Defense Contract Management
DOD's Lack of Adherence to Key Contracting Principles on Iraq Oil Contract Put Government Interests at Risk
Gao ID: GAO-07-839 July 31, 2007
The Department of Defense's (DOD) U.S. Army Corps of Engineers (Corps) awarded the $2.5 billion Restore Iraqi Oil (RIO I) contract to Kellogg Brown & Root in March 2003 in an effort to reestablish Iraq's oil infrastructure. The contract was also used to ensure adequate fuel supplies inside Iraq. RIO I was a cost-plus-award-fee type contract that provided for payment of the contractor's costs, a fixed fee determined at inception of the contract, and a potential award fee. The Defense Contract Audit Agency (DCAA) reviewed the 10 RIO I task orders and questioned $221 million in contractor costs. We were asked to determine (1) how DOD addressed DCAA's RIO I audit findings and what factors contributed to DOD's decision and (2) the extent to which DOD paid award fees for RIO I and followed the planned process for making that decision. To accomplish this, we reviewed DOD and DCAA documents related to RIO I and interviewed Corps, DCAA, and other officials.
DOD considered DCAA's audit findings on the RIO I contract and performed additional analysis before deciding to pay the contractor nearly all of the $221 million in costs that DCAA questioned. DOD did, however, remove about $112 million of the questioned costs from the amount used to establish the contractor's fee pool, which resulted in an effective lowering of the fee received by the contractor by approximately $5.8 million. Lack of timely negotiations contributed significantly to DOD's decision on how to address the questioned costs--all 10 task orders were negotiated more than 180 days after the work commenced. As a result, the contractor had incurred almost all its costs at the time of negotiations, which influenced DOD's decision to pay nearly all of the questioned costs. The negotiation delays were in part caused by changing requirements, funding challenges, and inadequate contractor proposals. In our previous work, we have found that negotiation delays can increase risk to the government. Overall, DCAA considers $26 million of the costs questioned on the RIO I contract to be sustained, which DCAA defines as cost reductions attributable to its audit findings. We compared the sustention rates on DCAA's 11 RIO I contract audits to the sustention rates for 100 DCAA audits of other Iraq contract actions, and found that the sustention rates varied widely for both groups. DOD's Army Corps of Engineers paid $57 million in award fees on the RIO I contract, or 52 percent of the maximum possible, and on individual task orders the fee awarded ranged from 4 to 72 percent of the fee available. While the award fee plan required regular award fee boards during the life of the contract, DOD did not conduct a formal board until nearly all work on the contract was complete. As a result, DOD was not able to provide the contractor with formal award fee feedback while work was ongoing, which federal regulations state should be done in order to motivate a contractor to either improve poor performance or continue good performance. DOD officials told us the workload of RIO staff members and logistical difficulties stemming from the challenging conditions in Iraq hindered efforts to hold evaluation boards during the period of performance. DOD also was unable to give us enough documentation for a full assessment of its compliance with other parts of its plan--it did not, for example, provide the scores the award fee board assigned to the contractor on the individual award fee criteria, so we could not see if the award fee board had followed contract criteria and weighting in evaluating performance. We compared the percentage of award fees earned on the RIO I contract to the fees earned on a group of other selected Iraq reconstruction contracts and found that the percentage of award fees earned on RIO I fell within the lower range of fees earned on the other contracts.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-07-839, Defense Contract Management: DOD's Lack of Adherence to Key Contracting Principles on Iraq Oil Contract Put Government Interests at Risk
This is the accessible text file for GAO report number GAO-07-839
entitled 'Defense Contract Management: DOD's Lack of Adherence to Key
Contracting Principles on Iraq Oil Contract Put Government Interests at
Risk' which was released on August 9, 2007.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
United States Government Accountability Office:
GAO:
July 2007:
Defense Contract Management:
DOD's Lack of Adherence to Key Contracting Principles on Iraq Oil
Contract Put Government Interests at Risk:
GAO-07-839:
GAO Highlights:
Highlights of GAO-07-839, a report to congressional requesters
Why GAO Did This Study:
The Department of Defense‘s (DOD) U.S. Army Corps of Engineers (Corps)
awarded the $2.5 billion Restore Iraqi Oil (RIO I) contract to Kellogg
Brown & Root in March 2003 in an effort to reestablish Iraq‘s oil
infrastructure. The contract was also used to ensure adequate fuel
supplies inside Iraq. RIO I was a cost-plus-award-fee type contract
that provided for payment of the contractor‘s costs, a fixed fee
determined at inception of the contract, and a potential award fee. The
Defense Contract Audit Agency (DCAA) reviewed the 10 RIO I task orders
and questioned $221 million in contractor costs. We were asked to
determine (1) how DOD addressed DCAA‘s RIO I audit findings and what
factors contributed to DOD‘s decision and (2) the extent to which DOD
paid award fees for RIO I and followed the planned process for making
that decision. To accomplish this, we reviewed DOD and DCAA documents
related to RIO I and interviewed Corps, DCAA, and other officials.
What GAO Found:
DOD considered DCAA‘s audit findings on the RIO I contract and
performed additional analysis before deciding to pay the contractor
nearly all of the $221 million in costs that DCAA questioned. DOD did,
however, remove about $112 million of the questioned costs from the
amount used to establish the contractor‘s fee pool, which resulted in
an effective lowering of the fee received by the contractor by
approximately $5.8 million. Lack of timely negotiations contributed
significantly to DOD‘s decision on how to address the questioned
costs”all 10 task orders were negotiated more than 180 days after the
work commenced. As a result, the contractor had incurred almost all its
costs at the time of negotiations, which influenced DOD‘s decision to
pay nearly all of the questioned costs. The negotiation delays were in
part caused by changing requirements, funding challenges, and
inadequate contractor proposals. In our previous work, we have found
that negotiation delays can increase risk to the government. Overall,
DCAA considers $26 million of the costs questioned on the RIO I
contract to be sustained, which DCAA defines as cost reductions
attributable to its audit findings. We compared the sustention rates on
DCAA‘s 11 RIO I contract audits to the sustention rates for 100 DCAA
audits of other Iraq contract actions, and found that the sustention
rates varied widely for both groups.
DOD‘s Army Corps of Engineers paid $57 million in award fees on the RIO
I contract, or 52 percent of the maximum possible, and on individual
task orders the fee awarded ranged from 4 to 72 percent of the fee
available. While the award fee plan required regular award fee boards
during the life of the contract, DOD did not conduct a formal board
until nearly all work on the contract was complete. As a result, DOD
was not able to provide the contractor with formal award fee feedback
while work was ongoing, which federal regulations state should be done
in order to motivate a contractor to either improve poor performance or
continue good performance. DOD officials told us the workload of RIO
staff members and logistical difficulties stemming from the challenging
conditions in Iraq hindered efforts to hold evaluation boards during
the period of performance. DOD also was unable to give us enough
documentation for a full assessment of its compliance with other parts
of its plan”it did not, for example, provide the scores the award fee
board assigned to the contractor on the individual award fee criteria,
so we could not see if the award fee board had followed contract
criteria and weighting in evaluating performance. We compared the
percentage of award fees earned on the RIO I contract to the fees
earned on a group of other selected Iraq reconstruction contracts and
found that the percentage of award fees earned on RIO I fell within the
lower range of fees earned on the other contracts.
What GAO Recommends:
GAO recommends the Secretary of the Army, in contingency situations,
ensure that an analysis of the feasibility of following a rigorous
award fee process is conducted when using cost-plus-award-fee
contracts. In written comments, DOD agreed with the recommendation.
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-839].
To view the full product, including the scope and methodology, click on
the link above. For more information, contact John Hutton at (202) 512-
4841 or huttonj@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
Delayed Negotiations Shaped DOD's Decision to Pay the Contractor for
Nearly All of the Costs Questioned on the RIO I Contract:
DOD Paid About Half of the Maximum Possible Award Fee for the RIO I
Contract, but Did Not Fully Adhere to Key Steps in Its Award Fee Plan
for Providing Performance Feedback to the Contractor:
Conclusion:
Recommendation for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: Comments from the Department of Defense:
Tables:
Table 1: GAO's Analysis of the Resolution of DCAA's Questioned Costs:
Table 2: DCAA's Questioned Costs Sustained on the RIO I Contract
Audits:
Table 3: Award Fee Paid for RIO I Task Orders:
Figures:
Figure 1: Reasons for DCAA Questioned Costs:
Figure 2: Elapsed Days from Notice to Proceed to Definitization:
Figure 3: Comparison of Sustention Rates:
Figure 4: Percentage of Award Fee Earned on the RIO I Contract and on
11 Other Selected Iraq Reconstruction Contracts from January 2004 to
June 2006:
Abbreviations:
DCAA: Defense Contract Audit Agency:
DESC: Defense Energy Support Center:
DFARS: Defense Federal Acquisition Regulation Supplement:
DOD: Department of Defense:
DFI: Development Fund for Iraq:
FAR: Federal Acquisition Regulation:
RIO: Restore Iraqi Oil:
United States Government Accountability Office:
Washington, DC 20548:
July 31, 2007:
The Honorable Henry A. Waxman:
Chairman:
The Honorable Tom Davis:
Ranking Member:
Committee on Oversight and Government Reform:
House of Representatives:
The Honorable Daniel K. Akaka:
Chair:
Subcommittee on Oversight of Government Management, the Federal
Workforce, and the District of Columbia:
Committee on Homeland Security and Governmental Affairs:
United States Senate:
The United States, along with its coalition partners and various
international organizations and donors, has embarked on a significant
effort to rebuild Iraq. As of October 2006, the United States had
obligated about $29 billion for reconstruction and stabilization
efforts in Iraq. The United States has relied heavily on private sector
contractors to provide the goods and services needed to support
reconstruction efforts in Iraq. For example, to help reestablish Iraq's
oil infrastructure, in March 2003 the U.S. Army Corps of Engineers
(Corps) awarded the Restore Iraqi Oil (RIO I) contract to Kellogg Brown
& Root[Footnote 1]. The contract was also used to import fuels from
neighboring countries to avoid domestic fuel shortages in Iraq. Under
this contract, the Corps issued 10 task orders worth approximately $2.5
billion. The RIO I contract, like many other reconstruction and support
contracts, was a cost-plus-award-fee type contract. In general, these
contracts provide for payment of the contractor's allowable, allocable,
and reasonable costs; a fixed base fee amount determined at inception
of the contract; and a potential award fee sufficient to provide
motivation for excellence in contract performance. A cost-plus-award-
fee contract, like other cost reimbursement type contracts, increases
the risk to the government of incurring higher than expected costs, as
compared to some other contract types. To mitigate this risk, these
types of contracts require sufficient oversight.
The Defense Contract Audit Agency (DCAA) provides services that can
help the Department of Defense (DOD) ensure accountability for its
acquisitions. DCAA performs audits and provides financial advisory
services in connection with the negotiation, administration, and
settlement of contracts and subcontracts. For example, DCAA has audited
many Iraq contract proposals and contracts and has identified costs it
considers to be questioned. DCAA defines questioned costs as those
costs that are not acceptable for negotiating a fair and reasonable
contract price. Ultimately, the contracting officer has the final
decision about whether questioned costs should be paid, taking into
account DCAA's advice and other information. On the RIO I contract,
DCAA identified $221 million in questioned costs in its final audits of
the task order proposals under the contract.
Because of your interest in understanding the final agreement reached
between DOD and the contractor on the RIO I contract, we examined (1)
how DOD addressed DCAA's audit findings on the contract and what
factors contributed to DOD's decision of how to address these findings
and (2) the extent to which DOD paid award fees for the contract and
followed the planned process for making that decision.
To determine how DOD addressed DCAA's audit findings on the RIO I
contract and the factors that contributed to DOD's decision of how to
address those findings, we reviewed negotiation memorandums and DCAA
audit reports for each of the 10 RIO I task orders and other documents
related to the negotiation process and resolution of DCAA's findings.
We also interviewed Corps, DCAA, and other government officials as well
as contractor representatives. Additionally, to put DOD's decisions
into context, we compared the resolution of DCAA's questioned cost
findings on 100 audits of Iraq-related contract actions that were
resolved as of the end of fiscal year 2006 to the resolution of the
questioned cost findings on the RIO I task order audits. Because a
contracting officer has the discretion to determine whether or not to
pay questioned costs when reaching agreement with a contractor, our
review does not include a determination of whether the DOD contracting
officer should have approved payment for the questioned costs.
To determine the extent to which DOD paid award fees for the RIO I
contract and followed its planned process for making that decision, we
collected and reviewed key documents related to the award fee process,
including the award fee determining official's decision and the award
fee plan. We also interviewed Corps officials to develop an
understanding of the process and outcome for the award fees and
contractor representatives to obtain their perspective on award fees.
Additionally, to put the award fee for the RIO I contract into context,
we examined available award fee documentation for 11 large contracts
that DOD awarded in 2004 to carry out reconstruction activities in
Iraq. During the period we looked at, January 2004 through June 2006, a
total of 37 award fee evaluation periods were conducted for the 11
contracts. Because an award fee determination is a unilateral decision
made solely at the discretion of the government based upon judgmental
evaluations of individual contractor performance, our review does not
include a determination of whether DOD reached the appropriate award
fee decision for the RIO I contract. Appendix I provides details on our
scope and methodology. We conducted our work from October 2006 through
July 2007 in accordance with generally accepted government auditing
standards.
Results in Brief:
DOD considered DCAA's audit findings on the RIO I contract and
performed additional analysis before deciding to pay the contractor
nearly all of the $221 million in costs that DCAA questioned, a
decision influenced by the fact that negotiations of the task orders'
terms and conditions did not begin until most of the work was complete.
DOD also removed about $112 million of the questioned costs from the
amount used to establish the contractor's fee pool, which resulted in
an effective lowering of the fee received by the contractor by
approximately $5.8 million. Lack of timely negotiations was a major
contributing factor to DOD's decision on how to address the questioned
costs. Although the Defense Federal Acquisition Regulation Supplement
(DFARS) generally requires that contract actions be definitized within
180 days after issuance of the action, all 10 task orders were
negotiated more than 180 days after the work commenced. As a result,
the contractor had incurred nearly all costs at the time of
negotiations, and this fact influenced the DOD contracting officer's
decision to pay most of the questioned costs. According to various DOD
officials and contractor representatives, changing requirements,
funding challenges, and inadequate contractor proposals contributed to
the negotiation delays. These findings are consistent with our previous
work, where we found that factors such as changing requirements and
difficulties with funding were linked to delays in definitization, and
that these delays can increase risk to the government. Overall, DCAA
considers $26 million of the costs questioned on the RIO I contract to
be sustained, which DCAA defines as cost reductions directly
attributable to its audit findings. We compared the sustention rates on
DCAA's 11 RIO I contract audits to the sustention rates for 100 DCAA
audits of other Iraq contract actions, and found that the sustention
rates varied widely for both groups.
DOD's Army Corps of Engineers paid about $57 million in award fees, or
52 percent of the maximum possible award fees, on the RIO I contract,
but it did not adhere to some key steps in its planned award fee
process related to providing performance feedback to the contractor.
The award fee paid varied by task order, ranging from 4 percent to 72
percent of the possible award fee. DOD developed an award fee plan that
laid out the steps for making its award fee decision, but it did not
fully adhere to that plan. For example, the plan required award fee
evaluations on a regular basis during the period of performance, but
DOD did not conduct a formal evaluation until July 2004, subsequent to
the completion of nearly all work on the contract. DOD officials told
us the workload of RIO staff members and logistical difficulties
stemming from the challenging conditions in Iraq hindered efforts to
hold evaluation boards during the period of performance. By not
conducting such evaluations during the period of performance, DOD was
not able to provide the contractor with formal award fee feedback while
work was ongoing, which federal regulations state should be done in
order to motivate a contractor to either improve poor performance or
continue good performance.[Footnote 2] Additionally, DOD was not able
to provide us with sufficient documentation to enable us to fully
assess its adherence to other steps of its plan. For example, DOD did
not have the scores the award fee board assigned to the contractor on
the individual award fee criteria in coming to its award fee
recommendation. Without these scores, we were unable to determine
whether the award fee board had followed the criteria and weighting
laid out in the contract in reaching its recommendation. We compared
the percentage of award fees earned on the RIO I contract to fees
earned on a group of other selected Iraq reconstruction contracts and
found that the percentage of award fee earned on the RIO I contract
fell within the lower range of fees earned on other contracts.
To ensure that cost-plus-award-fee contracts provide the intended
benefits, we are recommending to the Secretary of the Army that the
department conduct an analysis of the administrative feasibility of
following a rigorous award fee process before awarding a cost-plus-
award-fee contract in contingency situations. In written comments, DOD
agreed with the recommendation. DOD's comments are included in appendix
II.
Background:
The United States, along with its coalition partners and various
international organizations and donors, has embarked on a significant
effort to rebuild Iraq. As of October 2006, the United States had
obligated about $29 billion for reconstruction and stabilization
efforts in Iraq. The United States has relied heavily on private sector
contractors to provide the goods and services needed to support the
reconstruction efforts in Iraq.
Congress has appropriated substantial amounts to support rebuilding
efforts such as restoring Iraq's oil and electric infrastructures,
assisting in developing a market-based economy, and improving the
country's health, education, and medical services. With regard to
Iraq's oil sector, U.S. support has included efforts to (1) restore
Iraq's oil infrastructure to sustainable prewar crude oil production
and export capacity, and (2) deliver and distribute refined fuels for
domestic consumption. Specific U.S. activities and projects for the
restoration of Iraq's oil production and export capacity include
repairing the Al-Fathah oil pipeline crossing, restoring several gas
and/or oil separation plants near Kirkuk and Basrah, and repairing
natural gas and liquefied petroleum gas plant facilities in southern
Iraq. U.S. activities also include the restoration of wells, pump
stations, compressor stations, export terminals, and refineries, and
providing electrical power to many of these oil facilities. In addition
to infrastructure restoration activities, from late May 2003 through
August 2004, the United States facilitated and oversaw the purchase,
delivery, and distribution of refined fuels throughout Iraq, primarily
funded using the Development Fund for Iraq (DFI).[Footnote 3] These
imports--used for cooking, heating, personal transportation, and
private power generation--were required to supplement domestic
production due to increased demand and Iraq's limited refining
capacity.
In early 2003, DOD assigned the Corps the responsibility of the oil
restoration activities known as Restore Iraqi Oil. In March 2003 the
Corps awarded a cost-plus-award-fee contract, referred to as the RIO I
contract, to support the oil restoration mission. Under this contract,
the Corps awarded 10 task orders to the contractor worth a total of
$2.5 billion. Two task orders related to oil restoration planning and
extinguishing oil fires; two task orders were for the construction and
repair of the oil infrastructure; one was for life support activities,
such as lodging and dining services; and five task orders were for the
importation, delivery, and distribution of refined fuels throughout
Iraq.
At the request of the Corps, DCAA audited the contractor's proposals
for the RIO I contract.[Footnote 4] DCAA performs many types of audits
for DOD, including audits of contractor proposals, audits of estimating
and accounting systems, and incurred cost audits. Generally, the
results of DCAA audits of contractor proposals are intended to assist
contracting officials in negotiating reasonable contract prices.
Typically, DCAA audits contractors' proposals and provides contracting
officials advice on the reasonableness of contractor costs prior to
negotiations. DCAA also conducts audits of cost-type contracts after
they are negotiated to ensure costs incurred on these contracts are
acceptable. Relying on cost information provided by the contractor and
assessing whether the costs comply with government regulations, DCAA
may identify certain costs as questioned. DCAA defines questioned costs
as costs considered to be not acceptable for negotiating a fair and
reasonable contract price. DCAA reports its findings to contracting
officers for consideration in negotiating fair and reasonable contract
prices.
DCAA audit reports represent one way DCAA can assist contracting
officials as they negotiate government contracts. Also, contracting
officials may invite DCAA to participate in contract negotiations to
explain audit findings and recommendations. DCAA's role is advisory,
and the contracting officer is responsible for ensuring that the
contractor's proposed price is fair and reasonable.[Footnote 5] While
DCAA audit recommendations are nonbinding, federal regulations specify
that when significant audit recommendations are not adopted, the
contracting officer should provide rationale that supports the
negotiation result in the price negotiation documentation.[Footnote 6]
In its final 11 audits of the 10 task orders, DCAA identified $221
million in questioned costs on the RIO I contract. In total, DCAA
issued 22 proposal audits of the RIO I contract because DCAA audited
multiple proposals for some of the task orders. The final 11 audits
included one audit of each task order and an audit of a contractor
claim on the life support task order.[Footnote 7] Nearly 80 percent of
the questioned costs related to the costs paid for fuel and fuel
delivery. For example, DCAA questioned $139 million of the costs the
contractor paid for fuel and fuel transportation in Kuwait based on a
comparison of the price paid by the contractor and the price paid by
the Defense Energy Support Center (DESC) when it took over the mission
for the contractor in April 2004. Figure 1 outlines the reasons for
DCAA's questioned costs on the RIO I contract.
Figure 1: Reasons for DCAA Questioned Costs:
[See PDF for image]
Source: GAO analysis of DOD data.
Note: Numbers do not add to 100 percent due to rounding.
[End of figure]
The RIO I contract provided for payment of a fixed fee of 2 percent of
the negotiated estimated contract cost plus an award fee amount of up
to 5 percent, based on the government's evaluation of the contractor's
performance. Award fee contracts allow an agency to adjust the amount
of fee paid based on contractor performance.[Footnote 8] The award fee
is intended to motivate excellence in contractor performance, and can
also serve as a tool to control program risk and cost. However, the
monitoring and evaluation of contractor performance necessary under an
award fee contract requires additional administrative effort and cost,
and federal regulations provide that the use of such a contract is
suitable when the expected benefits of an award fee contract are
sufficient to warrant this additional effort and cost.[Footnote 9]
In general, for award fee contracts, DOD personnel (usually members of
an award fee evaluation board) conduct periodic evaluations of the
contractor's performance against specified criteria in an award fee
plan and recommend the amount of fee to be paid. These evaluations are
informed by input provided by government personnel who directly observe
the contractor's performance. Typically, award fee contracts emphasize
multiple aspects of contractor performance, such as quality,
timeliness, technical ingenuity, and cost-effective management. Because
award fees are intended to motivate contractor performance in areas
that are susceptible to judgmental and qualitative measurement and
evaluation, these criteria and evaluations tend to be subjective. After
receiving the recommendation of the award fee evaluation board, a fee-
determining official makes the final decision on the amount of fee the
contractor will receive. In certain cases the fee-determining official
may also decide to move unearned award fee from one evaluation period
to a subsequent evaluation period or periods, thus providing the
contractor an additional opportunity to earn previously unearned fee--
a practice called rollover.[Footnote 10]
Delayed Negotiations Shaped DOD's Decision to Pay the Contractor for
Nearly All of the Costs Questioned on the RIO I Contract:
DOD considered DCAA's audit findings and conducted additional analysis
before deciding to pay the RIO I contractor nearly all of the $221
million in costs that DCAA questioned, and to remove $112 million from
the amount used to establish the contractor's fixed and award fees. The
reduction in the amount used to establish the fee pool resulted in an
effective reduction of the contractor's fee by about $5.8 million.
DOD's decision to pay most questioned costs was shaped by the fact that
negotiations did not begin until most of the work was complete and the
costs had already been incurred. The delay in negotiations was
influenced by factors such as changing requirements, funding
challenges, and problems with the contractor's business systems. DCAA
considers $26 million of the costs questioned on the RIO I contract to
be sustained, which DCAA defines as cost reductions directly
attributable to its questioned cost findings. We compared the
sustention rates on DCAA's 11 RIO I contract audits to the sustention
rates for 100 DCAA audits of other Iraq contract actions, and found
that the sustention rates varied widely for both groups.
DOD Decided to Pay the Contractor for Nearly All of the $221 Million in
DCAA Questioned Costs, but Removed $112 Million from the Amount Used to
Establish the Contractor's Fee on the RIO I Contract:
To address the $221 million in costs questioned by DCAA, DOD collected
additional information and conducted additional analysis. For example,
after DCAA issued its final audits, DOD collected additional
information related to the difference in costs paid by the contractor
and those paid by DESC for fuel and fuel delivery from Kuwait, as well
as price adjustments the contractor paid to the subcontractor for fuel
from Turkey, the two largest reasons for questioned costs. The DOD
contracting officer also convened a meeting with contractor
representatives, DCAA officials, and other Corps officials to discuss
the additional information. As a result of the additional information
and analysis presented in the meeting, the DOD contracting officer
asked DCAA to conduct financial analyses to quantify options--referred
to as financial positions--that he could use in developing the
government's objectives for negotiations with the contractor. The
financial positions differed from DCAA's final audit reports in some
areas, for example, reflecting a narrower gap between the costs paid by
the contractor and the costs paid by DESC for the fuel and fuel
delivery from Kuwait[Footnote 11]:
DOD decided to address the $221 million in questioned costs in the
following ways:
* Pay both the costs and fees. The DOD contracting officer decided to
pay the contractor costs and associated fees for nearly half of the
costs questioned by DCAA. In general, these costs reflected the
financial positions prepared for negotiations by DCAA after DOD
collected additional information about some of the questioned costs.
For example, although DCAA's final audits questioned the costs paid for
fuel from Turkey, the financial positions did not include reductions
for these costs. The contracting officer used the financial positions
as a basis for deciding to pay the contractor for the costs for fuel
from Turkey.
* Not pay the contractor costs or fees. For less than $10 million of
the questioned costs, DOD decided not to pay the contractor for its
costs and the associated fees. For example, the Corps decided not to
reimburse approximately $4 million the contractor spent on leasing
diesel trucks that were not used.
* Pay the costs but not the fees. For almost half of the questioned
costs, DOD decided to pay the contractor but removed those costs from
the amount used to calculate the contractor's fee. These costs were
composed primarily of the difference that remained between the prices
paid by the contractor and by DESC for fuel and fuel delivery from
Kuwait after the contracting officer took into account the financial
positions.
When asked about the reason for paying for questioned costs but
removing those same costs from the amount used to establish the
contractor's fee, the DOD contracting officer told us that this outcome
was a result of negotiations. He stated that while the contractor
probably did not do everything it could have to lower prices, it took
reasonable actions to do so. For example, Corps officials stated that
the contractor attempted to obtain lower prices for the fuel and fuel
delivery from Kuwait through competition on several occasions. Also,
the officials told us that DOD decided to pay for these questioned
costs because it felt that it would have been unlikely to prevail in an
attempt not to pay costs that had already been incurred by the
contractor. Specifically, Corps officials told us they believed that in
the event of litigation, they would have been ordered to pay the
contractor for incurred costs because, for example, the Corps
continually directed the contractor to perform work under the
contract.[Footnote 12] However, these officials told us they believed
there was adequate justification to negotiate the exclusion of some
questioned costs from fee eligibility.
The DOD contracting officer also believed there were several
limitations to the primary reason for DCAA's questioned costs--the
comparison of the price paid by the contractor for fuel and fuel
delivery from Kuwait to the price paid by DESC, which took over the
fuel importation mission in 2004. Specifically, the contracting officer
attributed the contractor's higher price to factors such as the Kuwaiti
subcontractor's perception of the risk of working in Iraq, short-term
subcontracts for the fuel and fuel delivery because of the incremental
funding provided, and differences in overhead costs. DESC officials
also told us there were several factors that limited the usefulness of
the comparison between the prices paid by DESC and the prices paid by
the contractor for fuel and fuel delivery from Kuwait, such as the fact
that DESC could commit to longer contracts with the Kuwaiti
subcontractor and the fact that by contracting with the same
subcontractor, DESC could use the fuel transportation infrastructure
established under the prior contract (i.e., the start-up costs faced by
DESC were lower).
In total, $112 million of the questioned costs were removed from the
amount used to establish the contractor's fee pool. The contractor's
fixed and award fees were calculated as a percentage of the costs
included in the fee pool. Consequently, removing $112 million from the
amount used to establish the fee pool resulted in an effective lowering
of the fees the contractor received by about $5.8 million (see table 1
for details).[Footnote 13]
Table 1: GAO's Analysis of the Resolution of DCAA's Questioned Costs:
Dollars in thousands.
Task order: 1;
Purpose: Pre-positioning and training;
Primary reason for questioned costs: Differences between proposed and
actual costs;
DCAA questioned costs: $904;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: - $904;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -$38.
Task order: 2;
Purpose: Quick fix design;
Primary reason for questioned costs: Differences between proposed and
actual costs;
DCAA questioned costs: 200;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: - 197;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -11.
Task order: 3;
Purpose: Infrastructure repair and restoration;
Primary reason for questioned costs: Costs not allocable to task order;
DCAA questioned costs: 11,698;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -4,830;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -184.
Task order: 4;
Purpose: Life support;
Primary reason for questioned costs: Indirect costs due to rate and
base differences;
DCAA questioned costs: 86;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: 1,745[C];
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: 66[C].
Task order: 4;
Purpose: Equitable adjustment claim - life support;
Primary reason for questioned costs: Indirect costs due to rate and
base differences;
DCAA questioned costs: 39;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -39;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: N/A[D].
Task order: 5;
Purpose: Fuel import and distribution;
Primary reason for questioned costs: Kuwait and Turkey fuel and fuel
delivery charges;
DCAA questioned costs: 84,446;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -45,129;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -2,437.
Task order: 6;
Purpose: Infrastructure repair and restoration;
Primary reason for questioned costs: Timing of obtaining contracting
officer consent;
DCAA questioned costs: 32,078;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -5,289;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]:
-116.
Task order: 7;
Purpose: Fuel import and distribution;
Primary reason for questioned costs: Kuwait and Turkey fuel and fuel
delivery charges;
DCAA questioned costs: 35,681;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -16,598;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -896.
Task order: 8;
Purpose: Fuel import and distribution;
Primary reason for questioned costs: Kuwait and Turkey fuel and fuel
delivery charges;
DCAA questioned costs: 22,781;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -14,562;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -786.
Task order: 9;
Purpose: Fuel import and distribution;
Primary reason for questioned costs: Kuwait and Turkey fuel and fuel
delivery charges;
DCAA questioned costs: 19,903;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -15,578;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -841.
Task order: 10;
Purpose: Fuel import and distribution;
Primary reason for questioned costs: Kuwait and Turkey fuel and fuel
delivery charges;
DCAA questioned costs: 13,603;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -10,782;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -582.
Total;
Purpose: [Empty];
Primary reason for questioned costs: [Empty];
DCAA questioned costs: $221,418;
Changes resulting from DCAA's questioned costs: Adjustments to the
amount used to establish the fee pool[A]: -$112,163;
Changes resulting from DCAA's questioned costs: Effective fee
adjustments resulting from changes to the amount used to establish the
fee pool[B]: -$5,826.
Source: GAO analysis of DOD data.
[A] Numbers in this column reflect our analysis of cost adjustments
made to the amount used to establish the fee pool as result of DCAA's
questioned costs. At negotiations, DOD also adjusted other contract
costs not resulting from DCAA's questioned costs, which are not
reflected in this table.
[B] Numbers in this column reflect our analysis of what would have
happened if dod had applied the fixed and award fee percentages earned
for each of the task orders to the adjustments to the amount used to
establish the fee pool resulting from dcaa's questioned costs.
[C] Certain costs were questioned by DCAA based on the task order to
which they were allocated. The increase to the amount used to establish
the fee pool for task order 4 reflects allocation adjustments made
based on DCAA's findings associated with task order 3.
[D] Because the equitable adjustment claim exceeded the not-to-exceed
amount for task order 4, the contracting officer decided that no fixed
or award fees would be paid on the claim.
[End of table]
DCAA officials said they believed the DOD contracting officer followed
the standard process for addressing questioned costs. For example, the
Director of DCAA testified before Congress that the process worked as
it is defined, and that in making its decision of how to address the
costs, the Corps "rightly considered other evidence other than the
audit reports and considered extenuating circumstances that might have
affected the contractor's actions."[Footnote 14] When asked if he was
satisfied with the resolution of the questioned costs, a DCAA official
involved in the process told us he thought the DOD contracting officer
did the best job he could, given the circumstances.
Delays in Negotiations Influenced the Contracting Officer's Decision to
Pay Questioned Costs:
All 10 RIO I task orders were negotiated more than 180 days after the
work commenced, and all were negotiated after the work had been
completed. The RIO I task orders were considered undefinitized
contracting actions because DOD and the contractor had not reached
agreement on the terms, specifications, and price of the task orders
before performance began. Undefinitized contract actions are used when
government interests demand that the contractor be given a binding
commitment so that work can begin immediately, and negotiating a
definitive contract is not possible in time to meet the requirement.
DOD requires that contract actions be definitized within 180 days after
issuance of the action or when the amount of funds obligated under the
action is over 50 percent of the not-to-exceed price, whichever occurs
first. The head of an agency may waive these limitations in certain
circumstances that likely would have applied for this contract,
including for a contingency operation, but Corps officials told us that
waivers were not requested for these task orders. Figure 2 shows the
time it took for DOD and the contractor to reach agreement on the terms
and conditions for the task orders. Because of the delays in
negotiations, virtually all of the costs had been incurred by the
contractor at the time of negotiations.
Figure 2: Elapsed Days from Notice to Proceed to Definitization:
[See PDF for image]
Source: GAO analysis of DOD data.
[End of figure]
The contracting officer determined that the questioned costs he decided
to pay were reasonable and in accordance with the FAR, and his decision
to pay nearly all of the questioned costs was influenced by (1) the
fact that nearly all of the costs had been incurred at the time of
negotiations and (2) his belief that payment of incurred costs was
required, absent unusual circumstances.[Footnote 15] The contracting
officer stated in final negotiation documentation that unusual
circumstances did not exist for most of the questioned costs. For
example, the DOD contracting officer indicated that because DCAA chose
not to suspend or disallow the funds, which DCAA can do by issuing a
Form 1, unusual circumstances did not exist.[Footnote 16]
Changing Requirements, Funding Challenges, and Inadequate Contractor
Proposals Contribute to Negotiation Delays and Increase Risk to the
Government:
Several factors contributed to the delay in negotiations, including
DOD's changing requirements, DOD's funding challenges, and inadequacies
in several of the contractor's business systems. Based on contract
documentation as well as interviews with DOD officials and contractor
representatives, these factors made it difficult for the contractor to
submit proposals in a timely fashion. Without a qualifying contractor
proposal, the government and the contractor are not able to reach
agreement on the terms and conditions of a task order.[Footnote 17] For
many of the task orders, the contractor did not submit qualifying
proposals until late in the period of performance or after the work had
been completed. For example, for 6 of the 10 task orders, the
contractor did not submit a qualifying proposal that was audited by
DCAA until after the period of performance was complete.
Corps officials told us that changing requirements made it difficult
for the contractor to submit a proposal. In particular, the
requirements for the fuel mission were not well defined and changed
over time, particularly in terms of the quantity of fuel needed and the
period of performance for the work. According to Corps officials, the
fuel mission was initially envisioned as a 21-day requirement, but
ultimately extended into many months. The extension of the requirements
is reflected in modifications to task order 5, the initial fuel mission
task order, where the period of performance was extended. Additionally,
numerous correspondences between DOD officials demonstrate the
uncertainty as to how much fuel was required and the time frame during
which fuel importation would be needed. For example, one correspondence
indicates that as of April 21, 2003, there was no immediate need for
the importation of fuel products because Iraq was able to provide
sufficient refined products to satisfy the domestic need, and one DOD
official considered it unlikely that the need would arise.[Footnote 18]
Less than 2 weeks later, on May 2, 2003, DOD correspondence indicates
that fuel shortages were anticipated, and DOD officials began
preparations to execute the fuel importation mission. At that time,
officials anticipated the need for 10-to 30-day supplies of fuel, not a
mission that would expand into many months. In addition, the statements
of work for the fuel mission did not outline the quantities needed to
fulfill the mission. The quantities of fuel required changed numerous
times. For example, between July 16, 2003, and August 3, 2003, the
Corps issued four separate letters to the contractor, each one
increasing the quantities of fuel required to fulfill the mission.
Overall, through numerous modifications, the Corps increased the
funding on task order 5 from $24 million to $871 million, a value more
than 36 times greater than the initial allocation.
The Corps also experienced challenges in establishing and maintaining a
consistent, reliable, and sufficient source of funding for the RIO I
contract, which exacerbated the problem of fully defining the
requirements. The RIO I task orders were funded using several sources,
including the Army's Operation and Maintenance Appropriation, Iraqi
vested assets, and the Development Fund for Iraq.[Footnote 19] For the
fuel mission, a high-level Corps official involved in the funding
aspect of the contract told us that the Corps had a difficult time
finding enough funding to support the mission, a fact that contributed
to short-term requirements. For example, this official told us that the
Corps received funding on a short-term basis rather than the longer-
term funding it requested, which affected the quantity of fuel the
Corps could direct the contractor to purchase. Additionally, to support
the fuel mission when funding was tight, the Corps began using funds
from the infrastructure repair and restoration task orders to fund the
fuel mission task orders, resulting in the delay of work the Corps
believed was critical to the repair of the oil infrastructure.
DOD officials and contractor representatives also told us that the
contractor's business systems were not fully prepared to handle the
growth in work the company experienced as a result of the war in Iraq,
and this contributed to the delays in proposal submission. From 2002 to
2004, the contractor's revenues grew from $5.7 billion to $11.9
billion. Subsequent to the issuance of the RIO I contract, and after
the war in Iraq began, DCAA identified deficiencies in several of the
contractor's business systems. For example, DCAA considered the
contractor's estimating system--a system important for proposal
development--adequate prior to the issuance of the RIO I contract.
However, subsequent to the issuance of the RIO I contract, DCAA issued
an audit that found the contractor's estimating system to be inadequate
for providing verifiable, supportable, and documented cost estimates
that are acceptable for negotiating a fair and reasonable
price.[Footnote 20]
We have shown through our previous work the link between delays in
definitization and challenges with requirements, funding, and proposal
submission. For example, in a review of 77 undefinitized contract
actions issued by various DOD agencies, we found that contracting
officers cited timeliness of a qualifying proposal, changing or complex
requirements, and changes in funding availability as three of the top
four reasons for delays in definitization.[Footnote 21] In a previous
review of Iraq reconstruction contracts, agency officials told us that
delays in reaching agreement on the terms and conditions of a contract
resulted from the growth in requirements and from concerns over the
adequacy of contractor proposals.[Footnote 22]
Delays in definitization can increase the risk to the government
because when contracts remain undefinitized, the government bears most
of the risk. For example, in a prior review of how DOD addressed DCAA's
audit findings on 18 audits of Iraq contract actions, we found that DOD
contracting officials were less likely to remove questioned costs from
a contract proposal if the contractor had incurred these costs before
reaching agreement on the work's scope and price.[Footnote 23] In a
previous review of Iraq reconstruction contracts, as well as a review
of DOD's logistics support contracts, we found that delays in
definitizing contract actions can increase the risk to the government
by reducing cost control incentives, particularly for cost
reimbursement type contracts like the RIO I contract.[Footnote 24]
DCAA Attributes $26 Million in Cost Reductions on the RIO I Contract to
Its Audit Findings:
In total, DCAA considers $26 million of the costs questioned on the RIO
I contract to be sustained. DCAA defines questioned costs sustained as
the negotiated cost reductions directly attributable to questioned cost
findings reported by the DCAA auditor. DCAA's calculation of questioned
costs sustained includes costs DOD decided not to pay to the contractor
and other types of cost reductions. Specifically, the $26 million of
questioned costs sustained includes (1) $9 million composed primarily
of costs DOD decided not to pay to the contractor and including some
costs DOD decided to pay but moved from one task order to another
because of improper allocation[Footnote 25] and (2) $17 million in
costs removed from the contractor's final proposals but questioned by
DCAA in prior audits of previous contractor proposals. For example, in
an early version of a proposal for one of the fuel mission task orders,
the contractor proposed demobilization costs that DCAA questioned. The
contractor removed these costs in a subsequent proposal, and DCAA
considered the removal of these costs attributable to its audit
findings, and therefore counted that amount as sustained. For purposes
of calculating a sustention rate, which is a calculation of questioned
costs sustained divided by questioned costs, in its internal management
system DCAA increased its questioned costs on the final audits from
$221 million to $237 million to reflect the $17 million sustained from
prior audits.[Footnote 26]
Table 2 shows the questioned costs sustained and the sustention rate
for each of the audits of the RIO I contract. The sustention rates
ranged from 0 to 20 percent for the fuel mission task orders, which
represented a large portion of the questioned costs. As discussed
earlier in the report, the DOD contracting officer collected additional
information and conducted additional analysis to address some of these
questioned costs. Additionally, he identified limitations to the
comparison between the prices paid by the contractor and DESC used by
DCAA to question some of the fuel costs, such as differences in the
length of contract terms for purchase of fuel and fuel delivery from
Kuwait, and referred to these limitations in his rationale for his
decision on these costs.
Table 2: DCAA's Questioned Costs Sustained on the RIO I Contract
Audits:
Dollars in thousands.
1;
Purpose: Pre-positioning and training;
Primary questioned costs reason: Differences between proposed and
actual costs;
Questioned costs based on DCAA's internal management system[A]: $904;
Questioned costs sustained: $904; Sustention rate by audit report:
100%.
2;
Purpose: Quick fix design;
Primary questioned costs reason: Differences between proposed and
actual costs;
Questioned costs based on DCAA's internal management system[A]: 200;
Questioned costs sustained: 197;
Sustention rate by audit report: 99%.
3;
Purpose: Infrastructure repair and restoration;
Primary questioned costs reason: Costs not allocable to task order;
Questioned costs based on DCAA's internal management system[A]: 20,290;
Questioned costs sustained: 12,555;
Sustention rate by audit report: 62%.
4;
Purpose: Life support;
Primary questioned costs reason: Indirect costs due to rate and base
differences;
Questioned costs based on DCAA's internal management system[A]: 86;
Questioned costs sustained: 0;
Sustention rate by audit report: 0%.
4;
Purpose: Equitable adjustment claim - life support;
Primary questioned costs reason: Indirect costs due to rate and base
differences;
Questioned costs based on DCAA's internal management system[A]: 39;
Questioned costs sustained: 39;
Sustention rate by audit report: 100%.
5;
Purpose: Fuel import and distribution;
Primary questioned costs reason: Kuwait and Turkey fuel and fuel
delivery charges;
Questioned costs based on DCAA's internal management system[A]: 84,446;
Questioned costs sustained: 0;
Sustention rate by audit report: 0%.
6;
Purpose: Infrastructure repair and restoration;
Primary questioned costs reason: Timing of obtaining contracting
officer consent;
Questioned costs based on DCAA's internal management system[A]: 32,194;
Questioned costs sustained: 0;
Sustention rate by audit report: 0%.
7;
Purpose: Fuel import and distribution;
Primary questioned costs reason: Kuwait and Turkey fuel and fuel
delivery charges;
Questioned costs based on DCAA's internal management system[A]: 35,681;
Questioned costs sustained: 0;
Sustention rate by audit report: 0%.
8;
Purpose: Fuel import and distribution;
Primary questioned costs reason: Kuwait and Turkey fuel and fuel
delivery charges;
Questioned costs based on DCAA's internal management system[A]: 27,423;
Questioned costs sustained: 5,509;
Sustention rate by audit report: 20%.
9;
Purpose: Fuel import and distribution;
Primary questioned costs reason: Kuwait and Turkey fuel and fuel
delivery charges;
Questioned costs based on DCAA's internal management system[A]: 22,552;
Questioned costs sustained: 4,618;
Sustention rate by audit report: 20%.
10;
Purpose: Fuel import and distribution;
Primary questioned costs reason: Kuwait and Turkey fuel and fuel
delivery charges;
Questioned costs based on DCAA's internal management system[A]: 13,603;
Questioned costs sustained: 2,336;
Sustention rate by audit report: 17%.
Contract total;
Purpose: [Empty];
Primary questioned costs reason: [Empty];
Questioned costs based on DCAA's internal management system[A]:
$237,418;
Questioned costs sustained: $26,158; Sustention rate by audit report:
11%.
Source: GAO analysis of DOD data.
[A] Data in this column include costs questioned in the final audits
and costs questioned in prior audits that DCAA considers sustained.
[End of table]
The Sustention Rates on the DCAA Audits of the RIO I Contract and the
Sustention Rates on DCAA Audits of Other Iraq Contract Actions Both
Varied Widely:
We compared the sustention rates for the 11 RIO I audit reports to the
sustention rates for 100 DCAA audits of other Iraq contract actions,
and found a similar pattern in the distribution and range of sustention
rates for both groups.[Footnote 27] Specifically, as shown in figure 3,
the sustention rates for both groups of audit reports varied widely.
DCAA officials told us that it is not unusual to have a sustention rate
of 0 percent or of 100 percent on an individual audit, and these were
common values in the two groups we looked at.
Figure 3: Comparison of Sustention Rates:
[See PDF for image]
Source: GAO analysis of DOD data.
Note: While this analysis provides a basis for context, the
circumstances surrounding each of the contracts or task orders audited
are unique. Consequently, sustention rates between individual audit
reports may not be directly comparable.
[End of figure]
DCAA officials told us that they do not expect every questioned cost to
be sustained, because reasonable people can disagree about how some of
these costs should be resolved. Additionally, as discussed earlier,
contracting officers may consider other information provided subsequent
to DCAA's issued audit as part of the process of resolving DCAA audit
findings.
DOD Paid About Half of the Maximum Possible Award Fee for the RIO I
Contract, but Did Not Fully Adhere to Key Steps in Its Award Fee Plan
for Providing Performance Feedback to the Contractor:
DOD paid approximately $57 million in award fees, or 52 percent of the
maximum possible award fee, for the RIO I contract. However, DOD missed
potential opportunities to motivate contractor performance by not
following steps outlined in its award fee plan to provide performance
feedback to the contractor. Further, DOD was unable to provide
sufficient documentation to enable us to fully evaluate its adherence
to its award fee plan. In comparing the RIO I award fee to award fees
earned on other selected Iraq reconstruction contracts, we found that
the percentage of award fee earned on the RIO I contract fell within
the lower range of fees earned on these other contracts.
DOD Paid Approximately $57 Million in Award Fees for the RIO I
Contract:
The overall award fee paid to the contractor on the RIO I contract
totaled about $57 million, just over half of the maximum possible award
fee. The contract provided for a fixed fee of 2 percent of the
negotiated estimated contract cost and an award fee of up to an
additional 5 percent that could be earned based on the government's
evaluation of the contractor's performance in areas including technical
and cost performance and business management. The possible 5 percent
award fee was based on a negotiated estimated contract cost of about
$2.2 billion, translating into a maximum award fee of about $109
million.[Footnote 28] The award fee decision states that, overall,
while the quality of the contractor's work was generally rated highly,
the contractor did not do as well in the areas of adherence to schedule
and business management. As shown in table 3, the award fee varied by
task order, ranging from 4 percent to 72 percent of the possible award
fee.
Table 3: Award Fee Paid for RIO I Task Orders:
Dollars in thousands.
1;
Purpose: Pre-positioning and training;
Award fee possible: $399;
Award fee paid: $175;
Percentage of possible award fee paid: 44.
2;
Purpose: Quick fix design;
Award fee possible: 54;
Award fee paid: 39;
Percentage of possible award fee paid: 72.
3;
Purpose: Infrastructure repair and restoration;
Award fee possible: 32,333;
Award fee paid: 11,640;
Percentage of possible award fee paid: 36.
4;
Purpose: Life support;
Award fee possible: 2,207;
Award fee paid: 794;
Percentage of possible award fee paid: 36.
5;
Purpose: Fuel import and distribution;
Award fee possible: 39,208;
Award fee paid: 26,662;
Percentage of possible award fee paid: 68.
6;
Purpose: Infrastructure repair and restoration;
Award fee possible: 9,700;
Award fee paid: 388;
Percentage of possible award fee paid: 4.
7;
Purpose: Fuel import and distribution;
Award fee possible: 14,354;
Award fee paid: 9,761;
Percentage of possible award fee paid: 68.
8;
Purpose: Fuel import and distribution;
Award fee possible: 7,679;
Award fee paid: 5,222;
Percentage of possible award fee paid: 68.
9;
Purpose: Fuel import and distribution;
Award fee possible: 1,896;
Award fee paid: 1,289;
Percentage of possible award fee paid: 68.
10;
Purpose: Fuel import and distribution;
Award fee possible: 802;
Award fee paid: 546;
Percentage of possible award fee paid: 68.
Contract total;
Award fee possible: $108,631;
Award fee paid: $56,515;
Percentage of possible award fee paid: 52%.
Source: GAO analysis of DOD data.
Note: A separate request for equitable adjustment was also negotiated
for task order 4. However, because the equitable adjustment claim
exceeded the not-to-exceed amount for task order 4, The contracting
officer decided that no fixed or award fees would be paid on the claim.
[End of table]
DOD Missed Opportunities to Motivate Contractor Performance by Not
Following Key Steps Outlined in Its Award Fee Plan:
DOD's award fee plan for the RIO I contract included several steps
related to providing the contractor with ongoing performance feedback.
For example, the plan called for award fee evaluations to be conducted
on a regular basis during the period of performance.[Footnote 29] These
evaluations were to include a meeting of the award fee board to
determine a recommended award fee for the contractor and a final
decision by the award fee determining official. After each award fee
evaluation, the contractor was to be notified of the percentage and
amount of award fee earned. In addition to these formal award fee
evaluations, the plan also called for monthly interim evaluations to be
conducted in which award fee board members would consider performance
evaluation reports submitted by DOD staff designated as performance
monitors, reach an interim evaluation decision, and then notify the
contractor of the strengths and weaknesses for the evaluation period.
However, despite its plans to conduct formal award fee evaluations
during the period of performance, DOD did not convene an award fee
board for the RIO I contract until contract performance was almost
entirely completed. DOD officials told us that they were unable to hold
boards due to the heavy workload of RIO staff and logistical challenges
such as difficulties with communications, travel, and security
conditions. DOD officials and contractor representatives also indicated
that holding an award fee board was not a high priority because their
focus was on making sure that the work under the contract was
accomplished. Ultimately only one award fee board was held, in July
2004, after fieldwork on all but one task order had been completed. The
contractor was notified of its award fee scores in January 2005, after
completion of all work on the contract.[Footnote 30] This process was
in contrast to the rationale for award fee evaluations explained in
federal regulations: Evaluation at stated intervals during performance,
accompanied by partial payment of the fee generally corresponding to
the evaluation periods, can induce the contractor to improve poor
performance or to continue good performance.
In addition to not holding formal evaluations as planned during the
period of performance, DOD did not meet the rigor called for in the
award fee plan when providing interim performance feedback to the
contractor. DOD did provide some interim feedback to the contractor on
its performance during the period of performance. For example, DOD
officials and contractor representatives told us that DOD contracting
staff and contractor staff had daily informal discussions about
contractor performance. In addition, RIO administrative contracting
officers sent the contractor letters on a semiannual basis that
provided feedback on the contractor's performance. However, as
discussed previously, the award fee plan states that the award fee
board should hold monthly interim evaluations of the contractor's
performance and provide the contractor with feedback from the
evaluations. DOD officials were only able to provide us with
information about one interim evaluation board, and the contractor was
not provided with results from this evaluation. Contracting staff and
others providing feedback to the contractor expressed to us views
ranging from very negative to very positive on the contractor's
performance during the same time period. Thus, without feedback
reflecting consensus judgment, the contractor may not have been fully
aware of the government's views on the strengths and weaknesses of its
performance. Given that the award fee is intended to motivate
excellence in contractor performance, providing the contractor with
this type of feedback is an important step in achieving this aim.
The lack of adherence to the award fee plan also made it difficult to
ensure that all aspects of the contractor's performance were considered
in the final award fee decision. Although performance monitors were
supposed to complete reports monthly and at the end of each evaluation
period in order to provide the award fee board with information about
the contractor's performance, which would mean that hundreds of reports
should have been completed during the course of the contract, a DOD
official told us that fewer than 10 performance monitor reports were
ever provided to the award fee board. The board received so few reports
because (1) written reports were not prepared on a regular basis, as
required by the award fee plan, and (2) reports that were prepared were
not submitted to the award fee board. Specifically, DOD officials and
correspondence indicated that performance monitor reports did not begin
to be completed until several months into the contract period of
performance and even then were not completed on a monthly basis. In
addition, DOD officials provided us with more than 25 reports that they
told us had been completed but not provided to the award fee board
members. DOD officials told us that board members were not provided
with these documents because the Corps had received a large number of
documents related to the RIO I contract from Iraq that had not been
sorted through by the time the award fee board was held in July 2004.
Because the DOD officials had not sorted through all of the documents,
the award fee board was also not provided with full information about
an interim evaluation board held in May 2003. Specifically, award fee
board members were provided with only one task order score from the
interim evaluation board, despite the fact that documentation of
consensus scores and contractor strengths and weaknesses was prepared
for four task orders. DOD officials responsible for selecting the award
fee board members told us that they selected board members to ensure
that they included individuals who had directly observed the contractor
in different time periods and locations. However, because the award fee
board meeting was near the end of fieldwork on the contract and because
RIO staff rotated during the period of performance, written
observations of contractor performance would have been important in
ensuring that the board had full knowledge of all aspects of the
contractor's performance.
We have previously reported on problems with DOD adhering to its award
fee process in contingency situations. In our review of DOD's use of
logistics support contracts, for one large contract we found that the
Army was not holding award fee boards according to the terms of the
contract. We also found that Army officials were not evaluating and
documenting the contractor's performance on that contract.[Footnote 31]
DOD Could Not Provide Sufficient Documentation to Enable Us to Fully
Evaluate Its Adherence to Its Award Fee Plan:
To evaluate the extent to which DOD followed its planned process for
making the RIO I award fee decision, we attempted to review DOD's
adherence to the process outlined in its award fee plan, but were not
able to fully do so because DOD could not provide us with documentation
of some elements of the process. For example, according to DOD
officials and the award fee board minutes, the board determined its
recommended score for each task order by first reaching a consensus on
individual criteria outlined in the contract, and then computing the
overall score based on the weighting included in the contract for those
criteria. However, according to DOD officials, they could not provide
us with the consensus scores on the individual criteria because records
of those scores were destroyed after the final award fee decision was
reached.[Footnote 32] Without these scores, we could not determine
whether the award fee board adhered to the weighting of the criteria
outlined in the contract in reaching its recommendation. We also had
limited insight into any additional factors the award fee determining
official considered in making his initial decision, which included
upward adjustments to the award fee board's recommendation, because DOD
officials could not provide us with documentation of the reasons for
the difference and told us they did not believe such documentation had
ever been developed. This apparent lack of documentation was not in
accordance with the award fee plan, which states that reasons for any
differences between the award fee determining official's decision and
the award fee board's recommendation must be fully documented.
DOD officials also could not provide us with complete information
regarding the monitoring of the contractor's performance during the
period of performance. For example, we could not obtain full
documentation of interim boards referred to in the award fee board
minutes, including documentation of the number of boards held, the
dates of the boards, or the results from the boards. Without such
information, we could not determine how results from interim
evaluations were figured into the award fee board's recommendation, as
the award fee plan indicates they should be.
The Percentage of Award Fee Earned on the RIO I Contract Fell within
the Range of Award Fees Earned on a Sample of Other Iraq Reconstruction
Contracts:
To put the RIO I award fee into context, we also analyzed the award
fees earned on other selected Iraq reconstruction contracts and found
that the percentage of award fee earned on the RIO I contract was
within the range of award fees earned on these other contracts. More
specifically, we reviewed 11 contracts that DOD awarded in 2004 to
conduct reconstruction activities in Iraq, which, like the RIO I
contract, were large-scale cost-plus-award-fee contracts. During the
period we looked at, January 2004 through June 2006, a total of 37
award fee evaluation periods were conducted for the 11 contracts. As
illustrated in figure 4, the percentage of award fee earned during the
period varied by contract, ranging from 20 percent to nearly 100
percent.
Figure 4: Percentage of Award Fee Earned on the RIO I Contract and on
11 Other Selected Iraq Reconstruction Contracts from January 2004 to
June 2006:
[See PDF for image]
Source: GAO analysis of DOD data.
Notes: Because some of these contracts were still active as of June
2006, the ultimate amount and percentage of award fees earned may have
changed depending on contractor performance over the remainder of the
contract. In 11 of the 37 award fee evaluation periods we analyzed, the
award fee determining official chose to roll over the unearned award
fee from one evaluation period to a subsequent evaluation period or
periods. In these cases we excluded rolled-over fees from the available
fee pool. While this analysis provides a basis for context, the
circumstances surrounding each contract are unique. Consequently, the
percentage of award fee earned may not be directly comparable between
contracts.
[End of figure]
Conclusion:
To meet the urgent operational needs of reestablishing Iraq's oil
infrastructure and importing fuel, the Corps authorized the contractor
to begin work before task orders had been definitized. Factors such as
changing requirements, funding challenges, and problems with contractor
proposals delayed negotiations until well past the timing required by
DOD for definitization. For all 10 RIO I task orders, the work was
completed before negotiations were finalized. Delays in definitizing
contract actions can increase the risk to the government by reducing
cost control incentives, particularly for cost reimbursement type
contracts. In addition, our findings on the agreement reached between
DOD and the contractor on the RIO I contract build on other significant
evidence in our prior work that the value of DCAA's audits of
contractor proposals is limited when negotiations take place too long
after work has begun.
Award fees can serve as a valuable tool to help control program risk
and encourage excellence in contract performance. To reap the
advantages that cost-plus-award-fee contracts offer, the government
must implement an effective award fee process, which requires
additional administrative effort and cost to monitor and evaluate
performance. The FAR requires that the expected benefits of using a
cost-plus-award-fee contract are sufficient to warrant this additional
effort and cost, but in the case of the RIO I contract, even if this
condition had been met, DOD's Army Corps of Engineers did not carry out
its planned award fee process. According to DOD officials, efforts to
hold award fee boards during the period of performance were stymied in
part by the logistical conditions in Iraq. We have previously
identified problems with DOD's award fee process in contingency
environments. Given that the award fee is intended to motivate
excellence in contractor performance, providing the contractor with
regular feedback that reflects the consensus of the government about
its strengths and weaknesses is important to enable the contractor to
put forth its best effort to excel in the areas deemed important to the
government. While contingency situations may pose additional challenges
for adhering to an award fee process, without an effective process, the
government risks incurring the additional cost and administrative
effort of an award fee contract without receiving the expected
benefits.
Recommendation for Executive Action:
To ensure that cost-plus-award-fee contracts provide the intended
benefits, we recommend that the Secretary of the Army take the
following action:
* In contingency situations, as a part of weighing the costs and
benefits of using a cost-plus-award-fee contract, ensure that an
analysis of the administrative feasibility of following a rigorous
award fee process is conducted before the contract is awarded.
Agency Comments and Our Evaluation:
We provided a draft of this report to DOD for comment. In written
comments, DOD concurred with our recommendation. The department's
comments are reproduced in appendix II. In concurring with the
recommendation, DOD noted a number of factors that exist in this
contingency operation that it believed demonstrated the difficulty of
conducting an analysis of the administrative feasibility of using an
award fee contract in future contingency situations. These factors
included urgent contracting time frames, uncertain requirements, and
difficulties in identifying appropriate oversight personnel. As
specified in federal regulations, the use of an award fee contract is
suitable when the expected benefits of such a contract are sufficient
to warrant the additional effort and cost required to monitor and
evaluate contractor performance. It is precisely factors such as those
outlined by DOD that we believe are important for consideration when
determining the administrative feasibility of a cost-plus-award fee
contract in a contingency environment.
As agreed with your offices, unless you publicly announce the contents
of this report earlier, we plan no further distribution until 30 days
from the report date. At that time, we will send copies to the
Secretary of Defense and other interested parties. We will make copies
of this report available on request. In addition, this report will be
available at no charge on GAO's Web site at http://www.gao.gov.
If you have any questions concerning this report, please contact me at
(202) 512-4841 or by e-mail at huttonj@gao.gov. Contact points for our
Offices of Congressional Relations and Public Affairs may be found on
the last page of this report. Other major contributors to this report
were Marie Ahearn, Penny Berrier Augustine, Greg Campbell, Arthur James
Jr., Eric Lesonsky, Stephen Lord, Anne McDonough-Hughes, Janet
McKelvey, and Kenneth Patton.
Signed by:
John P. Hutton:
Director:
Acquisition and Sourcing Management:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
To determine how the Department of Defense (DOD) addressed the Defense
Contract Audit Agency's (DCAA) audit findings on the Restore Iraqi Oil
(RIO I) contract and the factors that contributed to DOD's decision of
how to address those findings, we reviewed negotiation memorandums and
22 DCAA audit reports, including 11 final audit reports, for the 10 RIO
I task orders. Additionally, we reviewed other documents related to the
negotiation process and resolution of DCAA's findings. We also
interviewed Corps, DCAA, and other government officials as well as
contractor representatives. Because a contracting officer has the
discretion to determine whether or not to pay questioned costs when
reaching agreement with a contractor, our review does not include a
determination of whether the DOD contracting officer should have
approved payment for the questioned costs. Additionally, to put DOD's
decisions of how to address DCAA's RIO I contract audit findings into
context, we compared the resolution of DCAA's questioned cost findings
on 100 audits of other Iraq-related contract actions to the resolution
of the questioned cost findings on the RIO I task order audits. We
selected the 100 audits for comparison because they represented all
audits of Iraq-related contract actions other than the RIO I contract
for which DCAA had calculated the questioned costs sustained as of the
end of fiscal year 2006, excluding those calculated
automatically.[Footnote 33] To ensure we used a consistent unit of
measurement, we used the audit report as the unit of analysis for
comparison. To develop an understanding and assess the reliability of
the information included in the database that contained the results for
these 100 audits, we held discussions with and obtained documentation
from DCAA officials located at Fort Belvoir and we conducted electronic
and manual testing for obvious inconsistencies and completeness. We
determined the data used in our review to be sufficiently reliable for
our purposes.
To determine the extent to which DOD paid award fees for the RIO I
contract and followed its planned process for making that decision, we
collected and reviewed key documents related to the award fee process,
including the award fee provisions of the RIO I contract, the award fee
determining official's decision, the award fee plan, and minutes from
the award fee board meeting. We also interviewed Corps officials,
including the award fee determining official and members of the award
fee board, to develop an understanding of the process and outcome for
the award fees, and contractor representatives to obtain their
perspective on award fees. Additionally, to put the award fee for the
RIO I contract into context, we gathered and analyzed award fee
documentation provided by the Joint Contracting Command-Iraq/
Afghanistan for 11 contracts that DOD awarded in 2004 to conduct
reconstruction activities in Iraq. We selected these contracts because,
like the RIO I contract, they were large-scale, cost-plus-award-fee
contracts. During the period we looked at, January 2004 through June
2006, a total of 37 award fee evaluation periods were conducted for the
11 contracts. In 11 of the 37 award fee evaluation periods we analyzed,
the award fee determining official chose to roll over the unearned
award fee from one evaluation period to a subsequent evaluation period
or periods. In these cases we excluded rolled-over fees from the
available fee pool. Because an award fee determination is a unilateral
decision made solely at the discretion of the government based upon
judgmental evaluations of contractor performance, our review does not
include an assessment of whether DOD reached the appropriate award fee
decision for the RIO I contract.
We conducted our work from October 2006 through July 2007 in accordance
with generally accepted government auditing standards.
[End of section]
Appendix II: Comments from the Department of Defense:
Department Of The Army:
U.S. Army Corps Of Engineers:
441 G St. Nw:
Washington, D.C. 20314-1000:
July 30, 2007:
Mr. John P. Hutton:
Director, Acquisition and Sourcing Management:
U.S. Government Accountability Office:
441 G Street, N.W.
Washington, D.C. 20548:
Dear Mr. Hutton:
This is the Department of Defense (DoD) response to the GAO draft
report 07-839, `Defense Contract Management: DOD's Lack of Adherence to
Key Contracting Principles on Iraq Oil Contract Put Government
Interests at Risk,' dated July 3, 2007, (GAO Code 120596).
I appreciate the opportunity to comment on the draft report. I concur
with the GAO recommendation as discussed in the enclosure.
If you have any questions or require additional information, please
contact Ms. Alicia Matias, 202-761-4375,
alicia.s.matias@usace.army.mil.
Signed by:
Norbert S. Doyle:
Colonel, Acquisition Corps:
Acting Director of Contracting:
GAO Draft Report Dated 3 July 2007, GAO-07-839 (GAO Code 120596):
Defense Contract Management: DOD's Lack Of Adherence To Key Contracting
Principles On Iraq Oil Contract Put Government Interests At Risk:
Department Of Defense Response To The Recommendation:
Recommendation 1: The GAO recommends that the Secretary of the Army: in
contingency situations, as a part of weighing the costs and benefits of
using a cost-plus-award-fee contract, ensure that an analysis of the
administrative feasibility of following a rigorous award fee process is
conducted before the contract is awarded.
DOD Response - Concur:
a. The bottom line recommendation is that the Secretary of the Army
conduct an analysis of the feasibility of conducting a rigorous award
fee process before awarding a contract containing such fees. In the
context of a contingency operation of the type involved in the RIO 1
contract, it is far from clear how such an analysis could be completed.
Making such a determination would be particularly difficult in similar
future contingency operations involving the following factors, which
were present in RIO 1. It was urgent to get a contract in place. Formal
responsibility for executing the RIO mission was assigned to the Army
on 22 Jan 03 and to USACE on 13 Feb 03. USACE developed a Justification
& Approval (J&A) supporting the award of a sole source contract to
KBRS, which was approved on 28 Feb 03. On 17 Mar 03 hostilities began
and USACE was directed to begin contract execution. Actions which had
been completed before 17 Mar 03 included identifying the necessary work
force, processing them through the CRC, and getting them and the
required equipment into the approved personnel/cargo flow so they could
be deployed to Kuwait. The requirements were not firm and even the
mission itself was classified. There was no firm funding for the
mission; no organization existed to administer the contract; the
volunteers who ultimately made up the organization had to be
identified; and there was no firm understanding of the type of security
or communications which would be available. To take one concrete
example, the contract specified that the work would be performed in
"benign" conditions and it would be somewhat of a stretch to describe
the resulting conditions in Iraq as "benign". Obtaining the necessary
approval for the J&A supporting the sole source contract at high levels
within Army resulted in delays in getting contractor personnel and
equipment deployed. Any additional administrative requirements of the
type recommended by GAO would have to be carefully designed to avoid
further delays in getting contractor personnel in place to respond to
requirements from contingency operations.
b. Military personnel can be ordered to deploy. Civilian personnel
cannot. USACE and other government organizations generally must rely on
volunteers to conduct contingency operations. So long as we continue to
do so, it will continue to be difficult to insure that we have the
right personnel in the right places to execute all contingency
contracting operations with the same degree of oversight used for other
than contingency contracts. Changes could be made to the personnel
system to help with this problem. Potential changes could include the
designation of more emergency essential positions in which the
incumbents agree to deploy up front as a condition of employment;
designation of positions in which the incumbents also have to become
members of the Individual Ready Reserve; or the use of NSPS authority
to set higher pay for persons who agree in advance to deploy if needed.
[End of section]
FOOTNOTES
[1] Kellogg Brown & Root is now known as KBR.
[2] Federal Acquisition Regulation (FAR) 16.405-2(b)(3).
[3] On May 22, 2003, United Nations Security Council Resolution 1483
noted the establishment of the Development Fund for Iraq, a special
account held on the books of the Central Bank of Iraq. The DFI includes
frozen assets of the former Iraqi regime and Iraq oil proceeds. The DFI
was to be used for the economic reconstruction and repair of Iraq's
infrastructure, among other purposes.
[4] These proposals were intended to definitize the contractual actions
and were generally submitted after the contractor had incurred some of
its costs.
[5] Federal Acquisition Regulation 1.602-2(c), 15.402(a).
[6] Federal Acquisition Regulation 15.405(a).
[7] More than 99 percent of DCAA's questioned costs were on task orders
3, 5-10, and the contractor claim for task order 4, all of which were
negotiated by one DOD contracting officer. Another DOD contracting
officer negotiated the other three task orders. Report references to
the DOD contracting officer refer to the contracting officer who
decided how to address nearly all of the questioned costs.
[8] GAO recently reviewed DOD's use of award and incentive fees. See
GAO, Defense Acquisitions: DOD Has Paid Billions in Award and Incentive
Fees Regardless of Acquisition Outcomes, GAO-06-66 (Washington, D.C.:
Dec. 19, 2005).
[9] Federal Acquisition Regulation 16.405-2(b)(iii).
[10] In a March 2006 policy memo, DOD established limitations on the
use of award fee rollover provisions, including that the use of
rollover provisions should be the exception rather than the rule and is
a business decision that should be addressed in the acquisition
strategy. According to the memo, if the fee-determining official
approves the use of rollover, the contract file must be documented
accordingly.
[11] DCAA officials told us the memos that outlined the financial
positions do not supercede DCAA's final audit reports, but were
provided to the contracting officer to assist with negotiations.
[12] The decision to pay the questioned costs rather than assume the
litigative risk and attendant costs associated with defending a claim
for disallowance of incurred costs is essentially a matter of the
contracting officer's business judgment. See FAR 1.602-2.
[13] We calculated the $5.8 million in the following manner: For each
task order, we multiplied the award and fixed fee percentages received
by the contractor by the adjustment to the amount used to establish the
fee pool (this amount totaled -$112 million across the task orders). We
then summed this total for each task order.
[14] Iraq Reconstruction: Hearing before the House Comm. on Oversight
and Government Reform, 110th Cong. (2007).
[15] Under the FAR, there is no presumption of reasonableness when
costs are incurred by the contractor. If the contracting officer
challenges a specific cost, the contractor has the burden of proof to
establish that such cost is reasonable. A cost is reasonable if, in its
nature and amount, it does not exceed that which would be incurred by a
prudent person in the conduct of competitive business. What is
reasonable depends upon a variety of considerations and circumstances,
including whether it is the type of cost generally recognized as
ordinary and necessary for the conduct of the contractor's business or
the contract performance. FAR 31.201-3. The contracting officer is
allowed wide latitude to exercise business judgment and could still
decide to pay the costs after consideration of the audit findings based
on a judgment of what the best business decision would be, including
the desire to avoid the cost of litigation.
[16] Pursuant to the authority of DOD Directive 5105.36, DCAA can issue
a Form 1. A Form 1 constitutes notice of costs suspended and/or
disapproved incident to the audit of contractor costs incurred under a
contract. Suspended costs are costs that have been determined to be
inadequately supported or otherwise questionable, and not appropriate
for reimbursement under contract terms at that time. Such costs may be
determined reimbursable after the contractor provides the auditor
additional documentation or explanation. Disapproved costs are costs
that have been determined to be unallowable, that is, not reimbursable
under the contract terms.
[17] The Defense Federal Acquisition Regulation Supplement defines a
qualifying proposal as a proposal containing sufficient information for
DOD to do complete and meaningful analyses and audits of the (1)
information in the proposal and (2) any other information the
contracting officer has determined DOD needs to review in connection
with the contract. DFARS 217.7401(c).
[18] However, DOD did recognize the need to have a contingency plan
available in case the need arose.
[19] "Vested assets" refers to former Iraqi regime assets held in U.S.
financial institutions that the President confiscated in March 2003 and
vested in the U.S. Treasury. The United States froze these assets
shortly before the first Gulf War. The USA PATRIOT ACT of 2001 amended
the International Emergency Economic Powers Act to empower the
President to confiscate certain property of designated entities,
including these assets, and vest ownership in an agency or individual.
The President has the authority to use the assets in the interests of
the United States. In this case, the President vested the assets in
March 2003, and these funds were made available for the reconstruction
of Iraq in May 2003.
[20] In its most recent audit of the contractor's estimating system,
issued in September 2005, DCAA found that the contractor had taken
corrective action and made improvements to the system. However, DCAA
continued to cite some deficiencies in the system. As of December 2004,
the DOD systems administrative contracting officer who is responsible
for determining the acceptability of the contractor's estimating system
determined the system to be acceptable with corrective action. This
determination was in effect as of the issuance of this report.
[21] GAO, Defense Contracting: Use of Undefinitized Contract Actions
Understated and Definitization Time Frames Often Not Met, GAO-07-559
(Washington D.C.: June 2007).
[22] GAO, Rebuilding Iraq: Fiscal Year 2003 Contract Award Procedures
and Management Challenges, GAO-04-605 (Washington D.C.: June 2004).
[23] GAO, Iraq Contract Costs: DOD Consideration of Defense Contract
Audit Agency's Findings, GAO-06-1132 (Washington D.C.: September 2006).
[24] GAO-04-605 and GAO, Military Operations: DOD's Extensive Use of
Logistics Support Contracts Requires Strengthened Oversight, GAO-04-854
(Washington D.C.: July 2004).
[25] For example, in one audit, DCAA questioned whether some costs were
properly allocated to the task order, and suggested the costs should be
allocated to another task order under the contract. The DOD contracting
officer agreed the costs were improperly allocated, and moved the costs
to the appropriate task order. Because DCAA calculates questioned costs
sustained for each audit, DCAA considered these questioned costs
sustained.
[26] Numbers do not add due to rounding. DCAA officials told us that,
in general, DCAA calculates a sustention rate across all audits for
each fiscal year. They use the sustention rates for internal management
purposes--for example, they compare the sustention rate from fiscal
year to fiscal year to see if there is variation. When there is
variation, they try to identify reasons for that variation. The
officials told us they do not have a specific goal for an overall
sustention rate, and that it is not unusual for an individual audit to
have a sustention rate of 0 percent or of 100 percent.
[27] For comparison purposes, we used the audit report as our unit of
analysis. By using the audit report as the unit of analysis, each
sustention rate generally reflects a contracting officer's decision on
how to address DCAA's findings for that particular audit. As a
management tool used by DCAA, sustention rates do not represent an
analysis of the validity of underlying costs or how the contracting
officer made a decision on the reasonableness of specific costs.
[28] The total value of the RIO I contract was about $2.5 billion,
including the negotiated costs to be paid and the fixed and potential
award fees that could be earned by the contractor.
[29] Specifically, the plan noted that end-of-period evaluations were
to be conducted semiannually for the first evaluation period and
quarterly for all remaining performance periods thereafter.
[30] After receiving DOD's initial award fee decision in January 2005,
the contractor requested the opportunity to have its award fee scores
reconsidered. The award fee determining official granted this request.
After the contractor presented additional information, the award fee
determining official made some upward adjustments to the award fee in
his final decision when he determined that new information provided by
the contractor was sufficiently significant to do so. In this report,
all award fee amounts and percentages refer to the award fee
determining official's final decision.
[31] GAO-04-854.
[32] The Defense Federal Acquisition Regulation Supplement provided
that the basis for all award fee determinations was required to be
documented in the contract file. DFARS § 216.405-2(a)(ii) (Currently,
this provision is in DFARS Procedures, Guidance, and Information §
216.405-2(2)). However, there is no specific requirement that records
of the award fee board's consensus scores on individual criteria be
kept.
[33] According to DCAA guidance, for certain types of audit assignments
with questioned costs lower than $500,000, DCAA's internal management
system automatically calculates questioned costs sustained based on the
actual average sustention rate of proposals for an agency with
questioned costs over $500,000 for the prior 3 fiscal years. Because
questioned costs sustained is calculated automatically for these
assignments, the sustention rate does not reflect the contracting
officer's decision on the specific audit, and therefore we excluded
these cases from our analysis.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts
newly released reports, testimony, and correspondence on its Web site.
To have GAO e-mail you a list of newly posted products every afternoon,
go to www.gao.gov and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548:
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202)
512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S.
Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548:
Public Affairs:
Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, D.C. 20548: