to the extent
prescribed in the contract. They are used when uncertainties involved
in contract performance do not permit costs to be estimated with
sufficient accuracy to use any type of fixed-price contract and place
greater cost risk on the buyer--in this case, DOD. In the case of the
JSF, a fixed-price contract will not be possible until late in the
development program.
JSF's Substantial Funding Requirements May Be Difficult to Sustain in
the Current Fiscal Environment:
Regardless of likely increases in program costs, the sizable continued
investment in JSF must be viewed within the context of the fiscal
imbalance facing the nation over the next 10 years. The JSF program
will have to compete with many other large defense programs as well as
other priorities external to DOD's budget. JSF's acquisition strategy
assumes an unprecedented $225 billion in funding over the next 22 years
or an average of $10 billion a year (see fig. 4).[Footnote 20]
Figure 4: JSF Program's Annual Funding Requirements (as of December
2003):
[See PDF for image]
[End of figure]
Funding challenges will be even greater if the program fails to stay
within current cost and schedule estimates. For example, we estimate
that another 1-year delay in JSF development would cost $4 billion to
$5 billion based on current and expected development spending rates. A
10-percent increase in production costs would amount to $20 billion.
Implications for the Current Status of Tactical Aircraft Programs:
Continuing changes and uncertainties in the F/A-22 and JSF programs
present significant challenges to DOD in achieving its modernization
plans which attempt to blend many factors within affordability
constraints. Factors in the decision making process can include
aircraft age, ownership costs, readiness, force structure, operating
concepts, competing needs, available funds, defense policy, and
others.[Footnote 21] Today, both F/A-22 and JSF programs include
significantly fewer aircraft than originally planned---30 percent fewer
or over 1,000 aircraft. Deliveries intended to provide an operational
capability have also been delayed in both programs, almost 10 years in
the case of the F/A-22, requiring legacy systems to operate longer than
planned. As legacy tactical aircraft age and near the end of their
useful life, they require ever increasing investments to keep them
ready and capable as the threat evolves--the cost of ownership.
The reduced F/A-22 force size, now fewer than 180 F/A-22 aircraft
instead of 750 aircraft planned at the start of the program, could
affect the Air Force's force structure and employment strategy. The Air
Force still maintains it has a nominal requirement for 381 aircraft to
meet its new Air and Space Expeditionary Forces--the operational
mechanism through which the Air Force allocates forces to meet the
combatant commanders' force rotation requirements--and Global Strike
concept of operations. The Air Force planned on 10 F/A-22 squadrons to
support this operational concept. Using the Air Force's normal methods
for calculating force requirements, only about 110 aircraft of the
total aircraft procured would be classified as available for combat and
assignment to operational units[Footnote 22]--yielding only 4 or 5
typical fighter squadrons for assigning across the planned 10 air and
space expeditionary units. The reduced fleet size may require the Air
Force to consider the F/A-22 as a low-density/high-demand asset, which
would require changes in these expected management and employment
strategies. It also has implications for related resources and plans,
including military personnel requirements, numbers of operating
locations, support equipment, spare parts, and logistical support
mechanisms.
Other factors will come to play in the 2005 Quadrennial Defense Review.
OSD has directed the review to include an assessment of joint air
dominance in future warfare and the contributions provided by all
tactical aircraft. An announced defense policy goal is to redirect
investment from areas of conventional warfare, where the United States
enjoys a strong combat advantage, toward more transformational
capabilities needed to counter "irregular" threats, such as the
insurgency in Iraq and the ongoing war on terror. DOD is also
conducting a set of joint capability reviews to ensure acquisition
decisions are based on providing integrated capabilities rather than
focused on individual weapons systems. The study results, although
still months away, could further affect the future of the F/A-22 and
JSF programs including the F/A-22's modernization plan. In these
analyses, the new tactical aircraft will also have to compete for
funding, priority, and mission assignments with operational systems,
such as the F-15 and F/A-18, and other future systems, such as the
Joint Unmanned Combat Air Systems.
The 2005 Quadrennial Defense Review provides an opportunity for DOD to
assess tactical fixed-wing aircraft modernization plans and weigh
options for accomplishing its specific as well as overarching tactical
aircraft goals. It is critical that their investment be well-managed
and balanced against DOD's other priorities. Through the review, DOD
can seek answers to overall investment strategy questions:
* What is the role of tactical aircraft in relation to other defense
capabilities?
* Will planned investments in tactical aircraft allow DOD to achieve
these capabilities and overall transformational goals?
* Where disconnects exist between goals and expected investment
outcomes, what are the impacts and how will DOD compensate to minimize
future security and investment risks?
If DOD fails to answer these questions and continues with its current
modernization strategy, it will likely arrive in the future with needs
similar to those that exist today but with fewer options and resources
to resolve those needs. As DOD evaluates its tactical aircraft
investment alternatives, knowledge at the program level is needed to
understand how the F/A-22 and JSF can help achieve overall tactical
aircraft modernization goals. More specific questions need to be
answered for these programs including:
* Is the F/A-22 the most cost-effective alternative to fill gaps in
ground attack and intelligence-gathering requirements?
* How many F/A-22s are needed and affordable to carry out the
aircraft's original mission, air superiority, and new ground attack and
intelligence gathering missions?
* If requirements for the new F/A-22 capabilities are legitimate and
not solvable by other means, does the Air Force have the resources
(mature technologies, design knowledge, time, and money) to begin
investments in a new development program for the F/A-22 enhancements?
* What is the immediate need for JSF aircraft? Delivery of its ultimate
capability or replacing aging aircraft with an initial capability? Does
the acquisition plan satisfy this need?
* Does the program have the required knowledge about needed quantities
and capabilities and resources (mature technologies, design knowledge,
time, and money) to develop a reliable business case at this time?
* Does DOD have the right acquisition strategy to develop and produce a
JSF that will maximize its return on the more than $220 billion
investment that remains in this program?
While the JSF program started off with a higher-risk approach by
starting system development with immature technologies, now is the time
to implement an evolutionary and knowledge-based acquisition strategy
to manage the system development phase and stabilize the design before
making large investments in tooling, labor, and facilities to test and
manufacture the aircraft. The JSF is relatively early in its system
development and demonstration phase and has an opportunity to learn
from the F/A-22 program experience. It must take the time needed now to
gather knowledge needed to resolve key issues that could ultimately
result in additional cost increases, delays, and performance problems.
Our March 2005 reports on the F/A-22 and JSF made recommendations to
the Secretary of Defense that would require answering some of these
questions before making significant additional investments. For the F/
A-22, we recommended that a new business case be made to justify
investments in new capabilities and the quantities needed to satisfy
mission requirements. For the JSF, we recommended the establishment of
an executable program consistent with policy and best practices,
including an affordable first increment with its own business case, and
the implementation of a knowledge-based acquisition approach to guide
future investments and reduce risks.
Mr. Chairman, this concludes my prepared statement. I would be happy to
respond to any questions that you or other members of the Subcommittee
may have.
Contacts and Staff Acknowledgments:
For future questions about our work on the F/A-22 or JSF, please call
me or Michael J. Hazard at (202) 512-4841. Other individuals making key
contributions to this statement include Michael W. Aiken, Marvin E.
Bonner, Lily J. Chin, Matthew T. Drerup, Bruce D. Fairbairn, Steven M.
Hunter, Matthew B. Lea, David R. Schilling, and Adam Vodraska.
FOOTNOTES
[1] The third major program, the FA-18EF, currently in production, is
not a subject of this testimony.
[2] GAO, Tactical Aircraft: Status of the F/A-22 and JSF Acquisition
Programs and Implications for Tactical Aircraft Modernization, GAO-05-
390T (Washington, D.C.: Mar. 3, 2005; GAO, Tactical Airlift: Air Force
Still Needs Business Case to Support F/A-22 Quantities and Increased
Capabilities, GAO-05-304 (Washington, D.C.: Mar. 15, 2005); and GAO
Tactical Aircraft: Opportunity to Reduce Risks in the Joint Strike
Fighter Program with Different Acquisition Strategy, GAO-05-271
(Washington, D.C.: Mar. 15, 2005).
[3] This amount consists of $61.3 billion currently budgeted for the
basic program and the initial stages of the modernization efforts, $1.3
billion for future start-up costs of a separate acquisition program for
the latter stages of modernization, and $1.2 billion in costs to
retrofit aircraft with enhanced capabilities and activate depot
maintenance activities.
[4] Global Strike is one of six complementary concepts of operations
laying out the Air Force's ability to rapidly plan and deliver limited-
duration and extended attacks against targets.
[5] The Defense Acquisition Board met in late March of this year to
discuss the F/A-22's progress and readiness for full-rate production. A
final decision by the milestone decision authority is expected in early
April.
[6] GAO, Tactical Aircraft: Changing Conditions Drive Need for New F/A-
22 Business Case, GAO-04-391 (Washington, D.C.: Mar. 15, 2004).
[7] GAO, Tactical Aircraft: Status of the F/A-22 and Joint Strike
Fighter Programs, GAO-04-597T (Washington, D.C.: Mar. 25, 2004).
[8] Pub. L. No. 105-85 (Nov. 18, 1997), section 217.
[9] Pub. L. No. 107-107 (Dec. 28, 2001), section 213.
[10] Program Budget Decision 753 nominally reduced the procurement
quantity to 179 aircraft. Subsequently, the Air Force transferred one
aircraft to be used as a permanent test bed, reducing the procurement
quantity to 178. The recent crash of an F/A-22 has reduced planned
operational aircraft to 177.
[11] Program acquisition unit cost includes funding for development,
procurement, related military construction, and initial modernization
divided by total production quantity. It does not include later stage
modernization costs and certain support costs.
[12] Average unit flyaway cost includes the costs associated with
procuring one aircraft, including the airframe, engines, avionics,
other mission equipment, and certain nonrecurring production costs. It
does not include "sunk" costs for development and test and other costs
to the whole system, including logistical support and construction.
[13] Statute 10 U.S.C. 2399 provides that a major defense acquisition
program may not proceed beyond low-rate initial production until
initial operational test and evaluation is completed and the
congressional defense committees have received the report of testing
results from the Director of Operational Test and Evaluation. This
report is to contain an opinion of test adequacy and whether the test
results confirm that the system actually tested is operationally
effective and suitable for combat.
[14] The F/A-22 initial operational test and evaluation was conducted
by the Air Force Operational Test and Evaluation Center from April
through December 2004 to support the full-rate production decision. Its
operational test plan was designed to assess the F/A-22's combat
effectiveness and suitability in an operationally representative
environment.
[15] Air-to-ground attack capabilities are increasingly emphasized by
the Air Force, and future enhancements are planned for 80 percent of
the modernized F/A-22s. More robust ground attack and intelligence
gathering capabilities will be tested in the future as they are
developed.
[16] The OSD CAIG acts as the principal advisory body to the milestone
decision authority on program cost. The CAIG estimate included costs
for development, procurement, and retrofit of modernized aircraft.
[17] In November 2004, the acting Under Secretary of Defense for
Acquisition, Technology and Logistics directed the Air Force to hold
separate milestone reviews for the latter stages of the modernization
program to be consistent with DOD acquisition policy. The Air Force
plans to manage these efforts as a separate acquisition program.
[18] DOD Directive 5000.1, The Defense Acquisition System (May 2003);
DOD Instruction 5000.2, Operation of the Defense Acquisition System
(May 2003). The directive establishes evolutionary acquisition
strategies as the preferred approach to satisfying DOD's operational
needs. The directive also requires program managers to provide
knowledge about key aspects of a system at key points in the
acquisition process.
[19] The preliminary plan was what was being considered at the time of
our review. Since then, in its fiscal year 2006 budget submission, DOD
has reduced the planned procurement quantities for the U.S. by 38
aircraft through fiscal year 2011. This includes planned quantities for
the United Kingdom of 2 aircraft in fiscal year 2009, 4 aircraft in
fiscal year 2010; 9 aircraft in fiscal year 2011, 9 aircraft in fiscal
year 2012, and 10 aircraft in fiscal year 2013.
[20] This is based on DOD's December 2003 JSF cost estimate.
[21] GAO, Tactical Aircraft: Modernization Plans Will Not Reduce
Average Age of Aircraft, GAO-01-163 (Washington, D.C.: Feb. 9, 2001).
Today acquisition plans include 3,083 aircraft (F/A-22, FA-18EF, and
JSF). The Air Force has been discussing buying fewer JSF, which would
further lower the amount of planned new tactical aircraft.
[22] The remaining aircraft are used for training and development
activities and to account for aircraft in for maintenance and those
held in reserve for normal attrition.