Military Base Closures
Projected Savings from Fleet Readiness Centers Likely Overstated and Actions Needed to Track Actual Savings and Overcome Certain Challenges
Gao ID: GAO-07-304 June 29, 2007
The 2005 Base Realignment and Closure (BRAC) recommendation to establish fleet readiness centers was expected to yield more savings than any other of the 2005 BRAC recommendations. To achieve these savings the Navy plans to integrate civilian depot personnel to complete some repairs at intermediate maintenance departments to reduce aviation maintenance costs. This report, prepared under the Comptroller General authority to conduct evaluations on his own initiative, is one in a series of reports related to the 2005 BRAC recommendations. GAO's objectives were to (1) analyze the reasons for changes in costs and savings estimates since the recommendation was approved, and (2) identify challenges in implementing this BRAC recommendation. GAO analyzed Navy and BRAC Commission costs and savings estimates and interviewed officials at the Naval Air Systems Command and at three fleet readiness centers.
The Navy has increased onetime costs, decreased onetime savings and increased annual recurring savings expected from the fleet readiness centers recommendation, but GAO believes the savings are likely overstated. In preparing a detailed business plan for implementing the recommendation, the Navy increased onetime costs by $31 million or 96 percent because of costs associated with relocating employees and inflation. The Navy also decreased expected onetime savings from reduced inventory levels by $594 million or 92 percent because Navy officials believed earlier estimates were too optimistic. GAO's analysis of inventory levels for a sample of aviation items indicates that the majority of the revised savings estimate will not occur during the 6-year BRAC implementation period and the amount of such savings are uncertain at this time. GAO believes the annual recurring savings are overstated by about $53 million or 15 percent because the Navy's estimate includes $28 million in savings from eliminating military personnel, which may be assigned elsewhere rather than taken out of the force structure, and $25 million in onetime savings that was erroneously reported as recurring savings. While projected savings would remain substantial, they are still subject to some uncertainties and further efforts will be required to assess actual savings as this recommendation is implemented. The Navy faces challenges in ensuring projected savings are realized and faces some workforce challenges in implementing the recommendation. Since the Navy has already included projected BRAC savings in its budget for fiscal years 2007 through 2011, it will be important for the Navy to monitor the extent to which these savings are actually achieved to prevent adverse affects on naval aviation readiness or the need for additional funding. The Navy also faces workforce challenges, such as identifying and moving about 150 depot artisans with the right skills to various intermediate maintenance departments and integrating a primarily civilian depot workforce with the military intermediate department workforce. This mixing of diverse cultures could pose some challenges in implementation but should help develop a better trained and more productive workforce. The Navy will need sustained leadership to successfully establish the fleet readiness centers.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-07-304, Military Base Closures: Projected Savings from Fleet Readiness Centers Likely Overstated and Actions Needed to Track Actual Savings and Overcome Certain Challenges
This is the accessible text file for GAO report number GAO-07-304
entitled 'Military Base Closures: Projected Savings from Fleet
Readiness Centers Likely Overstated and Actions Needed to Track Actual
Savings and Overcome Certain Challenges' which was released on June 29,
2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Committees:
United States Government Accountability Office:
GAO:
June 2007:
Military Base Closures:
Projected Savings from Fleet Readiness Centers Likely Overstated and
Actions Needed to Track Actual Savings and Overcome Certain Challenges:
Military Base Closures:
GAO-07-304:
GAO Highlights:
Highlights of GAO-07-304, a report to congressional committees.
Why GAO Did This Study:
The 2005 Base Realignment and Closure (BRAC) recommendation to
establish fleet readiness centers was expected to yield more savings
than any other of the 2005 BRAC recommendations. To achieve these
savings the Navy plans to integrate civilian depot personnel to
complete some repairs at intermediate maintenance departments to reduce
aviation maintenance costs. This report, prepared under the Comptroller
General authority to conduct evaluations on his own initiative, is one
in a series of reports related to the 2005 BRAC recommendations. GAO‘s
objectives were to (1) analyze the reasons for changes in costs and
savings estimates since the recommendation was approved, and (2)
identify challenges in implementing this BRAC recommendation. GAO
analyzed Navy and BRAC Commission costs and savings estimates and
interviewed officials at the Naval Air Systems Command and at three
fleet readiness centers.
What GAO Found:
The Navy has increased onetime costs, decreased onetime savings and
increased annual recurring savings expected from the fleet readiness
centers recommendation, but GAO believes the savings are likely
overstated. In preparing a detailed business plan for implementing the
recommendation, the Navy increased onetime costs by $31 million or 96
percent because of costs associated with relocating employees and
inflation. The Navy also decreased expected onetime savings from
reduced inventory levels by $594 million or 92 percent because Navy
officials believed earlier estimates were too optimistic. GAO‘s
analysis of inventory levels for a sample of aviation items indicates
that the majority of the revised savings estimate will not occur during
the 6-year BRAC implementation period and the amount of such savings
are uncertain at this time. GAO believes the annual recurring savings
are overstated by about $53 million or 15 percent because the Navy‘s
estimate includes $28 million in savings from eliminating military
personnel, which may be assigned elsewhere rather than taken out of the
force structure, and $25 million in onetime savings that was
erroneously reported as recurring savings. While projected savings
would remain substantial, they are still subject to some uncertainties
and further efforts will be required to assess actual savings as this
recommendation is implemented. The Navy faces challenges in ensuring
projected savings are realized and faces some workforce challenges in
implementing the recommendation. Since the Navy has already included
projected BRAC savings in its budget for fiscal years 2007 through
2011, it will be important for the Navy to monitor the extent to which
these savings are actually achieved to prevent adverse affects on naval
aviation readiness or the need for additional funding. The Navy also
faces workforce challenges, such as identifying and moving about 150
depot artisans with the right skills to various intermediate
maintenance departments and integrating a primarily civilian depot
workforce with the military intermediate department workforce. This
mixing of diverse cultures could pose some challenges in implementation
but should help develop a better trained and more productive workforce.
The Navy will need sustained leadership to successfully establish the
fleet readiness centers.
What GAO Recommends:
GAO is making recommendations for the Navy to adjust its business plan
to include only savings directly related to implementing this BRAC
recommendation and to monitor actual savings realized as the
recommendation is implemented. In commenting on a draft of this report,
DOD concurred with our recommendations.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-304]:
To view the full product, including the scope and methodology, click on
the link above. For more information, contact Brian Lepore at (202) 512-
4523 or leporeb@gao.gov.
[End of section]
Contents:
Letter:
Results In Brief:
Background:
Estimated Savings Likely Overstated:
Challenges to Realizing Savings from Establishing Fleet Readiness
Centers:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Scope and Methodology:
Appendix II: Fleet Readiness Centers Recommendation:
Appendix III: Comments from the Department of Defense:
Appendix IV: GAO Contacts and Staff Acknowledgments:
Tables:
Table 1: Comparison of Projected Costs and Savings Estimates:
Table 2: Time Frames for Reducing Aviation Component Inventory
Requirements to Yield Savings:
Figures:
Figure 1: Planned Fleet Readiness Centers (FRC) and Affiliated Sites:
Figure 2: Aviation Components Repair Cycle:
United States Government Accountability Office:
Washington, DC 20548:
June 29, 2007:
Congressional Committees:
On May 13, 2005, the Department of Defense (DOD) made public its
recommendations to realign and close bases. DOD projected these actions
would yield nearly $50 billion in net savings over a 20-year period.
The Base Realignment and Closure (BRAC) Commission[Footnote 1]
evaluated DOD's recommendations and recommended reducing the estimated
20-year net savings by about $12 billion over a 20-year period. The
BRAC Commission recommendations were accepted by the President and the
Congress, and became effective on November 9, 2005. The recommendation
to establish six fleet readiness centers reengineers naval air
maintenance, which blends some civilian depot employees with military
personnel to complete repairs at intermediate maintenance departments.
The intent behind this action was to avoid some redundant maintenance
procedures and supply overhead charges and reduce aviation maintenance
costs. DOD initially estimated this recommendation would yield about
$4.7 billion in net savings over 20 years including onetime
savings[Footnote 2] of about $648 million.
In July 2005,[Footnote 3] we reported some uncertainty regarding the
magnitude of the expected savings from the recommendation to establish
fleet readiness centers because the estimates were based on assumptions
that had undergone limited testing, and were also dependent on
transformation of the Navy supply system. In addition, after performing
its own analysis, the BRAC Commission believed the Navy overestimated
the savings that may be achieved from business process reengineering
efforts. The BRAC Commission approved the recommendation to establish
fleet readiness centers with an estimated 20-year net savings of $3.7
billion. Of the large number of 2005 BRAC recommendations, this
recommendation is projected to produce the most dollar savings, based
on DOD's total BRAC savings projections.
Once the recommendation became effective, the Navy became responsible
for executing the recommendation to establish fleet readiness centers.
The Office of the Secretary of Defense required the Navy to submit a
detailed business plan for implementing the recommendation, to update
estimated costs and savings, and to provide a schedule for implementing
the recommendation. The fleet readiness center plan was approved by the
Office of the Secretary of Defense on August 1, 2006.
This report is one in a series of reports that detail the progress DOD
has made in implementing the base closures and realignments included in
the 2005 BRAC round. We performed our work on the basis of the
authority of the Comptroller General to initiate reviews[Footnote 4]
and are reporting the results to you in order to facilitate your
oversight of DOD's infrastructure and BRAC initiative. In this report,
we address the Navy's efforts to implement the BRAC recommendation to
establish fleet readiness centers. Our specific objectives were to (1)
analyze the reasons for changes to the costs and savings estimates
since the recommendation to establish fleet readiness centers was
amended and approved as part of the 2005 BRAC round; and (2) identify
the challenges the Navy faces in successfully implementing this BRAC
recommendation.
To accomplish these objectives, we performed our work at the Naval Air
Systems Command headquarters, Patuxent River, Maryland; the aviation
intermediate maintenance departments at North Island, San Diego,
California; Mayport, Florida; and Whidbey Island, Oak Harbor,
Washington; and the naval aviation depots at North Island, San Diego,
California, and Jacksonville, Florida. We analyzed the changes to the
costs and savings estimates between the BRAC Commission's amended and
approved recommendation and the Navy's approved business plan and
interviewed key Navy officials to identify the reasons for changes and
the challenges they face in implementing the recommendation. To assess
the reliability of data used to generate costs and savings estimates,
we reviewed Navy regulations and instructions for reporting aviation
maintenance data and interviewed officials at the Navy Air Systems
Command, Naval Aviation Depots, and Commander, Naval Air Forces, about
the data and assumptions underlying the estimates. Based on these
discussions and observations and review of the Navy's calculations, we
believe the DOD data are sufficiently reliable for the purposes of this
report. We conducted our work between February and December 2006 in
accordance with generally accepted government auditing standards.
Further details on the scope and methodology are described in appendix
I.
Results in Brief:
In comparison to the BRAC Commission estimates, the Navy has increased
onetime costs, decreased one-time savings, and increased annual
recurring savings expected from the fleet readiness centers
recommendation.[Footnote 5] While the Navy has started to implement the
recommendation and achieve savings, we believe the amount of onetime
savings are uncertain at this time and projected net annual recurring
savings are overstated. The savings consist primarily of onetime
savings from projected decreases in the inventory of aircraft component
and replacement parts, and annual recurring savings[Footnote 6] from
reduced depot labor and overhead charges and personnel reductions. In
preparing its business plan, the Navy reduced expected one-time savings
from lower inventory levels by 92 percent (from $648 million to $54
million) because Navy officials believed their initial estimates were
too optimistic. Even though the Navy reduced its estimated onetime
savings, our analysis of inventory levels for a sample of aviation
items concluded that the majority of the revised savings estimate will
not occur during the 6-year BRAC implementation period, and the amount
of such savings over time are uncertain. While the Navy projects annual
recurring savings of about $311 million, we believe they are likely
overstated by $53 million. The Navy's estimate includes $28 million in
savings from eliminating military personnel, which may be assigned
elsewhere rather than taken out of the force structure, and $25 million
in onetime savings that were erroneously reported as recurring savings.
While projected savings remain substantial, they are still subject to
some uncertainties and additional efforts will be required to assess
actual savings over time as this recommendation is implemented.
The Navy faces challenges in ensuring projected savings from
implementing its fleet readiness center recommendation are realized
even as it also faces some workforce challenges in implementing the
recommendation. Since the Navy has already included projected BRAC
savings in its budget plans for fiscal years 2007 through 2011, the
Navy will need to monitor the extent to which these savings are
achieved. Therefore, if savings are not realized, the Navy may have to
take funds from other Navy programs or request additional funds to
offset unrealized savings or be unable to repair aviation components in
a timely manner which could affect readiness. The Navy has developed an
interim method for tracking aviation maintenance repair costs and
calculating the BRAC savings from establishing fleet readiness centers,
but follow through will be important to validate savings over time. In
addition, the Navy faces workforce challenges, such as potentially
moving over 150 depot artisans with the right skills to various
intermediate maintenance departments and integrating a primarily
civilian depot workforce with the military intermediate department
workforce. This mixing of diverse cultures could pose some challenges
in implementation but could result in a better-trained and more-
productive workforce. The Navy faces other challenges, such as the need
for sustained leadership and communication to successfully establish
the fleet readiness centers. Furthermore, the Navy needs to ensure that
depot maintenance performed at intermediate departments is accurately
recorded and reported to satisfy congressional reporting requirements.
The Navy has recognized many of these challenges and outlined steps to
be taken to address them.
We are making recommendations to the Secretary of Defense to direct the
Secretary of the Navy to update the business plan to include only
savings that are directly related to implementing the BRAC
recommendation and monitor and update savings as implementation
progresses. In commenting on a draft of this report, DOD concurred with
our recommendations. DOD noted that it considers military personnel
reductions attributable to a BRAC recommendation as real savings. It
noted that while the department may not reduce end strength, these
reductions allow the department to reapply these military personnel to
support new capabilities. We believe the department counting of savings
from eliminating military personnel positions, without corresponding
reductions in end strength, creates a false sense of savings available
for other purposes because they do not represent dollar savings that
can be readily reallocated outside the military personnel accounts. We
do agree that assigning these positions to other areas may enhance
capabilities. DOD's written comments are reprinted in appendix III. DOD
also provided technical comments, which we have incorporated into this
report as appropriate.
Background:
The Navy has three levels of naval aviation maintenance--
organizational, intermediate, and depot--to support naval
aviation.[Footnote 7] Organizational maintenance is performed by
sailors on the flight line and generally items are repaired on the
aircraft, whether at sea or at a naval station. The intermediate
maintenance activity is generally performed by sailors at the Navy's
aviation intermediate maintenance departments, which focus on item
repairs in close proximity to the flight line but off-aircraft. Depot
maintenance activities, generally performed by civilian aviation depot
artisans, provide a comprehensive combination of major repair,
overhaul, and modifications to weapons systems and components,
assemblies, and subassemblies in off-flight-line maintenance. The
current aviation maintenance process generally flows as follows: when
the organizational maintenance crews cannot fix a broken aircraft
component or item, it is sent to the intermediate department; if the
intermediate maintenance department cannot repair an item, it declares
that the item is beyond its capability of maintenance. The broken item
is then turned over to the supply system in exchange for a replacement
part; and the broken item is shipped to the depot for further repairs
or overhaul.
The recommendation to establish fleet readiness centers affects the
intermediate department and depot maintenance levels, but not the
organizational level. It involves moving about 150 artisans from the
depots to the intermediate departments to perform aviation repairs. In
addition, six fleet readiness centers will be established to transform
naval aviation maintenance at the intermediate departments and depots
as seen in figure 1.
Figure 1: Planned Fleet Readiness Centers (FRC) and Affiliated Sites:
[See PDF for image]
Source: GAO analysis of U.S. Navy data.
[End of figure]:
According to this BRAC recommendation, relocating depot artisans to
intermediate departments is expected to reduce the number of items that
are declared to be beyond the capability of maintenance at the
intermediate departments and therefore, will not require some items to
be sent to the depot for repair. As a result, repeated and duplicated
maintenance procedures are projected to be avoided and turnaround times
projected to be reduced. More specifically, prior to implementing this
recommendation, when an item is being repaired by military personnel at
the intermediate department, they perform diagnostics, disassemble the
item, and attempt to repair it. When they determine it cannot be
repaired and declare that it is beyond their capability of maintenance,
the item is reassembled, repackaged, and shipped to the depot for
repair. Upon arrival at the depot, the artisans must perform similar
diagnostics, and repeat the processes of disassembly and repair that
have already been performed at the intermediate department. According
to Navy officials, after fleet readiness centers are established, the
depot artisans positioned at the intermediate departments are expected
to be able to complete more repairs there, which will reduce or
eliminate some packaging, shipping, and administrative costs as seen in
figure 2.
Figure 2: Aviation Components Repair Cycle:
[See PDF for image]
Source: GAO analysis.
[End of figure]:
At the time DOD originally submitted its recommendations to the BRAC
Commission, it estimated this recommendation would yield $341 million
in annual recurring savings, or $4.7 billion net savings over 20 years.
The preponderance of the annual recurring savings was expected to come
from fewer items being sent to the depots for repair, thus reducing per
item maintenance costs. DOD also expected to achieve significant
onetime savings by reducing existing inventory levels of aircraft
component parts. In July 2005, we reported that while there is
potential for significant savings, there is some uncertainty over the
full magnitude of savings.[Footnote 8] Our report noted that the Navy
used assumptions that had undergone limited testing, and the full
savings realization depends upon the transformation of the Navy's
supply system to achieve organizational efficiencies. Moreover, we
pointed out that realizing the full extent of the savings would depend
on actual implementation of the recommended actions.
The BRAC Commission also believed DOD's overall estimated savings were
overstated because savings were derived from overhead efficiencies that
had not been validated. The commission projected annual recurring
savings of about $248 million a year or $3.7 billion[Footnote 9] net
present value savings over a 20-year period--about $1 billion less than
the DOD's estimate. Also, the commission reduced the estimated savings
because it eliminated the proposed realignment of workload from the
Naval Support Activity in Crane, Indiana, to Whidbey Island,
Washington, since the Navy planned to phase out the aircraft associated
with the proposed workload transfer in 10 to 15 years regardless of
BRAC. In addition, the commission found errors in DOD's estimation of
construction costs and the savings projections based on eliminated
personnel.
The President and the Congress accepted the BRAC Commission
recommendations, which became effective on November 9, 2005. Once the
recommendations became effective, the Office of the Secretary of
Defense designated one of the military services or defense agencies as
the business manager responsible for implementing each recommendation.
The Navy is responsible for establishing the six fleet readiness
centers. The Office of the Secretary of Defense also required the Navy
to submit a detailed business plan to update estimated costs and
savings and identify a schedule for implementing the recommendation.
The Navy's detailed business plan was approved to implement the
recommendation to establish fleet readiness centers on August 1, 2006.
However, the Office of the Secretary of Defense has requested that the
Navy resubmit its plan to accurately reflect the savings realized based
on the Navy's current implementation of this BRAC recommendation. The
Navy's plan was still in-process as of March 15, 2007.
In addition, the Navy must comply with Title 10, Section 2466 of the
United States Code (U.S.C.), which provides that not more than 50
percent of the funds made available in a fiscal year to the Navy for
depot maintenance and repair workload may be used to pay for work
performed by private contractors. The statute also requires the
Secretary of Defense to submit a report to Congress (known as the "50/
50" report) by April 1 annually, on public-private depot maintenance
funding distributions. The 50/50 report notes the percentage of depot
maintenance funding between the public and private sectors during the
preceding fiscal year, the projected distribution for the current
fiscal year, and the ensuing fiscal year.
Estimated Savings Likely Overstated:
In comparing the Navy's business plan with the BRAC Commission
estimates of costs and savings, the Navy's business plans shows an
increase in one-time costs, a decrease in one-time savings, and an
increase in annual recurring savings as seen in table 1 below.
Table 1: Comparison of Projected Costs and Savings Estimates:
Dollars in millions: Category: Onetime costs; BRAC Commission
approved[A]: $34; Navy business plan[B]: $65; Difference: Amount: $31;
Difference: Percent: 96.
Dollars in millions: Category: Onetime savings; BRAC Commission
approved[A]: 648; Navy business plan[B]: 54; Difference: Amount: (594);
Difference: Percent: (92).
Dollars in millions: Category: Annual recurring savings; BRAC
Commission approved[A]: 250; Navy business plan[B]: 311; Difference:
Amount: 61; Difference: Percent: 25.
Source: DOD data.
Notes: DOD did not accept the final BRAC Commission estimate because it
was based on actual versus authorized positions.
[A] In constant fiscal year 2005 dollars.
[B] In then year or current dollars.
[End of table]:
While the Navy has started to implement the recommendation and achieve
savings, we believe the latest savings estimates are still overstated
and uncertain. The majority of the savings consist of onetime savings
from projected decreases in the inventory of aircraft components and
replacement parts, and annual recurring savings from reduced depot
labor and overhead charges and reductions in military personnel. While
savings from lower inventory levels may be possible, our analysis of a
judgmental sample of items targeted for inventory reduction concluded
that the majority of these savings would not occur during the 6-year
implementation period of this BRAC recommendation.[Footnote 10]
Further, we believe the Navy's estimated annual recurring savings
remain overstated because they included savings from eliminating
military personnel that are not expected to result in a reduction to
its overall service force structure and included onetime savings
erroneously reported as recurring savings.
Onetime Costs Increased:
The Navy's business plan shows onetime costs increased by 96 percent
(from $34 million to $65 million) as compared to the BRAC Commission's
estimates, which was primarily due to increased costs associated with
relocating depot employees to the intermediate level, other
miscellaneous program management actions, and inflation.[Footnote 11]
For example, Navy officials stated that they need to add more equipment
or specialized workbenches to support depot artisans relocated to the
intermediate departments. The program management costs are primarily
for information technology upgrades. For example, Navy officials stated
the need for an interim logistics tracking and accounting mechanism,
using its current Naval Aviation Logistics Command/Management
Information System to track depot maintenance repairs at the
intermediate departments. While onetime costs have nearly doubled, they
have limited effect on the long-term recurring savings expected from
establishing fleet readiness centers once those savings offset
implementation costs.
Onetime Savings Have Been Reduced, but Uncertainty Exists about When
They Will be Achieved:
While the Navy has reduced the projected onetime savings from lower
levels of inventory, our analysis of a sample of aviation inventory
items targeted for reduction concludes that the majority of these
savings would not occur during the 6-year implementation period, and
the amount of such savings over time is uncertain. In preparing the
business plan, the Navy reduced its onetime savings by 92 percent (from
$648 million to $54 million) mostly by lowering the estimated savings
from reducing inventory of aircraft components and replacement parts.
According to Navy officials, the initial inventory savings estimate was
overly optimistic. In addition, the lower estimate was based on the
BRAC Commission's determination that the Navy's projected savings were
overstated because the commission found errors in the Navy's savings
estimates. Additionally, our July 2005 report stated that the magnitude
of the expected savings for the fleet readiness centers is in part
dependent upon transformation of the Navy's supply system, such as
eliminating unneeded management structures and duplicate layers of
inventory in the supply system.[Footnote 12]
DOD's original submission to the BRAC Commission assumed that the
dollar value of the inventory of aircraft components and replacement
parts could be reduced by 15 percent. According to Navy officials, the
15 percent savings factor was based on the professional judgment of the
Industrial Joint Cross Service Group members. They expected savings
because fewer items would need to be kept in the shore-based aviation
consolidated inventory because items would be getting repaired more
quickly and returned to the inventory faster.[Footnote 13] However, the
Navy officials stated that they did not have time during the BRAC
process to discuss the estimated inventory and supply savings with
officials from the Navy Supply Command to validate the estimate. Navy
officials stated that they estimated the onetime savings from inventory
reductions ($648 million) by multiplying the 15 percent factor times
the total dollar value of the inventory and supply of aircraft
components and replacement parts in fiscal year 2003.[Footnote 14]
In developing the business plan, the Navy reduced the inventory and
supply savings factor from 15 percent to less than 4 percent based on
discussions with Naval Supply Command officials and a better
understanding of how other BRAC recommendations affected DOD's and
Navy's supply system. Specifically, two other recommendations involved
significant savings projections from reengineering DOD's inventory and
supply system and the reconfiguration of supply, storage, and
distribution management. After considering how these other BRAC
recommendations could affect the Navy's projected inventory and supply
savings estimates, Navy officials concluded there would be a greater
potential overlap of savings with the fleet readiness center BRAC
recommendation. However, the Navy could not provide us documentation to
support the lower inventory savings estimate.
While savings from lower inventory may be possible, our analysis of a
judgmental sample of 99 items targeted for inventory reduction
concludes that the majority of these savings will not occur during the
6-year implementation period of this BRAC recommendation as the Navy
originally projected. Our analysis shows that for 83 percent of the
items sampled, the Navy will take more than the implementation period
to achieve lower inventory levels because the majority of replacement
items on-hand is sufficient to provide many years worth of supply, and
the rate of replacement for that inventory will not be a factor
contributing to savings, as seen in table 2.
Table 2: Time Frames for Reducing Aviation Component Inventory
Requirements to Yield Savings:
Fiscal year: 2006-2011; Number of items: 17; Percent: 17.
Fiscal year: 2012-2020; Number of items: 22; Percent: 27.
Fiscal year: Beyond 2021; Number of items: 60; Percent: 56.
Total; Number of items: 99; Percent: 100.
Source: GAO analysis.
[End of table]:
Since the Navy has not yet identified all of the inventory items that
could be affected by the fleet readiness centers recommendation, we
could not estimate the effect of delayed inventory savings reductions
on the Navy's estimated onetime savings or the total amount of savings
likely to be realized.
Annual Recurring Savings Likely Remain Overstated:
The Navy increased the annual recurring savings estimate by 25 percent
(from about $250 million to $311 million) primarily by increasing
projected savings from military personnel eliminations and inflation.
These increases were offset to some degree by decreases in projected
savings from maintaining facilities. However, we believe the Navy's
revised annual recurring savings estimates are still overstated by
approximately $53 million because they include $28 million in savings
from eliminating military personnel, which may be assigned elsewhere
rather than taken out of the force structure, and $25 million that
should have been reported as onetime, and not recurring, savings. In
addition, we estimate that projected annual recurring savings increased
by approximately $42 million due to inflation.[Footnote 15]
The BRAC Commission projected annual recurring savings of about $10
million from eliminating about 120 military positions, while the Navy
business plan includes about $28 million in annual recurring savings
from eliminating about 290 military positions as originally planned.
Regardless of the number of military personnel affected by the
recommendations, as we reported in July 2005, the projected net annual
recurring savings associated with eliminating jobs currently held by
military personnel could create a false sense of savings available for
other purposes because they do not represent dollar savings that can be
readily reallocated outside the military personnel accounts. Rather
than reduce end strength, these positions are expected to be reassigned
to other areas, which may enhance capabilities but also limit dollar
savings available for other uses.[Footnote 16]
The Navy incorrectly reported onetime savings as annual recurring
savings in its business plan. Navy officials stated that $25 million
onetime savings were incorrectly categorized as annual recurring
savings in its business plan. These onetime savings included reductions
in aviation depot level repair charges, decreased spare parts
inventory, and reduced materials to repair aviation components. As a
result of the fleet readiness center implementation to date, Navy has
begun to reduce its current spare parts inventory, which translates
into less physical space needed to store the inventory and fewer
sailors needed to manage it. However, GAO believes that the Navy's
business plan should correctly report the $25 million as onetime
savings and not annual recurring savings.
Increases in the Navy's annual recurring savings estimates were offset
to some degree by decreases in projected savings expected from reduced
facility costs. According to the Navy officials, the projected
reductions in personnel should result in reducing floor space for
numerous work shops, but they will not free up enough space to allow
the Navy to vacate any buildings at this time. Since no buildings will
be vacated, the Navy reduced the annual recurring savings expected from
facilities maintenance by about $3 million. Navy officials indicated
that as fleet readiness center implementation progresses, there may be
opportunities to combine similar work shops at some sites, which may
result in entire buildings being vacated, and produce savings in the
funding for facilities maintenance. If this occurs, a Navy official
noted the business plan would be updated to reflect these savings.
In addition, Navy's implementation efforts are beginning to show
savings. The Navy reported savings of $19 million from October 2006 to
April 2007 at the 6 fleet readiness centers. These savings are from
repairing selected aviation items at the fleet readiness centers
instead of sending them to the depots for repair.
Challenges to Realizing Savings from Establishing Fleet Readiness
Centers:
The Navy faces challenges in ensuring that projected savings are
realized from implementing the fleet readiness center recommendation in
addition to some workforce challenges in implementing the
recommendation. Since the Navy has already included projected BRAC
savings in its budget for fiscal years 2007 through 2011, the Navy will
need to monitor the extent to which these savings are achieved. If
savings are not realized, the Navy may need to get funds from another
Navy program or request additional funds to offset unrealized savings
or be unable to repair aviation components in a timely manner, which
could impact readiness. Accordingly, the Navy has developed an interim
method for tracking aviation maintenance repair costs and calculating
the BRAC savings from establishing fleet readiness centers, which
addresses our prior recommendation to DOD to update and track savings.
In addition, the Navy acknowledges that other challenges remain, such
as identifying and moving necessary depot artisans with the right
skills to various intermediate maintenance departments and integrating
a primarily civilian depot workforce with the military intermediate
department workforce. Navy officials recognize that this mixing of
workforces could create some cultural tension in the workforce, but
this blending may facilitate the development of a better-trained and
more-productive workforce. The Navy has recognized many of these
challenges and outlined steps to be taken to address them. Our prior
work has shown that strong and sustained executive leadership is needed
if reform efforts are to succeed.[Footnote 17] Furthermore, our prior
work has raised questions about the reasonableness and consistency of
depot maintenance workload data submitted to the Congress.[Footnote 18]
Therefore, the Navy will need to ensure that depot maintenance work
performed at intermediate departments is accurately reported to satisfy
congressional reporting requirements.
Planned Short-Term Monitoring Will Need to Be Extended:
The Navy has developed an interim method for tracking aviation
maintenance repair costs and calculating the BRAC savings from
establishing fleet readiness centers, but it will be important to
ensure this effort continues over time to validate savings. Navy
officials noted that if the expected savings are not realized, this
decrease in savings could adversely affect the Navy's ability to
perform its mission within budgeted funds. Furthermore, inadequate
implementation could affect readiness, and the Navy may need to request
additional funds to offset unrealized savings. Our previous work has
raised concerns with prior DOD efforts to reduce related operating
budgets in advance of actual savings being realized.[Footnote 19]
The Navy reduced its aviation maintenance budget for fiscal years 2007
through 2011 by the estimated BRAC savings it projects will result from
establishing fleet readiness centers. Navy officials recognized its
challenges in achieving these estimated savings as well as the
importance of monitoring and tracking the actual and realized BRAC
savings. The Navy has developed an interim method for calculating the
BRAC savings realized at the newly established fleet readiness centers
during the implementation time frame. This interim method utilizes
information from two separate logistic systems, one at the depots and
the other at the intermediate departments, to allow Navy officials to
evaluate each fleet readiness center's performance in meeting its BRAC
savings targets. However, this short-term solution for tracking BRAC
savings is not designed to go beyond 2011 or address long-standing
business and financial system challenges.
Workforce Challenges:
Identifying Maintenance Items and Critical Skills:
To achieve desired savings, the Navy has begun identifying which items
currently repaired at the depots could be repaired at the former
intermediate departments (now fleet readiness centers/sites). The Navy
originally calculated about 38,000 items that were beyond the
capability of maintenance of the intermediate departments, which could
be repaired by potentially moving about 150 depot artisans to the
intermediate departments. As of November 2006, the Navy has identified
about 1,800 items that can be repaired at intermediate departments.
Twenty-five depot artisans have already begun to repair 127 of these
items at the intermediate departments. The number of items ultimately
selected will dictate the number of personnel needed and savings to be
realized. Our prior work on strategic workforce planning highlighted
the need for organizations to identify the right number of staff with
the right skills and competencies in the right locations to fulfill
their missions and goals.[Footnote 20] Based on the items identified
for repair, the Navy will determine the skill sets required for depot
artisans to perform repairs at the intermediate departments.
Consequently, the Navy will request depot artisan volunteers to
relocate to the intermediate departments. If artisans do not volunteer
to relocate to the intermediate departments or if artisans with the
necessary skill sets have retired or stopped working through normal
attrition, the Navy plans to hire or contract for the necessary skill
sets. Navy officials stated that intermediate departments are located
in heavily industrialized areas that may enable them to hire people
with the necessary skill sets.
Introducing Civilian Depot Artisans at Intermediate Departments:
As the Navy establishes the fleet readiness centers, the Navy will
relocate some civilian depot artisans to work alongside military
personnel at the intermediate maintenance departments, which has the
potential to create cultural challenges within the workforce. Navy
officials recognized that this mixing of civilian and military
workforces with their differences in working environments could create
some cultural tension, but this blending may facilitate the development
of a better-trained and more-productive workforce. The Navy's civilian
depot artisans work under a collective bargaining agreement which
specifies employee work hours, maximum allowable excess work hours, and
the number and duration of an artisan's guaranteed breaks. At the
intermediate maintenance departments, the military personnel are
required to work according to mission needs, which may exceed normal
work hours and disallow breaks, if necessary. Navy officials stated
that they do not foresee any labor problems when the Navy establishes
fleet readiness centers. Our prior work recognizes that certain
organizational and environmental differences cause stresses that may
affect an agency's ability to attain its strategic goals. Certain key
human capital practices can be employed to overcome such differences,
such as developing policies and procedures to allow for the flexible
use of the workforce to ensure consistency, equity, transparency, and
address employee concerns.[Footnote 21]
While this mixing of diverse cultures could pose some challenges in
implementation, it could also help in developing a better-trained and
more-productive workforce if properly managed. As implementation of
this BRAC recommendation begins, the Navy will temporarily assign
civilian artisans to predominately military intermediate maintenance
departments to perform repairs. As fleet readiness centers are
established, the temporary assignments will become permanent. As the
artisans and military personnel become accustomed to working side-by-
side, the Navy may combine similar shops that have existed separately
at depots and intermediate maintenance departments to assure efficient
use of personnel, equipment, and facilities. This effort to determine
if shops can be combined will begin over the next several years.
According to Navy officials, when depot artisans begin to work with
military personnel, the artisans will provide on-the-job training as a
means to increase the military personnel ability to perform aviation
repairs and improve aviation maintenance efficiency. However, Navy
officials stated that some workforce members are concerned about the
long-term effect of these changes. For example, it is unclear whether
shops that are comprised of military and civilian workforce members
will be managed by military or civilian leadership. In addition, these
combined shops may have an effect on the career paths of aviation
maintenance officers and civilian managers.
Navy's Communication Strategy to Promote Goals of Fleet Readiness
Centers:
Communicating the mission and goals of the fleet readiness centers is
critical to implementing this BRAC recommendation. To address this
challenge, the Navy has focused on developing a communication plan to
mitigate the risk of inaccurate or inconsistent information and address
workforce fears. The communication plan goal is to maximize stakeholder
ownership and involvement with the implementation of the fleet
readiness centers to minimize uncertainty and anxiety inherent with
organizational change. In our prior report,[Footnote 22] we stated that
strategic workforce planning is most effective when an agency's goals,
approach, and results are communicated early, clearly, and often. Navy
officials said that early communication is critical to mitigate rumors
and speculation about potential workforce changes at the intermediate
departments and depot maintenance facilities. Accordingly, the Navy has
developed a detailed communication plan to describe the challenges
associated with implementing this BRAC recommendation. This plan
details the approach that will be used to establish fleet readiness
centers, the goals they are expected to achieve, and the results that
are desired from introducing depot artisans into the intermediate
workforce. The Navy expects to evaluate the success of the
communication plan using several methods including monthly key
stakeholder feedback reports; postbriefing and post-town hall audience
surveys; circulation or number of memos and number of people who
actually saw the message; and other surveys to determine changes in
awareness (knowledge), attitudes (opinions) or respondent's reports of
past or anticipated/intended actions (behaviors).
As part of the Navy's communications strategy, the Commander, Aviation
Depots, Naval Air Systems Command has traveled in excess of 200 days
during the past year in order to communicate the fleet readiness center
concept to the entire aviation maintenance workforce. He stated he will
meet or exceed that travel schedule during the implementation phase to
ensure that all workforce members have heard his message. During a
portion of his travel time, he plans to conduct "town hall" meetings
with the aviation maintenance workforce members at fleet readiness
center locations and affiliated sites. Following these meetings, the
commander will send teams to each newly established fleet readiness
center to introduce the concepts and the expected changes in
establishing the centers to the workforce. These teams will also
provide information with regard to procedural changes that will be
necessary to assure that costs and savings are properly tracked at each
fleet readiness center and affiliated site. According to Navy
officials, as the implementation proceeds, efforts will be undertaken
to apply lessons learned as fleet readiness centers are established.
Providing Sustained Leadership:
Generally, commanding officers in the Navy change commands every 2
years, which can make sustained leadership in a reorganization effort
challenging, and there is no guarantee that leadership will remain in
place throughout the implementation of this BRAC recommendation. Our
prior work on strategic workforce planning states that sustained
leadership and succession planning is necessary to achieve workforce
reorganizations and agency goals.[Footnote 23] Navy officials stated
that they expect to achieve the largest change in naval aviation
maintenance since 1959 in only 3 to 5 years and the Commander, Aviation
Depots, Naval Air Systems Command, expects his assignment to continue
until fleet readiness center implementation is complete. The Navy has
26 Naval Aviation Maintenance duty captains, which comprise a cadre of
officers available for selecting successive commanding officers to
oversee the implementation of the recommendation to establish and
manage fleet readiness centers. In addition to top-level leadership,
the Navy plans to utilize the Navy's chief petty officers, the Marine
Corps' senior noncommissioned officers, and seasoned civilian
maintainers as key enablers of the implementation process. Navy
officials feel that these individuals can reinforce the communications
of senior Navy leadership and clarify the intent of establishing fleet
readiness centers to sailors, marines, and the civilian workforce.
Reporting Depot Maintenance Funding between the Public and Private
Sectors:
Navy officials noted another challenge may exist after fleet readiness
centers are established that involves accurately recording and
reporting depot maintenance performed at intermediate departments.
Under 10 U.S.C. § 2466, the military departments and defense agencies
can use no more than 50 percent of annual depot maintenance funding for
work performed by private-sector contractors. In fiscal year 2006, the
Navy reported that 52 percent of naval aviation depot work was
performed by civilian depot artisans and 48 percent was performed by
private contractors. As depot artisans begin to work in intermediate
maintenance departments, adequate systems and management commitment for
verifying the amount of public-sector depot maintenance is necessary to
comply with 50/50 requirements. We previously reported that the Navy
did not maintain documentation to support the amounts in its 50/50
report and no formal training on procedural requirements or Navy
guidance to develop and report the 50/50 data was provided to the
personnel responsible for compiling the data. Our report noted that
persistent deficiencies limit the accuracy and usefulness of DOD's
funding allocation data reported to the Congress, and further, that it
is difficult to project out-year data due to factors such as changing
depot maintenance requirements and the ongoing consolidation of
maintenance facilities. When the fleet readiness centers are
implemented, depot artisans will be stationed at the intermediate
departments and must document the depot maintenance performed, which is
used for entry into the depot accounting system and the Naval Aviation
Logistics Command/Management Information System. The Navy has drafted a
handbook that provides procedures and quality assurance for the
required details of documentation by the artisans. For example, all
maintenance documentation goes through layers of quality assurance such
as validation specifications within the Naval Aviation Logistics
Command/Management Information System, production controls that approve
each component before moving it back into the supply system, database
administrator screening, and a final reality check by the fleet
readiness center command subject matter experts.
Conclusions:
Although projected savings from establishing fleet readiness center
remain significant, it appears likely that the majority of onetime
savings from reduced inventory levels may not occur as expected during
the BRAC implementation period, and projected long-term savings are
likely overstated. To accurately account for and report BRAC savings,
the Navy business plan to establish fleet readiness centers should
include onetime savings that will be achieved during the implementation
period and long-term savings that are directly attributed to
implementing the recommendation. While the Navy has recognized the need
to assess progress against goals and track savings, our prior work has
shown that sustained leadership and follow-through will be important to
ensure the recommendation is successfully implemented.
Recommendations for Executive Action:
To improve the reporting of savings projected from BRAC 2005
recommendations, we recommend that the Secretary of Defense direct the
Secretary of the Navy to:
* update the business plan for the fleet readiness centers (1) to
reflect only savings that are directly related to implementing the
recommendation, and (2) update projected onetime savings when data are
available; and:
* monitor implementation of the recommendation to determine the extent
that savings already taken from the Navy budget are actually achieved.
We are sending copies of this report to interested congressional
committees; the Secretaries of Defense and the Navy; and the Director,
Office of Management and Budget. We will also make copies available to
others upon request. In addition, the report will be available at no
charge on GAO's Web site at [Hyperlink; http://www.gao.gov]:
Agency Comments and Our Evaluation:
In commenting on a draft of this report, DOD concurred with our
recommendations. DOD noted that it considers military personnel
reductions attributable to a BRAC recommendation as real savings. It
noted that while the department may not reduce end strength, these
reductions allow the department to reapply these military personnel to
support new capabilities. We believe the department counting of savings
from eliminating military personnel positions, without corresponding
reductions in end strength, creates a false sense of savings available
for other purposes because they do not represent dollar savings that
can be readily reallocated outside the military personnel accounts. We
do agree that assigning these positions to other areas may enhance
capabilities. DOD's written comments are reprinted in appendix III. DOD
also provided technical comments, which we have incorporated into this
report as appropriate.
If you or your staff have any questions about this report, please
contact me on (202) 512-4523 or leporeb@gao.gov. Contact points for our
Offices of Congressional Relations and Public Affairs may be found on
the last page of this report. Additional contacts and staff
acknowledgments are provided in appendix IV.
Signed by:
Brian J. Lepore:
Director:
Defense Capabilities and Management:
List of Committees:
The Honorable Carl Levin:
Chairman:
The Honorable John McCain:
Ranking Member:
Committee on Armed Services:
United States Senate:
The Honorable Daniel K. Inouye:
Chairman:
The Honorable Ted Stevens:
Ranking Member:
Subcommittee on Defense Committee on Appropriations:
United States Senate:
The Honorable Tim Johnson:
Chairman:
The Honorable Kay Bailey Hutchison:
Ranking Member:
Subcommittee on Military Construction, Veterans' Affairs, and Related
Agencies:
Committee on Appropriations:
United States Senate:
The Honorable Ike Skelton:
Chairman:
The Honorable Duncan L. Hunter:
Ranking Member:
Committee on Armed Services:
House of Representatives:
The Honorable John P. Murtha, Jr.
Chairman:
The Honorable C.W. Bill Young:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
House of Representatives:
The Honorable Chet Edwards:
Chairman:
The Honorable Roger F. Wicker:
Ranking Member:
Subcommittee on Military Construction, Veterans' Affairs, and Related
Agencies:
Committee on Appropriations:
House of Representatives:
[End of section]
Appendix I: Scope and Methodology:
We performed our work at the Office of the Secretary of Defense, the
office the Commander, Naval Air Forces, Naval Air Systems Command,
Patuxent River, Maryland; the Naval Aviation Depots in Coronado,
California, and Jacksonville, Florida, as well as the Aviation
Intermediate Maintenance Departments located at Oak Harbor, Washington;
Coronado, California; and Mayport, Florida.
To determine the extent to which estimated costs and savings have
changed, we compared the Navy's business plan approved in August 2006
to the recommendation approved by the Base Realignment and Closure
(BRAC) Commission. We focused on the major factors that affected
projected onetime costs, onetime savings, and annual recurring savings.
We determined the reasonableness of these estimates by reviewing and
analyzing source data and the methodology used to generate savings
estimates and interviewing Navy officials who prepared these estimates.
We discussed the reasons for variances in costs and savings estimates
between the BRAC Commission and the approved business plan with Navy
officials. To analyze projected onetime savings from reduced levels of
aircraft component inventory, we took a judgmental sample of 99 items
targeted for inventory reduction. We calculated the years of supply for
each item using its required inventory level, inventory on-hand, excess
on-hand inventory, condition, and recurring and nonrecurring demands.
Our analysis was reviewed by Navy Supply System officials. We analyzed
the business plan to identify the major elements that contributed to
projected annual recurring savings. Our analysis indicated that the
business plan included savings from an initiative to reduce aviation
maintenance costs referred to as AirSpeed. We interviewed Navy
officials to determine the relationship of AirSpeed to the BRAC
recommendation. To assess the reliability of the data used to generate
estimates of costs and savings and the validity of underlying
assumptions used to generate cost and savings estimates, we reviewed
Navy regulations and instructions for reporting aviation maintenance
data and interviewed officials at Navy Air Systems Command, Navy
Aviation depots, Navy Aviation Intermediate Maintenance Departments,
and Naval Supply Systems Command knowledgeable about the data and the
assumptions underlying estimated costs and savings. Based on this, we
believe that the assumptions underlying estimated costs and savings are
generally valid, and that the data used were sufficiently reliable for
the purposes of this report.
To determine the challenges to successfully implement the fleet
readiness centers, we analyzed pertinent documents and reports and
interviewed officials responsible for developing the original proposal
and the business plan. We also interviewed Navy officials at the
Aircraft Intermediate Maintenance Departments at Whidbey Island,
Washington; North Island, California; and Mayport, Florida; and at
Naval Aviation Depots at North Island, California, and Jacksonville,
Florida. In addition, we also reviewed statutes related to continuing
congressional oversight of annual depot maintenance funding, related
reports, and court cases involving depot personnel.
We conducted our work from February 2006 to March 2007 in accordance
with generally accepted government auditing standards.
[End of section]
Appendix II: Fleet Readiness Centers Recommendation:
165. FLEET READINESS CENTERS (IND 19):
a. Realign Naval Air Station Oceana, VA, by disestablishing the
Aircraft Intermediate Maintenance Department Oceana, the Naval Air
Depot Cherry Point Detachment, and the Naval Air Depot Jacksonville
Detachment; establishing Fleet Readiness Center Mid Atlantic, Naval Air
Station Oceana, VA; and transferring all intermediate maintenance
workload and capacity to Fleet Readiness Center Mid Atlantic, Naval Air
Station Oceana, VA.
b. Realign Naval Air Station Patuxent River, MD, by disestablishing the
Aircraft Intermediate Maintenance Department at Naval Air Warfare
Center Aircraft Division; establishing Fleet Readiness Center Mid
Atlantic Site Patuxent River, Naval Air Station Patuxent River, MD; and
transferring all intermediate maintenance workload and capacity to
Fleet Readiness Center Mid Atlantic Site Patuxent River, Naval Air
Station Patuxent River, MD.
c. Realign Naval Air Station Norfolk, VA, by disestablishing the
Aircraft Intermediate Maintenance Department Norfolk VA, the Naval Air
Depot Jacksonville Detachment, and Naval Air Warfare Center Aircraft
Division Lakehurst Detachment; establishing Fleet Readiness Center Mid
Atlantic Site Norfolk, Naval Air Station Norfolk, VA; and transferring
all intermediate and depot maintenance workload and capacity to Fleet
Readiness Center Mid Atlantic Site Norfolk, Naval Air Station Norfolk,
VA.
d. Realign Naval Air Station Joint Reserve Base New Orleans, LA, by
disestablishing the Aircraft Intermediate Maintenance Department,
establishing Fleet Readiness Center Mid Atlantic Site New Orleans,
Naval Air Station Joint Reserve Base New Orleans, LA; and transfer all
intermediate maintenance workload and capacity to Fleet Readiness
Center Mid Atlantic Site New Orleans, Naval Air Station Joint Reserve
Base New Orleans, LA.
e. Realign Marine Corps Air Station Cherry Point, NC, as follows:
disestablish Naval Air Depot Cherry Point; establish Fleet Readiness
Center East, Marine Corps Air Station Cherry Point, NC; relocate depot
maintenance workload and capacity for Aircraft Avionics/Electronics
Components (approximately 39 K DLHs) [direct labor hours], Aircraft
Hydraulic Components (approximately 69 K DLHs), Aircraft Landing Gear
Components (approximately 8 K DLHs), Aircraft Other Components
(approximately 23 K DLHs), and Aircraft Structural Components
(approximately 126 K DLHs) to Fleet Readiness Center Mid Atlantic,
Naval Air Station Oceana, VA; relocate depot maintenance workload and
capacity for Aircraft Avionics/Electronics Components (approximately 11
K DLHs), Aircraft Hydraulic Components (approximately 19 K DLHs),
Aircraft Landing Gear Components (approximately 2 K DLHs), Aircraft
Structural Components (approximately 35 K DLHs), and Aircraft Other
Components (approximately 6 K DLHs) to Fleet Readiness Center Mid
Atlantic Site Norfolk, Naval Air Station Norfolk, VA; relocate depot
maintenance workload and capacity for Aircraft Avionics/Electronics
Components (approximately 6 K DLHs), Aircraft Hydraulic Components
(approximately 10 K DLHs), Aircraft Landing Gear Components
(approximately 1 K DLHs), Aircraft Other Components (approximately 3 K
DLHs), and Aircraft Structural Components (approximately 18 K DLHs) to
FleetReadiness Center Mid Atlantic Site Patuxent River, Naval Air
Station Patuxent River, MD; relocate depot maintenance workload and
capacity for Aircraft Avionics/Electronics Components (approximately 2
K DLHs), Aircraft Hydraulic Components (approximately 3 K DLHs),
Aircraft Landing Gear Components (approximately 0.4K DLHs), Aircraft
Other Components (approximately 1 K DLHs), and Aircraft Structural
Components (approximately 6 K DLHs) to FRC Mid Atlantic Site New
Orleans, Naval Air Station JRB New Orleans, LA; relocate depot
maintenance workload and capacity for Aircraft Avionics/Electronics
Components (approximately 9 K DLHs), Aircraft Hydraulic Components
(approximately 16 K DLHs), Aircraft Landing Gear Components
(approximately 2 K DLHs), Aircraft Other Components (approximately 6 K
DLHs) and Aircraft Structural Components (approximately 30 K DLHs) to
the Fleet Readiness Center East Site Beaufort, hereby established at
Marine Corps Air Station Beaufort, SC; relocate depot maintenance
workload and capacity for Aircraft Avionics/Electronics Components
(approximately 11 K DLHs), Aircraft Hydraulic Components (approximately
20 K DLHs), Aircraft Landing Gear Components (approximately 2 K DLHs),
Aircraft Other Components (approximately 6 K DLHs), Aircraft Structural
Components (approximately 36 K DLHs), Aircraft Rotary (approximately 1
K DLHs), Aircraft VSTOL (approximately 2 K DLHs), Aircraft Cargo/Tanker
(approximately 0.02K DLHs,), Aircraft Other (approximately 18 K DLHs),
Aircraft Structural Components (approximately 0.001K DLHs), Calibration
(approximately 0.15 K DLHs) and "Other" Commodity (approximately 0.3 K
DLHs) to Fleet Readiness Center East Site New River, hereby established
at Marine Corps Air Station New River, Camp Lejeune, NC; and transfer
all remaining depot maintenance workload and capacity to Fleet
Readiness Center East, Marine Corps Air Station Cherry Point, NC.
f. Realign Marine Corps Air Station Beaufort, SC, by disestablishing
Naval Air Depot Jacksonville Detachment Beaufort and transferring all
depot maintenance workload and capacity to Fleet Readiness Center East
Site Beaufort, Marine Corps Air Station Beaufort, SC.
g. Realign Naval Air Station Jacksonville, FL, as follows: disestablish
Naval Air Depot Jacksonville, Naval Air Depot Jacksonville Detachment
Jacksonville, and Aircraft Intermediate Maintenance Department
Jacksonville; establish Fleet Readiness Center Southeast, Naval Air
Station, Jacksonville, FL; relocate depot maintenance workload and
capacity for Aircraft Avionics/Electronics Components (approximately 8
K DLHs), Aircraft Hydraulic Components (approximately 6 K DLHs),
Aircraft Landing Gear Components (approximately 3 K DLHs), Aircraft
Other Components (approximately 27 K DLHs), and Aircraft Structural
Components (approximately 9 K DLHs) to Fleet Readiness Center Southeast
Site Mayport, hereby established at Naval Air Station, Mayport, FL;
transfer all remaining intermediate and depot maintenance workload and
capacity to Fleet Readiness Center Southeast, Naval Air Station
Jacksonville, FL.
h. Realign Naval Air Station Mayport, FL, by disestablishing Aircraft
Intermediate Maintenance Department, Naval Air Depot Jacksonville
Detachment Mayport, and Naval Air Warfare Center Aircraft Division
Lakehurst Voyage Repair Team Detachment Mayport and transferring all
intermediate maintenance workload and capacity to Fleet Readiness
Center Southeast Site Mayport, Naval Air Station Mayport, FL.
i. Realign Naval Air Station Lemoore, CA, by disestablishing Aircraft
Intermediate Maintenance Department Lemoore and Naval Air Depot North
Island Detachment; establishing Fleet Readiness Center West, Naval Air
Station Lemoore, CA; and transferring all intermediate and depot
maintenance workload and capacity to Fleet Readiness Center West, Naval
Air Station Lemoore, CA.
j. Realign Naval Air Station Fallon, NV, by disestablishing the
Aircraft Intermediate Maintenance Department Fallon and the Naval Air
Depot North Island Detachment Fallon; establishing Fleet Readiness
Center West Site Fallon, Naval Air Station Fallon, NV; and transferring
all intermediate and depot maintenance workload and capacity to Fleet
Readiness Center West Site Fallon, Naval Air Station Fallon, NV.
k. Realign Naval Air Warfare Center Weapons Division China Lake, CA, by
disestablishing the Aircraft Intermediate Maintenance Department and
relocating its maintenance workload and capacity for Aircraft
(approximately 3 K DLHs), Aircraft Components (approximately 45 K
DLHs), Fabrication & Manufacturing (approximately 6 K DLHs) and Support
Equipment (approximately 16 K DLHs) to Fleet Readiness Center West,
Naval Air Station Lemoore, CA.
l. Realign Naval Air Station Joint Reserve Base Fort Worth, TX, by
disestablishing the Aircraft Intermediate Maintenance Department,
establishing Fleet Readiness Center West Site Fort Worth, Naval Air
Station Fort Worth, TX, and transferring all intermediate maintenance
workload and capacity to Fleet Readiness Center West Site Fort Worth,
Naval Air Station Joint Reserve Base Fort Worth, TX.
m. Realign Naval Air Station Whidbey Island, WA, by disestablishing the
Aircraft Intermediate Maintenance Department, establishing Fleet
Readiness Center Northwest, Naval Air Station Whidbey Island, WA, and
transferring all intermediate maintenance workload and capacity to
Fleet Readiness Center Northwest, Naval Air Station Whidbey Island, WA.
n.[Footnote 24] (Deleted):
o. Realign Naval Air Station North Island, Naval Base Coronado, CA, as
follows: disestablish Naval Air Depot North Island, COMSEACONWINGPAC
(AIMD), and NADEP North Island Detachment North Island; establish Fleet
Readiness Center Southwest, Naval Air Station North Island, Naval Base
Coronado, CA; relocate depot maintenance workload and capacity for
aircraft Avionics/Electronics Components (approximately 6 K DLHs),
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft
Landing Gear Components (approximately 3 K DLHs), aircraft Other
Components (approximately 13 K DLHs), and Aircraft Structural
Components (approximately 4 K DLHs) from Naval Air Depot North Island
to Fleet Readiness Center Southwest Site Point Mugu, hereby established
at Naval Air Station Point Mugu, Naval Base Ventura, CA; relocate depot
maintenance workload and capacity for Aircraft avionics/Electronics
Components (approximately 26 K DLHs), Aircraft Hydraulic Component
(approximately 8 K DLHs), Aircraft Landing Gear Components
(approximately 13 K DLHs), Aircraft Other Components (approximately 55
K DLHs), Aircraft Structural Components (approximately 16 K DLHs) from
Naval Air Depot North Island to Fleet Readiness Center Southwest Site
Miramar, hereby established at Marine Corps Air Station Miramar, CA;
relocate depot maintenance workload and capacity for Aircraft Avionics/
Electronics Components (approximately 8 K DLHs), Aircraft Hydraulic
Components (approximately 2 K DLHs), Aircraft Landing Gear Components
(approximately 4 K DLHs), Aircraft Other Components (approximately 17 K
DLHs), and Aircraft Structural Components (approximately 5 K DLHs) from
Naval Air Depot North Island to Fleet Readiness Center Southwest Site
Pendleton, hereby established at Marine Corps Air Station Camp
Pendleton, CA; relocate depot maintenance workload and capacity for
Aircraft Avionics/Electronics Components (approximately 6 K DLHs),
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft
Landing Gear Components (approximately 3 K DLHs), Aircraft Other
Components (approximately 12 K DLHs), Aircraft Structural Components
(approximately 3 K DLHs) from Naval Air Depot North Island to Fleet
Readiness Southwest Site Yuma, hereby established at Marine Corps Air
Station Yuma, AZ; relocate depot maintenance workload and capacity for
Aircraft Avionics/Electronics Components (approximately 6 K DLHs),
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft
Landing Gear Components (approximately 3 K DLHs), Aircraft Other
Components (approximately 12 K DLHs), and Aircraft Structural
Components (approximately 3 K DLHs) from Naval Air Depot North Island
to Fleet Readiness Center West Site Fort Worth, Fort Worth TX; relocate
depot maintenance workload and capacity for Aircraft Avionics/
Electronics Components (approximately 25 K DLHs), Aircraft Hydraulic
Components (approximately 8 K DLHs), Aircraft Landing Gear Components
(approximately 13 K DLHs), Aircraft Other Components (approximately 53
K DLHs), and Aircraft Structural Components (approximately 15 K DLHs),
from Naval Air Depot North Island to Fleet Readiness Center Northwest,
Naval Air Station Whidbey Island, WA; and transfer all remaining
intermediate and depot maintenance workload and capacity to Fleet
Readiness Center Southwest, Naval Air Station North Island, Naval Base
Coronado, CA.
p. Realign Naval Air Station Point Mugu, Naval Base Ventura, CA, by
disestablishing the Aircraft Intermediate Maintenance Department and
transferring all intermediate maintenance workload and capacity to
Fleet Readiness Center Southwest Site Point Mugu, Naval Base Ventura,
CA.
q. Realign Marine Corps Air Station Miramar, CA, by transferring depot
maintenance workload and capacity for Aircraft Other (approximately 28
K DLHs) and Aircraft Fighter/Attack (approximately 39 K DLHs) and
intermediate maintenance workload and capacity for Aircraft Components,
Aircraft Engines, Fabrication & Manufacturing and Support Equipment
from Marine Aviation Logistics Squadron (MALS)-11 and 16 to Fleet
Readiness Center Southwest Site Miramar, Marine Corps Air Station
Miramar, CA.
r. Realign Marine Corps Air Station Camp Pendleton, CA, by transferring
depot maintenance workload and capacity for Aircraft Other
(approximately 22 K DLHs) and Aircraft Rotary (approximately 102 K
DLHs) and intermediate maintenance workload and capacity for Aircraft
Components, Aircraft Engines, Fabrication & Manufacturing and Support
Equipment from MALS-39 to Fleet Readiness Center Southwest Site Camp
Pendleton, Marine Corps Air Station Camp Pendleton, CA.
s. Realign Marine Corps Air Station Yuma, AZ, by transferring depot
maintenance workload and capacity for Aircraft Fighter/Attack, Aircraft
Other and Aircraft Rotary and intermediate maintenance workload and
capacity for Aircraft Components, Aircraft Engines, Communication/
Electronics Equipment, Ordnance Weapons & Missiles, Software and
Support Equipment from MALS-13 to Fleet Readiness Center Southwest Site
Yuma, Marine Corps Air Station Yuma, AZ.
[End of section]
Appendix III: Comments from the Department of Defense:
[See PDF for image]:
[End of figure]
Acquisition, Technology And Logistics:
Office Of The Under Secretary Of Defense:
3000 Defense Pentagon:
Washington, Dc 20301-3000:
JUN 20 2007:
Mr. Brian J. Lepore:
Director, Defense Capabilities and Management:
U.S. Government Accountability Office:
441 G Street, N.W. Washington, DC 20548:
Dear Mr. Lepore,
This letter is the Department of Defense (DoD) response to the GAO
draft report, GAO 07-304, "MILITARY BASE CLOSURES: Projected Savings
from Fleet Readiness Centers Are Likely Overstated and Actions Needed
to Track Actual Savings and Overcome Certain Challenges" dated May 16,
2007, (GAO Code 350804).
The Department concurs with both of the GAO's recommendations in the
draft report and GAO's recognition that projected savings remain
substantial, however, it is important to note that the issue regarding
the treatment of military personnel savings represents a longstanding
difference of opinion between DoD and GAO. The Department considers
military personnel reductions attributable to a BRAC recommendation as
savings that are just as real as savings generated through end-strength
reductions. While the Department may not reduce overall end-strength,
the reductions in military personnel for each recommendation at a
specific location are real. As is the case of monetary savings,
personnel reductions allow the Department to re-apply these military
personnel to support new capabilities and to improve operational
efficiencies.
The Department's comments regarding the draft report are outlined in
the enclosure. The Department appreciates the work performed by the GAO
and appreciates the opportunity to comment on the draft report.
Sincerely,
Signed by:
Philip W. Grone:
Deputy Under Secretary of Defense:
(Installations and Environment):
[See PDF for image]
[End of figure]
Enclosure: As stated:
Gao Draft Report - Dated May 16, 2007:
Gao Code 350804/GAO-07-304:
"Military Base Closures: Projected Savings from Fleet Readiness Centers
Are Likely Overstated and Actions Needed to Track Actual Savings and
Overcome Certain Challenges":
Department Of Defense Comments:
To The Recommendations:
Recommendation 1: The GAO recommends that the Secretary of Defense
direct the Secretary of the Navy to update the business plan for the
fleet readiness centers (1) to reflect only savings that are directly
related to implementing the recommendation, and (2) to update projected
one-time savings when data is available.
Dod Response: DoD concurs.
Recommendation 2: The GAO recommends that the Secretary of Defense
direct the Secretary of the Navy to monitor implementation of the
recommendation to determine the extent that savings already taken from
the Navy budget are actually achieved.
Dod Response: DoD concurs.
Enclosure pg. 1:
[End of section]
Appendix IV: GAO Contacts and Staff Acknowledgments:
GAO Contact:
Brian J. Lepore, (202) 512-4523 or leporeb@gao.gov:
Acknowledgments:
In addition to the person named above, Michael Kennedy, Assistant
Director; Avrum I. Ashery; Pat L Bohan; Grace A. Coleman; Julia C.
Matta; Charles W. Perdue; Maria-Alaina I. Rambus; and John E. Trubey
also made major contributions to this report.
FOOTNOTES
[1] The BRAC legislation (Pub. L. No. 101-510, Title XXIX, as amended
by Pub. L. No. 107-107, Title XXX) provided for an independent
Commission to review the Secretary of Defense's realignment and closure
recommendations, and present its findings and conclusions on the
Secretary's recommendations, along with its own recommendations to the
President.
[2] Onetime savings are estimated savings to be realized during the
2006-2011 implementation period. Onetime savings are nonrecurring
savings that stop at the end of implementation in 2011.
[3] GAO, Military Bases: Analysis of DOD's 2005 Selection Process and
Recommendations for Base Closures and Realignments, GAO-05-785
(Washington, D.C.: July 1, 2005).
[4] 31 U.S.C. § 717.
[5] DOD did not accept the final BRAC Commission estimate because it
was based on actual versus authorized positions.
[6] Annual recurring savings are expected to occur annually after the
costs of implementing a BRAC action have been offset by the savings.
[7] The Navy and Marine Corps currently operate 20 aviation
intermediate maintenance departments including the Presidential
Helicopter support at Quantico, 11 Marine aviation logistics squadrons,
and three Naval Aviation Depot maintenance activities in the United
States.
[8] GAO-05-785.
[9] The $3.7 billion is the 20-year net present value of the projected
savings in fiscal year 2005 constant dollars.
[10] The Department of Defense has 6 years (2006-2011) to implement the
BRAC 2005 recommendations.
[11] Of the approximate $31 million difference, about $4 million is
inflation.
[12] GAO-05-785.
[13] The shore-based aviation consolidated allowance list inventory is
a consolidated list of components, repair parts, and consumable items
and depot-and field-level repairable items required to support planned
operational and maintenance missions at designated naval and Marine
Corps air stations.
[14] In fiscal year 2003, the inventory and supply of aircraft
components and replacement parts had a value of about $4.3 billion.
[15] DOD assumed the cumulative inflation over the 2006-2011 time
period was 15.37 percent. It ranged from 2.1 percent to 2.6 percent per
year.
[16] GAO-05-785.
[17] GAO, DOD's High-Risk Areas: Successful Business Transformation
Requires Sound Strategic Planning and Sustained Leadership, GAO-05-520T
(Washington, D.C.: Apr. 13, 2005).
[18] GAO, Depot Maintenance: Management Attention Required to Further
Improve Workload Allocation Data, GAO-02-95 (Washington, D.C.: Nov. 9,
2001) and GAO, Depot Maintenance: DOD's 50-50 Reporting Should Be
Streamlined, GAO-03-1023 (Washington, D.C.: Sept. 15, 2003).
[19] GAO-05-785.
[20] GAO, Human Capital: Key Principles for Effective Strategic
Workforce Planning, GAO-04-39 (Washington, D.C.: Dec. 11, 2003).
[21] GAO-04-39.
[22] GAO-04-39.
[23] GAO-04-39.
[24] By Motion 165-3A, the Commission struck paragraph "n", which read
"Realign Naval Support Activity Crane, IN, by relocating the depot
maintenance workload and capacity for ALQ-99 Electronic Warfare to
Fleet Readiness Center Northwest, Naval Air Station Whidbey Island, WA."
GAO's Mission:
The Government Accountability Office, the investigative arm of
Congress, exists to support Congress in meeting its constitutional
responsibilities and to help improve the performance and accountability
of the federal government for the American people. GAO examines the use
of public funds; evaluates federal programs and policies; and provides
analyses, recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's commitment to
good government is reflected in its core values of accountability,
integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains
abstracts and full-text files of current reports and testimony and an
expanding archive of older products. The Web site features a search
engine to help you locate documents using key words and phrases. You
can print these documents in their entirety, including charts and other
graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as "Today's Reports," on its
Web site daily. The list contains links to the full-text document
files. To have GAO e-mail this list to you every afternoon, go to
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order
GAO Products" heading.
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office
441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm
E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Public Affairs:
Jeff Nelligan, managing director,
NelliganJ@gao.gov
(202) 512-4800
U.S. Government Accountability Office,
441 G Street NW, Room 7149
Washington, D.C. 20548: