Defense Acquisitions
Missile Defense Agency's Flexibility Reduces Transparency of Program Cost
Gao ID: GAO-07-799T April 30, 2007
Over the next 5 years the Missile Defense Agency (MDA) expects to invest $49 billion in the Ballistic Missile Defense (BMD) system's development and fielding. MDA's strategy is to field new capabilities in 2-year blocks. In January 2006, MDA initiated its second block--Block 2006--to protect against attacks from North Korea and the Middle East. Congress requires GAO to assess MDA's progress annually. GAO's March 2007 report addressed MDA's progress during fiscal year 2006 and followed up on program oversight issues and the current status of MDA's quality assurance program. GAO assessed the progress of each element being developed by MDA, examined acquisition laws applicable to major acquisition programs, and reviewed the impact of implemented quality initiatives.
During fiscal year 2006, MDA fielded additional assets for the Ballistic Missile Defense System (BMDS), enhanced the capability of some assets, and realized several noteworthy testing achievements. For example, the Ground-based Midcourse Defense (GMD) element successfully conducted its first end-to-end test of one engagement scenario, the element's first successful intercept test since 2002. However, MDA will not meet its original Block 2006 cost, fielding, or performance goals because the agency has revised those goals. In March 2006, MDA: reduced its goal for fielded assets to provide funds for technical problems and new and increased operations and sustainment requirements; increased its cost goal by about $1 billion--from $19.3 to $20.3 billion; and reduced its performance goal commensurate with the reduction of assets. MDA may also reduce the scope of the block further by deferring other work until a future block because four elements incurred about $478 million in fiscal year 2006 budget overruns. With the possible exception of GMD interceptors, MDA is generally on track to meet its revised quantity goals. But the deferral of work, both into and out of Block 2006, and inconsistent reporting of costs by some BMDS elements, makes the actual cost of Block 2006 difficult to determine. In addition, GAO cannot assess whether the block will meet its revised performance goals until MDA's models and simulations are anchored by sufficient flight tests to have confidence that predictions of performance are reliable. Because MDA has not formally entered the Department of Defense (DOD) acquisition cycle, it is not yet required to apply certain laws intended to hold major defense acquisition programs accountable for their planned outcomes and cost, give decision makers a means to conduct oversight, and ensure some level of independent program review. MDA is more agile in its decision-making because it does not have to wait for outside reviews or obtain higher-level approvals of its goals or changes to those goals. Because MDA can revise its baseline, it has the ability to field fewer assets than planned, defer work to a future block, and increase planned cost. All of this makes it hard to reconcile cost and outcomes against original goals and to determine the value of the work accomplished. Also, using research and development funds to purchase operational assets allows costs to be spread over 2 or more years, which makes costs harder to track and commits future budgets. MDA continues to identify quality assurance weaknesses, but the agency's corrective measures are beginning to produce results. Quality deficiencies are declining as MDA implements corrective actions, such as a teaming approach designed to restore the reliability of key suppliers.
GAO-07-799T, Defense Acquisitions: Missile Defense Agency's Flexibility Reduces Transparency of Program Cost
This is the accessible text file for GAO report number GAO-07-799T
entitled 'Defense Acquisitions: Missile Defense Agency's Flexibility
Reduces Transparency of program Cost' which was released on April 30,
2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony before the Subcommittee on Defense, Committee on
Appropriations,
U.S. House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 1:30 p.m. EDT:
Monday, April 30, 2007:
Defense Acquisitions:
Missile Defense Agency's Flexibility Reduces Transparency of Program
Cost:
Statement of Paul Francis, Director,
Acquisition and Sourcing Management:
GAO-07-799T:
GAO Highlights:
Highlights of GAO-07-799T, a testimony before the Subcommittee on
Defense, Committee on Appropriations, U.S. House of Representatives
Why GAO Did This Study:
Over the next 5 years the Missile Defense Agency (MDA) expects to
invest $49 billion in the BMD system‘s development and fielding. MDA‘s
strategy is to field new capabilities in 2-year blocks. In January
2006, MDA initiated its second block”Block 2006”to protect against
attacks from North Korea and the Middle East.
Congress requires GAO to assess MDA‘s progress annually. GAO‘s March
2007 report addressed MDA‘s progress during fiscal year 2006 and
followed up on program oversight issues and the current status of MDA‘s
quality assurance program. GAO assessed the progress of each element
being developed by MDA, examined acquisition laws applicable to major
acquisition programs, and reviewed the impact of implemented quality
initiatives.
What GAO Found:
During fiscal year 2006, MDA fielded additional assets for the
Ballistic Missile Defense System (BMDS), enhanced the capability of
some assets, and realized several noteworthy testing achievements. For
example, the Ground-based Midcourse Defense (GMD) element successfully
conducted its first end-to-end test of one engagement scenario, the
element‘s first successful intercept test since 2002. However, MDA will
not meet its original Block 2006 cost, fielding, or performance goals
because the agency has revised those goals. In March 2006, MDA:
* reduced its goal for fielded assets to provide funds for technical
problems and new and increased operations and sustainment requirements;
* increased its cost goal by about $1 billion”from $19.3 to $20.3
billion; and
* reduced its performance goal commensurate with the reduction of
assets. MDA may also reduce the scope of the block further by deferring
other work until a future block because four elements incurred about
$478 million in fiscal year 2006 budget overruns.
With the possible exception of GMD interceptors, MDA is generally on
track to meet its revised quantity goals. But the deferral of work,
both into and out of Block 2006, and inconsistent reporting of costs by
some BMDS elements, makes the actual cost of Block 2006 difficult to
determine. In addition, GAO cannot assess whether the block will meet
its revised performance goals until MDA‘s models and simulations are
anchored by sufficient flight tests to have confidence that predictions
of performance are reliable.
Because MDA has not formally entered the Department of Defense (DOD)
acquisition cycle, it is not yet required to apply certain laws
intended to hold major defense acquisition programs accountable for
their planned outcomes and cost, give decision makers a means to
conduct oversight, and ensure some level of independent program review.
MDA is more agile in its decision-making because it does not have to
wait for outside reviews or obtain higher-level approvals of its goals
or changes to those goals. Because MDA can revise its baseline, it has
the ability to field fewer assets than planned, defer work to a future
block, and increase planned cost. All of this makes it hard to
reconcile cost and outcomes against original goals and to determine the
value of the work accomplished. Also, using research and development
funds to purchase operational assets allows costs to be spread over 2
or more years, which makes costs harder to track and commits future
budgets.
MDA continues to identify quality assurance weaknesses, but the
agency‘s corrective measures are beginning to produce results. Quality
deficiencies are declining as MDA implements corrective actions, such
as a teaming approach designed to restore the reliability of key
suppliers.
What GAO Recommends:
GAO continues to encourage DOD to act on prior recommendations to
implement a knowledge-based acquisition strategy for all BMDS elements
and to adopt more transparent criteria for reporting each element‘s
quantities, cost, and performance. In March 2007, GAO recommended that
DOD adopt firm baselines, use procurement funds for operational assets,
and adopt other measures to better track cost and outcomes against
goals. DOD did not agree to an element-based reporting approach, but is
investigating other ways to provide more program transparency.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-799T].
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Paul Francis, (202) 512-
4841, francisp@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
I am pleased to be here today to discuss the Missile Defense Agency's
(MDA) strategy for acquiring a Ballistic Missile Defense System (BMDS)
and its progress in developing and fielding Block 2006--the second
iteration of BMDS.
MDA's mission is to develop and field an integrated, layered Ballistic
Missile Defense System capable of defending the United States, its
deployed forces, allies, and friends against enemy ballistic missiles
launched from all ranges and during all phases of the missiles' flight.
To carry out its mission, MDA is fielding missile defense capabilities
in 2-year increments known as blocks. The first block--Block 2004--
fielded a limited initial capability that included early versions of
Ground-Based Midcourse Defense (GMD); Aegis Ballistic Missile Defense
(BMD); Patriot Advanced Capability-3 (PAC-3); and Command, Control,
Battle Management, and Communications (C2BMC). Each of these components
is an element of the integrated BMDS. During calendar years 2006 and
2007, MDA is focusing Block 2006 to enhance and field four BMDS
elements--GMD, Aegis BMD, Sensors, and C2BMC. Block 2006 is not only
expected to field additional assets, but it also continues the
evolution of Block 2004 by providing improved GMD interceptors,
enhanced Aegis BMD missiles, upgraded Aegis BMD ships, a Forward-Based
X-Band Transportable radar, and enhancements to the C2BMC software.
The National Defense Authorization Acts for fiscal years 2002 and 2005
mandate that we prepare annual assessments of MDA's ongoing cost,
schedule, testing, and performance progress. We issued our most recent
report on March 15, 2007.[Footnote 1] My statement today will focus on
the issues covered in that report, specifically:
* MDA's progress toward developing the Block 2006 configuration of the
BMDS,
* the flexibility granted to MDA and its effect on oversight and
accountability, and:
* the status of MDA's efforts to improve its quality processes.
Summary:
MDA continues to make progress on missile defense, but costs have grown
and less work is being completed than planned. The fielding of
additional assets and the first end-to-end test of GMD were notable
accomplishments in fiscal year 2006, as was being able to put BMDS on
alert status. Yet, MDA will not meet its original Block 2006 cost,
fielding, or performance goals. MDA will field fewer assets than
planned, which will cause a commensurate decrease in performance.
Although scope has been reduced, costs are expected to increase by
about $1 billion. There is no baseline against which to measure cost.
For several reasons, we cannot be precise about the actual cost of
Block 2006. MDA defers work from block to block and counts the cost of
deferred work as a cost of the block in which the work is performed
even though that work benefits the original block. For example, work
deferred from Block 2004 is counted as a cost of Block 2006. Element
program offices report costs inconsistently, with most underreporting
costs. The cost of Block 2006 may change further because MDA may defer
other work from Block 2006 until Block 2008 to cover $478 million in
fiscal year 2006 budget overruns experienced by element prime
contractors. We could not assess whether MDA is likely to achieve its
revised performance goal because too few tests have been completed to
have confidence in the models and simulations used to predict
performance. Overall, the block approach has had advantages for
fielding capabilities incrementally, but it has not proven to be a good
construct for reconciling actual cost and performance with the
justifications that MDA submits to support its budget request.
Because the BMDS program has not formally entered system development
and demonstration, application of laws that are designed to facilitate
oversight and accountability of DOD acquisition programs has
effectively been deferred. This gives MDA unique latitude to manage the
BMDS. Specifically, the BMDS cost, schedule, and performance baseline
does not have to be approved by anyone outside MDA. MDA is not yet
required to obtain independent assessments of each configuration's cost
or test results. Unlike other programs, MDA is permitted to use
research and development funds to incrementally fund all activities,
including the purchase and support of operational assets. MDA keeps
others informed, but it does not need their approval. Collectively,
this flexibility enables MDA to be more agile in its decision-making.
By the same token, MDA can revise its own baseline to field fewer
assets than planned, defer work to a future block, and increase planned
cost. Over time, it becomes difficult to reconcile cost and outcomes
against original goals and to determine the value of the work
accomplished. Ultimately, Congress may know that it is getting less
than expected for its investment, but it will not necessarily know the
cost of what it did receive or whether it is being asked to again
appropriate funds for work that had been scheduled in a prior block but
could not be completed because its funding was diverted to pay for
other activities. The foregoing does not mean that MDA has acted
inconsistently with the authorities it has been granted. Rather, MDA
has the sanctioned flexibility to manage exactly as it has. It could be
argued that without this flexibility, the initial capability fielded
last year and put on alert would not have been possible. Yet, the
question remains as to whether this degree of flexibility should be
retained for a program that is planning to spend on the order of $10
billion a year for the foreseeable future.
MDA auditors report that quality deficiencies are declining and on-time
deliveries are improving as corrective measures are implemented. For
example, MDA quality audits show that one key supplier has decreased
open quality issues by 64 percent, reduced test failures by 43 percent,
and increased on-time deliveries by 9 percent. The mechanisms being
used to improve quality assurance processes include the development of
a teaming approach to restore reliability in key suppliers, conducting
regular quality audits, adjusting award fee plans to encourage
contractors to maintain a good quality assurance program and implement
industry best practices, and continuing to incorporate key quality
provisions into the agency's prime contracts.
In our March 2007 report, we recommended that MDA establish firm
baselines for those elements considered far enough along to be in
system development and demonstration, and report against those
baselines; propose an approach for those same elements that provides
information consistent with the acquisition laws that govern baselines
and unit cost reporting, independent cost estimates, and operational
test and evaluation; include in blocks only those elements that will
field capabilities during the block period and develop a firm block
baseline that includes the unit cost of its assets; request and use
procurement funds, rather than research, development, test, and
evaluation funds, to acquire fielded assets; and conduct an independent
evaluation of the ABL and KEI elements prior to making a decision on
the future of the programs.
DOD partially concurred with the report's first three recommendations,
but did not agree to use procurement funds to acquire fielded assets or
to conduct an independent evaluation of the ABL and KEI elements. In
partially agreeing, DOD recognized the need to provide greater program
transparency and committed to providing information consistent with
acquisition laws that govern baselines and unit cost reporting.
However, DOD objected to the element-centric approach recommended,
believing that this would detract from managing the BMDS as a single,
integrated system. DOD also stated that reporting at the BMDS-level in
accordance with our third recommendation would appear to be
inconsistent with reporting at the element level. We continue to
believe that all recommended changes are needed to provide a better
balance between MDA's flexibility and BMDS program transparency.
Because DOD awards contracts and requests funding by individual
elements that compose the BMDS, we believe that the element approach is
the best way to achieve increased program transparency. However, a BMDS-
level baseline derived from the capabilities that individual elements
yield is needed to describe and manage a BMDS-wide capability. We also
believe that the use of procurement funds contributes to program
transparency by making clear at the outset the size of the investment
being requested in fielded assets. Finally, we continue to believe that
an independent assessment of the ABL and KEI capabilities can provide a
transparent basis for making decisions on the future of the programs,
but we did revise the recommendation to specify that the assessment
should follow key demonstrations in 2009.
Background:
Missile defense is important because at least 25 countries now possess
or are acquiring sophisticated missile technology that could be used to
attack the United States, deployed troops, friends, and allies. MDA's
mission is to develop and field an integrated, layered BMDS capable of
defending against enemy ballistic missiles launched from all ranges and
during all phases of the missiles' flight. DOD has spent and continues
to spend large sums of money to defend against this threat. Since the
mid-1980s, about $107 billion has been spent, and over the next 5
years, another $49 billion is expected to be invested. While the
initial set of BMDS assets was fielded during 2004-2005, much of the
technical and engineering foundation was laid by this prior investment.
DOD also expects to continue investing in missile defense for many more
years as the system evolves into one that can engage an enemy ballistic
missile launched from any range during any phase of the missile's
flight.
To enable MDA to field and enhance a missile defense system quickly,
the Secretary of Defense, in 2002, directed a new acquisition strategy.
The Secretary's strategy included removing the BMDS program from DOD's
traditional acquisition process until a mature capability was ready to
be handed over to a military service for production and operation.
Therefore, development of the BMDS program is not segmented into
concept refinement, technology development, and system development and
demonstration phases, as other major defense acquisition programs are.
Instead, MDA initiates one development phase that incorporates all
acquisition activities and that is known simply as research and
development. MDA also has approval to use research and development
funds, rather than procurement funds, to acquire assets that could be
made available for operational use.
To carry out its mission, MDA is fielding missile defense capabilities
in 2-year increments known as blocks. The first block--Block 2004--
fielded a limited initial capability that included early versions of
GMD, Aegis BMD, PAC-3, and C2BMC. This was the capability that was put
on alert status in 2006. MDA formally began a second BMDS block on
January 1, 2006, that will continue through December 31, 2007. This
block is expected to provide protection against attacks from North
Korea and the Middle East. During the 2-year block timeframe, MDA is
focusing its program of work on the enhancement and fielding of
additional quantities of the GMD, Aegis BMD, and C2BMC elements, as
well as fielding a Forward-Based X-Band radar that is part of the
Sensors element. When MDA defined the block in March 2005, shortly
after submitting its fiscal year 2006 budget request to Congress, it
also included three other elements--Airborne Laser (ABL), Space
Tracking and Surveillance System (STSS), and Terminal High Altitude
Area Defense (THAAD)--that are primarily developmental in nature.
According to MDA, these elements were included in the block even though
they were not expected to be operational until future blocks because
the elements offered some emergency capability during the block
timeframe. In March 2006, MDA removed THAAD from Block 2006. According
to MDA, this action better aligned resources and fielding plans. The
development of two other elements--Multiple Kill Vehicle (MKV) and
Kinetic Energy Interceptor (KEI)--also continued in fiscal year 2006,
but these elements were not considered part of Block 2006 because,
according to MDA officials, the elements provide no capability--
emergency or operational--during the block.
The bulk of the funding that MDA requests for the BMDS each fiscal year
is for the development, fielding, and sustainment of BMDS elements. For
example, in fiscal year 2006, funding for the nine BMDS elements
collectively accounted for 72 percent of MDA's research and development
budget. MDA requests funds for each of these elements, with the
exception of C2BMC and THAAD, under separate budget line items. In
addition, MDA issues separate contracts for each of the nine elements.
Prior to beginning each new block, MDA establishes and submits block
goals to Congress. These goals present the business case for the new
block. MDA presented its Block 2006 goals to Congress in March 2005,
shortly after submitting its fiscal year 2006 budget. At that time, MDA
told Congress that the agency expected to field the following assets:
up to 15 GMD interceptors, an interim upgrade of the Thule Early
Warning Radar, a Forward-Based X-Band radar, 19 Aegis BMD missiles, 1
new Aegis cruiser for the missile defense mission, 4 new Aegis
destroyers capable of providing long-range surveillance and tracking,
and 8 Aegis destroyers upgraded for the engagement mission. MDA's cost
goal for the development of the six elements that compose the block,
the manufacture of assets being fielded, and logistical support for
fielded assets was $19.3 billion.[Footnote 2] MDA also notified
Congress of the Block 2006 performance goals established for the BMDS.
These goals were composed of numerical values for the probability of
engagement success, the land area from which the BMDS could deny a
launch, and the land area that the BMDS could defend.[Footnote 3]
Fiscal year testing goals were also established by element program
offices, but these goals were not formally reported to Congress.
We examined numerous documents and held discussions with agency
officials. In determining the elements' progress toward Block 2006
goals, we looked at the accomplishments of six BMDS elements--ABL,
Aegis BMD, BMDS Sensors, C2BMC, GMD, and STSS--that compose the Block
2006 configuration. Our work included examining System Element Reviews,
test plans and reports, production plans, and Contract Performance
Reports. We also interviewed officials within each element program
office and within MDA functional offices. In assessing whether MDA's
flexibility impacts BMDS oversight and accountability, we examined
documents such as those defining MDA's changes to Block 2006 goals,
acquisition laws for major DOD programs, and BMDS policy directives
issued by the Secretary of Defense. We examined the current status of
MDA's quality assurance program by visiting various contractor
facilities and holding discussions with MDA officials, such as
officials in the Office of Quality, Safety, and Mission Assurance. We
performed our work from June 2006 through March 2007 in accordance with
generally accepted government auditing standards.
MDA Has Made Progress with Block 2006, but Scope Has Been Reduced and
Costs Have Gone Up:
MDA made progress during fiscal year 2006, but it will not achieve the
goals it set for itself in March 2005. One year after establishing its
Block 2006 goals, the agency informed Congress that it planned to field
fewer assets, reduce performance goals, and increase the block's cost
goal. It is also likely that in addition to fielding fewer assets,
other Block 2006 work will be deferred to offset growing contractor
costs. MDA is generally on track to meet its revised quantity goals,
but the performance of the BMDS cannot yet be fully assessed because
there have been too few flight tests conducted to anchor the models and
simulations that predict overall system performance. Several elements
continue to experience technical problems that pose questions about the
performance of the fielded system and could delay the enhancement of
future blocks. In addition, the Block 2006 cost goal cannot be
reconciled with actual costs because work travels to and from other
blocks and individual element program offices report costs
inconsistently.
During the first year of Block 2006, MDA continued to improve the BMDS
by enhancing its performance and fielding additional assets. In
addition, the BMDS elements achieved some notable test results. For
example, the GMD element completed its first successful intercept
attempt since 2002. The test was also notable because it was an end-to-
end test of one engagement scenario, the first such test that the
program has conducted. Also, the Aegis BMD element conducted a
successful intercept test of its more capable Standard Missile-3 design
that is being fielded for the first time during Block 2006.
In March 2006, soon after the formal initiation of Block 2006, MDA
announced that events such as hardware delays, technical challenges,
and budget cuts were causing the agency to field fewer assets than
originally expected. MDA's goal now calls for fielding 3 fewer GMD
interceptors; deferring the upgrade of the Thule radar until Block
2008, when it can be fully upgraded; producing 4 fewer Aegis BMD
missiles; upgrading 1 less Aegis destroyer for the engagement mission;
and delivering 3 C2BMC Web browsers rather than the more expensive
C2BMC suites. With the exception of the GMD interceptors, MDA is on
track to deliver the revised quantities. The GMD program planned to
emplace 8 interceptors during calendar year 2006, but was only able to
emplace 4. Program officials told us that the contractor has increased
the number of shifts that it is working and that this change will
accelerate deliveries. However, to meet its quantity goal, the GMD
program will have to more than double its interceptor emplacement rate
in 2007.
MDA also reduced the performance expected of Block 2006 commensurate
with the reduction in assets. However, insufficient data are available
to determine whether MDA is on track to meet the new goal. Although the
GMD test program has achieved some notable results, officials in DOD's
Office of the Director of Operational Test and Evaluation told us that
the element has not completed sufficient tests to provide a high level
of confidence that the BMDS can reliably intercept intercontinental
ballistic missiles. Further testing is needed as well to confirm that
GMD can use long-range tracking data developed by Aegis BMD to prepare-
-in real time--a weapon system task plan for GMD interceptors.
Delayed testing and technical problems may also impact the performance
of the current and future configurations of the BMDS. For example, the
performance of the Block 2006 configuration of the Aegis BMD missile is
unproven because design changes in the missile's solid attitude and
divert system and one burn pattern of the third stage rocket motor were
not flight-tested before they were cut into the production line. The
current configuration of the GMD interceptor also continues to struggle
with an anomaly that has occurred in each of the element's flight
tests. The anomaly has not yet prevented the program from achieving its
primary test objectives, but neither its source nor a solution has been
clearly identified or defined. The reliability of some GMD interceptors
remains uncertain as well because inadequate mission assurance/quality
control procedures may have allowed less reliable or inappropriate
parts to be incorporated into the manufacturing process. Program
officials plan to introduce new parts into the manufacturing process,
but not until interceptor 18. MDA also plans to retrofit the previous
17 interceptors, but not until fiscal year 2009. In addition to the
performance problems with elements being fielded, the ABL element that
is being developed to enhance a future BMDS configuration experienced
technical problems with its Beam Control/Fire Control component. These
problems have delayed a lethality demonstration that is needed to
demonstrate the element's leading-edge technologies. ABL is an
important element because if it works as desired, it will defeat enemy
missiles soon after launch, before decoys are released to confuse other
BMDS elements. MDA plans to decide in 2009 whether ABL or KEI, whose
primary boost phase role is to mitigate the risk in the ABL program,
will become the BMDS boost phase capability.
While MDA reduced Block 2006 quantity and performance goals, it
increased the block's cost goal from about $19.3 billion to
approximately $20.3 billion.[Footnote 4] The cost increases were caused
by the addition of previously unknown operations and sustainment
requirements, realignment of the GMD program to support a successful
return to flight, realignment of the Aegis BMD program to address
technical challenges and invest in upgrades, and preparations for round-
the-clock operation of the BMDS. Although MDA is expected to operate
within its revised budget of $20.3 billion, the actual cost of the
block cannot be reconciled with the cost goal. To stay within its Block
2004 budget, MDA shifted some of that block's work to Block 2006 and is
counting it as a cost of Block 2006, which overstates Block 2006 cost.
In addition, MDA officials told us that it is likely that some Block
2006 work will be deferred until Block 2008 to cover the $478 million
fiscal year 2006 budget overruns experienced by five of the six element
prime contractors. If MDA reports the cost of deferred work as it has
in the past, the actual cost of Block 2006 will be complicated further.
Another factor complicating the reconciliation of Block 2006 cost is
that the elements report block cost inconsistently. Some elements
appropriately include costs that the program will incur to reach full
capability, while others do not.[Footnote 5]
MDA's Flexibility Makes Oversight and Accountability More Difficult:
Because the BMDS has not formally entered the system development and
demonstration phase of the acquisition cycle, it is not yet required to
apply several important oversight mechanisms contained in certain
acquisition laws that, among other things, provide transparency into
program progress and decisions. This has enabled MDA to be agile in
decision making and has facilitated fielding an initial BMDS capability
quickly. On the other hand, MDA operates with considerable autonomy to
change goals and plans, making it difficult to reconcile outcomes with
original expectations and to determine the actual cost of each block
and of individual operational assets.
Over the years, a framework of laws has been created that make major
defense acquisition programs accountable for their planned outcomes and
cost, give decision makers a means to conduct oversight, and ensure
some level of independent program review. The application of many of
these laws is triggered by a program's entry into system development
and demonstration. To provide accountability, once major defense
programs cross this threshold, they are required by statute to document
program goals in an acquisition program baseline that as implemented by
DOD has been approved by a higher-level DOD official prior to the
program's initiation. The baseline provides decision makers with the
program's best estimate of the program's total cost for an increment of
work, average unit costs for assets to be delivered, the date that an
operational capability will be fielded, and the weapon's intended
performance parameters. Once approved, major acquisition programs are
required to measure their program against the baseline, which is the
program's initial business case, or obtain the approval of a higher-
level acquisition executive before making significant changes. Programs
are also required to regularly provide detailed program status
information to Congress, including information on cost, in Selected
Acquisition Reports. In addition, Congress has established a cost-
monitoring mechanism that requires programs to report significant
increases in unit cost measured from the program baseline.[Footnote 6]
Other statutes provide for independent program verifications and place
limits on the use of appropriations. For example, 10 U.S.C. § 2434
prohibits the Secretary of Defense from approving system development
and demonstration unless an independent estimate of the program's life-
cycle cost has been conducted by the Secretary. In addition, 10 U.S.C.
§ 2399 requires completion of initial operational test and evaluation
before a program can begin full-rate production. These statutes ensure
that someone external to the program examines the likelihood that the
program can be executed as planned and will yield a system that is
effective and suitable for combat. The use of an appropriation is also
controlled so that it will not be used for a purpose other than the one
for which it was made, except as otherwise provided by law. Research
and development appropriations are typically specified by Congress to
be used to pay the expenses of basic and applied scientific research,
development, test, and evaluation. On the other hand, procurement
appropriations are, in general, to be used for production and
manufacturing. In the 1950s, Congress established a policy that items
being purchased with procurement funds be fully funded in the year that
the item is procured. This is meant to prevent a program from
incrementally funding the purchase of operational systems. Full funding
ensures that the total procurement costs of weapons and equipment are
known to Congress up front and that one Congress does not put the
burden on future Congresses of deciding whether they should appropriate
additional funds or expose weapons under construction to uneconomic
start-up and stop costs.
The flexibility to defer application of specific acquisition laws has
benefits. MDA can make decisions faster than other major acquisition
programs because it does not have to wait for higher-level approvals or
independent reviews. MDA's ability to quickly field a missile defense
capability is also improved because assets can be fielded before all
testing is complete. MDA considers the assets it has fielded to be
developmental assets and not the result of the production phase of the
acquisition cycle. Additionally, MDA enjoys greater flexibility than
other programs in the use of its funds. Because MDA uses research and
development funds to manufacture assets, it is not required to fully
fund those assets in the year of their purchase. Therefore, as long as
its annual budget remains fairly level, MDA can request funds to
address other needs.
On the other hand, the flexibilities granted MDA make it more difficult
to conduct program oversight or to hold MDA accountable for the large
investment being made in the BMDS program. Block goals can be changed
by MDA, softening the baseline used to assess progress toward expected
outcomes. Similarly, because MDA can redefine the work to be completed
during a block, the actual cost of a block cannot be compared with the
original cost estimate. MDA considers the cost of deferred work, which
may be the delayed delivery of assets or other work activities, as a
cost of the block in which the work is performed even though the work
benefits or was planned for a prior block. Further, MDA does not track
the cost of the deferred work and, therefore, cannot make adjustments
that would match the cost with the block that is benefited. For
example, during Block 2004, MDA deferred some planned development,
deployment, characterization, and verification activities until Block
2006 so that it could cover contractor budget overruns. The costs of
the activities are now considered part of the cost of Block 2006. Also,
although Congress provided funding for these activities during Block
2004, MDA used these funds for the overruns and will need additional
funds during Block 2006 to cover their cost. Planned and actual unit
costs of fielded assets are equally difficult to reconcile. Because MDA
is not required to develop an approved acquisition program baseline, it
is not required to report the expected average unit cost of assets.
Also, because MDA is not required to report significant increases in
unit cost,[Footnote 7] it is not easy to determine whether an asset's
actual cost has increased significantly from its expected cost.
Finally, using research and development funds to purchase fielded
assets further reduces cost transparency because these dollars are not
covered by the full-funding policy as are procurement funds. Therefore,
when a program for a 2-year block is first presented in the budget,
Congress is not necessarily fully aware of the dimensions and cost of
that block. For example, although a block may call for the delivery of
a specific number of interceptors, the full cost of those interceptors
is requested over 3 to 5 years. Calculating unit costs from budget
documents is difficult because the cost of components that will become
fielded assets may be spread across 3 to 5 budget years--a consequence
of incremental funding.
MDA Audits Show Improvement in Quality Processes:
During Block 2004, poor quality control procedures caused the missile
defense program to experience test failures and slowed production. MDA
has initiated a number of actions to correct quality control
weaknesses, and the agency reports that these actions have been largely
successful. Although MDA continues to identify quality assurance
procedures that need strengthening, recent audits by MDA's Office of
Quality, Safety, and Mission Assurance show such improvements as
increased on-time deliveries, reduced test failures, and sustained
improvement in product quality.
MDA has taken a number of steps to improve quality assurance. These
include developing a teaming approach to restore the reliability of key
suppliers, conducting regular quality inspections to quickly identify
and find resolutions for quality problems, adjusting award fee plans to
encourage contractors to maintain a good quality assurance program and
encourage industry best practices, as well as placing MDA-developed
assurance provisions on prime contracts. For example, as early as 2003,
MDA made a critical assessment of a key supplier's organization and
determined that the supplier's manufacturing processes lacked
discipline, its corrective action procedures were ineffective, its
technical data package was inadequate, and personnel were not properly
trained. The supplier responded by hiring a Quality Assurance Director,
five quality assurance professionals, a training manager, and a
scheduler. In addition, the supplier installed an electronic problem-
reporting database, formed new boards--such as a failure review board-
-established a new configuration management system, and ensured that
manufacturing activity was consistent with contract requirements.
During different time periods between March 2004 and August 2006, MDA
measured the results of the supplier's efforts and found a 64 percent
decrease in open quality control issues, a 43 percent decline in test
failures, and a 9 percent increase in on-time deliveries. MDA expanded
its teaming approach in 2006 to another problem supplier and reports
that many systemic solutions are already underway.
During fiscal year 2006, MDA's audits continued to identify both
quality control weaknesses and quality control procedures that
contractors are addressing. During 2006, the agency audited six
contractors and identified 372 deficiencies and observations.[Footnote
8] As of December 2006, the six contractors had collectively closed
157, or 42 percent, of the 372 audit findings. MDA also reported other
signs of positive results. For example, in 2006, MDA conducted a follow-
on audit of Raytheon, the subcontractor for GMD's exoatmospheric kill
vehicle. A 2005 audit of Raytheon had found that the subcontractor was
not correctly communicating essential kill vehicle requirements to
suppliers, did not exercise good configuration control, and could not
build a consistent and reliable product. The 2006 audit was more
positive, reporting less variability in Raytheon's production
processes, increasing stability in its statistical process control
data, fewer test problem reports and product waivers, and sustained
improvement in product quality.
Actions Recommended In Our Recent Report:
In our March 15, 2007, report, we made several recommendations to DOD
to increase transparency in the missile defense program. These
included:
* Develop a firm cost, schedule, and performance baseline for those
elements considered far enough along to be in system development and
demonstration, and report against that baseline.
* Propose an approach for those same elements that provides information
consistent with the acquisition laws that govern baselines and unit
cost reporting, independent cost estimates, and operational test and
evaluation for major DOD programs. Such an approach could provide
necessary information while preserving the MDA Director's flexibility
to make decisions.
* Include in blocks only those elements that will field capabilities
during the block period and develop a firm cost, schedule, and
performance baseline for that block capability, including the unit cost
of its assets.
* Request and use procurement funds, rather than research, development,
test, and evaluation funds, to acquire fielded assets.
DOD partially agreed with the first three recommendations and
recognized the need for greater program transparency. It committed to
provide information consistent with the acquisition laws that govern
baselines and unit cost reporting, independent cost estimates, and
operational test and evaluation. DOD did not agree to use elements as a
basis for this reporting, expressing its concern that an element-
centric approach to reporting would have a fragmenting effect on the
development of an integrated system. We respect the need for the MDA
Director to make decisions across element lines to preserve the
integrity of the system of systems. We recognize that there are other
bases rather than elements for reporting purposes. However, we believe
it is essential that MDA report in the same way that it requests funds.
Currently MDA requests funds and contracts by element, and at this
time, that appears to be the most logical way to report. MDA currently
intends to modify its current block approach. We believe that a
management construct like a block is needed to provide the vehicle for
making system-of-system decisions and to provide for system-wide
testing. However, at this point, the individual assets to be managed in
a block--including quantities, cost, and delivery schedules--can only
be derived from the individual elements.
Mr. Chairman, this concludes my statement. I would be pleased to
respond to any questions you or members of the subcommittee may have.
Contacts and Staff Acknowledgements:
For future questions about this statement, please contact me at (202)
512-4841 or francisp@gao.gov. Individuals making key contributions to
this statement include Barbara H. Haynes, Assistant Director; LaTonya
D. Miller; Michael J. Hesse; Letisha T. Jenkins; Sigrid L. McGinty;
Kenneth E. Patton; and Steven B. Stern.
FOOTNOTES
[1] GAO, Defense Acquisitions: Missile Defense Acquisition Strategy
Generates Results but Delivers Less at a Higher Cost, GAO-07-387
(Washington, D.C.: Mar. 15, 2007).
[2] We have adjusted the cost goal reported to Congress to reflect
MDA's removal of the THAAD element and its future development cost from
Block 2006.
[3] Specifics of the BMDS performance goals are classified and cannot
be presented in an open forum.
[4] Specific details regarding the cost increase can be found in GAO-07-
387.
[5] An element has reached full capability if it has completed all
system-level testing and has shown that it meets expectations. At this
state, all doctrine, organization, training, material, leadership,
personnel, and facilities are in place.
[6] 10 U.S.C. § 2433, known as Nunn-McCurdy.
[7] Because the BMDS or its major elements have not been designated by
MDA as being in system development and demonstration, no acquisition
program baseline is required under 10 U.S.C. § 2435. Thus there is no
basis for determining unit cost under 10 U.S.C. § 2433 (also known as
Nunn-McCurdy), which requires calculation of unit cost from the
baseline. Further, for the same reason, only limited Selected
Acquisition Reports to Congress on program status are generated [10
U.S.C. § 2432(h)] that do not include unit costs.
[8] Deficiencies are considered more serious and are recognized when
contractors do not comply with a contractual or internal procedure
requirement. On the other hand, observations are made when a contractor
fails to employ an MDA or industry best practice.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts
newly released reports, testimony, and correspondence on its Web site.
To have GAO e-mail you a list of newly posted products every afternoon,
go to www.gao.gov and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202)
512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S.
Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548:
Public Affairs:
Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, D.C. 20548: