Defense Acquisitions
Termination Costs Are Generally Not a Compelling Reason to Continue Programs or Contracts That Otherwise Warrant Ending
Gao ID: GAO-08-379 March 14, 2008
The nation's long-term fiscal imbalances will likely make DOD's $1.6 trillion planned investment in new weapon systems unsustainable. Thus, it is critical that DOD retains the flexibility to end programs and contracts when necessary and appropriate. Although the federal government generally has the legal right to terminate contracts for convenience, defense stakeholders have sometimes expressed concerns that it will cost more to terminate a contract than to complete it. To address this perception, GAO examined (1) how expected contract termination costs and other factors affect DOD decisions on whether to end programs and contracts; (2) the circumstances under which it would cost more to terminate a contract for convenience than to complete it; and (3) the options DOD has for retaining value or reducing costs, when DOD ends programs or contracts. To do this, GAO examined DOD data on terminated contracts over $100 million; reviewed laws, regulations, and guidance; and met with key DOD officials.
Contract termination costs were generally not a major factor in Department of Defense (DOD) decisions to end programs or contracts for the weapon systems GAO reviewed. GAO found that these program cancellations were driven by factors such as changes in warfighter need and budgetary constraints. In the contract termination decisions GAO reviewed, DOD considered termination costs, but they were generally not as significant as other factors, such as contract cost growth. For the contracts reviewed, GAO found that it did not cost more to terminate than to complete them. When the government terminates a contract for convenience, it must compensate the contractor for the incurred costs on the completed work, a fee or profit on that work, and the termination costs. Federal regulations place various limits on this compensation for both cost-reimbursement and fixed-price contracts. GAO found eight fully terminated contracts of weapon systems that were over $100 million in value, terminated after 1995, and for which data were available. Of these, none cost more to terminate than to complete. When a program or contract ends, DOD can retain some value from the work completed. For example, DOD can end the work immediately and transfer materials or technology to other efforts. Alternatively, DOD can modify the scope of a contract and complete a limited portion of the original work. GAO's review of DOD's past experience with terminations highlights important lessons for DOD in making decisions to cancel individual programs as well as in managing its broader investment portfolio. For example, when considering cancellation of individual programs, contract termination costs are generally not a compelling reason to continue programs or contracts that otherwise warrant ending. Moreover, while incurred or "sunk" costs in programs being considered for termination may be substantial, they must be paid regardless of whether or not a contract is terminated. Therefore, the decision to terminate a contract or cancel a program should not be driven by sunk costs. From an investment portfolio perspective, terminations can be a valuable tool in responding to long-term fiscal imbalances as well as unexpected events that could constrain spending. More specifically, they can be used to create more trade space in the over $850 billion that still remains in outstanding commitments in DOD's planned $1.6 trillion investment in weapons programs. However, to make the most effective use of this tool, decision-makers need to be able to anticipate and plan for possible terminations and have a sound understanding of costs, benefits, and legal requirements. As a result, guidance on terminations developed by the military services and other DOD entities should be clear, consistent, proactive, and detailed enough to provide the knowledge needed to use terminations as an investment portfolio tool.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-08-379, Defense Acquisitions: Termination Costs Are Generally Not a Compelling Reason to Continue Programs or Contracts That Otherwise Warrant Ending
This is the accessible text file for GAO report number GAO-08-379
entitled 'Defense Acquisitions: Termination Costs Are Generally Not a
Compelling Reason to Continue Programs or Contracts That Otherwise
Warrant Ending' which was released on March 17, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Committees:
United States Government Accountability Office:
GAO:
March 2008:
Defense Acquisitions:
Termination Costs Are Generally Not a Compelling Reason to Continue
Programs or Contracts That Otherwise Warrant Ending:
Contract Terminations for Convenience:
GAO-08-379:
GAO Highlights:
Highlights of GAO-08-379, a report to congressional committees.
Why GAO Did This Study:
The nation‘s long-term fiscal imbalances will likely make DOD‘s $1.6
trillion planned investment in new weapon systems unsustainable. Thus,
it is critical that DOD retains the flexibility to end programs and
contracts when necessary and appropriate.
Although the federal government generally has the legal right to
terminate contracts for convenience, defense stakeholders have
sometimes expressed concerns that it will cost more to terminate a
contract than to complete it. To address this perception, GAO examined
(1) how expected contract termination costs and other factors affect
DOD decisions on whether to end programs and contracts; (2) the
circumstances under which it would cost more to terminate a contract
for convenience than to complete it; and (3) the options DOD has for
retaining value or reducing costs, when DOD ends programs or contracts.
To do this, GAO examined DOD data on terminated contracts over $100
million; reviewed laws, regulations, and guidance; and met with key DOD
officials.
What GAO Found:
Contract termination costs were generally not a major factor in
Department of Defense (DOD) decisions to end programs or contracts for
the weapon systems GAO reviewed. GAO found that these program
cancellations were driven by factors such as changes in warfighter need
and budgetary constraints. In the contract termination decisions GAO
reviewed, DOD considered termination costs, but they were generally not
as significant as other factors, such as contract cost growth.
For the contracts reviewed, GAO found that it did not cost more to
terminate than to complete them. When the government terminates a
contract for convenience, it must compensate the contractor for the
incurred costs on the completed work, a fee or profit on that work, and
the termination costs. Federal regulations place various limits on this
compensation for both cost-reimbursement and fixed-price contracts. GAO
found eight fully terminated contracts of weapon systems that were over
$100 million in value, terminated after 1995, and for which data were
available. Of these, none cost more to terminate than to complete.
When a program or contract ends, DOD can retain some value from the
work completed. For example, DOD can end the work immediately and
transfer materials or technology to other efforts. Alternatively, DOD
can modify the scope of a contract and complete a limited portion of
the original work.
GAO's review of DOD‘s past experience with terminations highlights
important lessons for DOD in making decisions to cancel individual
programs as well as in managing its broader investment portfolio. For
example, when considering cancellation of individual programs, contract
termination costs are generally not a compelling reason to continue
programs or contracts that otherwise warrant ending. Moreover, while
incurred or "sunk" costs in programs being considered for termination
may be substantial, they must be paid regardless of whether or not a
contract is terminated. Therefore, the decision to terminate a contract
or cancel a program should not be driven by sunk costs.
From an investment portfolio perspective, terminations can be a
valuable tool in responding to long-term fiscal imbalances as well as
unexpected events that could constrain spending. More specifically,
they can be used to create more trade space in the over $850 billion
that still remains in outstanding commitments in DOD's planned $1.6
trillion investment in weapons programs. However, to make the most
effective use of this tool, decision-makers need to be able to
anticipate and plan for possible terminations and have a sound
understanding of costs, benefits, and legal requirements. As a result,
guidance on terminations developed by the military services and other
DOD entities should be clear, consistent, proactive, and detailed
enough to provide the knowledge needed to use terminations as an
investment portfolio tool.
What GAO Recommends:
GAO recommends that DOD review, and as needed amend, guidance on
terminations across the military services and DOD agencies to ensure
that termination guidance identifies the conditions under which it is
appropriate to end programs or contracts, and provides knowledge needed
to use terminations as an investment portfolio tool. DOD agreed.
To view the full product, including the scope and methodology, click on
[hyperlink, http://www.GAO-08-379]. For more information, contact
Cristina Chaplain at (202) 512-4841 or ChaplainC@gao.gov.
[End of section]
Contents:
Letter:
Results in Brief:
Background:
Contract Termination Costs Generally Do Not Drive Program Cancellation
or Contract Termination Decisions:
Terminating a Contract Generally Costs Less than Completing It:
DOD Has Options for Retaining Value or Reducing Costs when Programs Are
Canceled or Contracts Are Terminated:
Conclusions:
Recommendation:
Agency Comments and Our Evaluation:
Appendix I: Termination Costs and Settlement Amounts:
Appendix II: Comments from the Department of Defense:
Appendix III: GAO Contact and Staff Acknowledgments:
Table:
Table 1: Contracts Over $100 Million Terminated Since 1995:
Figures:
Figure 1: Contracts Terminated for Convenience Processed by DCMA in FY
2006 by Contract Price of Items Terminated:
Figure 2: Costs Included in the Total Settlement:
Figure 3: Termination Costs versus the Value of the Remaining Work:
Figure 4: Termination Costs versus the Value of Remaining Work for
Fixed-Price Contracts:
Figure 5: Components of a Settlement:
Figure 6: Two Possible Contract Cost Curves:
Figure 7: Cost Implications of Delaying a Termination Decision:
Figure 8: The Break-Even Point:
Abbreviations:
CPIT: Contract Price of Items Terminated:
DCMA: Defense Contract Management Agency:
DOD: Department of Defense:
FAR: Federal Acquisition Regulation:
LCS: Littoral Combat Ship:
NLOS-C: Non-Line-of-Sight Cannon:
OSD: Office of the Secretary of Defense:
TSSAM: Tri-Service Standoff Attack Missile:
United States Government Accountability Office:
Washington, DC 20548:
March 14, 2008:
Congressional Committees:
In 2007, Department of Defense (DOD) planned investment in new weapon
systems totaled $1.6 trillion. Of this, over $850 billion remains in
outstanding commitments. Prior GAO work has shown that the nation's
long term fiscal imbalances, as well as DOD's tendency to start more
programs than current and likely future resources can support, will
place pressure on the agency's ability to carry out planned
investments. Given this, as well as continual cost overruns and
performance problems among some weapon programs, it is critical that
DOD retains the flexibility to cancel programs and terminate contracts
when necessary. Program cancellation decisions are related to but
separate from contract termination decisions. When canceling a program,
DOD may complete a contract, or it may terminate a contract if it is in
the interests of the government. While DOD terminates hundreds of
contracts for convenience in part or in whole each year, fewer than a
dozen contracts terminated since 1995 were worth more than $100
million. Although the government generally has the legal right to
terminate contracts for its convenience, there are costs associated
with doing so. In recent years, defense stakeholders have sometimes
expressed concerns that it will cost more to terminate a contract than
to complete it. In order to address this perception and better
understand the relationship between DOD's decision making and contract
termination costs, this report will examine (1) how expected contract
termination costs and other factors affect DOD decisions on whether to
cancel programs and terminate contracts, (2) the circumstances under
which it would cost more to terminate a contract for convenience than
to complete it, and (3) the options DOD has for retaining value or
reducing costs when programs are canceled or contracts are terminated.
We prepared this report under the authority of the Comptroller General
of the United States to conduct evaluations on his own initiative. We
conducted our work at the Department of Defense, including the Office
of the Secretary of Defense (OSD), Army, Air Force, Department of the
Navy, and Defense Contract Management Agency (DCMA). To understand
program acquisitions, related contracting practices, and the
cancellation of programs and termination of contracts, we reviewed
relevant laws, regulations, and guidance related to program management
and contract terminations for convenience. We reviewed data on
terminated contracts from the DCMA Terminations Center database, which
has data on programs for which DCMA has handled the termination. For
the purposes of this review, we reviewed all fully terminated contracts
in the DCMA database--both fixed-price and cost-reimbursement--of
weapons systems that were over $100 million in value and were
terminated after 1995. In addition, we examined a termination of a
weapon system contract that had been handled by its program office and
was not in the DCMA database--the Comanche helicopter. This was the
only weapon system contract terminated after 1995 for over $100 million
that DOD officials were able to identify that was not terminated by
DCMA.[Footnote 1] We met with officials at DOD and at the Army, Air
Force, and the Department of the Navy to discuss programs that had been
canceled and contracts that had been terminated. In addition, we
reviewed programs and/or contracts that had been publicly discussed for
cancellation and/or termination, for which data were readily available,
but were not canceled or terminated, such as the C-130J Air Force cargo
airplane program.
We conducted our review from October 2006 to March 2008 in accordance
with generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings and
conclusions based on our audit objectives. We believe that the evidence
obtained provides a reasonable basis for our findings and conclusions
based on our audit objectives.
Results in Brief:
Termination costs for the contracts we reviewed were generally not as
significant as other factors in making program cancellation and
contract termination decisions. Rather, the weapon systems we reviewed
tended to be canceled when they no longer met warfighter need or when
they did not fit within budget constraints. For example, the Crusader
howitzer was canceled because the warfighter no longer needed a 60-ton
armored cannon to combat Soviet forces on the battlefields of Europe.
Termination costs were also not cited by DOD officials as a major
factor in contract termination decisions. Instead, contracts were
terminated because the program was canceled or because the contractor
experienced cost growth. Of the programs and contracts that we
reviewed, anticipated termination costs were only significant in
reversing the decision to terminate the C-130J cargo plane contract.
The decision to terminate this contract was made for budgetary reasons;
however, higher than anticipated termination cost estimates were a key
factor in reversing the decision.
There are limited circumstances in which it could cost the government
more to terminate a contract than to complete it. The Federal
Acquisition Regulation (FAR) specifies the categories of costs a
contractor may be entitled to when the government terminates a contract
for convenience. These costs include incurred costs, a reasonable fee/
profit, and termination costs such as disposing of inventories and
negotiating with subcontractors. Provisions in the FAR limit the total
settlement amount (the total amount paid on the terminated contract)
paid to the contractor. For example, the FAR generally limits the
government's liability under a fixed-price contract to the contract
price plus termination costs.[Footnote 2] Therefore, it would only cost
more to terminate a fixed-price contract than to complete it if the
termination costs were greater than the cost of the remaining work
under the contract. The government's liability in the event of a
contract termination is also limited under cost-reimbursable contracts.
Of the eight contracts we reviewed, we did not find any cases in which
the termination settlement exceeded the estimated contract price.
When a line of work ends by either a program cancellation or a contract
termination, DOD may be able to recover useful items, information, or
technology that can reduce costs on other DOD programs. More
specifically, when a contract is nearly complete, it may be in the
government's best interest to complete the contract, rather than
terminate it. For example, on the canceled E-10A program, Air Force
officials decided to complete the contract for the aircraft, because
the program only had to make one additional payment to take delivery of
the plane. When a contract is terminated, DOD can take steps to retain
value by transferring technology, information, and property to other
efforts. For example, when the Army's Comanche helicopter program was
canceled, the Army transferred flight control system technology and
70,000 line items of property to other DOD programs. Finally, DOD can
also continue a limited amount of work on a line item of a terminated
contract if this will result in technology or items in production that
could be used in the future. When the Littoral Combat Ship 3 (LCS-3)
was terminated, for example, the Navy decided to continue work on the
gears and gas turbines for use on other ships.
We are recommending that DOD review, and as needed amend, guidance on
terminations across the military services and DOD entities to ensure
that termination guidance consistently identifies the conditions under
which it is appropriate to end programs or contracts, and provides
knowledge needed to use terminations as an investment portfolio tool.
DOD concurred with our recommendation to review, and amend as needed,
guidance on contract terminations for convenience across the military
services and DOD. This is a positive step toward using terminations as
an investment portfolio tool.
Background:
Over the life cycle of a weapon system, DOD typically executes several
contracts with a prime contractor for the program. These contracts
cover development, production, or maintenance efforts. Although a
program and its contracts are related, they are separate, distinct
efforts that can end separately. For the purposes of this review, we
refer to the end of a program as a cancellation, and the end of a
contract as a termination. For example, DOD may cancel a program but
continue a contract related to that program. Alternatively, DOD can
terminate a contract but continue the program.
Since most federal contracts are mutually binding legal agreements that
are governed by the FAR, they must be terminated by proper procedures.
These procedures include the issuance of a termination notice.
Programs, in comparison, are institutionally directed and funded
efforts and not legal agreements.[Footnote 3] Based upon our audit
work, program cancellations may be done through an official program
document such as an acquisition decision memorandum. However,
documenting cancellations with a memorandum is not a DOD requirement
and DOD does not have specific guidance on how a program is to be
officially ended.
The programs we reviewed used two broad categories of contracts: cost-
reimbursement and fixed-price. In cost-reimbursement contracts, the
contractor is reimbursed for allowable[Footnote 4] costs incurred,
regardless of whether the anticipated work is completed. As a result,
the exact final cost of a cost-reimbursement contract may often not be
known at the start of a contract. In such cases, cost-reimbursement
contracts will have an estimated total cost for purposes of
establishing a not-to-exceed dollar value, which may be exceeded only
with the approval of the contracting officer. Contractors with cost-
reimbursement contracts may also be provided incentives, generally
referred to as fees, through various metrics that assess the
contractor's performance and reward that performance
accordingly.[Footnote 5] For fixed-price contracts, the government
agrees to pay the contractor a prenegotiated price for a product or
service and, therefore, the price is typically known at award.
Contractors with fixed-price contracts can also be provided additional
incentives based upon performance metrics. For DOD weapon systems, most
development is typically done with cost-reimbursement contracts, and
production can be done with fixed-price contracts.
Generally, parties' obligations under contracts end when the required
performance is completed, that is, when the government has accepted the
supplies or services and paid the contractor in full. However, if a
contractor has not performed as agreed, the government may choose to
end its obligations by terminating the contract for default. In other
cases, however, even when the contractor is performing acceptably, it
may be in the interest of the government to end its contractual
obligations before the contract is completed. To acknowledge the unique
position of the federal government in such circumstances, a legal right
to terminate procurement contracts for the government's convenience has
developed. This right gives the government--e.g., DOD and other federal
agencies--the option to terminate a contract for convenience when
changed circumstances, such as the end of a war, mean termination is in
the government's interests.[Footnote 6] If the government did not have
this right, in order to prematurely end a contract, the government
might breach its contract and potentially pay damages to the
contractor, which would result in unnecessary expenditure of government
funds and expenses for the taxpayer. For example, DOD officials told us
that when the Gulf War ended, DOD no longer needed large quantities of
prepackaged, shelf-stable meals and thus terminated those contracts for
convenience.
As mentioned earlier, when a contractor is unable to meet the terms and
conditions of the contract, the government may terminate the contract
for default. DOD officials, in reference to contracts for weapon
systems, told us that while a termination for default might be
considered, the standard for proving default is so high that instead,
terminations for convenience are often done.[Footnote 7] The Navy's A-
12 stealth attack aircraft program illustrates the difficulty of
pursuing a termination for default. In 1991, the Navy terminated the A-
12 contract for default. In doing so, the Navy contended that the
contractors were behind schedule and unable to deliver an aircraft that
met the contract requirements. The contractors challenged the
termination, resulting in 16 years of litigation, which was still
ongoing at the time we did our work. The contractor contended that a
termination for default is only permitted when it is absolutely
impossible for the contractor to complete the work or when the
contractor completely abandons the work. In this case, a termination
for default would require the contractors to repay over a billion
dollars in progress payments, as opposed to a termination for
convenience in which the contractor would be eligible to recover its
incurred costs.
The FAR requires that a termination for convenience clause be included
in most federal procurement contracts[Footnote 8], granting the
government the right to terminate the contract prior to
completion.[Footnote 9] In a complete termination for convenience, the
contract ends on the date specified in the government's notice of
termination. The FAR also gives the government the right to partially
terminate a contract for convenience, meaning the government can choose
to terminate only a portion of the contract. In contrast, the
contractor is not given a right to terminate for convenience, and this
type of contractual right is rare outside the world of federal
government contracting.
The process for terminating a contract for convenience is specified in
the FAR.[Footnote 10] When the government terminates a contract for
convenience, the contracting officer must send a written termination
notice to the contractor indicating whether the termination is for
convenience or default. The written notice may also contain, special
instructions, and in some cases personnel mitigation efforts.[Footnote
11] Upon receiving the notice of termination, the contractor is
required to stop all work immediately under the terminated portion of
the contract and terminate all related subcontracts. When inventories
exist, the contractor must, as directed by the contracting officer,
deliver to the government a "termination inventory" that lists
materials produced or acquired under the contract and government-
furnished property[Footnote 12] and account for all inventory related
to the terminated portion of the contract by completing termination
inventory schedules, generally within 120 days of the effective date of
the termination.[Footnote 13] The contractor must dispose of all
remaining property, as agreed with the government.[Footnote 14] The
contractor also begins the process of settling with its
subcontractors.[Footnote 15]
The contractor has 1 year from the effective date of the termination to
submit a settlement proposal to the contracting officer, unless the
period is extended by the contracting officer handling the
termination.[Footnote 16] The amount of the settlement proposal
reflects all of the costs for which the contractor believes it is
entitled to be reimbursed, including incurred costs for work performed,
termination costs, plus in some cases, a reasonable profit or fee on
its completed work, minus all payments made to date and the value of
the property the contractor retained upon termination.[Footnote 17]
When the contracting officer receives the contractor's settlement
proposal, he or she can choose to pay the proposed amount or negotiate
with the contractor.[Footnote 18] If the contractor does not submit a
settlement proposal within 1 year from the effective termination date,
or if the contracting officer cannot reach agreement with the
contractor, the contracting officer may unilaterally decide on the
amount to which the contractor is entitled, applying the standards that
are set forth in the FAR. The FAR also provides the contractor the
right to appeal[Footnote 19] the termination settlement to the
applicable Board of Contract Appeals[Footnote 20] or to the United
States Court of Federal Claims, if the contractor has met its deadline
for submission of the settlement proposal.[Footnote 21]
At DOD, when a procuring activity decides to terminate a contract for
convenience, although it is not required to do so, it may employ the
assistance of the termination contracting officers at the DCMA
Terminations Center. The Terminations Center employs contracting
officers who specialize in terminations for convenience and whose only
mission is to settle contracts terminated for the convenience of the
government. In fiscal year 2006, the Terminations Center data show that
DCMA processed about 600 terminations.[Footnote 22] Figure 1 shows that
only 10 percent of these terminated contracts involved terminated items
valued at more than $1 million.
Figure 1: Contracts Terminated for Convenience Processed by DCMA in FY
2006 by Contract Price of Items Terminated:
This figure is a pie chart showing contracts terminated for convenience
processed by DCMA in FY 2006 by contract price of items terminated.
36%: $5,001-$50,000;
17%: $50,001-$100,000;
22%: $100,001-$500,000;
6%: $500,001-$1,000,000;
10%: Greater than $1,000,000;
9%: $1-$5,000.
[See PDF for image]
Source: Data from the DCMA Terminations Center.
Note: DCMA's Contract Price of Items Terminated (CPIT) is the value of
the terminated portions of the contract. Under a complete termination,
CPIT would equal the contract price. Under a partial termination, CPIT
would equal only the value of the portion of the contract that was
terminated.
[End of figure]
Contract Termination Costs Generally Do Not Drive Program Cancellation
or Contract Termination Decisions:
When DOD decides to cancel a program or terminate a contract,
termination costs are generally not a major factor in these decisions.
DOD officials told us that the weapon systems we reviewed were canceled
for two primary reasons: when they no longer met warfighter need or
when they did not fit within budget constraints. While programs may
have experienced cost growth, schedule slippages, poor performance, and
changing requirements, cancellations were generally driven by
warfighter need and budgetary constraints. In contrast, DOD officials
did not cite contract termination costs as a major factor in program
cancellation decisions. In addition, while termination costs were
considered, DOD officials did not mention them as a major factor in
contract termination decisions. The one exception that we found was the
C-130J cargo plane in which higher than anticipated termination costs
were a key factor in reversing the decision.
Factors That Influence Program Cancellation Decisions:
Figure:
Crusader (Army);
Prime contractor: United Defense Limited Partnership;
Program started: 1987;
Last contract awarded: 1995;
Contract price: $1.87 billion;
Contract terminated: 2002;
Total settlement: $1.66 billion;
[See PDF for image]
Source: United Defense Limited Partnership.
The Crusader”an automated, next- generation field artillery system”was
designed to have greater firepower, range, and mobility than the
existing self-propelled howitzer. In 2000, the Army changed its
requirements to make the Crusader lighter and more deployable by air.
However, the program was unable to achieve lower weight requirements
within cost and schedule limitations. Ultimately, the Crusader was
canceled because the Army needed a more mobile and deployable force as
opposed to a 60-ton armored cannon designed to combat Soviet forces on
the battlefields of Europe. The Army was able to transition nearly
26,000 inventory line items”valued at more than $150 million”from the
Crusader to create the Non-Line-of-Sight Cannon program as well as an
additional 9,800 inventory line items”valued at $25.8 million”to other
DOD programs.
[End of figure]
Among the programs that we reviewed, contract termination costs did not
drive program cancellation decisions; rather, DOD canceled programs
when they no longer met warfighter need or when they did not fit within
budgetary constraints. For example, according to a program official,
the Crusader--an automated, self-propelled howitzer--was canceled
because the warfighter no longer needed a 60-ton armored cannon to
combat Soviet forces on the battlefields of Europe. Similarly, Army
officials determined that the operating environment faced by the
warfighter had changed and funds for the Comanche helicopter would be
better spent on other aviation priorities. Furthermore, the Comanche
program had experienced schedule slips and cost overruns. When
interviewed about the Comanche cancellation, an Army official told us
that the program's costs could no longer be justified.
Even if a program can deliver a useful capability, officials told us
that DOD may still decide to cancel the program to meet projected
budgetary constraints. For example, although Air Force officials stated
that there is still a need for the E-10A, an air-to-air and air-to-
ground radar platform, DOD canceled the program to match expenditures
against future budgets. Army officials stated that in recent years the
Army has also canceled programs for budgetary reasons. Army officials
told us that in the fiscal year 2008 budget request, the Army is
proposing to cancel 10 programs in order to meet the budget shortfall.
DOD officials confirmed that each service has a process to assess its
needs and resources over a 6-year time frame, but only the Army has a
formal process as part of its annual budget cycle to cancel the least
needed programs to cover a budget shortfall.
Factors That Influence Contract Termination Decisions:
Figure:
C-130J (Air Force);
Prime contractor: Lockheed Martin;
Aeronautics Company–Marietta;
Program started: 1996;
Contract began: 1996;
Total program costs: $8.07 billion (as of December 2006).
[See PDF for image]
Source: C-130J Program Office.
The C-130J is the latest addition to DOD‘s fleet of C-130 aircraft. The
C-130J climbs faster and higher, flies farther at a higher cruise
speed, and takes off and lands in a shorter distance than older models
and is designed primarily for the transport of cargo and personnel
within an area of armed conflict. The contract was considered for
termination due to budgetary reasons, but ultimately the Air Force
decided not to terminate the contract because estimated termination
costs were higher than expected.
[End of figure]
Contract termination costs generally did not drive contract termination
decisions; rather, officials told us that the contracts were terminated
because of cost growth or because the program that the contract
supported was canceled. For example, the Navy canceled the third and
fourth Littoral Combat Ships (LCS-3 and LCS-4) following a series of
cost overruns and schedule delays on LCS-1 and LCS-2 as well as an
inability to reach an agreement with the prime contractors to modify
their existing cost-reimbursement contracts to fixed-price
contracts.[Footnote 23] Navy officials stated that termination costs
were considered before the termination decision was made, but the
estimates of these costs were not significant enough to affect the
decision. Both the Crusader and the Comanche contracts were terminated
because their respective programs were canceled. In contrast,
termination costs did play a role in the reversal of the decision to
terminate the C-130J cargo plane. Estimated termination costs for the C-
130J were high enough to reverse the initial decision, though these
estimates were still less than the contract price. Air Force officials
estimated that termination costs ranged from $450 million to $1.7
billion. The Department of Defense Inspector General reported that this
estimate may have been overstated. Nevertheless, the termination cost
estimate that the officials had at the time of their decision played a
key role in continuing the C-130J contract.
Terminating a Contract Generally Costs Less than Completing It:
It generally costs less to terminate a contract than to complete it.
When the government terminates a contract for convenience, it must
compensate the contractor in the form of a termination settlement,
which includes the costs of work performed and termination costs.
Settlements are typically less than the cost of completing a contract,
although in limited circumstances it could cost more to terminate than
to complete a contract. And while we found no examples in which it cost
more to terminate than to complete a contract, the timing of a
termination as well as contract specific factors may increase the
settlement amount.
A Termination Settlement Compensates the Contractor for Work Performed
and Termination Costs:
When the government decides to terminate a contract for convenience, it
must compensate the contractor fairly--in the form of a termination
settlement (hereafter referred to as a settlement)--for the work it has
performed.[Footnote 24] Settlements generally include three components:
incurred costs for the work performed, fee or profit on that work, and
termination costs.[Footnote 25] (See fig. 2.) Settlements only include
costs related to a terminated contract and therefore will not reflect
additional costs that may be a result of a termination, but outside the
scope of the contract, such as a larger community effect--for example,
a contractor going out of business.
Figure 2: Costs Included in the Total Settlement:
This figure is a chart showing costs included in the total settlement.
Termination costs: Expenses associated with terminating a contract,
such as preparing a settlement proposal, negotiating with
subcontractors, and disposing of inventory;
Fee/profit: Fee (for cost-type contracts) or profit (for fixed-price
contracts) for the work contractors perform;
Incurred cost: Cost of contractor work performed.
[See PDF for image]
Source: GAO analysis.
[End of figure]
The contractor's incurred costs include direct costs such as materials
and labor, as well as indirect costs such as overhead.[Footnote 26]
Factors that affect incurred costs include the amount of work performed
when the contract is terminated and the amount of materials purchased.
Contractors may choose to retain some of the materials they purchased
for a terminated contract and would then have to credit the government
for the value of the materials, thus reducing the total settlement
amount.
Figure:
Tri-Service Standoff Attack Missile (Air Force);
Prime contractor: Northrop Grumman Corp.;
Program started: 1986;
Contract began: 1986;
Contract price: $2,838,312,523;
Contract terminated: 1995;
Total settlement: $2,474,157,972.
(Photo not available)
The Tri-Service Standoff Attack Missile (TSSAM) program was an effort
to develop and acquire a conventional, medium-range cruise missile with
stealth capability. TSSAM was expected to be a low-cost cruise missile
able to deliver several different munitions at a standoff range of over
100 nautical miles. It was a tri-service development program with the
Air Force as the lead service. The program was marked by significant
technical problems, cost growth, and schedule delays. In 1994, DOD
restructured the TSSAM program after a series of flight test failures.
The Secretary of Defense directed the program‘s cancellation because
these technical problems and escalating costs persisted.
[End of figure]
In addition to incurred costs, contractors generally get paid a fee
(for cost-reimbursement contracts) or profit (for fixed-price
contracts) for the work they performed.[Footnote 27] Fee/profit under a
termination only applies to work the contractor performed and not to
any anticipated fee or profit for the terminated portions of the
contract. Moreover, for a fixed-price contract, if the contractor
spends more than the contract price, then the government is generally
only obligated to pay the contractor the contract price of the work
completed. For example, when the government terminated a fixed-price
contract for the Tri-Service Standoff Attack Missile (TSSAM), the
contractor claimed that it had spent about $3 billion on work that was
priced at $2.47 billion in the contract. Because the government stated
that the contractor would have been at a loss due to being over budget,
the contractor was not entitled to reimbursement for all of its
expenditures and lost more than $559 million.
The government also is required to pay contractors for termination
costs--the expenses associated with terminating a contract, such as
preparing a settlement proposal, negotiating with subcontractors, and
disposing of inventory.[Footnote 28] According to a DCMA official,
termination costs are not associated with performing the work under the
contract, but rather for ending the contract. Contractors are not
entitled to reimbursement for legal costs associated with challenging a
termination for convenience in court, although a contractor may be
reimbursed for legal costs arising from subcontractor suits.[Footnote
29]
A settlement only addresses the government's obligation under a
terminated contract. According to DOD officials, there may be
additional costs associated with a termination for convenience.
However, these costs are not included in the terminated contract's
settlement. Higher operations and maintenance costs for legacy systems
that would have been replaced, the costs of awarding a new contract to
replace a terminated contract, and economic impacts on communities
where terminated work was to be performed are examples of costs that
are outside the scope of a settlement, but could potentially result
from a termination for convenience.
When a termination is actually settled, the amount paid to the
contractor may be less than the settlement amount. A settlement is the
total amount the government must pay under a termination, which may be
viewed as the gross settlement. However, the government may have paid
for some of the work prior to termination. In such cases, the
government would only have to pay the net settlement amount, i.e., the
gross settlement amount less any payments made to date. For example,
incurred costs for the terminated Comanche contract were over $2.3
billion. However, the government had made progress payments over the
life of the Comanche contract, so the outstanding balance due at the
time of termination was only a fraction of the incurred costs. To pay
such outstanding balances, DOD uses the funding already available on
the contract.
Comanche (Army);
Prime contractor: Boeing Sikorsky;
Program started: 1983;
Last contract awarded: 2000;
Contract price: $6.59 billion;
Contract terminated: 2004;
Total settlement: $2.74 billion.
[See PDF for image]
Source: Boeing Sikorsky.
The Comanche was the Army's next- generation armed reconnaissance
helicopter, which would have supplied a system capable of operating in
adverse weather conditions across a wide spectrum of threat
environments. It was expected to provide lower operating costs as well
as improved speed, agility, reliability, and maintainability, and was
to be harder to detect than existing helicopters. The Comanche program
experienced substantial cost increases, schedule delays, and
performance shortfalls. The Army determined that the operating
environment had changed and that funds would be better spent on other
aviation priorities. The Comanche was estimated to cost $40 million per
aircraft whereas both the Kiowa Helicopter and the Armed Reconnaissance
Helicopter were estimated to cost $10 million each. When the Army
terminated the program, it transferred the Comanche‘s fly-by-wire
flight control system technology and 70,000 line items of property to
other Army aviation efforts.
[End of figure]
Settlements Are Generally Less than the Cost of Completing the
Contract:
In general, it will not cost more to terminate than to complete a
contract, whether it is a fixed-price contract or a cost-reimbursement
contract. The FAR places limits on the settlement amount in the event
of a termination for both types of contracts, although the limits are
different depending on the contract type.
Fixed-Price Contracts: It will generally not cost more to terminate
than to complete a fixed-price contract unless it is terminated late in
its life. Under the FAR, for fixed-price contracts, incurred costs plus
profit generally cannot exceed the contract price.[Footnote 30] As long
as termination costs are allowable, there is no specific dollar limit
on them. Thus, termination costs, when added to incurred costs and
profit, could push the settlement amount above the contract price,
depending on the value of the remaining work. As shown in figure 3
(case 1), if termination costs are less than the value of the remaining
work, it would cost less to terminate the contract than to complete it.
If termination costs are greater than the value of the remaining work,
then it would cost more to terminate the contract than to complete it,
as shown in figure 3 (case 2).[Footnote 31]
Figure 3: Termination Costs versus the Value of the Remaining Work:
This figure is a flowchart showing termination costs versus the value
of the remaining work.
[See PDF for image]
Source: GAO analysis.
[End of figure]
Termination costs are more likely to exceed the value of the remaining
work late in the life of a fixed-price contract because the
government's savings as a result of a termination (i.e., the value of
the remaining work) decrease over the life of a contract. For example,
if the contract is terminated after 30 percent of the costs under the
contract have been incurred, the government would save 70 percent of
the contract price (before accounting for termination costs). It would
only cost more to terminate the contract than to complete it if
termination costs were greater than 70 percent of the contract price.
Figure 4 shows that as the completed work increases, the potential cost
savings decrease. (Fig. 4 depicts the incurred costs and profit curve
as linear to illustrate these concepts, but may not reflect actual
incurred cost and profit curves. See app. I for further discussion of
how cost and profit curves affect settlements.) Of the contracts we
reviewed, the TSSAM had the highest termination costs, at $172 million,
or 6 percent of the contract price. However, the value of the remaining
work was over 13 percent of the contract price (over $384 million of
about $2.8 billion), so it cost less to terminate the TSSAM contract
than to complete it. In determining whether it would cost more to
terminate a contract than to complete it, we believe the value of the
termination costs does not matter as much as the ratio of termination
costs to the value of the remaining work.
Figure 4: Termination Costs versus the Value of Remaining Work for
Fixed-Price Contracts:
This figure is a flowchart showing termination costs versus the value
of remaining work for fixed-price contracts.
[See PDF for image]
Source: GAO analysis.
[End of figure]
Cost-reimbursement contracts: Cost-reimbursement contracts generally
would not cost more to terminate than to complete unless the government
authorized the contractor to exceed the estimated contract cost. For
fully funded cost-reimbursement contracts, the FAR's Limitation of Cost
clause provides that the government is not obligated to reimburse the
contractor in excess of the estimated cost of the contract.
Nevertheless, whether the clause's cost limitations act as a total cap
on the government's liability is sometimes determined on a case-by-case
basis by courts and agency boards which decide whether it is equitable
for the agency to provide funding over the estimated cost.[Footnote
32],[Footnote 33] For all fully funded cost-reimbursement contracts,
the Limitation of Cost clause requires the contractor to notify the
government in writing when the total estimated cost of performing the
contract, exclusive of any fee, will be greater than previously
estimated.[Footnote 34] The government then has a choice--it must
notify the contractor in writing that (1) it increased the estimated
contract cost (and obligated more money to the contract) or (2) the
contract will be terminated.[Footnote 35] If the contractor's incurred
costs are equal to the estimated contract cost, the contractor is not
obligated to perform any work to settle a termination (i.e., dispose of
inventory or negotiate with sub-contractors). The government would be
required to add additional funds to pay for termination costs before
directing the contractor to take actions to settle the
termination.[Footnote 36] Therefore, while the government is not
required to pay more under a cost-reimbursement contract than the
previously estimated contract cost, it may choose to do so when it is
in its best interest.[Footnote 37]
For the purposes of this review, we examined eight terminated contracts
of weapon systems whose contract price or estimated cost exceeded $100
million. While it is possible that a contract could cost more to
terminate than to complete, as shown in table 1, we did not find any
cases in which this occurred.
Table 1: Contracts Over $100 Million Terminated Since 1995:
Contract name: Comanche;
Contract type: Cost-reimbursement;
Contract price at time of termination: $6,586,200,000;
Total settlement: $2,739,126,125;
Amount contract price exceeded total settlement: $3,847,073,875.
Contract name: Tri-Service Standoff Attack Missile;
Contract type: Fixed-price;
Contract price at time of termination: $2,838,312,523;
Total settlement: $2,474,157,972;
Amount contract price exceeded total settlement: $364,154,551.
Contract name: Crusader;
Contract type: Cost-reimbursement;
Contract price at time of termination: $1,873,914,504;
Total settlement: $1,662,737,672;
Amount contract price exceeded total settlement: $211,176,832.
Contract name: B-1 B Defense Systems Upgrade Program;
Contract type: Cost-reimbursement;
Contract price at time of termination: $282,434,749;
Total settlement: $257,900,000;
Amount contract price exceeded total settlement: $24,534,749.
Contract name: Tomahawk Baseline Improvement Program;
Contract type: Cost-reimbursement;
Contract price at time of termination: $239,676,147;
Total settlement: $230,540,804;
Amount contract price exceeded total settlement: $9,135,343.
Contract name: Space and Missile Tracking System Low Earth Orbit;
Contract type: Cost-reimbursement;
Contract price at time of termination: $204,292,000;
Total settlement: $203,227,527;
Amount contract price exceeded total settlement: $1,064,473.
Contract name: Smart Target Activated Fire and Forget;
Contract type: Cost-reimbursement;
Contract price at time of termination: $162,781,580;
Total settlement: $156,808,356;
Amount contract price exceeded total settlement: $5,973,224.
Contract name: Land Warrior;
Contract type: Cost-reimbursement;
Contract price at time of termination: $133,559,667;
Total settlement: $121,991,538;
Amount contract price exceeded total settlement: $11,568,129.
Source: GAO analysis of data from DCMA's Termination Center and the
Army.
Note: The contract price for the Space and Missile Tracking System Low
Earth Orbit at the time of termination was unavailable. This figure
represents the contract price of items terminated.
[End of table]
Some Factors May Increase Settlement Amounts:
Although we found that it generally does not cost more to terminate a
contract than to complete it, factors such as the timing of a
termination, how costs are incurred over the life of a contract, and
the cost of disposing of inventory and negotiating with subcontractors
could result in higher settlements. Settlements tend to be lower if a
contract is terminated sooner rather than later because incurred costs
increase over time. (See app. I for further discussion of this topic.)
In addition, any contract in which costs are incurred sooner rather
than later could potentially increase the settlement amount in the
event of a termination. Multiyear contracts, for example, allow
contractors to enter into contracts for a period of up to 5 years so
that they can purchase more than 1 year's worth of equipment for
materials from their suppliers. This could result in savings with
regard to the total estimated cost of carrying out the program if the
contract is completed, but may also result in higher incurred costs if
the contract is terminated. For example, if the contractor bought all
the materials for a 5-year multiyear contract at the beginning of the
contract and the contract was terminated after the second year, the
government would have to reimburse the contractor for 3 years' worth of
materials that it no longer needed. By shifting costs from the fourth
or fifth year to the first year, a multiyear contract may result in
higher termination settlements than a series of annual contracts.
Finally, termination costs are driven in part by the cost of disposing
of inventory and settlement negotiations, including those between the
prime contractor and subcontractors. Therefore, a large amount of
inventory or large number of subcontractors could result in higher
termination costs, because of the increased time it could take to
finalize a settlement for each of those situations. In addition, other
factors such as the complexity of the actual service or product may
also play a role. For example, as a DOD official stated, disposing of a
small amount of classified stealth material may cost more because
classified materials have to be protected and destroyed.
DOD Has Options for Retaining Value or Reducing Costs when Programs Are
Canceled or Contracts Are Terminated:
When a line of work ends by either a program cancellation or a contract
termination, DOD may be able to recover useful items of value that can
be used on other DOD efforts. Furthermore, the way in which the work
ends may affect the value of what DOD is able to recover. The
government must decide whether it is in its best interest to complete a
contract, or terminate it and transfer technology, information, and
property to other DOD programs. For example, both the Comanche and
Crusader were canceled programs in which DOD had invested billions of
dollars. Yet following each of those cancellations, the government was
able to transfer significant amounts of technology and property from
those programs to other DOD programs.
Figure:
E-10A (Air Force);
Prime contractor: Northrup Grumman Corp.;
Program started: 2003;
Program canceled: 2007;
Estimated program cost: $1.61 to $1.74 billion[A];
[See PDF for image]
Source: Northrup Grumman Corp.
[End of table]
The E-10A was a plane equipped with radar that was intended to provide
next-generation air and ground moving target detection capabilities and
an imaging capability for surface surveillance. Through a DOD program
budget decision, the budget was restructured and the program was
canceled. However, none of the contracts associated with the program
were terminated. The Air Force plans to complete the commercial-item,
fixed-price contract to obtain the plane. The Air Force also descoped
and continued acquisition of the radar under a modified contract for
use on the Global Hawk. The contract to integrate the radar and the
plane was discontinued at the end of the period of performance.
[A] Program officials were unable to give an exact value because the
radar contract included funding for a variant to be used on another
system, the Global Hawk.
[End of figure]
DOD Can Complete the Original Contract or Modify It: When a contract is
nearly complete, it may be in the government's best interest to
complete it rather than terminate it, even when the associated program
has been canceled. For example, when DOD canceled the E-10A program,
Air Force officials examined the program in order to determine how to
most effectively end work on the program's various contracts. Under the
E-10A program, the Air Force had entered into a commercial-item, fixed-
price contract to purchase a plane and a separate cost-reimbursement
contract for the radar. Air Force officials decided to complete the
contract for the plane by making one final payment to take delivery of
it. Had the Air Force terminated this commercial contract, it would
have received nothing of value in return.[Footnote 38] In addition, the
Air Force decided not to terminate the radar contract, but to descope
it and continue it under a modified contract.
Figure:
Littoral Combat Ship (Navy);
The Littoral Combat Ship (LCS) is designed to counter threats from
mines, submarines, and surface craft in shallow water, where there is
currently a capability gap. The LCS program has experienced substantial
design changes, schedule delays, and cost growth. The Navy anticipates
LCS-1 and LCS-2 to exceed their combined budget of $472 million by more
than 100 percent and anticipates lead ship delivery to occur
approximately 18 months later than initially planned. Due to these
challenges, the Navy stopped construction of the LCS-3 and LCS-4 after
failing to reach agreement with the prime contractors to modify the
existing cost-reimbursement contracts to fixed-price contracts. Because
a significant amount of work on the gears and gas turbines on LCS-3 had
been completed, the Navy completed work on these items for use on other
ships.
[See PDF for image]
Source: U.S. Government.
[End of table]
DOD Can Terminate a Contract and Transfer Technology or Property: When
a contract is terminated, DOD can take steps to retain value by
transferring technology, information, and property to a new or ongoing
program. For example, in the wake of the Crusader termination, the Army
transferred almost 26,000 inventory line items (valued at more than
$150 million) from the Crusader to create the Non-Line-of-Sight-Cannon
(NLOS-C) program. According to one Army official, the technology
transfer also preserved DOD's technical and scientific expertise in its
armored community. Moreover, an additional 9,800 inventory line items
from the Crusader program, valued at $25.8 million, were transferred to
the NLOS-C program. When the Army terminated the Comanche helicopter
program, it transferred the Comanche's fly-by-wire flight control
system technology and 70,000 line items of property to other DOD
programs as a way to retain value for work performed as well as lower
termination costs. Overall, the Army was able to reutilize more than 60
percent of the Comanche's property, valued at more than $360 million.
DOD Can Terminate a Contract and Continue Limited Work: If a contract
is terminated, it may also be in the government's best interest to
continue a limited amount of work on a line item of a terminated
contract to complete technology or items for future use. For example,
following the termination of the LCS-3, Navy officials told us that a
significant amount of work on the gears and gas turbines, among other
items, had been completed. As a result, the Navy decided to complete
work on those line items of the terminated contract for use on other
ships.
Conclusions:
Past experience with terminations highlights important lessons for DOD
in making decisions to cancel individual programs as well as in
managing its broader investment portfolio. When considering
cancellation of individual programs, defense stakeholders have
sometimes expressed concerns that it will cost more to terminate a
contract than to complete it. Among the contracts that we reviewed, we
did not find evidence to support this contention. Moreover, none of the
DOD officials with whom we spoke identified a contract that cost more
to terminate than complete. Accordingly, contract termination costs are
generally not a compelling reason to continue programs or contracts
that otherwise warrant ending. In addition, while incurred or "sunk"
costs in programs being considered for termination may be substantial,
they must be paid regardless of whether or not a contract is
terminated. Therefore, the decision to terminate a contract or cancel a
program should not be driven by sunk costs. Lastly, when a contract
warrants termination, the decision should be made as soon as possible
because delaying a termination almost always results in higher
settlement costs to the government.
From an investment portfolio perspective, terminations can be a
valuable tool in responding to long-term fiscal imbalances as well as
unexpected threats and other events that could constrain spending.
While not a substitute for sound upfront investment decisions,
terminations can create more trade space in the more than $850 billion
that still remains in outstanding commitments in DOD's planned $1.6
trillion investment in weapons programs. However, to make the most
effective use of this tool, decision-makers need to be able to
anticipate and plan for possible terminations and have a sound
understanding of costs, benefits, and legal requirements. As a result,
guidance on terminations developed by the military services and other
DOD entities, should be clear, consistent, proactive, and detailed
enough to provide the knowledge needed to use terminations as an
investment portfolio tool.
Recommendation:
GAO recommends that DOD review, and as needed amend, guidance on
terminations across the military services and DOD entities to ensure
that termination guidance consistently identifies the conditions under
which it is appropriate to end programs or contracts, and provides
knowledge needed to use terminations as an investment portfolio tool.
Agency Comments and Our Evaluation:
DOD provided us with written comments on a draft of this report. The
comments appear in appendix II. DOD also provided one technical
comment, which we incorporated in this report.
DOD concurred with our recommendation to review, and amend as needed,
guidance on contract terminations for convenience across the military
services and DOD. This is a positive step toward using terminations as
an investment portfolio tool.
We are sending copies of this report to the Secretary of Defense and
other appropriate congressional committees. We will also make copies
available to others upon request. In addition, the report will be
available at no charge on GAO's Web site at [hyperlink,
http://www.gao.gov].
Should you or your staff have any questions about matters discussed in
this report, please contact me at (202) 512-4841 or chaplainc@gao.gov.
Contact points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. GAO staff who
made major contributions to this report are listed in appendix III.
Signed by:
Cristina Chaplain:
Director, Acquisition and Sourcing Management:
List of Committees:
The Honorable Carl Levin:
Chairman:
The Honorable John McCain:
Ranking Member:
Committee on Armed Services:
United States Senate:
The Honorable Daniel K. Inouye:
Chairman:
The Honorable Ted Stevens:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
United States Senate:
The Honorable Ike Skelton:
Chairman:
The Honorable Duncan L. Hunter:
Ranking Member:
Committee on Armed Services:
House of Representatives:
The Honorable John P. Murtha:
Chairman:
The Honorable C.W. Bill Young:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
House of Representatives:
[End of section]
Appendix I: Termination Costs and Settlement Amounts:
In general, terminating a contract sooner will result in a lower
settlement amount than terminating later, and eventually it will cost
more to terminate than to complete a contract. How contract costs are
spread out over the life of the contract will vary from one contract to
another, as will termination costs. That variation in the timing and
amount of costs could have important implications for termination
settlement amounts. It will also determine the point at which it would
be more cost-effective for the government to complete a contract rather
than terminate it. This appendix will graphically illustrate these
points.
Components of a Termination for Convenience:
Figure 5 illustrates the components of a settlement for a hypothetical
contract termination for convenience. The settlement is the sum of the
contract costs (contractor's incurred costs for work performed and fee/
profit on that work) and termination costs. To start our discussion,
the cost curves are depicted as linear for the sake of simplicity. This
means that contract costs (5A) are assumed to increase at a constant
rate over the life of the contract, and termination costs (5B) are
assumed to be constant over the life of the contract. The settlement is
the sum of the contract costs and termination costs as shown in figure
5C. Changing either of the components will alter the settlement amount.
Figure 5: Components of a Settlement:
This figure is a combination of line graphs showing the components of a
settlement. Time is the X axis, and Cost is the Y axis. Contract costs
are increasing over time, termination costs are staying the same, and
total settlement is increasing over time.
[See PDF for image]
Source: GAO analysis.
[End of figure]
Contract Costs:
Figure 5 depicts linear contract cost curves. Although we do not know
the shape of the contract cost curves for the contracts we reviewed or
for defense contracts in general, they probably fluctuate from one
period to the next and may resemble some form of the S curves in figure
6.[Footnote 39] The shape of the curves in figure 6 illustrates how the
cost of work, which presumably is driven by the amount and type of
work, can change over the life of a contract. In figure 6, the total
cost is the same for both curves.[Footnote 40] How that cost is spread
out over the life of the contract can vary dramatically, as is depicted
by the two curves in figure 6. At any given point, the contract costs
(and ultimately the settlement) could be higher or lower depending on
the shape of the curve. For example, if the contracts depicted in
figure 6 were terminated early in the life of the contracts (time T1),
contract costs would be lower under curve A than under curve B.
Alternatively, contract costs would be higher under curve A if the
contract were terminated later in the life of the contract (time
T2).[Footnote 41]
Figure 6: Two Possible Contract Cost Curves:
This figure is a line graph showing two possible contract cost curves.
Time is the X axis, and the Y axis represents cost.
[See PDF for image]
Source: GAO analysis.
[End of figure]
How Timing of a Termination May Affect the Settlement:
Contract costs will typically be less if a contract is terminated
sooner rather than later, but the cost of delaying a termination will
be greater in some cases than in others. For example, as depicted in
Figure 3, if a termination decision is delayed over a steep portion of
the curve, the delay will result in much higher costs (i.e., delaying
from T1 to T2 results in an increase in costs from C1 to C2). If the
decision is delayed over a flatter portion of the curve, the delay will
result in higher costs, but only marginally higher (i.e., delaying from
T2 to T3 results in an increase in costs from C2 to C3). This would be
important to know if DOD was considering a termination, but had not yet
made a final decision.
Figure 7: Cost Implications of Delaying a Termination Decision:
This figure is line graph showing the cost implications of delaying a
termination decision. Time is the X axis, and cost is the Y axis.
[See PDF for image]
Source: GAO analysis.
[End of figure]
Termination Costs:
Like contract costs, it is unlikely that termination costs would be
linear, although we do not know the shape of the termination cost
curves for the contracts we reviewed or for defense contracts in
general. Unlike contract costs, termination costs could go down at
different points in the contract. Termination costs can be driven by a
variety of factors such as negotiating with subcontractors and the cost
of disposing of inventory. Thus, when the contractor purchases
materials or issues a subcontract, termination costs would likely go
up. Alternatively, if the subcontractor completes its contract before a
termination, the prime contractor would not have to negotiate with a
subcontractor. Thus, termination costs could increase early in the
contract and decrease towards the end of the contract.
In theory, if termination costs dropped enough over a short period of
time, the settlement amount could go down, at least temporarily. A
settlement consists of the contract costs and the termination costs.
Contract costs always go up over time, but if they were increasing at a
slow rate and a large subcontractor completed its work, resulting in a
significant drop in termination costs, the sum of the two could
actually be less than the settlement amount for the period before the
subcontractor completed its work. However, as work continues, contract
costs would continue to increase. Therefore, the settlement would go up
again.
The Break-Even Point:
Delaying a termination decision will generally result in higher
settlement amounts, and at some point the settlement will exceed the
contract price. There is a break-even point at which it would cost the
same to terminate a contract as to complete it. Terminating before that
point would cost less than completing the contract and terminating
after that point would cost more. Figure 8 shows that the break-even
point is determined by contract costs, termination costs, and the
contract price. The contract price is the amount a contractor would be
paid if a contract is completed. At any point in the life of the
contract, the government would have to pay for the work performed up to
that point regardless of whether the contract is completed or
terminated. In the event of a termination, the government would not
have to pay for work the contractor did not perform, so the value of
unperformed work represents the cost of completing the
contract.[Footnote 42] We refer to the cost of completing the contract
as the value of the remaining work. The break-even point is where the
settlement amount is equal to the contract price. It is also where the
value of the remaining work (the contract price less contract costs) is
equal to termination costs. Changing the shape of the contract cost
curve or the termination cost curve could shift when the break-even
point occurs.
Figure 8: The Break-Even Point:
This figure is a line graph showing the break-even point. Work
represent the X axis, and dollars represent the Y axis.
[See PDF for image]
Source: GAO analysis.
[End of figure]
We do not know where the break-even point occurred for the contracts we
reviewed. However, the termination costs we observed were relatively
low compared to the contract price (or estimated contract price). This
suggests that the break-even point for the contracts we reviewed would
have occurred toward the end of the contract, at least in terms of
costs. For example, termination costs for the TSSAM contract were 6
percent of the contract price. The break-even point would occur where
contract costs reached 94 percent of the contract price.
[End of section]
Appendix II Comments from the Department of Defense:
Office Of The Under Secretary Of Defense:
3000 Defense Pentagon:
Washington, DC 20301-3000:
Acquisition Technology And Logistics:
March 12, 2008:
Ms. Cristina T. Chaplain:
Director, Acquisition and Sourcing Management:
U.S. Government Accountability Office:
441 G Street, N.W.:
Washington, D.C. 20548
Dear Ms. Chaplain:
This is the Department of Defense (DoD) response to the GAO draft
report GAO- 08-379, `Defense Acquisitions: Termination Costs Are
Generally Not a Compelling Reason to Continue Programs or Contracts
That Otherwise Warrant Ending,' dated February 11, 2008, (GAO Code
120599). Detail comments on the report recommendations are enclosed.
Sincerely,
Signed by:
Shay D. Assad:
Director, Defense Procurement and Acquisition Policy:
Enclosure:
As stated:
GAO Draft Report Dated February 11, 2008 GAO-08-379 (GAO CODE 120599)
"Defense Acquisitions: Termination Costs Are Generally Not A Compelling
Reason To Continue Programs Or Contracts That Otherwise Warrant
Ending":
Department Of Defense Comments To The Gao Recommendations:
Recommendation 1: The GAO recommends that DoD review, and as needed,
amend guidance on terminations across the military services and DoD
entities to ensure that termination guidance consistently identifies
the conditions under which it is appropriate to end programs or
contracts, and provides knowledge needed to use terminations as an
investment portfolio tool. (Page 23/GAO Draft Report)
DOD Response: DoD concurs with the recommendation with comment. DPAP
will review, and amend as needed, current guidance on terminations to
ensure that termination guidance consistently identifies the conditions
under which it is appropriate to end programs or contracts, and
provides knowledge needed to use terminations as an investment
portfolio tool.
[End of section]
Appendix III GAO Contact and Staff Acknowledgments:
GAO Contact:
Cristina Chaplain (202) 512-4841 or chaplainc@gao.gov:
Acknowledgments:
In addition to the contact named above, Carol Dawn Petersen, Assistant
Director; E. Brandon Booth; James Kim; Anne McDonough-Hughes; Marcus
Lloyd Oliver; Kenneth Patton; Charles Perdue; Kelly A. Richburg; Sylvia
Schatz; and Ann Marie Udale made key contributions to this report.
[End of section]
Footnotes:
[1] At DOD, when a procuring activity decides to terminate a contract
for convenience, although it is not required to do so, it may employ
the assistance of the termination contracting officers at the DCMA
Terminations Center. In the case of the Comanche helicopter, the
termination was handled by the Army.
[2] FAR 49.207 and 52.249-2(f).
[3] Programs are efforts to provide a new, improved, or continuing
material, weapon or information system, or service capability in
response to an approved need rather than a legal agreement. DOD
Directive 5000.1.
[4] A cost is only allowable when the cost complies with all of the
following requirements: that the cost is reasonable, allocable, it
meets cost accounting standards (if applicable), the terms of the
contract, and applicable FAR provisions. FAR 31.201-2.
[5] For information on the use of award fees, see GAO reports GAO-07-58
NASA Procurement: Use of Award Fees for Achieving Program Outcomes
Should Be Improved (January 17, 2007) and GAO-06-66 Defense
Acquisitions: DOD Has Paid Billions in Award and Incentive Fees
Regardless of Acquisition Outcomes (December 19, 2005).
[6] termination for convenience only has to be in the government's
interest. See generally, FAR 52.249-2; 52.249-6.
[7] Since default terminations involve serious consequences for a
contractor, they are considered drastic sanctions that should be
imposed or sustained only for good grounds and on solid evidence. The
government bears the burden of proving the termination was justified.
For example, see Lisbon Contractors, Inc. v. U.S., 828 F.2d 759, 765
(Fed. Cir. 1987).
[8] FAR subpart 49.501.
[9] For cost-reimbursement contracts, a single clause under FAR 52.249-
6 is used for both default and convenience terminations.
[10] FAR Part 49.
[11] FAR 49.102(a).
[12] FAR 49.206-3. For commercial-item contracts, the government has no
claim to any work in progress.
[13] FAR 49.303-2.
[14] FAR 49.104(i).
[15] FAR 49.104(g).
[16] FAR 49.206-1(a) and 49.303-1.
[17] FAR 52.249-2 (fixed-price contracts) and FAR 52.249-6 (cost-
reimbursement contracts).
[18] FAR 49.105.
[19] FAR 49.109-7(f).
[20] Appeals for contracts with the Department of Defense are filed
with the Armed Services Board of Contract Appeals.
[21] FAR 52.249-2(j) and 52.249-6(j).
[22] Comparable data for civilian agencies of contracts terminated for
convenience are not readily available.
[23] The terminated LCS-3 and LCS-4 ships were partial terminations, as
they were line items under the same contracts as LCS-1 and LCS-2,
respectively.
[24] FAR 49.201.
[25] For the purposes of this report, fee is for cost-reimbursement
contracts whereas profit is for fixed-price contracts.
[26] For the purposes of this report, incurred costs are all allowable
costs under the contract defined under FAR §31.2 except for settlement
expenses as described in FAR §31.205-42(g). Incurred costs would
include the contractor's allowable costs prior to termination as well
as reasonable costs continuing after termination.
[27] Fixed-price contracts are not generally divided into incurred
costs and profit. When a fixed-price contract is terminated, it is
treated in some respects like a cost-reimbursement contract. For
example, the contractor has to determine its incurred costs under the
terminated contract and determine what, if any, profit it earned on its
incurred costs. The contractor would not typically have to do this
under a fixed-price contract that had been completed.
[28] We use the term termination costs rather than settlement expenses
to avoid confusion between termination settlements in general and the
cost of settling a termination (i.e., termination costs). Our
definition of termination costs is narrower than the FAR definition
because we only consider those costs that are unique to a termination
under FAR 31.205-42 (g).
[29] The costs of preparing a settlement proposal by an attorney are
allowable termination costs for which the contractor would be
reimbursed.
[30] FAR 49.207; see also FAR 52.249-2(f), which states that the total
contract price is reduced by (1) the amount of payments previously made
and (2) the contract price of work not terminated.
[31] For terminations lasting more than a year, the time value of money
would also have to be considered in determining whether it costs more
to terminate than to complete a contract.
[32] The FAR's Limitation of Funds clause (FAR 52.232-22) applies to
incrementally funded cost-reimbursement contracts. It is similar to the
Limitation of Cost clause, but limits the government's contractual
liability to the amount of funding available on a contract, which may
be less than the estimated contract cost.
[33] The Limitation of Cost clause will not apply when the contractor
could not have reasonably foreseen the cost overrun. RMI, Inc. v. U.S.
800 F.2d 246 (Fed. Cir. 1986).
[34] The contractor is also required to notify the government in
writing when the contractor has reason to believe that the costs it
will incur in the next 60 days, when added to all previously incurred
costs, will exceed 75 percent of the estimated contract price or when
the estimated contract cost is substantially less than previously
estimated.
[35] Other options include notifying the contractor in writing that (1)
the contract will no longer be funded and the contractor should submit
its proposal for a fee adjustment, as applicable; or (2) the government
is considering whether to allot additional funds or to increase the
estimated cost.
[36] FAR 32.704(b) states, in part: Under a cost-reimbursement
contract, the contracting officer may issue a termination notice
without immediately increasing the funds available. Since a contractor
is not obligated to incur costs in excess of the estimated cost in the
contract, the contracting officer shall ensure availability of funds
for directed actions.
[37] However, contracting officers cannot abuse their discretion in
failing to fund overruns, since they will be found to have breached
their implied contractual duty of good faith and fair dealing. See
generally, Nash Janitorial Serv., Inc., GSBCA 6390, 84-1 BCA 17,135 at
85,370.
[38] If a contract for commercial items is terminated for the
government's convenience, any uncompleted inventory belongs to the
contractor.
[39] Contract cost curve A in figure 7 resembles the shape of the
Actual Cost of Work Performed curves in DOD's earned value management
literature, whereas curve B resembles total cost curves in
microeconomic theory. One possible explanation for the difference in
the two curves is that microeconomics generally focuses on production,
whereas earned value management applies to a single contract that may
cover only one phase of development or production.
[40] In practice, the sequencing of the work and when costs are
incurred will affect the contract cost curve. There may be a number of
ways to structure a contract to accomplish a given amount of work, some
that are more efficient and cost-effective than others. The most cost-
effective way to complete a contract may not necessarily result in the
lowest termination settlement amount.
[41] Any contract in which costs are incurred sooner rather than later
could potentially increase a settlement amount in the event of a
termination. For example, multiyear contracts allow contractors to
engage in contracts up to five years so that they can purchase more
than one year's worth of equipment or materials from their suppliers.
This could result in savings with regard to the total estimated cost of
carrying out the program if the contract is completed, but may also
result in higher incurred costs if the contract is terminated. For
example, if the contractor bought all the materials for a 5-year
multiyear contract at the beginning of the contract and the contract
was terminated after the second year, the government would have to
reimburse the contractor for 3 years' worth of materials that it no
longer needed. By shifting costs from the fourth or fifth year to the
first year, a multiyear contract may result in higher termination
settlements than a series of annual contracts.
[42] To determine whether it would cost more to terminate than to
complete a contract, we would compare the unique costs of each course
of action. The value of the remaining work is the unique cost of
completing the contract, whereas termination costs are the unique costs
of terminating a contract. For terminations lasting more than a year,
the time value of money would also have to be considered in determining
whether it costs more to terminate than to complete a contract.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "Subscribe to Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: