Defense Acquisitions
Assessment of Progress Made on Block 2006 Missile Defense Capabilities and Oversight
Gao ID: GAO-08-608T April 1, 2008
Funded at $8 billion to nearly $10 billion per year, the Missile Defense Agency's (MDA) effort to develop and field a Ballistic Missile Defense System (BMDS) is the largest research and development program in the Department of Defense (DOD). The program has been managed in 2-year increments, known as blocks. Block 2006, the second BMDS block, was completed in December 2007. By law, GAO annually assesses MDA's progress. This testimony is based on GAO's March 2008 report that addressed MDA's progress in (1) meeting Block 2006 goals for fielding assets, completing work within estimated cost, conducting tests, and demonstrating the performance of the overall system in the field, and (2) making managerial improvements to transparency, accountability, and oversight. GAO reviewed the assets fielded; contractor cost, schedule, and performance; and tests completed during 2007. GAO also reviewed pertinent sections of the U.S. Code, acquisition policy, and the charter of a new missile defense board.
In the past year, MDA has fielded additional and new assets, enhanced the capability of some existing assets, and achieved most test objectives. MDA did not meet the goals it originally set for the block. Ultimately, MDA fielded fewer assets, increased costs by about $1 billion and conducted fewer tests. Even with the cost increase, MDA deferred work to keep costs from increasing further, as some contractors overran their fiscal year 2007 budgets. Deferring work obscures the cost of the block because such work is no longer counted as part of Block 2006. The cost of the block may have been further obscured by a way of planning work used by several contractors that could underestimate the actual work completed. If more work has to be done, MDA could incur additional costs that are not yet recognized. MDA also sets goals for determining the overall performance of the BMDS. Similar to other DOD programs, MDA uses models and simulations to predict BMDS performance. GAO was unable to assess whether MDA met its overall performance goal because there have not been enough flight tests to provide a high confidence that the models and simulations accurately predict BMDS performance. Moreover, the tests that have been done do not provide enough information for DOD's independent test organization to fully assess the BMDS' suitability and effectiveness. GAO has previously reported that MDA has been given unprecedented funding and decision-making flexibility. While this flexibility has expedited BMDS fielding, it has also made MDA less accountable and transparent in its decisions than other major programs, making oversight more challenging. MDA, with some direction from Congress, has taken significant steps to address these concerns. MDA implemented a new way of defining blocks--its construct for developing and fielding BMDS increments--that should make costs more transparent. For example, under the newly-defined blocks, MDA will no longer defer work from one block to another. Accountability should also be improved as MDA will, for the first time, estimate unit costs for selected assets and report variances from those estimates. DOD also chartered a new executive board with more BMDS oversight responsibility than its predecessor. Finally, MDA will begin buying certain assets with procurement funds like other programs. This will benefit transparency and accountability, because to use procurement funding generally means that assets must be fully paid for in the year they are bought. Previously, Congress authorized MDA to pay for assets incrementally using research and development funds. Some oversight concerns remain, however. For example, MDA has not yet estimated the total cost of a block, and therefore, cannot have a block's costs independently verified--actions required of other programs to inform decisions about affordability and investment choices. However, MDA does plan to estimate block costs and have them verified at some future date. Also, the executive board faces a challenge in overseeing MDA's large technology development efforts and does not have approval authority for some key decisions made by MDA.
GAO-08-608T, Defense Acquisitions: Assessment of Progress Made on Block 2006 Missile Defense Capabilities and Oversight
This is the accessible text file for GAO report number GAO-08-608T
entitled 'Defense Acquisitions: Assessment of Progress Made on Block
2006 Missile Defense Capabilities and Oversight' which was released on
April 2, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony before the Subcommittee on Strategic Forces, Committee on
Armed Services, U.S. Senate:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 2:30 p.m. EDT:
Tuesday, April 1, 2008:
Defense Acquisitions:
Assessment of Progress Made on Block 2006 Missile Defense Capabilities
and Oversight:
Statement of Paul Francis, Director, Acquisition and Sourcing
Management:
GAO-08-608T:
Mr. Chairman and Members of the Subcommittee:
I am pleased to be here today to discuss the Missile Defense Agency's
(MDA's) strategy for acquiring a Ballistic Missile Defense System
(BMDS) and its progress in fielding Block 2006--its second increment of
capability.
MDA has been charged with developing and fielding the BMDS, a system
expected to be capable of defending the United States, deployed troops,
friends, and allies against ballistic missiles of all ranges in all
phases of flight. In fulfilling this charge, MDA placed an initial set
of missile defense components in the field in December 2005. These
components are collectively referred to as Block 2004. Recently, MDA
delivered its second increment of capability--Block 2006--which
includes additional components as well as performance enhancements.
The National Defense Authorization Acts for fiscal years 2002 and 2006
mandated that we prepare annual assessments of MDA's ongoing cost,
schedule, testing, and performance progress. In March 2008, we issued
our report covering MDA's progress toward achieving Block 2006 goals
during fiscal year 2007 as well as its efforts to improve transparency,
accountability, and oversight. My statement today will focus on the
issues covered in that report. We conducted this performance audit from
May 2007 to March 2008 in accordance with generally accepted government
auditing standards. Those standards require that we plan and perform
the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a reasonable
basis for our findings and conclusions based on our audit objectives.
Summary:
During Block 2006, MDA fielded additional and new assets, enhanced the
capability of some existing assets, and achieved most test objectives.
In short, MDA increased BMDS capability. However, MDA did not meet the
goals it originally set for the block. Ultimately, MDA fielded fewer
assets, increased costs by about $1 billion, and conducted fewer tests.
Even with the cost increase, MDA deferred work to keep Block 2006 costs
from increasing further, as some contractors overran their fiscal year
2007 budgets. We could not determine the full cost of the block as
deferred work is no longer counted as part of the block. Further,
several BMDS contractors plan work in such a way that could result in
MDA incurring costs that are not yet recognized. We could not assess
attainment of another MDA goal: the overall performance of fielded
assets as an integrated BMDS. This is because (1) there have not been
enough flight tests to validate the models and simulations that are
used to predict system-level performance, (2) the reliability of some
interceptors could be affected by problematic parts that have not been
replaced yet, and (3) tests done to date do not provide enough
information for DOD's operational test and evaluation Director to fully
determine if the BMDS is suitable and effective for battle.
MDA has been given unprecedented funding and decision-making
flexibility that has expedited the fielding of assets but also lessened
the transparency and accountability provided for oversight. In the past
year, MDA has taken significant actions to improve oversight. First,
MDA has adopted a new block approach that offers several improvements-
-unit costs for selected assets will now be tracked and work will no
longer be deferred from one block to another. Second, DOD has
established an executive board to review and make recommendations on
MDA's acquisition strategy, plans, and funding that could play a more
significant role than its predecessor. Third, Congress directed that
MDA begin using procurement funds to purchase certain assets, which
generally means they must be fully paid for in the year they are
bought. Previously, using research and development funding, MDA could
pay for assets over several years, making it difficult to determine
their cost. Some oversight concerns remain, however. For example,
although MDA plans to do so, it has not yet estimated the total cost of
any block, therefore it cannot have block costs independently verified,
as is done for other major programs. While the new executive board
promises to be more substantive than the previous Missile Defense
Support Group, it will not have the information--such as on cost
estimates and operational testing--to provide the oversight the Defense
Acquisition Board provides on other major programs. The new board, like
its predecessor, does not have approval authority. The executive board
also faces the unique challenge of evaluating technology development
efforts that range from $2 billion to about $5 billion a year--efforts
that normally do not have a firm cost, schedule, and performance
baseline.
We have previously made recommendations to improve oversight in the
areas that MDA has recently taken action. In March 2008, we also made
recommendations to build on the actions already taken to further
improve the transparency of block costs and oversight of the BMDS
program. These included having MDA develop a full cost estimate for
each block of BMDS capability with verification of that estimate, and
examine ways to develop a baseline or some other standard against which
the progress of technology programs may be assessed. We also
recommended that MDA and the Director of Operational Test and
Evaluation agree on criteria and incorporate corresponding scope into
developmental tests that will allow a determination of whether a block
of BMDS capability is suitable and effective for fielding. DOD
concurred with having MDA develop block cost estimates and obtaining
independent verification of those estimates. DOD partially concurred
with the recommendations regarding examining ways to measure the
progress of technology programs and adding scope to developmental
tests.
Background:
Funded at $8 billion to nearly $10 billion annually, MDA's BMDS is the
largest research development program in DOD's budget. Since the 1980s,
DOD has spent more that $100 billion to develop and field the BMDS and
it estimates that continued development and fielding will require an
additional $50 billion between fiscal years 2008 and 2013.
Since 2002, MDA has worked to fulfill its mission through its
development and fielding of a diverse collection of land-, air-, sea-,
and space-based assets. These assets are developed and fielded through
nine BMDS elements and include the Airborne Laser (ABL); Aegis
Ballistic Missile Defense (Aegis BMD); BMDS Sensors; Command, Control,
Battle Management, and Communications (C2BMC); Ground-based Midcourse
Defense (GMD); Kinetic Energy Interceptors (KEI); Multiple Kill
Vehicles (MKV); Space Tracking and Surveillance System (STSS); and
Terminal High Altitude Area Defense (THAAD).[Footnote 1]
To develop a system capable of carrying out its mission, MDA, until
December 2007, executed an acquisition strategy in which the
development of missile defense capabilities was organized in 2-year
increments known as blocks. Each block was intended to provide
capabilities that enhanced the development and overall performance of
the BMDS. The first 2-year block, known as Block 2004, fielded a
limited initial capability that included early versions of the GMD,
Aegis BMD, Patriot Advanced Capability-3, and C2BMC elements. The
agency's second 2-year block--Block 2006--culminated on December 31,
2007 and fielded additional BMDS assets. This block also provided
improved GMD interceptors, enhanced Aegis BMD missiles, upgraded Aegis
BMD ships, a Forward-Based X-Band-Transportable radar, and enhancements
to C2BMC software. In December 2007, MDA's Director approved a new
block construct that will be the basis for all future development and
fielding, which I will discuss in more detail shortly.
To assess progress during Block 2006, we examined the accomplishments
of nine BMDS elements that MDA is developing and fielding. Our work
included examining documents such as Program Execution Reviews, test
plans and reports, production plans, and Contract Performance Reports.
We also interviewed officials within each element program office and
within MDA functional directorates. In addition, we discussed each
element's test program and its results with DOD's Office of the
Director, Operational Test and Evaluation. Regarding transparency,
accountability, and oversight, we held discussions with officials in
MDA's Directorate of Business Operations to determine whether its new
block structure improved accountability and transparency of the BMDS.
In addition, we reviewed pertinent sections of the U.S. Code to compare
MDA's current level of accountability with federal acquisition laws. We
also interviewed officials from the Office of the Under Secretary of
Defense for Acquisition, Technology, and Logistics and DOD's Joint
Staff to discuss the oversight role of the new Missile Defense
Executive Board (MDEB). Additionally, we reviewed the MDEB charter to
identify the oversight responsibility of the board.
Fielded Capability Increased, but Less than Planned at Higher Cost:
MDA made progress in developing and fielding the BMDS during 2007.
Additional assets were fielded and/or upgraded, several tests met
planned objectives, and other development activities were conducted. On
the other hand, fewer assets were fielded than originally planned, some
tests were delayed, and the cost of the block increased by
approximately $1 billion. To stay within the revised budget despite
increasing contractor costs, MDA deferred some budgeted work to future
blocks. Such deferrals, coupled with a planning methodology too often
used by some contractors that could obscure cost reporting, prevent us
from determining the full cost of Block 2006. MDA was able to meet most
test objectives despite delays in several elements' test schedules.
Neither we nor DOD could evaluate the aggregate performance of fielded
assets because flight testing to date has not generated sufficient
data. An evaluation of aggregate performance would also have to
consider that (1) some parts in fielded interceptors identified as
potentially problematic have not been replaced yet, and (2) tests done
to date do not provide enough information for DOD's independent test
organization to fully determine if the BMDS is suitable and effective
for battle.
Fielding of Assets and Cost:
During Block 2006, MDA increased its inventory of BMDS assets while
enhancing the system's performance. It fielded 14 additional Ground-
based interceptors, 12 Aegis BMD missiles designed to engage more
advanced threats, 4 new Aegis BMD destroyers, 1 new Aegis BMD cruiser,
and 8 Web browsers and 1 software suite for C2BMC. In addition, MDA
upgraded half of its Aegis BMD ship fleet, successfully conducted four
Aegis BMD and two GMD intercept tests, and completed a number of ground
tests to demonstrate the capability of BMDS components.
MDA was unable to deliver all assets originally planned for Block
2006.[Footnote 2] The Sensors element was the only Block 2006 element
to meet all of its original goals set in March 2005 while the remaining
elements--GMD, Aegis BMD, C2BMC--did not meet all of their original
quantity goals. Sensors delivered a second FBX-T in January 2007 while
the GMD element fielded 14 of the 15 Ground-Based interceptors
originally planned during Block 2006. Last year, we reported that MDA
delayed the partial upgrade of the Thule early warning radar--one of
GMD's original goals--until a full upgrade could be accomplished.
Additionally, the Aegis BMD element delivered 4 additional Destroyers
and 1 new Cruiser as originally planned, but delivered 12 of the 19 SM-
3 missiles planned for the block. C2BMC did not deliver two of the
three software suites originally planned for Block 2006, but did
provide the needed capability less expensively through Web browsers and
other techniques.
The work MDA completed for Block 2006 cost more than planned. In March
2007, we reported that MDA's cost goal for Block 2006 increased by
approximately $1 billion because of greater than expected GMD
operations and sustainment costs and technical problems. If the
contractors continue to perform as they did in fiscal year 2007, we
estimate that at completion, the cumulative overrun in the contracts
could be between about $1.3 billion and $1.9 billion. To stay within
its revised budget, MDA deferred some work it expected to accomplish
during the block. When work is deferred, its costs are no longer
accounted for in the original block. In other words, if work planned
and budgeted for Block 2006 was deferred to Block 2008, that work would
be counted as a Block 2008 cost. Because MDA did not track the cost of
the deferred work, the agency could not make an adjustment that would
have matched the cost with the correct block. Consequently, we were
unable to determine the full cost of Block 2006.
Another reason why it is difficult to determine the actual cost of
Block 2006 is a planning methodology too often employed by some MDA
prime contractors that can obscure the full cost of work. Contractors
typically divide the total work of a contract into small efforts in
order to define them more clearly and to ensure proper oversight. Work
may be planned into categories including: (1) level of effort--work
that contains tasks of a general or supportive nature and does not
produce a definite end product and (2) discrete--work that has a
definable end product or event. When work is discrete, delivery of the
end product provides a sound basis for determining actual contractor
performance. When discrete work is instead planned as level of effort,
the contractor's performance becomes less transparent because work is
considered complete when the time planned for it has expired, whether
or not the intended product has been completed. Earned value management
does not recognize such variances in completing scheduled work and to
the extent more work has to be done to complete the product, additional
costs could be incurred that are not yet recognized.[Footnote 3] Many
of MDA's prime contractors plan a large percentage of their work as
level of effort. MDA officials agree that its contractors have
improperly planned discrete work as level of effort, and are taking
steps to remedy the situation.
We also observed that while several contractors had difficulty with
controlling costs, during fiscal year 2007, MDA awarded approximately
95 percent or $606 million of available award fee to its prime
contractors. In particular, contractors developing the ABL and Aegis
BMD Weapon System were rated as performing very well in the cost and/or
program management elements and received commensurate fees, even though
earned value management data showed that their cost and schedule
performance was declining. Although DOD guidance discourages the use of
earned value performance metrics in award fee criteria, MDA includes
this--one of many factors for consideration in rating contractors'
performance--in several of its award fee plans. The agency recognizes
that there is not always a good link between its intentions for award
fees and the amount of fee being earned by its contractors. In an
effort to rectify this problem, the agency has begun to revise its
award fee policy to align agency practices more closely with DOD's
current policy that better links performance with award fees.
Testing and Performance of Fielded Capability:
Most test objectives were achieved during 2007, although several BMDS
programs experienced setbacks in their test schedules. The MKV, KEI,
and Sensors elements were able to execute all scheduled activities as
planned. The Aegis BMD, THAAD, ABL, STSS, and C2BMC elements
experienced test delays, but all were able to achieve their primary
test objectives. GMD successfully completed an intercept with an
operationally representative interceptor and a radar characterization
test. A second intercept test employing the SBX radar has been delayed
because a target malfunction delayed the execution of the first
intercept test. The SBX capability is important as it is a primary
sensor to be used to engage ballistic missiles in the midcourse phase
of flight. As of yet, this capability has not been verified through
flight testing.
As we reported in March 2007, MDA altered its original Block 2006
performance goals commensurate with the agency's reductions in the
delivery of fielded assets.[Footnote 4] For several reasons,
information is not sufficient to assess whether MDA achieved its
revised performance goals. First, MDA uses a combination of simulations
and flight tests to determine whether performance goals are met.
However, too few flight tests have been completed to ensure the
accuracy of the models and simulations predictions. Second, confidence
in the performance of the BMDS is reduced because of unresolved
technical and quality issues in the GMD element. For example, the GMD
element has experienced the same anomaly during each of its flight
tests since 2001. This anomaly has not yet prevented the program from
achieving any of its primary test objectives, but to date neither its
source nor solution has been clearly identified. Program officials plan
to continue their assessment of test data to determine the anomaly's
root cause. The performance of some fielded GMD assets is also
questionable because they contain parts identified by auditors in MDA's
Office of Quality, Safety, and Mission Assurance as less reliable or
inappropriate for use in space that have not yet been replaced. MDA has
begun to replace the questionable parts in the manufacturing process
and to purchase the parts for retrofit into fielded interceptors.
However, it will not complete the retrofit effort until 2012.
Finally, tests of the GMD element have been of a developmental nature,
and have not included target suite dynamic features and intercept
geometries representative of the operational environment in which GMD
will perform its mission. MDA has added operational test objectives to
its developmental test program, but many of the objectives are aimed at
proving that military personnel can operate the equipment. Up until
2007, the lack of data limited the operational test and evaluation
Director's annual BMDS assessment to commenting on aspects of tests
that were operationally realistic and recommending other tests to
characterize system effectiveness and suitability. In 2007, tests
allowed a partial assessment of the BMDS' effectiveness, suitability,
and survivability. According to the Office of the Director of
Operational Test and Evaluation, (1) further testing that incorporates
realistic operational objectives and (2) verification, validation, and
accreditation of models and simulations will be needed before the
performance, suitability, and survivability of the BMDS can be fully
characterized.
Key Steps Taken to Enhance BMDS Oversight, but More Can Be Done:
Since its initiation in 2002, MDA has been given a significant amount
of flexibility. While this flexibility allows agile decision making, it
lessens the transparency of MDA's acquisition processes, making it
difficult to conduct oversight and hold the agency accountable for its
planned outcomes and costs. As we reported in March 2007, MDA operates
with considerable autonomy to change goals and plans, which makes it
difficult to reconcile outcomes with original expectations and to
determine the actual cost of each block and of individual operational
assets. In the past year, MDA has begun implementing two initiatives--
a new block construct and a new executive board--to improve
transparency, accountability, and oversight. These initiatives
represent improvements over current practices, although we see
additional improvements MDA can make. In addition, Congress has
directed that MDA begin buying certain assets with procurement funds
like other programs, which should promote accountability for and
transparency of the BMDS.
New Block Structure Offers Improvements, but Does Not Resolve All
Issues:
In 2007, MDA redefined its block construct to better communicate its
plans and goals to Congress. The agency's new construct is based on
fielding capabilities that address particular threats as opposed to the
previous biennial time periods. MDA's new block construct makes many
positive changes. These include establishing unit cost for selected
block assets, incorporating into a block only those elements or
components that will be fielded during the block, and abandoning the
practice of deferring work from block to block.
These changes should improve the transparency of the BMDS program and
make MDA more accountable for the investment being made in missile
defense. For example, the actual cost of each block can be tracked
because MDA will no longer defer work planned for one block, along with
its cost, to a future block. In addition, MDA plans to develop unit
costs for selected BMDS assets--such as THAAD interceptors--so that the
cost of those assets can be monitored. In addition, the agency plans to
request an independent verification of these unit costs and report
significant cost growth to Congress. However, MDA has not yet
determined all of the assets that will report a unit cost or how much a
unit cost must increase before it is reported to Congress.
Although improvements are inherent in MDA's proposed block construct,
the new construct does not resolve all transparency and accountability
issues. For example, MDA has not yet estimated the full cost of a
block. According to its fiscal year 2009 budget submission, MDA does
not initially plan to develop a full cost estimate for any BMDS block.
Instead, when a firm commitment can be made to Congress for a block of
capability, MDA will develop a budget baseline for the block. This
budget will include anticipated funding for each block activity that is
planned for the 6 years included in DOD's Future Years Defense
Plan.[Footnote 5] Once baselined, if the budget for a block changes,
MDA plans to report and explain those variations to Congress. At some
future date, MDA does expect to develop a full cost estimate for each
committed block and is in discussions with DOD's Cost Analysis
Improvement Group on having the group verify each estimate; but
documents do not yet include a timeline for estimating block cost or
having that estimate verified. Other DOD programs are required to
provide the full cost estimate of developing and producing their weapon
systems before system development and demonstration can begin. Until
the full cost of each block is known, it will be difficult for decision
makers to compare the value of investing in each block to the value of
investing in other DOD programs or to determine whether a block is
affordable over the long term.
Another issue yet to be addressed is whether the concurrent development
and fielding of BMDS assets will continue. Fully developing an asset
and demonstrating its capability prior to production increases the
likelihood that the product will perform as designed and can be
produced at the cost estimated. To field an initial capability quickly,
MDA accepted the risk of concurrent development and fielding during
Block 2004. It continued to do so during Block 2006 as it fielded
assets before they were fully tested. For example, by the end of Block
2004, the agency realized that the performance of some ground-based
interceptors could be degraded because the interceptors included
inappropriate or potentially unreliable parts.[Footnote 6] As noted
earlier, MDA has begun the process of retrofitting these interceptors,
but work will not be completed until 2012. Meanwhile, there is a risk
that some interceptors might not perform as designed. MDA has not
addressed whether it will accept similar performance risks under its
new block construct or whether it will fully develop and demonstrate
all elements/components prior to fielding.
MDA has not addressed whether it will transfer assets produced during a
block to a military service for production and operation at the block's
completion. Officials representing multiple DOD organizations recognize
that transfer criteria are neither complete nor clear given the BMDS's
complexity. Without clear transfer criteria, MDA has transferred the
management of only one element--the Patriot Advanced Capability-3--to
the military for production and operation. For other elements, MDA and
the military services have been negotiating the transition of
responsibilities for the sustainment of fielded elements-
-a task that has proven to be time consuming. Although MDA documents
show that under its new block construct the agency should be ready to
deliver BMDS components that are fully mission-capable, MDA officials
could not tell us whether at the end of a block MDA's Director will
recommend when management of components, including production
responsibilities, will be transferred to the military.
New Executive Board Offers Improved, but Not Full, Oversight:
Oversight improvement initiatives are also underway for MDA. In March
2007, the Deputy Secretary of Defense established a Missile Defense
Executive Board (MDEB) to recommend and oversee implementation of
strategic policies and plans, program priorities, and investment
options for protecting the United States and its allies from missile
attacks. The MDEB is also to replace existing groups and structures,
such as the Missile Defense Support Group.
The MDEB appears to be vested with more authority than its predecessor,
the Missile Defense Support Group. When the Support Group was chartered
in 2002, it was to provide constructive advice to MDA's Director.
However, the Director was not required to follow the advice of the
group. According to a DOD official, although the Support Group met many
times initially, it did not meet after June 2005. This led to the
formation of the MDEB. Its mission is to review and make
recommendations on MDA's comprehensive acquisition strategy to the
Deputy Secretary of Defense. It is also to provide the Under Secretary
of Defense (Acquisition, Technology and Logistics) with a recommended
strategic program plan and a feasible funding strategy based on
business case analysis that considers the best approach to fielding
integrated missile defense capabilities in support of joint MDA and
warfighter objectives. The MDEB will be assisted by four standing
committees. These committees, which are chaired by senior-level
officials from the Office of the Secretary of Defense and the Joint
Staff, could play an important oversight role as they are expected to
make recommendations to the MDEB, which in turn, will recommend courses
of action to the Under Secretary of Defense and the Director, MDA as
appropriate.
Although the MDEB is expected to exercise some oversight of MDA, it
will not have all the information normally available to DOD oversight
bodies. For other major defense acquisition programs, the Defense
Acquisition Board has access to critical information because before a
program can enter the System Development and Demonstration phase of the
acquisition cycle, statute requires that certain information be
developed. However, in 2002, the Secretary of Defense deferred
application of DOD policy to BMDS that, among other things, requires
major defense programs to obtain approval before advancing from one
phase of the acquisition cycle to another. Because MDA does not yet
follow this cycle, and has not yet entered System Development and
Demonstration, it has not triggered certain statutes requiring the
development of information that the Defense Acquisition Board uses to
inform its decisions. For example, most major defense acquisition
programs are required by statute to obtain an independent verification
of life-cycle cost estimates prior to beginning system development and
demonstration, and/or production and deployment. Independent life-
cycle cost estimates provide confidence that a program is executable
within estimated cost. Although MDA plans to develop unit cost for
selected block assets and to request that DOD's Cost Analysis
Improvement Group verify the unit costs, the agency does not initially
plan to develop a block cost estimate and therefore, cannot seek an
independent verification of that cost. Although MDA will not be
required to obtain an independent verification of block costs when they
are estimated, MDA officials told us that they have initiated
discussions with the Cost Analysis Improvement Group on independent
verifications of block cost estimates.
Statute also requires an independent verification of a system's
suitability for and effectiveness on the battlefield through
operational testing before a program can proceed beyond low-rate
initial production.[Footnote 7] After testing is completed, the
Director for Operational Test and Evaluation assesses whether the test
was adequate to support an evaluation of the system's suitability and
effectiveness for the battlefield, whether the test showed the system
to be acceptable, and whether any limitations in suitability and
effectiveness were noted. However, a comparable assessment of the BMDS
assets being fielded will not be available to the MDEB. As noted
earlier, the limited amount of testing completed, which has been
primarily developmental in nature, and the lack of verified, validated,
and accredited models and simulations prevent the Director of
Operational Test and Evaluation from fully assessing the effectiveness,
suitability, and survivability of the BMDS in annual assessments.
MDA will also make some decisions without needing approval from the
MDEB or any higher level DOD official. Although the charter of the MDEB
includes making recommendations to MDA and the Under Secretary of
Defense (Acquisition, Technology and Logistics) on investment options,
program priorities, and MDA's strategy for developing and fielding an
operational missile defense capability, the MDEB will not necessarily
have the opportunity to review and recommend changes to BMDS blocks.
MDA documents show that the agency plans to continue to define each
block of development without requiring input from the MDEB. According
to a briefing on the business rules and processes for MDA's new block
structure, the decision to initiate a new block of BMDS capability will
be made by MDA's Director. Also cost, schedule, and performance
parameters will be established by MDA when technologies that the block
depends upon are mature, a credible cost estimate can be developed,
funding is available, and the threat is both imminent and severe. The
Director will inform the MDEB as well as Congress when a new block is
initiated, but he will not seek the approval of either.
Finally, there will be parts of the BMDS program that the MDEB will
have difficulty overseeing because of the nature of the work being
performed. MDA plans to place any program that is developing technology
in a category known as Capability Development. These programs, such as
ABL, KEI, and MKV, will not have a firm cost, schedule, or performance
baseline. This is generally true for technology development programs in
DOD because they are in a period of discovery, which makes schedule and
cost difficult to estimate. Yet, the scale of the technology
development in BMDS is unusually large, ranging from $2 billion to
about $5 billion dollars a year--eventually comprising nearly half of
MDA's budget by fiscal year 2012. The MDEB will have access to the
budgets planned for these programs over the next 5 or 6 years, each
program's focus, and whether the technology is meeting short-term key
events or knowledge points. But without some kind of baseline for
matching progress with cost, the MDEB will not know how much more time
or money will be needed to complete technology maturation. MDA's
experience with the ABL program provides a good example of the
difficulty in estimating the cost and schedule of technology
development. In 1996, the ABL program believed that all ABL technology
could be demonstrated by 2001 at a cost of about $1 billion. However,
MDA now projects that this technology will not be demonstrated until
2009 and its cost has grown to over $5 billion.
MDA Directed to Use Procurement Funding:
In an effort to further improve the transparency of MDA's acquisition
processes, Congress has directed that MDA's budget materials delineate
between funds needed for research, development, test and evaluation;
procurement; operations and maintenance; and military
construction.[Footnote 8] Congress gave MDA the flexibility to field
certain assets using research, development, test and evaluation funding
which allowed MDA to fund the purchase of assets over multiple years.
Congress recently restricted MDA's authority and required MDA to
purchase certain assets with procurement funds. Using procurement funds
will mean that MDA will be required to ensure that assets are fully
funded in the year of their purchase, rather than incrementally funded
over several years. Additionally, our analysis of MDA data shows that
incremental funding is usually more expensive than full-funding, in
part, because inflation decreases the buying power of the dollar each
year. For example, after reviewing MDA's incremental funding plan for
THAAD fire units and Aegis BMD missiles, we analyzed the effect of
fully funding these assets and found that the agency could save about
$125 million by fully funding their purchase and purchasing them in an
economical manner. In the National Defense Authorization Act for Fiscal
Year 2008, Congress directed that MDA request procurement funding and
advanced procurement funding for long lead items in its fiscal year
2009 budget including funding for THAAD fire units and Aegis BMD SM-3
missiles. MDA did not request such funding because it slipped the
schedule for procuring THAAD fire units 3 and 4 by one year and because
the National Defense Authorization Act for Fiscal Year 2008 was not
signed in time to allow MDA to adjust its budget request for SM-3
missiles. However, in MDA's fiscal year 2010 budget submittal, the
agency intends to incorporate a detailed plan of action and milestones
to transition from incremental funding to full funding beginning in
fiscal year 2010 and for all fiscal years thereafter.
Actions Recommended in Our Recent Report:
In our March 2008 report, we made several recommendations to build on
efforts to further improve the transparency, accountability, and
oversight of the missile defense program. Specifically, we recommended
that the Secretary of Defense direct:
* MDA to develop a full cost for each block and request an independent
verification of that cost;
* MDA to clarify the criteria that it will use for reporting unit cost
variances to Congress;
* MDA to examine a contractor's planning efforts when 20 percent or
more of a contract's work is proposed as level of effort;
* MDA to investigate ways of developing a baseline or some other
standard against which the progress of technology programs may be
assessed; and:
* MDA and the Director of Operational Test and Evaluation to agree on
criteria and incorporate corresponding scope into developmental tests
that will allow a determination of whether a block of BMDS capability
is suitable and effective for fielding.
DOD concurred with the first three recommendations DOD partially
concurred with the remaining two recommendations to investigate ways of
developing a baseline or some other standard against which the progress
of technology programs may be assessed and to agree on criteria and
incorporate corresponding scope into developmental tests. DOD stated
that MDA already uses key knowledge points, technology levels, and
engineering readiness levels to assess the progress of technology
programs and that it will continue to investigate other ways of making
such assessments. DOD also noted that MDA's mission is to work with the
warfighter, rather than Director of Operational Test and Evaluation, to
determine that the BMDS is ready for fielding. However, DOD stated that
MDA will continue to work with operational testers to strengthen the
testing of BMDS suitability and effectiveness. We believe that DOD and
Congress would benefit from understanding the remaining cost and time
needed to complete a technology program, important information that
MDA's methods do not yet provide. Since BMDS testing will continue to
serve both developmental and operational purposes, its scope should be
sufficient to enable the Director of Operational Test and Evaluation to
evaluate the system's operational effectiveness, suitability, and
survivability.
Mr. Chairman, this concludes my statement. I would be pleased to
respond to any questions you or members of the subcommittee may have.
Contact and Staff Acknowledgments:
For questions about this statement, please contact me at (202) 512-4841
or Francisp@gao.gov. Individuals making key contributions to this
statement include David Best, Assistant Director; LaTonya D. Miller;
Steven B. Stern; Meredith Allen Kimmett; Kenneth E. Patton; and Alyssa
Weir.
[End of section]
Footnotes:
[1] The BMDS also includes a 10th element, Patriot Advanced Capability-
3 which has been transferred to the Army for production, operation, and
sustainment. This report does not evaluate Patriot because its initial
development is complete and is now being managed by the Army.
[2] In March 2006, MDA made reductions to its block 2006 goals. It was
able in nearly all instances to meet or exceed these revised goals. Two
elements--GMD and C2BMC--were able to exceed their revised fielding
goals. In addition, the Aegis BMD element was able to meet its revised
block goals for one of its two components. The program upgraded all
planned ships, but fielded three fewer Aegis BMD Standard Missile-3s
(SM-3) than planned because the missiles were delayed into 2008 to
accommodate an unanticipated requirement to deliver three missiles to
Japan.
[3] Earned Value Management (EVM) is a program management tool that
integrates the technical, cost, and schedule parameters of a contract.
During the planning phase, an integrated baseline is developed by time
phasing budget resources for defined work. As work is performed and
measured against the baseline, the corresponding budget value is
"earned". Using this earned value metric; cost and schedule variances
can be determined and analyzed. EVM is program management that provides
significant benefits to both the Government and the contractor.
[4] GAO, Defense Acquisitions: Missile Defense Acquisition Strategy
Generates Results but Delivers Less at a Higher Cost, GAO-07-387
(Washington, D.C.: Mar.15, 2007). BMDS performance goals included a
numerical goal for the probability of a successful BMDS engagement, a
defined area from which the BMDS would prevent an enemy from launching
a ballistic missile, and a defined area that the BMDS would protect
from ballistic missile attacks.
[5] There are five blocks included in the new block construct--1.0,
2.0, 3.0, 4.0, and 5.0. MDA expects to initially develop budget
baselines and report variances to this baseline for Blocks 1.0, 2.0,
and a portion of 3.0.
[6] See GAO, Defense Acquisitions: Missile Defense Agency Fields
Initial Capability but Falls Short of Original Goals, GAO-06-327
(Washington, D.C.: Mar. 15, 2006).
[7] The Defense Acquisition Board advises the Under Secretary of
Defense for Acquisition, Technology, and Logistics on critical
acquisition decisions.
[8] 10 U.S.C § 2399 requires completion of initial operational test and
evaluation of a weapon system before a program can proceed beyond low-
rate initial production. According to DOD policy, low-rate initial
production is intended to result in completion of manufacturing
development in order to ensure adequate and efficient manufacturing
capability and to produce the minimum quantity necessary to provide
production or production-representative articles for operational test
and evaluation, establish an initial production base for the system;
and permit an orderly increase in the production rate for the system,
sufficient to lead to full-rate production upon successful completion of
operational (and live-fire, where applicable) testing.
[9] The National Defense Authorization Act for Fiscal Year 2008, Pub.
L. No. 110-181, § 223.
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548: