Defense Acquisitions
2009 Review of Future Combat System Is Critical to Program's Direction
Gao ID: GAO-08-638T April 10, 2008
The Future Combat System (FCS) program--which comprises 14 integrated weapon systems and an advanced information network--is the centerpiece of the Army's effort to transition to a lighter, more agile, and more capable combat force. The substantial technical challenges, the Army's acquisition strategy, and the cost of the program are among the reasons why the program is recognized as needing special oversight and review. This testimony is based on GAO's two March 2008 reports on FCS and addresses (1) how the definition, development, and demonstration of FCS capabilities are proceeding, particularly in light of the go/no-go decision scheduled for 2009; (2) the Army's plans for making production commitments for FCS and any risks related to the completion of development; and (3) the estimated costs for developing and producing FCS.
Today, the FCS program is about halfway through its development phase, yet it is, in many respects, a program closer to the beginning of development. This portends additional cost increases and delays as FCS begins what is traditionally the most expensive and problematic phase of development. In the key areas of defining and developing FCS capabilities, requirements definition is still fluid, critical technologies are immature, software development is in its early stages, the information network is still years from being demonstrated, and complementary programs are at risk for not meeting the FCS schedule. It is not yet clear if or when the information network that is at the heart of the FCS concept can be developed, built, and demonstrated. Yet, the time frame for completing FCS development is ambitious; even if all goes as planned, the program will not test production-representative prototypes or fully demonstrate the system of systems until after low rate production begins. Even though the development of FCS will finish late in its schedule, commitments to production will come early. Production funding for the first spinout of FCS technologies and the early version of the FCS cannon begin in fiscal years 2008 and 2009. Production money for the core FCS systems will be requested beginning in February 2010, with the DOD fiscal year 2011 budget request--just months after the go/no-go review and before the stability of the design is determined at the critical design review. In fact, by the time of the FCS production decision in 2013, a total of about $39 billion, which comprises research and development and production costs, will already have been appropriated for the program, with another $8 billion requested. Also, the Army plans to contract with its lead system integrator for the initial FCS production, a change from the Army's original rationale for using an integrator. This increases the burden of oversight faced by the Army and the Office of the Secretary of Defense. While the Army's cost estimates for the FCS program remain about the same as last year--$160.9 billion--the content of the program has been reduced, representing a reduction in buying power for the Army. The level of knowledge for the program does not support a confident estimate, and cost estimates made by two independent organizations are significantly higher. Competing demands from within the Army and DOD limits the ability to fund higher FCS costs. Thus, the Army will likely continue to reduce FCS capabilities in order to stay within available funding limits. Accordingly, FCS's demonstrated performance, the reasonableness of its remaining work, and the resources it will need and can reasonably expect will be of paramount importance at the 2009 milestone review for the FCS program.
GAO-08-638T, Defense Acquisitions: 2009 Review of Future Combat System Is Critical to Program's Direction
This is the accessible text file for GAO report number GAO-08-638T
entitled 'Defense Acquisitions: 2009 Review of Future Combat System Is
Critical to Program's Direction' which was released on April 10, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Air and Land Forces, Committee on Armed
Services, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 2:00 p.m. EDT:
Thursday, April 10, 2008:
Defense Acquisitions:
2009 Review of Future Combat System Is Critical to Program's Direction:
Statement of Paul L. Francis:
Director:
Acquisition and Sourcing Management:
GAO-08-638T:
GAO Highlights:
Highlights of GAO-08-638T, a testimony before the Subcommittee on Air
and Land Forces, Committee on Armed Services, House of Representatives.
Why GAO Did This Study:
The Future Combat System (FCS) program”which comprises 14 integrated
weapon systems and an advanced information network”is the centerpiece
of the Army‘s effort to transition to a lighter, more agile, and more
capable combat force. The substantial technical challenges, the Army‘s
acquisition strategy, and the cost of the program are among the reasons
why the program is recognized as needing special oversight and review.
This testimony is based on GAO‘s two March 2008 reports on FCS and
addresses (1) how the definition, development, and demonstration of FCS
capabilities are proceeding, particularly in light of the go/no-go
decision scheduled for 2009; (2) the Army‘s plans for making production
commitments for FCS and any risks related to the completion of
development; and (3) the estimated costs for developing and producing
FCS.
What GAO Found:
Today, the FCS program is about halfway through its development phase,
yet it is, in many respects, a program closer to the beginning of
development. This portends additional cost increases and delays as FCS
begins what is traditionally the most expensive and problematic phase
of development. In the key areas of defining and developing FCS
capabilities, requirements definition is still fluid, critical
technologies are immature, software development is in its early stages,
the information network is still years from being demonstrated, and
complementary programs are at risk for not meeting the FCS schedule. It
is not yet clear if or when the information network that is at the
heart of the FCS concept can be developed, built, and demonstrated.
Yet, the time frame for completing FCS development is ambitious; even
if all goes as planned, the program will not test production-
representative prototypes or fully demonstrate the system of systems
until after low rate production begins.
Even though the development of FCS will finish late in its schedule,
commitments to production will come early. Production funding for the
first spinout of FCS technologies and the early version of the FCS
cannon begin in fiscal years 2008 and 2009. Production money for the
core FCS systems will be requested beginning in February 2010, with the
DOD fiscal year 2011 budget request”just months after the go/no-go
review and before the stability of the design is determined at the
critical design review. In fact, by the time of the FCS production
decision in 2013, a total of about $39 billion, which comprises
research and development and production costs, will already have been
appropriated for the program, with another $8 billion requested. Also,
the Army plans to contract with its lead system integrator for the
initial FCS production, a change from the Army‘s original rationale for
using an integrator. This increases the burden of oversight faced by
the Army and the Office of the Secretary of Defense.
While the Army‘s cost estimates for the FCS program remain about the
same as last year”$160.9 billion”the content of the program has been
reduced, representing a reduction in buying power for the Army. The
level of knowledge for the program does not support a confident
estimate, and cost estimates made by two independent organizations are
significantly higher. Competing demands from within the Army and DOD
limits the ability to fund higher FCS costs. Thus, the Army will likely
continue to reduce FCS capabilities in order to stay within available
funding limits. Accordingly, FCS‘s demonstrated performance, the
reasonableness of its remaining work, and the resources it will need
and can reasonably expect will be of paramount importance at the 2009
milestone review for the FCS program.
What GAO Recommends:
In its March 2008 reports, GAO made several recommendations to the
Secretary of Defense that included: establishing criteria that the FCS
program will have to meet in the 2009 milestone review in order to
justify continuation; identifying viable alternatives to FCS; and
taking other actions. DOD concurred with GAO‘s recommendations.
To view the full product, including the scope and methodology, click on
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-638T]. For more
information, contact Paul Francis at (202) 512-4841 or
francisp@gao.gov.
[End of section]
Mr. Chairman and Members of the Subcommittee:
I am pleased to be here today to discuss the Department of the Army's
Future Combat System (FCS), a networked family of weapons and other
integrated systems. FCS is in the forefront of efforts to help the Army
transform itself into a lighter, more agile, and more capable combat
force by using a new concept of operations, new technologies, and a new
information network linking whole brigades together in a system of
systems. In 2009, FCS faces a congressionally mandated go/no-go
decision review to determine the program's future. This review is
crucial, as production funding and commitments will build rapidly after
that point, limiting the government's ability to alter course.
My statement today is based on the work we conducted over the past year
in response to the National Defense Authorization Act for Fiscal Year
2006, which requires GAO to report annually on the FCS
program.[Footnote 1] Accordingly, this statement discusses (1) how the
definition, development, and demonstration of FCS capabilities are
proceeding, particularly in light of the go/no-go decision scheduled
for 2009; (2) the Army's plans for making production commitments for
FCS and any risks related to completing development; and (3) the
estimated costs for developing and producing FCS and risks the Army
faces in both meeting the estimate and providing commensurate funding.
[Footnote 2]
Summary:
Definition, development, and demonstration of capabilities will finish
late in the FCS schedule. At this point, requirements definition is
still fluid, critical technologies are immature, software development
is in its early stages, the information network is still years from
being demonstrated, and complementary programs are at risk for not
meeting the FCS schedule. Significant commitments to production will be
made before FCS capabilities are demonstrated. Production money for the
core FCS systems will be requested beginning in February 2010, with the
DOD fiscal year 2011 budget request--just months after the go/no-go
review and before the stability of the design is determined at the
critical design review. By the time of the FCS production decision in
2013, about $39 billion will already have been invested in the program.
While the Army's cost estimates for the FCS program remain about the
same as last year--$160.9 billion--the content of the program has been
reduced. FCS costs are likely to grow as the current level of knowledge
does not support a confident estimate, and cost estimates made by two
independent organizations are significantly higher. Competing demands
from within the Army and DOD limit the ability to fund higher FCS
costs. Thus, the Army will likely continue to reduce FCS capabilities
in order to stay within available funding limits.
In our March 2008 reports, we made several recommendations to ensure
that the 2009 FCS milestone review is positioned to be both well-
informed and transparent. Specifically, we recommended that the
Secretary of Defense, among other things, (1) establish objective and
quantitative criteria that the FCS program will have to meet in order
to justify its continuation and gain approval for the remainder of its
acquisition strategy, (2) identify viable alternatives to FCS as
currently structured that can be considered in the event that FCS does
not measure up to the criteria set for the review, and (3) closely
examine the oversight implications of the Army's decision to contract
with the lead system integrator for early production of FCS spin outs,
the non-line-of-sight cannon (NLOS-C), and low rate production for the
FCS core program. In the area of FCS network and software, we
recommended that the FCS program stabilize the network and software
requirements of each software build to enable software developers to
follow disciplined software practices and establish a clear set of
criteria for acceptable network performance at each of the key program
events. Finally, in setting expectations for the 2009 milestone review,
we recommended that the expectations include an analysis of network
technical feasibility and risks, synchronization of the network with
other elements of FCS, and a reconciliation of cost estimates of
network and software development scope and cost.
DOD concurred with our recommendations and stated that criteria for the
2009 FCS Defense Acquisition Board review will be established and will
be reviewed and finalized at the 2008 Defense Acquisition Board review.
The results of the analyses and assessments planned to support the 2009
review will inform DOD's acquisition and budget decisions for FCS.
These are positive steps toward informing the 2009 Defense Acquisition
Board review.
Background:
The FCS concept is designed to be part of the Army's Future Force,
which is intended to transform the Army into a more rapidly deployable
and responsive force that differs substantially from the large division-
centric structure of the past. The Army is reorganizing its current
forces into modular brigade combat teams, each of which is expected to
be highly survivable and the most lethal brigade-sized unit the Army
has ever fielded. The Army expects FCS-equipped brigade combat teams to
provide significant warfighting capabilities to DOD's overall joint
military operations. The Army has also instituted plans to spin out
selected FCS technologies and systems to current Army forces throughout
the program's system development and demonstration phase.
The FCS program is recognized as being high risk and needing special
oversight. Accordingly, in 2006, Congress mandated that the Department
of Defense (DOD) hold a milestone review following its preliminary
design review.[Footnote 3] Congress directed that the review include an
assessment of whether (1) the needs are valid and can best be met with
the FCS concept, (2) the FCS program can be developed and produced
within existing resources, and (3) the program should continue as
currently structured, be restructured, or be terminated. Congress
required the Secretary of Defense to review and report on specific
aspects of the program, including the maturity of critical
technologies, program risks, demonstrations of the FCS concept and
software, and a cost estimate and affordability assessment.
This statement is based on work we conducted between March 2007 and
March 2008 and is in accordance with generally accepted government
auditing standards. Those standards require that we plan and perform
the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a reasonable
basis for our findings and conclusions based on our audit objectives.
Definition, Development, and Demonstration of Capabilities Will Finish
Late in the FCS Schedule:
Ideally, the Army should have entered development in 2003 with firm
requirements and mature technologies. However, the FCS program will be
challenged to meet these markers by the time of the preliminary design
review in 2009. The Army has only recently formed an understanding of
what will be expected of the FCS network. Complementary programs,
necessary to the success of the FCS, are not yet fully synchronized
with the FCS schedule and face funding and technical challenges. By
2009, the Army will have spent 6 years and $18 billion on these initial
efforts, with the costlier components of a development program still to
come. It will be years before demonstrations validate that the FCS will
provide needed capabilities.
Requirements, Technologies, and Designs Are Not Yet Mature:
While the Army should have firmed requirements at the outset of its
development program, it now faces a daunting task in completing this
work by the preliminary design review and subsequent milestone review
in 2009--6 years into a 10-year development schedule. Many of FCS's
thousands of requirements are almost certain to be modified as the
program approaches these reviews. The Army's decision to restructure
the program in early 2007, reducing the set of systems from 18 to 14,
resulted in requirements modifications, deferrals, and redistributions
that affected the requirements balance among the remaining systems. As
this program adjustment is implemented, further requirements changes to
the systems, as well as to the network, could be required. The Army
also continues to make design trade-offs to accommodate restrictions
such as space, weight, and power constraints; affordability; and
technical risks, such as transport requirements for manned ground
vehicles. FCS software development is hampered by incomplete
requirements and designs for the information network. While the Army's
user community expects that FCS will deliver capabilities that are as
good as or better than current forces, this position is based on the
results of modeling and simulation activities--it will be several years
before field demonstrations validate the user community's position.
FCS's critical technologies remain at low maturity levels. According to
the Army's latest technology assessment, only two of FCS's 44 critical
technologies have reached a level of maturity that, based on best
practice standards, should have been demonstrated at program start.
Even applying the Army's less rigorous standards, only 73 percent can
be considered mature enough to begin system development today. The
technological immaturity, coupled with incomplete requirements, is a
mismatch that has prevented the Army from reaching the first critical
knowledge point for this program--a precursor for cost growth. Many of
these immature technologies may have an adverse cumulative impact on
key FCS capabilities such as survivability. In addition, the Army is
struggling to synchronize the schedules and capabilities of numerous
essential complementary programs with the overall FCS program. The Army
has identified problems that raise concerns about the likelihood that
many complementary systems will deliver the required capabilities when
needed. In some cases, complementary programs have been adversely
affected by FCS demands, and in others, lack of coordination between
FCS and complementary program officials has stalled efforts aimed at
synchronizing programs and resolving cost, schedule, and technical
issues.
Significant Challenges in Developing And Demonstrating FCS Network and
Software:
It is not yet clear if or when the information network that is at the
heart of the FCS concept can be developed, built, and demonstrated by
the Army and lead system integrator (LSI). Significant management and
technical challenges--owing more to the program's complexity and
immaturity than to the approach to software--have placed development of
the network and software at risk. These risks include network
performance and scalability, immature network architecture, and
synchronization of FCS with Joint Tactical Radio System (JTRS) and
Warfighter Information Network-Tactical programs that have significant
technical challenges of their own. The amount of estimated software
code required for the FCS network and platforms has recently increased
to 95.1 million lines. This is nearly triple the size of the original
estimate in 2003, and the largest software effort by far for any weapon
system. Software code is difficult to estimate, and underestimation is
not unique to FCS. Compounding this inherent difficulty on FCS were the
program's poorly defined requirements, indicative of its immaturity.
Lines of code have grown as requirements have become better understood.
The Army believes the latest increases will not substantially increase
software development costs, but updated Army and independent cost
estimates will not be available until next year. Previously, the
independent estimates have differed sharply from the Army's in the area
of FCS software development costs.
Although several disciplined practices are being used to develop FCS's
network and software, the program's immaturity and aggressive pace
during development have delayed requirements development at the
software developer level. For example, software developers for five
major software packages that we reviewed report that high-level
requirements provided to them were poorly defined, omitted, or late in
the development process. These caused the software developers to do
rework or defer functionality to future builds. In turn, these poor or
late requirements had a cascading effect that caused other software
development efforts to be delayed.
It is unclear when or how it can be demonstrated that the FCS network
will work as needed, especially at key program junctures. For example,
in 2009, network requirements, including software, may not be well
defined nor designs completed at the preliminary design review; and at
the FCS milestone review later that year, network demonstration is
expected to be very limited. The Army and LSI have identified and need
to address numerous areas of high risk such as network performance and
scalability. The first large scale FCS network demonstration--the
limited user test in 2012--will take place at least a year after the
critical design review and only a year before the start of FCS
production. That test will seek to identify the impact of the
contributions and limitations of the network on the ability to conduct
missions. This test will be conducted after the designs have been set
for the FCS ground vehicles, a situation that poses risks because the
designs depend on the network's performance. A full demonstration of
the network with all of its software components will not be
demonstrated until at least 2013 when the fully automated battle
command system is expected to be ready.
FCS Capabilities Will Be Demonstrated after Key Decision Points:
When FCS reaches its planned preliminary design review in 2009, the
Army will have expended over 60 percent of its development funds and
schedule. However, much will still need to be done in terms of
technology maturation, system integration and demonstration, and
preparing for production--all three knowledge points fundamental to a
successful acquisition. Large scale demonstrations of the network will
not occur until after manned ground vehicles, which depend on the
performance of the network, are already designed and prototyped. The
Army does not plan to demonstrate that the FCS system of systems
performs as required until after the production decision for the core
program in 2013. That would preclude opportunities to change course if
warranted by test results and increasing the likelihood of costly
discoveries in late development or during production. The cost of
correcting problems in those stages is high because program
expenditures and schedules are less forgiving than in the early stages
of a program. Conversely, the test standards we apply reflect the best
practice of having production-representative prototypes tested prior to
a low rate production decision. This approach demonstrates the
prototypes' performance and reliability as well as manufacturing
processes--in short, that the program is ready to be manufactured
within cost, schedule, and quality goals.
Significant Commitments to Production Will Be Made Before FCS
Capabilities Are Demonstrated:
While the FCS production decision for the core FCS program is to be
held in fiscal year 2013, production commitments will begin in fiscal
years 2008 and 2009 with production for the first of a series of three
planned spin out efforts and the early versions of the NLOS-C vehicle.
When considering these activities, along with long-lead and
facilitization investments associated with the production of FCS core
systems, a total of $11.9 billion in production money will have been
appropriated and another $6.9 billion requested by the time of the
production decision for the FCS core systems in 2013. When development
funds are included, $39 billion will have been appropriated and another
$8 billion requested. As noted previously, key demonstrations will not
yet have taken place by this time. Also, in April 2007, the Army
announced its intention to contract with the LSI for the production for
the first three brigade combat teams of FCS systems, the production of
the FCS spin out items, and the early production of NLOS-C vehicles.
This decision makes an already unusually close relationship between the
Army and the LSI even closer, and heightens the oversight challenges
FCS presents.
Spin Out Procurement to Begin before Testing Completed:
In 2004, the Army revised its acquisition strategy to bring selected
technologies and systems to current forces via spin outs while
development of the core FCS program is underway. The first of these
spin out systems will be tested and evaluated in the coming year, and a
production decision is planned in 2009. However, the testing up to that
point will feature some surrogate subsystems rather than the fully
developed subsystems that would ultimately be deployed to the current
forces. For example, none of the tests will include fully functional
JTRS radios or associated software. The Army believes this strategy is
adequate; however, testing of surrogates may not provide quality
measurements to gauge system performance, and the Army may have to
redesign if JTRS radios have different form, fit, and function than
expected. Taken together, these spin out 1 capabilities serve as a
starting point for FCS but represent only a fraction of the total
capability that the Army plans for FCS to provide. The Army has general
plans for a second and third set of spin out items but, according to
the Army, these have not yet been funded.
NLOS-C Production to Begin Soon at Congress' Direction:
Responding to congressional direction, the Army will begin procuring
long lead production items for the NLOS-C vehicle in 2008.[Footnote 4]
The Army will deliver six units per year in fiscal years 2010 through
2012; however, these early NLOS-C vehicles will not meet threshold FCS
requirements and will not be operationally deployable without
significant modifications. Rather, they will be used as training assets
for the Army Evaluation Task Force.
To meet the early fielding dates, the Army will begin early production
of the NLOS-C vehicles with immature technologies and designs. Several
key technologies will not be mature for several years, and much
requirements and design work remains on the manned ground vehicles,
including the NLOS-C. Significant challenges involving integrating the
technologies, software, and design will follow. To the extent these
aspects of the manned ground vehicles depart from the early production
cannons, costly rework of the cannons may be necessary.
The Army is planning a seamless transition between NLOS-C production
and core FCS production. However, beginning the production of NLOS-C
vehicles 5 years before the start of FCS core production could create
additional pressure to proceed with FCS core production. Moreover, to
the extent that beginning NLOS-C production in 2008 starts up the
manned ground vehicle industrial base, it could create a future need to
sustain the base. If decision makers were to consider delaying FCS core
production because it was not ready, a gap could develop when early
NLOS-C production ends. Sustaining the industrial base could then
become an argument against an otherwise justified delay. The Under
Secretary of Defense for Acquisition, Technology, and Logistics
recently took steps to keep the decisions on the NLOS-C early
production separate from FCS core production. In approving procurement
of long lead items for the NLOS-C vehicles in 2008, the Under Secretary
designated the 18 early prototypes as a separate, special interest
program for which he will retain authority for making milestone
decisions. The Under Secretary will make a second decision in 2009
whether to approve NLOS-C production and has put a cost limit of $505.2
million (fiscal year 2003 dollars) on production of these vehicles. He
also added that specific requirements be met at that time, such as a
capability production document, technology readiness assessment, test
plan, independent estimate of costs, and an approved acquisition
program baseline. This is a positive step in ensuring that the Army's
efforts to meet Congressional direction do not result in unfavorable
consequences.
Army Commitment to LSI for Production Heightens Oversight Challenges:
The Army's April 2007 decision to contract with the LSI for FCS
production makes an already close relationship closer, represents a
change from the Army's original rationale for using an LSI, and may
further complicate oversight. The specific role the LSI will play in
production of spin outs, NLOS-C, and FCS core production are unclear at
this point. According to program officials, the statements of work for
the long lead items contracts for spin outs and NLOS-C have not yet
been worked out. The statements of work for the production contract
will also be negotiated later. The work the LSI does in actual
production of FCS is likely to be small compared to the other hardware
suppliers and assemblers. Thus, the production role of the LSI is
likely to be largely in oversight of the first tier subcontractors.
From the outset of the program, the LSI was to focus its attention on
development activities that the Army judged to be beyond what it could
directly handle. Army leadership believed that by using an LSI that
would not necessarily have to be retained for production, the Army
could get the best effort from the contractor during the development
phase while at the same time making the effort profitable for the
contractor. Nonetheless, the LSI's involvement in the production phase
has been growing over time. The current LSI development contract for
the core FCS systems extends almost 2 years beyond the 2013 production
decision. The Army does not expect the initial brigades outfitted by
FCS will meet the upper range of its requirements and has made the LSI
responsible for planning future FCS enhancements during the production
phase. Combined with a likely role in sustainment, the LSI will remain
indefinitely involved in the FCS program. By committing to the LSI for
early production, the Army effectively ceded a key point of leverage it
had held--source selection--and is perhaps the final departure from the
Army's initial efforts to keep the LSI's focus solely on development.
This decision also creates a heightened burden of oversight in that
there is now additional need to guard against the natural incentive of
production from creating more pressure to proceed through development
checkpoints prematurely. As we have previously reported, this is a
burden that will need to be increasingly borne by the Office of the
Secretary of Defense.
FCS Costs Likely to Grow beyond Army Estimates:
The Army's $160.9 billion cost estimate for the FCS program is largely
unchanged from last year's estimate despite a program adjustment that
reduced the number of systems from 18 to 14. This may mean a reduction
in capabilities of the FCS program and thus represents a reduction in
the Army's buying power on FCS. Further, two independent cost
estimates--from DOD's Cost Analysis Improvement Group (CAIG) and the
other from the Institute for Defense Analyses (IDA), a federally funded
research and development center--are significantly higher than the
Army's estimate. Both assessments estimate higher costs for software
development, to which a recent increase in lines of code adds credence.
The Army has not accepted either of the independent estimates on the
grounds that they each include additional work scope, particularly in
the later years of the development phase. Also, the CAIG and IDA both
use historical growth factors in their estimates, based on the results
of previous programs. It is reasonable to include such growth factors,
based on our own analysis of weapon systems and the low level of
knowledge attained on the FCS program at this time.
Given the program's relative immaturity in terms of technology and
requirements definition and demonstrations of capabilities to date,
there is not a firm foundation for a confident cost estimate. The Army
has not calculated confidence levels on its estimates, though this is a
best practice and could reduce the probability of unbudgeted cost
growth. Under its current structure, the Army will make substantial
investments in the FCS program before key knowledge is gained on
requirements, technologies, system designs, and system performance,
leaving less than half its development budget to complete significantly
expensive work, such as building and testing prototypes, after its
preliminary design review. The Army maintains that if it becomes
necessary, FCS content will be further reduced, by trading away
requirements or changing the concept of operations, to keep development
costs within available funding levels. As the Army begins a steep ramp-
up of FCS production, FCS costs will compete with other Army funding
priorities, such as the transition to modular organizations and
recapitalizing the weapons and other assets that return from current
operations. Together, the program's uncertain cost estimate and
competing Army priorities make additional reductions in FCS scope and
increases in cost likely.
Conclusion:
The deficiencies we cite in areas such as requirements and technology
are not criticisms of progress in the sense that things should have
gone smoother or faster. At issue, rather, is the misalignment of the
program's normal progress with the events used to manage and make
decisions on such acquisitions--key decisions are made well before
sufficient knowledge is available. The decision in 2009 will provide an
opportunity to realign the progress of knowledge in FCS with events
such as the critical design review and tests of prototypes before the
production decision. The 2009 decision may also be the government's
last realistic opportunity to safeguard its ability to change course on
FCS, should that be warranted. The first decision, as we see it, will
have to determine whether FCS capabilities have been demonstrated to be
both technically feasible and militarily worthwhile. If they have not,
then DOD and the Army will need to have viable alternatives to fielding
the FCS capability as currently envisioned. Depending on the results of
the first decision, the second decision is to determine how to
structure the remainder of the FCS program so that it attains high
levels of knowledge before key commitments.
Other aspects of the FCS program warrant attention that should not wait
until the 2009 decision. Primary among these is the Army's decision to
extend the role of the LSI into FCS production. This is a decision that
will necessarily heighten the role the Office of the Secretary of
Defense will have to play in overseeing the program and departs from
the Army's philosophy of having the LSI focus on development without
the competing demands and interests that production poses. A second
aspect of the program warranting attention is the Army's approach to
spin outs. It will be important for the Army to clearly demonstrate the
military utility of the spin outs to current Army forces, based on
testing high-fidelity, production-representative prototypes, before a
commitment is made to their low rate production. This is not the
current plan, as the Army plans to use some surrogate equipment in the
testing that will support the production decision for spin out 1.
Finally, it is important that the production investments in the spin
outs and NLOS-C do not create undue momentum for production of the FCS
core systems. As noted above, commitment to production of the FCS core
systems must be predicated on attaining high levels of knowledge,
consistent with DOD policy.
Actions Recommended in Our Recent Reports:
In our March 2008 reports, we made several recommendations to ensure
that the 2009 FCS milestone review is positioned to be both well-
informed and transparent. Specifically, we recommended that the
Secretary of Defense establish objective and quantitative criteria that
the FCS program will have to meet in order to justify its continuation
and gain approval for the remainder of its acquisition strategy. The
criteria should be set by at least July 30, 2008, in order to be
prescriptive, and should be consistent with DOD acquisition policy and
best practices. At a minimum, the criteria should include, among other
things, the completion of the definition of all FCS requirements
including those for the information network and the synchronization of
FCS with all essential complementary programs. We also recommended that
the Secretary of Defense, in advance of the 2009 milestone review,
identify viable alternatives to FCS as currently structured that can be
considered in the event that FCS does not measure up to the criteria
set for the review. As we have previously reported, an alternative need
not be a rival to the FCS, but rather the next best solution that can
be adopted if FCS is unable to deliver the needed capabilities. For
example, an alternative need not represent a choice between FCS and the
current force, but could include fielding a subset of FCS, such as a
class of vehicles, if they perform as needed and provide a militarily
worthwhile capability. We further recommended that the Secretary of
Defense (1) closely examine the oversight implications of the Army's
decision to contract with the LSI for early production of FCS spin
outs, NLOS-C, and low rate production for the core FCS program; (2)
take steps to mitigate the risks of the Army's decisions, including the
consideration of the full range of alternatives for contracting for
production; and (3) evaluate alternatives to the LSI for long-term
sustainment support of the FCS system of systems.
Finally, regarding the FCS network and software development and
demonstration efforts, we recommended that the Secretary of Defense (1)
direct the FCS program to stabilize network and software requirements
on each software build to enable software developers to follow
disciplined software practices; (2) establish a clear set of criteria
for acceptable network performance at each of the key program events;
and (3) in setting expectations for the 2009 milestone review, include
a thorough analysis of network technical feasibility and risks,
synchronization of network development and demonstration with that of
other FCS elements, and a reconciliation of the differences between
independent and Army estimates of network and software development
scope and cost.
DOD concurred with our recommendations and stated that criteria for the
2009 FCS Defense Acquisition Board review will be established and will
be reviewed and finalized at the 2008 Defense Acquisition Board review.
The results of the analyses and assessments planned to support the 2009
review will inform DOD's acquisition and budget decisions for FCS.
These are positive steps toward informing the 2009 Defense Acquisition
Board review.
Mr. Chairman, this concludes my prepared statement. I would be happy to
answer any questions you or members of the subcommittee may have.
Contacts and Staff Acknowledgements:
For future questions about this statement, please contact me on (202)
512-4841 or francisp@gao.gov. Individuals making key contributions to
this statement include William R. Graveline, Assistant Director; Martin
G. Campbell; Ronald N. Dains; Tana M. Davis; Marcus C. Ferguson; John
A. Krump, John M. Ortiz; and Carrie R. Wilson.
[End of section]
Footnotes:
[1] Pub. L. No. 109-163 §211 (2006).
[2] GAO, Defense Acquisitions: 2009 Is a Critical Juncture for the
Army's Future Combat System, [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-08-408] (Washington, D.C.: Mar. 7, 2008); GAO, Defense
Acquisitions: Significant Challenges Ahead in Developing and
Demonstrating Future Combat System's Network and Software, [hyperlink,
http://www.gao.gov/cgi-bin/getrpt?GAO-08-409] (Washington, D.C.: Mar.
7, 2008).
[3] John Warner National Defense Authorization Act for Fiscal Year
2007, Pub. L. No. 109-364, § 214 (2006).
[4] Department of Defense Appropriations Act, 2003, Pub. L. No. 107-248
§ 8121 (2002), and similar provisions in subsequent defense
appropriations acts.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: