The National Polar-orbiting Operational Environmental Satellite System (NPOESS) is a tri-agency acquisition--managed by the Department of Commerce's National Oceanic and Atmospheric Administration (NOAA), the Department of Defense (DOD), and the National Aeronautics and Space Administration (NASA)--which has experienced escalating costs, schedule delays, and technical difficulties. These factors led to a June 2006 decision to restructure the program thereby decreasing its complexity, increasing its estimated cost to $12.5 billion, and delaying the first two satellites by 3 to 5 years. GAO was asked to summarize a report being released today that evaluates progress in restructuring the acquisition, assesses the status of key program components and risks, and assesses the agencies' plans for obtaining the data originally planned to be collected by NPOESS sensors, but eliminated by the restructuring.
The NPOESS program office has completed most of the major activities associated with restructuring the acquisition, but key activities remain to be completed. In the past year, the program redefined the program's deliverables, costs, and schedules, and renegotiated the NPOESS contract. However, agency executives have not yet finalized selected acquisition documents. Without executive approval, the program lacks the underlying commitment needed to effectively manage a tri-agency program. In addition, given that DOD has stated it would not release fiscal year 2009 funds to the NPOESS program if key acquisition documents are not completed by August 2008, delays in completing these documents could affect the program's funding and schedule. In the past year, the NPOESS program has made progress in completing development and testing activities associated with the spacecraft, sensors, and ground systems. However, key milestones have been delayed and multiple risks remain. Specifically, poor workmanship and testing delays caused an 8-month slip in the delivery of a complex imaging sensor called the Visible/infrared imager radiometer suite. This late delivery caused a corresponding 8-month delay in the expected launch date of the NPOESS Preparatory Project demonstration satellite, moving it from late September 2009 to early June 2010. Moving forward, risks remain in completing the testing of key sensors and integrating them on the spacecraft, resolving interagency disagreements about the appropriate level of system security, and revising outdated operations and support cost estimates--which program officials say could increase the lifecycle cost by about $1 billion. The program office is aware of these risks and is working to mitigate them, but these issues could affect the program's overall schedule and cost. When the NPOESS restructuring agreement removed four climate and space environment sensors from the program and degraded four others, it led NASA, NOAA, and DOD to reassess their priorities and options for obtaining climate and space environment data. Since the June 2006 restructuring decision, the three agencies have taken preliminary steps to restore the capabilities of selected climate and space weather sensors that were removed from the NPOESS program by prioritizing the sensors, assessing options for restoring them, and making decisions to mitigate near-term data continuity needs by restoring two sensors to the demonstration satellite and one sensor to the first NPOESS satellite. However, the agencies have not yet developed plans on whether and how to replace sensors on a long-term basis as no plans have been made for sensors or satellites after the first satellite of the program. Until such a plan is developed, the agencies may lose their windows of opportunity for selecting cost-effective options or they may resort to an ad hoc approach to restoring these sensors. Almost 2 years have passed since key sensors were removed from the NPOESS program; further delays in establishing a plan could result in gaps in the continuity of climate and space data.
GAO-08-899T, Environmental Satellites: Polar-orbiting Satellite Acquisition Faces Delays; Decisions Needed on Whether and How to Ensure Climate Data Continuity
This is the accessible text file for GAO report number GAO-08-899T
entitled 'Environmental Satellites: Polar-orbiting Satellite
Acquisition Faces Delays; Decisions Needed on Whether and How to Ensure
Climate Continuity' which was released on June 19, 2008.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the House Committee on Science and Technology Subcommittee on
Energy and Environment:
United States Government Accountability Office:
GAO:
For Release on Delivery Expected at 10:00 a.m. EST:
Thursday, June 19, 2008:
Environmental Satellites:
Polar-orbiting Satellite Acquisition Faces Delays; Decisions Needed on
Whether and How to Ensure Climate Continuity:
Statement of David A. Powner, Director Information Technology
Management Issues:
GAO-08-899T:
GAO Highlights:
Highlights of GAO-08-899T, a testimony before the House Committee on
Science and Technology, Subcommittee on Energy and Environment.
Why GAO Did This Study:
The National Polar-orbiting Operational Environmental Satellite System
(NPOESS) is a tri-agency acquisition”managed by the Department of
Commerce‘s National Oceanic and Atmospheric Administration (NOAA), the
Department of Defense (DOD), and the National Aeronautics and Space
Administration (NASA)”which has experienced escalating costs, schedule
delays, and technical difficulties. These factors led to a June 2006
decision to restructure the program thereby decreasing its complexity,
increasing its estimated cost to $12.5 billion, and delaying the first
two satellites by 3 to 5 years.
GAO was asked to summarize a report being released today that evaluates
progress in restructuring the acquisition, assesses the status of key
program components and risks, and assesses the agencies‘ plans for
obtaining the data originally planned to be collected by NPOESS
sensors, but eliminated by the restructuring.
What GAO Found:
The NPOESS program office has completed most of the major activities
associated with restructuring the acquisition, but key activities
remain to be completed. In the past year, the program redefined the
program‘s deliverables, costs, and schedules, and renegotiated the
NPOESS contract. However, agency executives have not yet finalized
selected acquisition documents. Without executive approval, the program
lacks the underlying commitment needed to effectively manage a tri-
agency program. In addition, given that DOD has stated it would not
release fiscal year 2009 funds to the NPOESS program if key acquisition
documents are not completed by August 2008, delays in completing these
documents could affect the program‘s funding and schedule.
In the past year, the NPOESS program has made progress in completing
development and testing activities associated with the spacecraft,
sensors, and ground systems. However, key milestones have been delayed
and multiple risks remain. Specifically, poor workmanship and testing
delays caused an 8-month slip in the delivery of a complex imaging
sensor called the Visible/infrared imager radiometer suite. This late
delivery caused a corresponding 8-month delay in the expected launch
date of the NPOESS Preparatory Project demonstration satellite, moving
it from late September 2009 to early June 2010. Moving forward, risks
remain in completing the testing of key sensors and integrating them on
the spacecraft, resolving interagency disagreements about the
appropriate level of system security, and revising outdated operations
and support cost estimates”which program officials say could increase
the lifecycle cost by about $1 billion. The program office is aware of
these risks and is working to mitigate them, but these issues could
affect the program‘s overall schedule and cost.
When the NPOESS restructuring agreement removed four climate and space
environment sensors from the program and degraded four others, it led
NASA, NOAA, and DOD to reassess their priorities and options for
obtaining climate and space environment data. Since the June 2006
restructuring decision, the three agencies have taken preliminary steps
to restore the capabilities of selected climate and space weather
sensors that were removed from the NPOESS program by prioritizing the
sensors, assessing options for restoring them, and making decisions to
mitigate near-term data continuity needs by restoring two sensors to
the demonstration satellite and one sensor to the first NPOESS
satellite. However, the agencies have not yet developed plans on
whether and how to replace sensors on a long-term basis as no plans
have been made for sensors or satellites after the first satellite of
the program. Until such a plan is developed, the agencies may lose
their windows of opportunity for selecting cost-effective options or
they may resort to an ad hoc approach to restoring these sensors.
Almost 2 years have passed since key sensors were removed from the
NPOESS program; further delays in establishing a plan could result in
gaps in the continuity of climate and space data.
What GAO Recommends:
In its report, GAO recommends that Commerce, DOD, and NASA coordinate
to develop plans on whether and how to restore climate and space
weather sensors removed from the NPOESS program. GAO also reemphasizes
that the appropriate executives finalize and approve key acquisition
documents. Agency officials agreed with both recommendations.
[End of section]
Mr. Chairman and Members of the Subcommittee:
We appreciate the opportunity to participate in today's hearing to
discuss our work on the $12.5 billion dollar National Polar-orbiting
Operational Environmental Satellite System (NPOESS) program. NPOESS is
expected to be a state-of-the-art, environment-monitoring satellite
system that will replace two existing polar-orbiting environmental
satellite systems. Polar-orbiting satellites provide data and imagery
that are used by weather forecasters, climatologists, and the military
to map and monitor changes in weather, climate, the oceans, and the
environment. The NPOESS program is considered critical to the United
States' ability to maintain the continuity of data required for weather
forecasting (including severe weather events such as hurricanes) and
global climate monitoring through the year 2026.
Three agencies share responsibility for the NPOESS program: the
Department of Commerce's National Oceanic and Atmospheric
Administration (NOAA), the Department of Defense (DOD)/United
States Air Force, and the National Aeronautics and Space Administration
(NASA). To manage the NPOESS program, these agencies established a tri-
agency integrated program office. In recent years, the program has
experienced escalating costs, schedule delays, and technical
difficulties, which led to a June 2006 decision to restructure it. This
decision decreased the complexity of the program by reducing the number
of satellites and sensors, increased the estimated cost of the program
to $12.5 billion, and delayed the launches of the first two satellites
by 3 and 5 years, respectively.
As requested, this statement summarizes our report being released today
that (1) evaluates the NPOESS program office's progress in
restructuring the acquisition, (2) assesses the status of key program
components and risks, (3) and assesses NASA's, NOAA's, and DOD's plans
for obtaining the environmental data originally planned to be collected
by NPOESS sensors, but then eliminated by the restructuring.[Footnote
1]
In preparing this testimony, we relied on our work supporting the
accompanying report. That report contains a detailed overview of our
scope and methodology. In addition, we updated factual information on
sensors and due dates as warranted. All the work on which this
testimony is based was performed in accordance with generally accepted
government auditing standards.
Results in Brief:
The NPOESS program office has completed most of the major activities
associated with restructuring the acquisition, but key activities
remain to be completed. In the past year, the program redefined the
program's deliverables, costs, and schedules, and renegotiated the
NPOESS contract. However, agency executives have not yet finalized
selected acquisition documents, including the tri-agency memorandum of
agreement and the acquisition program baseline. In April 2007, we
reported that key acquisition documents were already over six months
late and recommended that agency officials complete them
immediately.[Footnote 2] Agency officials subsequently extended the due
dates of the documents. Moreover, although DOD has had a role in
delaying their completion, the Department has stated it would not
release fiscal year 2009 funds to the NPOESS program if key acquisition
documents are not completed by August 2008. Without executive approval
of the memorandum of agreement and other key documents, the program
lacks the underlying commitment needed to effectively manage a tri-
agency program. In addition, given DOD's recent instructions, any
further delays in completing these documents could affect the program's
funding and schedule.
In the past year, the NPOESS program has made progress in completing
development and testing activities associated with the spacecraft,
sensors, and ground systems. However, key milestones have been delayed
and multiple risks remain. Specifically, poor workmanship and testing
delays caused an 8-month slip in the delivery of a complex imaging
sensor called the Visible/infrared imager radiometer suite. This late
delivery caused a corresponding 8-month delay in the expected launch
date of the NPOESS Preparatory Project demonstration satellite, moving
it from late September 2009 to early June 2010. Any delay in this
launch date shortens the time available for identifying lessons learned
from the demonstration satellite while it is in orbit and incorporating
these lessons in the development of the first NPOESS satellite. Such
delays could also lead to gaps in weather and climate data continuity
if existing satellites begin to degrade or fail. Moving forward, risks
remain in completing the testing of key sensors and integrating them on
the spacecraft, resolving interagency disagreements about the
appropriate level of system security, and revising outdated operations
and support cost estimates--which program officials say could increase
the lifecycle cost by about $1 billion. The program office is aware of
these risks and is working to mitigate them, but these issues could
affect the program's overall schedule and cost.
When the NPOESS restructuring agreement removed four climate and space
environment sensors from the program and degraded four others, it led
NASA, NOAA, and DOD to reassess their priorities and options for
obtaining climate and space environment data. Since the June 2006
restructuring decision, the three agencies have taken preliminary steps
to restore the capabilities of selected climate and space weather
sensors that were removed from the NPOESS program by prioritizing the
sensors, assessing options for restoring them, and making decisions to
mitigate near-term data continuity needs by restoring two sensors to
the demonstration satellite and one sensor to the first NPOESS
satellite. However, the agencies have not yet developed plans on
whether and how to ensure climate and space weather data on a long-term
basis as no plans have been made for sensors or satellites after the
first satellite of the program. Until such a plan is developed, the
agencies may lose their windows of opportunity for selecting cost-
effective options or they may resort to an ad hoc approach to restoring
these sensors. Almost 2 years have passed since key sensors were
removed from the NPOESS program; further delays in establishing a plan
could result in gaps in the continuity of climate and space data.
In our report, we made recommendations to all three agencies to
establish plans on whether and how to restore the climate and space
sensors removed from the NPOESS program by June 2009, in cases where
the sensors are warranted and justified. In addition, we also
reemphasized a recommendation made in our prior report[Footnote 3] that
the appropriate NASA, NOAA, and DOD executives immediately finalize key
acquisition documents. All three agencies concurred with these
recommendations.
Background:
Since the 1960s, the United States has operated two separate
operational polar-orbiting meteorological satellite systems: the Polar-
orbiting Operational Environmental Satellite (POES) series-- managed by
NOAA--and the Defense Meteorological Satellite Program (DMSP)--managed
by the Air Force. These satellites obtain environmental data that are
processed to provide graphical weather images and specialized weather
products--including both terrestrial and space weather. These satellite
data are also the predominant input to numerical weather prediction
models, which are a primary tool for forecasting weather 3 or more days
in advance--including forecasting the path and intensity of hurricanes.
The weather products and models are used to predict the potential
impact of severe weather so that communities and emergency managers can
help prevent and mitigate their effects. Polar satellites also provide
data used to monitor environmental phenomena, such as ozone depletion
and drought conditions, as well as data sets that are used by
researchers for a variety of studies such as climate monitoring.
NPOESS Overview:
With the expectation that combining the POES and DMSP programs would
reduce duplication and result in sizable cost savings, a May 1994
Presidential Decision Directive required NOAA and DOD to converge the
two satellite programs into a single satellite program capable of
satisfying both civilian and military requirements.[Footnote 4] The
converged program, NPOESS, is considered critical to the United States'
ability to maintain the continuity of data required for weather
forecasting and global climate monitoring through the year 2026. To
manage this program, DOD, NOAA, and NASA formed the tri-agency
Integrated Program Office, located within NOAA.
Within the program office, each agency has the lead on certain
activities: NOAA has overall program management responsibility for the
converged system and for satellite operations; DOD has the lead on the
acquisition; and NASA has primary responsibility for facilitating the
development and incorporation of new technologies into the converged
system. NOAA and DOD share the costs of funding NPOESS, while NASA
funds specific technology projects and studies. The NPOESS program
office is overseen by an Executive Committee, which is made up of the
Administrators of NOAA and NASA and the Under Secretary of the Air
Force.
NPOESS is a major system acquisition that was originally estimated to
cost about $6.5 billion over the 24-year life of the program from its
inception in 1995 through 2018. The program is to provide satellite
development, satellite launch and operation, and ground-based satellite
data processing. These deliverables are grouped into four main
categories: (1) the space segment, which includes the satellites and
sensors; (2) the integrated data processing segment, which is the
system for transforming raw data into environmental data records (EDR)
and is to be located at four data processing centers; (3) the command,
control, and communications segment, which includes the equipment and
services needed to support satellite operations; and (4) the launch
segment, which includes launch vehicle services.
When the NPOESS engineering, manufacturing, and development contract
was awarded in August 2002, the cost estimate was adjusted to $7
billion. Acquisition plans called for the procurement and launch of six
satellites over the life of the program, as well as the integration of
13 instruments--consisting of 10 environmental sensors and 3
subsystems. Together, the sensors were to receive and transmit data on
atmospheric, cloud cover, environmental, climatic, oceanographic, and
solar-geophysical observations. The subsystems were to support non-
environmental search and rescue efforts, sensor survivability, and
environmental data collection activities. The program office considered
4 of the sensors to be critical because they provide data for key
weather products; these sensors are in bold in table 1, which describes
each of the expected NPOESS instruments.
Table 1: Expected NPOESS Instruments, as of August 31, 2004 (critical
sensors are in bold):
Instrument: Advanced technology microwave sounder;
Description: Measures microwave energy released and scattered by the
atmosphere and is to be used with infrared sounding data from the cross-
track infrared sounder to produce daily global atmospheric temperature,
humidity, and pressure profiles.
Instrument: Aerosol polarimetry sensor;
Description: Retrieves specific measurements of clouds and aerosols
(liquid droplets or solid particles suspended in the atmosphere, such
as sea spray, smog, and smoke).
Instrument: Conical-scanned microwave imager/sounder;
Description: Collects microwave images and data needed to measure rain
rate, ocean surface wind speed and direction, amount of water in the
clouds, and soil moisture, as well as temperature and humidity at
different atmospheric levels.
Instrument: Cross-track infrared sounder;
Description: Collects measurements of the earth's radiation to
determine the vertical distribution of temperature, moisture, and
pressure in the atmosphere.
Instrument: Data collection system;
Description: Collects environmental data from platforms around the
world and delivers them to users worldwide.
Instrument: Earth radiation budget sensor;
Description: Measures solar short-wave radiation and long-wave
radiation released by the earth back into space on a worldwide scale to
enhance long-term climate studies.
Instrument: Ozone mapper/profiler suite;
Description: Collects data needed to measure the amount and
distribution of ozone in the earth's atmosphere. Consists of two
components (limb and nadir), which can be provided separately.
Instrument: Radar altimeter;
Description: Measures variances in sea surface height/topography and
ocean surface roughness, which are used to determine sea surface
height, significant wave height, and ocean surface wind speed and to
provide critical inputs to ocean forecasting and climate prediction
models.
Instrument: Search and rescue satellite aided tracking system;
Description: Detects and locates aviators, mariners, and land-based
users in distress.
Instrument: Space environmental sensor suite;
Description: Collects data to identify, reduce, and predict the effects
of space weather on technological systems, including satellites and
radio links.
Instrument: Survivability sensor;
Description: Monitors for attacks on the satellite and notifies other
instruments in case of an attack.
Instrument: Total solar irradiance sensor;
Description: Monitors and captures total and spectral solar irradiance
data.
Instrument: Visible/infrared imager radiometer suite (VIIRS);
Description: Collects images and radiometric data used to provide
information on the earth's clouds, atmosphere, ocean, and land
surfaces.
Source: GAO analysis of NPOESS program office data.
[End of table]
In addition, a demonstration satellite, called the NPOESS Preparatory
Project (NPP), was planned to be launched several years before the
first NPOESS satellite in order to reduce the risk associated with
launching new sensor technologies and to ensure continuity of climate
data with NASA's Earth Observing System satellites. NPP was to host
three of the four critical NPOESS sensors, as well as one other
noncritical sensor and to provide the program office and the processing
centers an early opportunity to work with the sensors, ground control,
and data processing systems.[Footnote 5]
When the NPOESS development contract was awarded, the schedule for
launching the satellites was driven by a requirement that the
satellites be available to back up the final POES and DMSP satellites
should anything go wrong during the planned launches of these
satellites. Early program milestones included (1) launching NPP by May
2006, (2) having the first NPOESS satellite available to back up the
final POES satellite launch in March 2008, and (3) having the second
NPOESS satellite available to back up the final DMSP satellite launch
in October 2009. If the NPOESS satellites were not needed to back up
the final predecessor satellites, their anticipated launch dates would
have been April 2009 and June 2011, respectively.
NPOESS Experienced Cost Increases, Schedule Delays, and Technical
Problems That Led to Decision to Restructure the NPOESS Program:
Over several years, we reported that NPOESS had experienced continued
cost increases, schedule delays, and serious technical
problems.[Footnote 6] By November 2005, we estimated that the cost of
the program had grown from $7 billion to over $10 billion. In addition,
the program was experiencing major technical problems with the VIIRS
sensor and expected to delay the launch date of the first satellite by
almost 2 years. These issues ultimately required difficult decisions to
be made about the program's direction and capabilities. The Nunn-
McCurdy law requires DOD to take specific actions when a major defense
acquisition program cost growth exceeds certain thresholds.[Footnote 7]
The law requires the Secretary of Defense to notify Congress when a
major defense acquisition is expected to overrun its current baseline
by 15 percent or more and to certify the current program to Congress
when it is expected to overrun its baseline by 25 percent or
more.[Footnote 8] In November 2005, NPOESS exceeded the 25 percent
threshold, and DOD was required to certify the program. Certifying a
program entails providing a determination that (1) the program is
essential to national security, (2) there are no alternatives to the
program that will provide equal or greater military capability at less
cost, (3) the new estimates of the program's cost are reasonable, and
(4) the management structure for the program is adequate to manage and
control costs. DOD established tri-agency teams--made up of DOD, NOAA,
and NASA experts--to work on each of the four elements of the
certification process.
In June 2006, DOD (with the agreement of both of its partner agencies)
certified a restructured NPOESS program, estimated to cost $12.5
billion through 2026.[Footnote 9] This decision approved a cost
increase of $4 billion over the prior approved baseline cost and
delayed the launch of NPP and the first 2 satellites by roughly 3 to 5
years. The new program also entailed reducing the number of satellites
to be produced and launched from 6 to 4, and reducing the number of
instruments on the satellites from 13 to 9--consisting of 7
environmental sensors and 2 subsystems. It also entailed using NPOESS
satellites in the early morning and afternoon orbits and relying on
European satellites for midmorning orbit data.[Footnote 10] Table 2
summarizes the major program changes made under the Nunn-McCurdy
certification decision.
Table 2: Summary of Changes to the NPOESS Program, as of June 2006:
Key area: Life cycle range;
Program before the Nunn-McCurdy decision: 1995-2020;
Program after the Nunn-McCurdy decision: 1995-2026.
Key area: Estimated life cycle cost;
Program before the Nunn-McCurdy decision: $8.4 billion;
Program after the Nunn-McCurdy decision: $12.5 billion.
Key area: Launch schedule;
Program before the Nunn-McCurdy decision: NPP by October 2006;
First NPOESS by November 2009;
Second NPOESS by June 2011;
Program after the Nunn-McCurdy decision: NPP by January 2010[A];
First NPOESS by January 2013;
Second NPOESS by January 2016.
Key area: Management structure;
Program before the Nunn-McCurdy decision: System Program Director
reports to a tri-agency steering committee and a tri-agency Executive
Committee;
Independent program reviews noted insufficient system engineering and
cost analysis staff;
Program after the Nunn-McCurdy decision: System Program Director is
responsible for day-to-day program management and reports to the
Program Executive Officer.
Program Executive Officer oversees program and reports to the tri-
agency Executive Committee.
Key area: Number of satellites;
Program before the Nunn-McCurdy decision: 6 (in addition to NPP);
Program after the Nunn-McCurdy decision: 4 (in addition to NPP).
Key area: Number of orbits;
Program before the Nunn-McCurdy decision: 3 (early morning, midmorning,
and afternoon);
Program after the Nunn- McCurdy decision: 2 (early morning and
afternoon;
will rely on European satellites for midmorning orbit data).
Key area: Number and complement of instruments;
Program before the Nunn-McCurdy decision: 13 instruments (10 sensors
and 3 subsystems);
Program after the Nunn-McCurdy decision: 9 instruments (7 sensors and 2
subsystems);
4 of the sensors are to provide fewer capabilities.
Key area: Number of EDRs;
Program before the Nunn-McCurdy decision: 55;
Program after the Nunn-McCurdy decision: 39 (6 are to be degraded
products).
Source: GAO analysis of NPOESS program office data.
[A] Although the Nunn-McCurdy certification decision specifies NPP is
to launch by January 2010, NASA planned to launch it by September 2009
to reduce the possibility of a climate data continuity gap.
[End of table]
The Nunn-McCurdy certification decision established new milestones for
the delivery of key program elements, including launching NPP by
January 2010, launching the first NPOESS satellite by January 2013, and
launching the second NPOESS satellite by January 2016. These revised
milestones deviated from prior plans to have the first NPOESS satellite
available to back up the final POES satellite should anything go wrong
during that launch.
Delaying the launch of the first NPOESS satellite meant that if the
final POES satellite fails on launch, satellite data users would need
to rely on the existing constellation of environmental satellites until
NPP data becomes available--almost 2 years later. Although NPP was not
intended to be an operational asset, NASA agreed to move NPP to a
different orbit so that its data would be available in the event of a
premature failure of the final POES satellite. If the health of the
existing constellation of satellites diminishes--or if NPP data is not
available, timely, and reliable--there could be a gap in environmental
satellite data.
In order to reduce program complexity, the Nunn-McCurdy certification
decision decreased the number of NPOESS sensors from 13 to 9 and
reduced the functionality of 4 sensors. Specifically, of the 13
original sensors, 5 sensors remain unchanged (but 2 are on a reduced
number of satellites), 3 were replaced with older or less capable
sensors, 1 was modified to provide less functionality, and 4 were
canceled. The certification decision also made allowances for the
reintegration of the cancelled sensors. Specifically, the program was
directed to build each NPOESS spacecraft with enough room and power to
accommodate the sensors that were removed from the program and to fund
the integration and testing of any sensors that are later restored.
Agency sponsors external to the program would be responsible for
justifying and funding the sensor's development, while the NPOESS
Executive Committee would have the final decision on whether to include
the sensor on a specific satellite. Table 3 identifies the changes to
the NPOESS instruments.
Table 3: Changes to NPOESS Instruments (critical sensors in bold):
Instrument: Advanced technology microwave sounder;
Status of instrument after Nunn-McCurdy Decision: Sensor unchanged;
to be included on NPP and on afternoon satellites.
Instrument: Aerosol polarimetry sensor;
Status of instrument after Nunn-McCurdy Decision: Sensor was
canceled[A].
Instrument: Conical-scanned microwave imager/sounder;
Status of instrument after Nunn-McCurdy Decision: Sensor was canceled;
program office to procure a less complex microwave imager/sounder for
inclusion beginning on the second NPOESS satellite.
Instrument: Cross-track infrared sounder;
Status of instrument after Nunn-McCurdy Decision: Sensor unchanged;
to be included on NPP and on afternoon satellites.
Instrument: Data collection system;
Status of instrument after Nunn- McCurdy Decision: No change;
subsystem is to be included on all four NPOESS satellites.
Instrument: Earth radiation budget sensor;
Status of instrument after Nunn-McCurdy Decision: Sensor was canceled;
is to be replaced by a legacy sensor[A].
Instrument: Ozone mapper/profiler suite;
Status of instrument after Nunn-McCurdy Decision: One part of the
sensor (OMPS-Limb) was canceled;
remaining part is to be included on NPP and on all four NPOESS
satellites[A].
Instrument: Radar altimeter;
Status of instrument after Nunn-McCurdy Decision: Sensor was
canceled[A].
Instrument: Search and rescue satellite aided tracking system;
Status of instrument after Nunn-McCurdy Decision: Sensor unchanged;
subsystem is to be included on all four NPOESS satellites.
Instrument: Space environmental sensor suite;
Status of instrument after Nunn-McCurdy Decision: Sensor was canceled;
is to be replaced by a less capable, less expensive legacy sensor[A].
Instrument: Survivability sensor;
Status of instrument after Nunn- McCurdy Decision: Subsystem was
canceled[A].
Instrument: Total solar irradiance sensor;
Status of instrument after Nunn-McCurdy Decision: Sensor was
canceled[A].
Instrument: Visible/infrared imager radiometer suite;
Status of instrument after Nunn-McCurdy Decision: Sensor unchanged;
sensor is to be included on NPP and on all four NPOESS satellites.
Source: GAO analysis of NPOESS program office data.
[A] While direct program funding for these sensors was eliminated,
these sensors could be reintegrated should other parties choose to fund
them. The Nunn-McCurdy certification decision notes that the spacecraft
is to include space for these sensors and funds to integrate them.
[End of table]
The changes in NPOESS sensors affected the number and quality of the
resulting weather and environmental products, called environmental data
records (EDR). In selecting sensors for the restructured program during
the Nunn-McCurdy process, decision makers placed the highest priority
on continuing current operational weather capabilities and a lower
priority on obtaining selected environmental and climate measuring
capabilities. As a result, the revised NPOESS system has significantly
less capability for providing global climate measures than was
originally planned. Specifically, the number of EDRs was decreased from
55 to 39, of which 6 are of a reduced quality. The 39 EDRs that remain
include cloud base height, land surface temperature, precipitation type
and rate, and sea surface winds. The 16 EDRs that were removed include
cloud particle size and distribution, sea surface height, net solar
radiation at the top of the atmosphere, and products to depict the
electric fields in the space environment. The 6 EDRs that are of a
reduced quality include ozone profile, soil moisture, and multiple
products depicting energy in the space environment.
Major Restructuring Activities Have Been Completed, but Key Remaining
Activities Could Affect Funding and Schedule:
The program office has completed major activities associated with
restructuring NPOESS, but key supporting activities remain--including
obtaining approval of key acquisition documents--and delays in
completing these activities could affect the program's funding and
schedule. Restructuring a major acquisition program like NPOESS is a
process that involves reassessing and redefining the program's
deliverables, costs, and schedules, and renegotiating the contract. The
restructuring process also involves revising important acquisition
documents such as the tri-agency memorandum of agreement, the
acquisition strategy, the system engineering plan, the integrated
master schedule defining what needs to happen by when, and the
acquisition program baseline. In April 2007, we reported that the key
acquisition documents were over six months late from their original
September 2006 due date, and we recommended that the appropriate
executives immediately finalize them[Footnote 11]. This recommendation
has not yet been addressed and agency officials subsequently extended
the due dates of the documents to September 2007.
During the past year, the program redefined the program's deliverables,
costs, and schedules, and renegotiated the NPOESS contract. To do so,
the program developed a new program plan and conducted an integrated
baseline review of the entire program, which validated that the new
deliverables, costs, and schedules were feasible. It also completed key
acquisition documents including the system engineering plan and the
integrated master schedule. The program and the prime contractor signed
a modified contract in July 2007.
However, key activities remain to be completed, including obtaining
executive approval of key acquisition documents. Specifically, even
though agency officials were expected to approve key acquisition
documents by September 2007, the appropriate executives have not yet
signed off on documents including the tri-agency memorandum of
agreement or the acquisition strategy report. They have also not signed
off on the acquisition program baseline, the fee management plan, the
test and evaluation master plan, and the two-orbit program plan (a plan
for how to use European satellite data with NPOESS).
Program officials stated that the program has been able to renegotiate
the contract and to proceed in developing sensors and systems without
these documents being signed because the documents have widespread
acceptance within the three agencies. They reported that the delays are
largely due to the complexity of obtaining approval from three
agencies. For example, program officials reported that an organization
within DOD suggested minor changes to the tri-agency memorandum of
agreement after months of coordination and after it had already been
signed by both the Secretary of Commerce and the Administrator of NASA.
Further, after this issue was resolved, a senior official at DOD
requested another change to the document. The program office has now
made the recommended changes and is re-initiating the coordination
process.
More recently, in April 2008, DOD moved the due dates for all of the
acquisition documents other than the memorandum of agreement and fee
management plan from September 2007 to August 31, 2008. (See appendix I
for the history of the due dates and status of each document). In
addition, even though DOD has had a role in delaying these documents,
the Department has stated it would not release fiscal year 2009 funds
to the program if these acquisition documents are not completed by the
new due date. Without executive approval of key acquisition documents,
the program lacks the underlying commitment necessary to effectively
manage a tri-agency program. In addition, given DOD's newest
instructions, any further delays in completing these acquisition
documents could affect the program's funding and schedule.
Program Has Made Progress, but Key Milestones Have Been Delayed and
Risks Remain:
Over the last year, the NPOESS program has made progress by completing
planned development and testing activities on its ground and space
segments, but key milestones for delivering the VIIRS sensor and
launching NPP have been delayed by about 8 months. Moving forward,
risks remain in completing the testing of key sensors and integrating
them on the NPP spacecraft, in resolving interagency disagreements on
the appropriate level of system security, and in revising estimated
costs for satellite operations and support. The program office is aware
of these risks and is working to mitigate them, but continued problems
could affect the program's overall schedule and cost. Given the tight
time frames for completing key sensors, integrating them on the NPP
spacecraft, and getting the ground-based data processing system
developed, tested, and deployed, it is important for the NPOESS
Integrated Program Office, the Program Executive Office, and the
Executive Committee to continue to provide close oversight of
milestones and risks.
Ground Segment--Progress Made but Important Work Remains to Be Done:
Development of the ground segment--which includes the interface data
processing system, the ground stations that are to receive satellite
data, and the ground-based command, control, and communications system-
-is under way and on track. For example, the Interface Data Processing
System has been installed at one of the two locations that are to
receive NPP data, and the command, control, and communications system
passed acceptance testing for use with NPP. However, important work in
developing the algorithms that translate satellite data into weather
products within the integrated data processing segment remains to be
completed. Table 4 describes each of the components of the ground
segment and identifies the program-provided risk level and status of
each.
Table 4: Status of Ground Segment Components:
Ground segment component/ description: Interface Data Processing System
(IDPS)--;
A ground-based system that is to process the sensors' data so that they
are usable by the data processing centers and the broader community of
environmental data users. IDPS will be deployed at the four weather
data processing centers;
Program-identified risk level: Low;
Status: IDPS software is being developed in a series of builds. In
2007, software developers required additional resources and fell behind
schedule on build 1.5 activities due to unanticipated complexities in
developing algorithms that will make use of data collected by the Ozone
mapper/profiler suite in orbit--as well as late delivery of key
information on this instrument.
As of January 2008, IDPS build 1.5 had been developed and was
undergoing testing to check the quality of its performance;
additional builds are planned to be developed prior to launch and will
be used with NPP.
In January 2008, IDPS hardware was installed at one of the data
processing centers (NOAA's National Satellite Operations Facility in
Suitland, Maryland) and is expected to be installed at the Air Force
Weather Agency this summer. In addition, the Air Force Weather Agency
has begun early testing of NPOESS data. Site acceptance testing for NPP
is scheduled to be completed in December 2008.
Ground segment component/ description: Ground stations for receiving
satellite data--.
15 unmanned ground stations around the world (called SafetyNet™) are to
receive satellite data and send it to the four data processing centers;
Program-identified risk level: Low;
Status: NOAA is working with domestic and foreign authorities to obtain
approval to operate ground stations to receive satellite data.
According to agency officials, the full complement of ground stations
will not be in place in time for the first NPOESS satellite launch. The
ground stations will be phased in by the launch of the second
satellite. To date, the program office has reached agreement with 4 of
15 ground station sites.
Ground segment component/ description: Command, control, and
communications segment--.
Performs the day-to-day monitoring and command of the spacecraft and
sensors;
Program-identified risk level: Low;
Status: The command, control, and communications segment is being
developed in a series of builds. In August 2007, build 1.4 transitioned
from development to operations and support. In addition, the command,
control, and communications acceptance testing for NPP has been
completed.
Source: GAO summary of NPOESS program office data.
[End of table]
Space Segment--Progress Made, but One Sensor Was Delayed and Sensors
Continue to Face Risks:
Over the past year, the program made progress on the development of the
space segment, which includes the sensors and the spacecraft. Five
sensors are of critical importance because they are to be launched on
the NPP satellite.[Footnote 12] Initiating work on another sensor, the
Microwave Imager Sounder, is also important because this new sensor--
which is to replace the canceled Conical-scanned microwave imager/
sounder sensor--will need to be developed in time for the second NPOESS
satellite launch. Among other activities, the program has successfully
completed vibration testing of the flight unit of the Cross-track
infrared sounder (CrIS), a major pre-environmental testing review for
the VIIRS instrument, integration and risk reduction testing of the
flight unit of the Ozone mapper/profiler suite, and thermal testing of
the NPP spacecraft with three sensors on board.[Footnote 13] In
addition, the program made decisions on how to proceed with the
Microwave imager sounder and recently awarded a contract to a
government laboratory for its development.
However, the program experienced problems on VIIRS, including poor
workmanship on selected subcomponents and delays in completing key
tests. These issues delayed VIIRS delivery to the NPP contractor by 8
months. This late delivery will in turn delay the satellite's launch
from late September 2009 to early June 2010. This delay shortens the
time available for incorporating lessons learned from NPP while it is
in orbit into future NPOESS missions and could lead to gaps in the
continuity of climate and weather data if predecessor satellites fail
prematurely. Also, the CrIS sensor experienced a cost overrun and
schedule delays as the contractor worked to recover from a structural
failure and is currently several weeks behind its schedule due to
thermal vacuum testing taking longer than planned. The status and risk
level of each of the components of the space segment is described in
table 5.
Table 5: Status of Selected Components of the Space Segment, as of May
2008:
Space segment component: Visible/infrared imager radiometer suite
(VIIRS);
Program-identified risk level: High;
Status: In April 2007, we reported that the contractor had identified a
problem with the VIIRS baseline filter during environmental testing
that caused degraded performance in the filter's image quality.
Specifically, this problem involves light leaking across the seams of
the filter, resulting in inaccurate measurements of ocean color. In
October 2007, the NPOESS Executive Committee decided to continue sensor
development with the baseline filter because changing it would increase
risks to sensor development, delay the delivery of the sensor, and risk
delays to the launch of NPP. An improved VIIRS filter is planned to be
included on the flight units on future NPOESS missions.
More recently, the VIIRS contractor experienced problems with
workmanship on electrical and cryoradiator components and delays in
executing tests.[A] These factors slowed the sensor's development.
The VIIRS flight unit was originally scheduled to be delivered to NPP
by July 2008, but due to technical issues and testing schedule delays,
VIIRS' delivery to NPP is now planned for April 2009.
Space segment component: Cross-track infrared sounder (CrIS);
Program- identified risk level: Moderate;
Status: In April 2007, we reported that development of CrIS was put on
hold in October 2006 when the flight unit designated to go on NPP
experienced a major structural failure during its vibration testing.
Acceptance testing began again in mid-2007, and the structural
stability of the frame was approved in August 2007. The flight unit is
currently undergoing thermal vacuum testing--which has taken longer
than planned. The flight unit was expected to be delivered to NPP by
May 2008, but it is now expected to be delivered in August 2008.
Space segment component: Ozone mapper/profiler suite (nadir and limb);
Program-identified risk level: Low;
Status: In April 2007, program officials had agreed to fund the
reintegration of the limb component on NPP. The first flight unit
completed key integration risk reduction testing and is expected to be
delivered to the NPP contractor for integration in August 2008.
Space segment component: Advanced technology microwave sounder;
Program-identified risk level: Low;
Status: The flight unit for NPP was developed by a NASA contractor and
delivered to the program in October 2005. The NPP contractor integrated
the flight unit on the spacecraft in December 2006 and is awaiting
delivery of the other sensors in order to complete integration testing.
Space segment component: Clouds and the earth's radiant energy system;
Program-identified risk level: Not yet rated;
Status: In January 2008, the NPOESS Executive Committee approved
including this instrument on NPP. The sensor has already been built but
requires some refurbishment. It is expected to be delivered to the NPP
spacecraft for integration in October 2008. In January 2008, the
program office was directed to develop an additional sensor for the
first NPOESS satellite.
Space segment component: Microwave imager/ sounder;
Program-identified risk level: Low;
Status: A new microwave imager/sounder sensor is being planned to
replace the canceled Conical-scanned microwave imager/ sounder. In May
2008, the program office selected the U.S. Naval Research Lab to
develop the sensor for the second NPOESS satellite. If it is more cost
effective to do so, the program office plans to move production of the
second and third MIS sensors to a contractor.
Space segment component: Spacecraft;
Program-identified risk level: Low;
Status: Both the development of the spacecraft for NPP and the
spacecraft for NPOESS are on track; The NPP spacecraft was completed in
June 2005. The NPP contractor has completed over a year's worth of risk
reduction activities, which included thermal testing of the spacecraft
with three of the sensors on board; The critical design review of the
first NPOESS spacecraft is scheduled to be completed in April 2009,
with the launch date scheduled for January 2013.
Source: GAO analysis of NPOESS Integrated Program Office data.
[A] The cryoradiator is a key component of the VIIRS sensor. It is
intended to cool down components of the sensor.
[End of table]
Program Risks Remain; Continued Oversight Is Needed to Prevent Further
Cost Increases and Schedule Delays:
Moving forward, the program continues to face risks. Over the next 2
years, it will need to complete the development of the key sensors,
test them, integrate and test them on the NPP spacecraft, and test
these systems with the ground-based data processing systems. In
addition, the program faces two other issues that could affect its
overall schedule and cost. One is that there continues to be
disagreement between NOAA and DOD on the appropriate level of system
security. To date, NPOESS has been designed and developed to meet DOD's
standards for a mission essential system, but NOAA officials believe
that the system should be built to meet more stringent
standards.[Footnote 14] Implementing more stringent standards could
cause rework and retesting, and potentially affect the cost and
schedule of the system. Another issue is that program life cycle costs
could increase once a better estimate of the cost of operations and
support is known. The $12.5 billion estimated life cycle cost for
NPOESS includes a rough estimate of $1 billion for operations and
support.
The NPOESS program office is working closely with the contractor and
subcontractors to resolve these program risks. To address sensor risks,
the program office and officials from NASA's Goddard Space Flight
Center commissioned an independent review team to assess the
thoroughness and adequacy of practices being used in the assembly,
integration, and testing of the VIIRS and CrIS instruments in
preparation for the NPP spacecraft. The team found that the contractors
for both sensors had sound test programs in place, but noted risks with
VIIRS's schedule and with CrIS's reliability and performance. The
program office adjusted the VIIRS testing schedule and is monitoring
the CrIS testing results. In addition, the program office recently
instituted biweekly senior-level management meetings to review progress
on VIIRS's development, and program officials noted that both the prime
contractor and the program executive office will have senior officials
onsite at the contractor's facility to provide extensive, day-to-day
oversight of management activities to assist in resolving issues.
To address the risk posed by changing security requirements late in the
system's development, program officials commissioned a study to
determine the effect of more stringent standards on the system. This
study was completed in March 2008, but has not yet been released. To
address the risk of cost growth due to poor estimates of operations and
support costs, DOD's cost analysis group is currently refining this
estimate. Program officials estimated that the program costs could grow
by about $1 billion, and expect to finalize revised operations and
support costs in July 2008.
The program office is aware of program risks and is working to mitigate
them, but these issues could affect the program's overall schedule and
cost. Given the tight time frames for completing key sensors,
integrating them on the NPP spacecraft, and getting the ground-based
data processing system developed, tested, and deployed, it is important
for the NPOESS program office, the Program Executive Office, and the
Executive Committee to continue to provide close oversight of
milestones and risks.
Agencies Have Undertaken Preliminary Steps to Restore Key Sensors, but
Lack Timely Plans to Ensure Long-Term Data Continuity:
When the NPOESS restructuring agreement removed four climate and space
environment sensors from the program and degraded four others, it led
NASA, NOAA, and DOD to reassess their priorities and options for
obtaining climate and space environment data. Since the June 2006
restructuring decision, the three agencies have taken preliminary steps
to restore the capabilities of selected climate and space weather
sensors that were degraded or removed from the NPOESS program by
prioritizing the sensors, assessing options for restoring them, and
making decisions to restore selected sensors in order to mitigate near-
term data gaps. However, the agencies have not yet developed plans to
mitigate the loss of these sensors on a long-term basis. Best practices
in strategic planning suggest that agencies develop and implement long-
term plans to guide their short-term activities. Until such plans are
developed, the agencies may lose their windows of opportunity for
selecting cost-effective options or they may resort to an ad hoc
approach to restoring these sensors. Lacking plans almost 2 years after
key sensors were removed from the NPOESS program, the agencies face
increased risk of gaps in the continuity of climate and space
environment data.
While NPOESS was originally envisioned to provide only weather
observations, this mission was later expanded to include long-term
continuity for key climate data. Maintaining the continuity of climate
and space data over decades is important to identify long-term
environmental cycles (such as the 11-year solar cycle and multiyear
ocean cycles including the El Niño effect) and their impacts, and to
detect trends in climate change and global warming. The Nunn-McCurdy
restructuring decision removed four sensors and degraded the
functionality of four other sensors that were to provide these data.
DOD, NASA, and NOAA are now responsible for determining what to
restore, how to restore it, and the means for doing so. This
responsibility includes justifying the additional funding needed to
develop these sensors within their respective agencies' investment
decision processes. Best practices of leading organizations call for
defining a strategic plan to formalize priorities and plans for meeting
mission goals. Such a plan would include the agency's long-term goals
for climate and space weather measurements, the short-term activities
needed to attain these goals, and the milestones and resources needed
to support the planned activities.
NASA, NOAA, and DOD Have Identified Priorities, Assessed Options, and
Made Decisions to Restore Selected Sensors:
Since the June 2006 restructuring, NASA, NOAA, and DOD have taken
preliminary steps to restore sensor capabilities by determining
priorities for restoring sensor capabilities, assessing options for
obtaining sensor data over time, and making decisions to restore
selected sensors. Specifically, in August 2006, the NPOESS Senior User
Advisory Group--a group representing NASA, NOAA, and DOD system users-
-assessed the impact of the canceled or degraded sensors and identified
priorities for restoring them. In January 2007, a NOAA and NASA working
group on climate sensors prioritized which of the sensors were most
important to restore for climate purposes and proposed possible
solutions and mitigation efforts. Two other groups--the National
Research Council and a NOAA-DOD working group--have also issued reports
describing the impact of the loss of climate and space environmental
sensors, respectively.[Footnote 15] Table 6 summarizes the results of
these studies.
Table 6: Summary of Studies on Impacts of the Loss of Sensors and
Priorities for Restoring Them:
Sensor/ Description: Aerosol polarimetry sensor;
Likely impact of sensor loss: Decreased ability to improve air quality
monitoring over time;
Decreased ability to improve understanding of aerosol's impact on the
earth's radiation budget; that is, whether aerosols play a role in
global warming; Decreased ability to study the global distribution of
aerosols and the impact of aerosols on climate; Decreased ability to
improve military munitions targeting and intelligence collection;
Climate Working Group's priority for restoration: 6;
NPOESS Advisory Group's priority for restoration: 7.
Sensor/ Description: Conical-scanned microwave imager/sounder, to be
replaced by the Microwave imager/sounder;
Likely impact of sensor loss: Cancellation of the Conical-scanned
microwave imager/sounder raised concerns about the loss of critical
environmental data including sea surface temperatures, ice and snow
cover, and ocean surface wind speed; The Microwave imager/sounder is
intended to replace the Conical-scanned microwave imager/sounder.
However, because the new sensor's capabilities have not yet been fully
defined, the impact of the cancellation of the Conical-scanned
microwave imager/sounder is not clear;
Climate Working Group's priority for restoration: 5;
NPOESS Advisory Group's priority for restoration: 2.
Sensor/ Description: Earth radiation budget sensor (being replaced on
selected satellites by an existing sensor, the Clouds and the earth's
radiant energy system);
Likely impact of sensor loss: Decreased ability to measure the amount
of energy entering and leaving the earth; Reduced ability to determine
the causes of climate variability and change; Disruption of an over 28-
year measurement heritage of earth radiation budget data, which is
needed to assess long-term trends;
Climate Working Group's priority for restoration: 2;
NPOESS Advisory Group's priority for restoration: 6.
Sensor/ Description: Ozone mapper/profiler suite (limb);
Likely impact of sensor loss: Decreased ability to understand the
health of the ozone layer which absorbs solar ultraviolet radiation
that is potentially harmful to humans; Decreased ability to improve
global warming and air quality models to differentiate the impact of
changing ozone levels within the atmosphere;
Climate Working Group's priority for restoration: 4;
NPOESS Advisory Group's priority for restoration: 4.
Sensor/ Description: Space environmental sensor suite (to be replaced
on selected satellites by an existing technology sensor, the Space
environment monitor);
Likely impact of sensor loss: Decreased understanding of the effect of
space weather on military and civilian communications and electrical
systems--and ability to take timely mitigation actions; Decreased
situational awareness for missile intercept capabilities; Decreased
ability to assess Global Positioning System (GPS) accuracy;
Climate Working Group's priority for restoration: unranked;
NPOESS Advisory Group's priority for restoration: 1.
Sensor/ Description: Total solar irradiance sensor;
Likely impact of sensor loss: Decreased ability to understand the
influence of natural causes of climate change; Disruption of an over
28-year measurement heritage of solar irradiance data, which is needed
to assess long-term trends;
Climate Working Group's priority for restoration: 1;
NPOESS Advisory Group's priority for restoration: 5.
Sensor/ Description: Radar altimeter;
Likely impact of sensor loss: Reduced number of sea surface height and
other ocean measurements used in climate monitoring; Decreased ability
to measure sea-air interactions that affect regional weather patterns,
such as El Niño; Decreased understanding of storm intensification
(e.g., hurricanes), coastal turbulence, and underwater features
important to sailors; Climate Working Group's priority for restoration:
3;
NPOESS Advisory Group's priority for restoration: 3.
Sensor/ Description: Survivability sensor;
Likely impact of sensor loss: Sensor was to identify possible threats
to the NPOESS spacecraft and has no impact on climate observations;
Climate Working Group's priority for restoration: unranked;
NPOESS Advisory Group's priority for restoration: 8.
Source: GAO analysis of NASA, NOAA, DOD, and NRC data.
[End of table]
In addition to prioritizing the sensors, NASA, NOAA, and DOD identified
a variety of options for obtaining key sensor data over the next two
decades and continue to seek other options. The agencies identified
options including adding sensors back to a later NPOESS satellite,
adding sensors to another planned satellite, and developing a new
satellite to include several of the sensors. Examples of options for
several sensors are provided in figure 1. In addition, in December
2007, NOAA released a request for information to determine whether
commercial providers could include selected environmental sensors on
their satellites.
Figure 1: Selected Options for Restoring Selected Climate Sensors, as
of May 2008:
This figure is a horizontal flowchart showing selected options for
restoring selected climate sensors, as of May 2008.
[See PDF for image]
Source: DOD, NASA, and NOAA data.
Notes: (1) The satellites Terra, Aqua, Aura, Glory, and the Solar
radiation and climate experiment (SORCE) are all NASA missions. Jason-
1 is a joint mission between NASA and France, and the Ocean surface
topography mission (OSTM) is a joint mission between NASA, NOAA,
France, and the European Organization for the Exploitation of
Meteorological Satellites.
(2) The MIS sensor is not included in this chart because NOAA, NASA,
and DOD have already agreed to include it on the second, third, and
fourth NPOESS satellites. Options for the Space environment sensor
suite/ Space environment monitor and the Survivability sensor are not
included because DOD has not yet released them.
[End of figure]
In addition to prioritizing sensors and identifying options, over the
last year, NASA, NOAA, and DOD have taken steps to restore three
sensors on a near-term basis. Specifically, in April 2007, the NPOESS
Executive Committee decided to restore the limb component of the Ozone
mapper/profiler suite to the NPP satellite; in January 2008, to add the
Clouds and the earth's radiant energy sensor to NPP; and in May 2008 to
add the Total solar irradiance sensor to the first NPOESS satellite.
These decisions are expected to provide continuity for these sensors
through approximately 2015. Table 7 shows the latest planned
configuration of NPOESS satellites. NASA officials noted that they also
took steps to mitigate a potential gap in total solar irradiance data
by proposing to fund an additional 4 years of the SORCE mission (from
2008 to 2012).
Table 7: Planned Configuration of Instruments on NPP and NPOESS
Satellites, as of May 2008 (critical sensors are in bold):
Instrument: Advanced technology microwave sounder (unchanged);
NPP: X;
NPOESS C1 (PM): X;
NPOESS C2 (AM): O;
NPOESS C3 (PM): X;
NPOESS C4 (AM): O.
Instrument: Aerosol polarimetry sensor (canceled);
NPP: --;
NPOESS C1 (PM): O;
NPOESS C2 (AM): --;
NPOESS C3 (PM): O;
NPOESS C4 (AM): --.
Instrument: Microwave imager/sounder (replacing the canceled Conical-
scanned microwave imager/sounder);
NPP: --;
NPOESS C1 (PM): --;
NPOESS C2 (AM): X;
NPOESS C3 (PM): X;
NPOESS C4 (AM): X.
Instrument: Cross-track infrared sounder (unchanged);
NPP: X;
NPOESS C1 (PM): X;
NPOESS C2 (AM): O;
NPOESS C3 (PM): X;
NPOESS C4 (AM): O.
Instrument: Data collection system (unchanged);
NPP: --;
NPOESS C1 (PM): X;
NPOESS C2 (AM): X;
NPOESS C3 (PM): X;
NPOESS C4 (AM): X.
Instrument: Earth radiation budget sensor (canceled, but replaced on
NPP and C1 by the Clouds and the earth's radiant energy system sensor);
NPP: X;
NPOESS C1 (PM): X;
NPOESS C2 (AM): --;
NPOESS C3 (PM): O;
NPOESS C4 (AM): --.
Instrument: Ozone mapper/profiler suite (nadir-unchanged);
NPP: X;
NPOESS C1 (PM): X;
NPOESS C2 (AM): --;
NPOESS C3 (PM): X;
NPOESS C4 (AM): --.
Instrument: Ozone mapper/profiler suite (limb) (canceled, but added to
NPP);
NPP: X;
NPOESS C1 (PM): O;
NPOESS C2 (AM): --;
NPOESS C3 (PM): O;
NPOESS C4 (AM): --.
Instrument: Radar altimeter (canceled);
NPP: --;
NPOESS C1 (PM): --;
NPOESS C2 (AM): O;
NPOESS C3 (PM): --;
NPOESS C4 (AM): O.
Instrument: Space environmental sensor suite (canceled);
NPP: --;
NPOESS C1 (PM): O;
NPOESS C2 (AM): O;
NPOESS C3 (PM): O;
NPOESS C4 (AM): O.
Instrument: Space environment monitor (replacing selected capabilities
of the space environmental sensor suite);
NPP: --;
NPOESS C1 (PM): X;
NPOESS C2 (AM): --;
NPOESS C3 (PM): X;
NPOESS C4 (AM): --.
Instrument: Total solar irradiance sensor (canceled but added to NPOESS
C1);
NPP: --;
NPOESS C1 (PM): X;
NPOESS C2 (AM): O;
NPOESS C3 (PM): -- ;
NPOESS C4 (AM): O.
Instrument: Survivability sensor (canceled);
NPP: --;
NPOESS C1 (PM): O;
NPOESS C2 (AM): O;
NPOESS C3 (PM): O;
NPOESS C4 (AM): O.
Instrument: Search and rescue satellite aided tracking system
(unchanged);
NPP: --;
NPOESS C1 (PM): X;
NPOESS C2 (AM): X;
NPOESS C3 (PM): X;
NPOESS C4 (AM): X.
Instrument: Visible/infrared imager radiometer suite (unchanged);
NPP: X;
NPOESS C1 (PM): X;
NPOESS C2 (AM): X;
NPOESS C3 (PM): X;
NPOESS C4 (AM): X.
Source: GAO analysis of program office data.
Key:
X = Sensor is currently planned for this satellite:
O = Sensor was canceled but could be restored to this satellite:
-- = Not applicable--sensor was never planned for this satellite:
[End of table]
Agencies Lack Plans to Ensure Long-Term Data Continuity:
While NASA, NOAA, and DOD have taken preliminary steps to address the
climate and space sensors that were removed from the NPOESS program
almost 2 years ago, they do not yet have plans for restoring climate
and space environment data on a long-term basis. Specifically, there
are as yet no firm plans for obtaining most of this data after 2015.
The Office of Science and Technology Policy, an organization within the
Executive Office of the President, is currently working with NASA,
NOAA, and DOD to sort through the costs and benefits of the various
options and to develop plans. However, this effort has been under way
for almost 2 years and officials could not estimate when such plans
would be completed.
Delays in developing a comprehensive strategy for ensuring climate and
space data continuity may result in the loss of selected options. For
example, NASA and NOAA estimated that they would need to make a
decision on whether to build another satellite to obtain ocean
altimeter data in 2008. Also, the NPOESS program office estimated that
if any sensors are to be restored to an NPOESS satellite, it would need
a decision about 6 years in advance of the planned satellite launch.
Specifically, for a sensor to be included on the second NPOESS
satellite, the sponsoring agency would need to commit to do so by
January 2010.
Without a timely decision on a plan for restoring satellite data on a
long-term basis, NASA, NOAA, and DOD risk losing their windows of
opportunity on selected options and restoring sensors in an ad hoc
manner. Ultimately, the agencies risk a break in the continuity of
climate and space environment data. As national and international
concerns about climate change and global warming grow, these data are
more important than ever to try to understand long-term climate trends
and impacts.
GAO Made Recommendations To Ensure That Future Climate Needs are
Addressed and to Complete Restructuring Activities:
Because of the importance of effectively managing the NPOESS program to
ensure that there are no gaps in the continuity of critical weather,
environmental, and climate observations, in our accompanying
report[Footnote 16] we made recommendations to the Secretaries of
Commerce and Defense and to the Administrator of NASA to establish
plans on whether and how to restore the climate and space sensors
removed from the NPOESS program by June 2009, in cases where the
sensors are warranted and justified. In their comments on the report,
all three agencies concurred with our recommendations. In addition,
both the Department of Commerce and NASA reiterated that they are
working with their partner agencies to finalize plans for restoring
sensors.
In addition, we also reemphasized a recommendation made in our prior
report that the appropriate NASA, NOAA, and DOD executives immediately
finalize key acquisition documents. All three agencies also concurred
with this recommendation. Further, Commerce noted that DOD and NASA
executives need to weigh in to resolve issues at, or immediately below,
their levels in order to ensure prompt completion of the key
acquisition documents. NASA noted that difficulties in gaining
consensus across all three NPOESS agencies have delayed the signature
of key acquisition documents, and reported that they are committed to
moving these documents through the signature cycle once all of the
issues and concerns are resolved.
In summary, over the past year, program officials have completed major
activities associated with restructuring the NPOESS program and have
made progress in developing and testing sensors, ground systems, and
the NPP spacecraft. However, multiple risks remain. Agency executives
have still not signed off on key acquisition documents that were
originally to be completed in September 2006, and now DOD is
threatening to withhold funding if the documents are not completed by
August 2008--even though DOD has contributed to the delays in
completing these documents. Also, one critical sensor has experienced
technical problems and schedule delays that have led program officials
to delay the NPP launch date by about 8 months. Any delay in the NPP
launch date shortens the time available for incorporating lessons
learned from NPP onto future NPOESS missions and could also lead to
gaps in critical climate and weather data. In addition, risks to the
program remain in resolving interagency disagreements on the
appropriate level of system security and in revising estimated costs
for satellite operations and support. The program office is aware of
these risks and is working to mitigate them, but continued problems
could affect the program's overall schedule and cost.
When selected climate and space weather sensors were removed from the
NPOESS program during its restructuring, NASA, NOAA, and DOD became
responsible for determining what environmental data to restore and how
to restore them. This responsibility includes justifying the additional
funding needed to develop these sensors within their respective
agency's investment decision processes. In the 2 years since the
restructuring, the agencies have identified their priorities and
assessed their options for restoring sensor capabilities. In addition,
the agencies made decisions to restore two sensors to the NPP satellite
and one to the first NPOESS satellite in order to mitigate near-term
data gaps. However, the agencies lack plans for restoring sensor
capabilities on a long-term basis. Without a timely decision on a long-
term plan for restoring satellite data, the agencies risk a break in
the continuity of climate and space environment data. With the
increased concern about climate change and global warming, these data
are more important than ever to try to understand long-term climate
trends and impacts.
Mr. Chairman, this concludes my statement. I would be happy to answer
any questions that you or members of the committee may have at this
time.
If you have any questions on matters discussed in this testimony,
please contact me at (202) 512-9286 or by e-mail at pownerd@gao.gov.
Other key contributors to this testimony include Colleen Phillips
(Assistant Director), Kate Agatone, and Kathleen S. Lovett.
[End of section]
Appendix I: Status of Key Acquisition Documents:
Table 1 identifies the key NPOESS acquisition documents as well as
their original and revised due dates. Original due dates were specified
in the June 2006 restructuring decision memo. The revised due dates
were specified in an addendum to that memo, dated June 2007, and then
revised again in another addendum, dated April 2008. Documents that are
in bold are overdue.
Table 8: Status of NPOESS Acquisition Documents:
Acquisition document: Alternative Management Plan;
Original due date: June 2007;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Award Fee Plan/ Fee Management Plan;
Original due date: Unspecified;
Revised due date, as of June 2007: October 1, 2007;
Revised due date, as of April 2008: Due date not revised--remains
October 1, 2007;
Status: Not completed.
Acquisition document: Acquisition Program Baseline;
Original due date: September 1, 2006;
Revised due date, as of June 2007: December 1, 2007;
Revised due date, as of April 2008: August 31, 2008;
Status: Not completed.
Acquisition document: Acquisition Strategy Report;
Original due date: September 1, 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: August 31, 2008;
Status: Not completed.
Acquisition document: Test and Evaluation Master Plan;
Original due date: September 1, 2006;
Revised due date, as of June 2007: March 1, 2008;
Revised due date, as of April 2008: August 31, 2008;
Status: Not completed.
Acquisition document: System Engineering Plan;
Original due date: September 1, 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Two-Orbit Plan;
Original due date: November 15, 2006;
Revised due date, as of June 2007: October 1, 2007;
Revised due date, as of April 2008: August 31, 2008;
Status: Not completed.
Acquisition document: Human Capital Management Plan (to fill vacancies
in the Integrated Program Office);
Original due date: August 4, 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Logistics Support Plan;
Original due date: September 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Diminishing Manufacturing Sources/;
Parts Obsolescence Plan;
Original due date: September 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Tri-agency Memorandum of Agreement;
Original due date: August 4, 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Due date not revised--remains
September 1, 2007;
Status: Not completed.
Acquisition document: Integrated Master Plan;
Original due date: April 2007;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Acquisition document: Quarterly Integrated Baseline Review;
Original due date: September 2006;
Revised due date, as of June 2007: September 1, 2007;
Revised due date, as of April 2008: Not applicable;
Status: Completed.
Source: GAO analysis of DOD and NPOESS program office data.
[End of table]
Footnotes:
[1] GAO, Environmental Satellites: Polar-orbiting Satellite Acquisition
Faces Delay; Decisions Needed on Whether and How to Ensure Climate Data
Continuity, GAO-08-518 (Washington, D.C.: May 16, 2008).
[2] GAO, Polar-orbiting Operational Environmental Satellites:
Restructuring is Under Way, but Technical Challenges and Risks Remain,
GAO-07-498 (Washington, D.C.: April 27, 2007).
[3] GAO-07-498
[4] Presidential Decision Directive NSTC-2, May 5, 1994
[5] The four sensors are the Visible/infrared imager radiometer suite,
the Cross-track infrared sounder, the Advanced technology microwave
sounder, and the Ozone mapper/profiler suite.
[6] GAO, Polar-orbiting Operational Environmental Satellites: Cost
Increases Trigger Review and Place Program's Direction on Hold, GAO-06-
573T (Washington, D.C.: Mar. 30, 2006); GAO, Polar-orbiting Operational
Environmental Satellites: Technical Problems, Cost Increases, and
Schedule Delays Trigger Need for Difficult Trade-off Decisions, GAO-06-
249T (Washington, D.C.: Nov. 16, 2005); GAO, Polar-orbiting
Environmental Satellites: Information on Program Cost and Schedule
Changes, GAO-04-1054 (Washington, D.C.: Sept. 30, 2004); GAO, Polar-
orbiting Environmental Satellites: Project Risks Could Affect Weather
Data Needed by Civilian and Military Users, GAO-03-987T (Washington,
D.C.: July 15, 2003); and GAO, Polar-orbiting Environmental Satellites:
Status, Plans, and Future Data Management Challenges, GAO-02-684T
(Washington, D.C.: July 24, 2002).
[7] 10 U.S.C. § 2433 is commonly referred to as Nunn-McCurdy.
[8] 10 U.S.C. § 2433 has recently been amended by Pub. L. No. 109-163,
§ 802 (Jan. 6, 2006) and Pub. L. No. 109-364, § 213(a) (Oct. 17, 2006).
The law now also includes cost growth thresholds from the program's
original baseline.
[9] DOD estimated that the acquisition portion of the certified program
would cost $11.5 billion. The acquisition portion includes satellite
development, production, and launch, but not operations and support
costs after launch. When combined with an estimated $1 billion for
operations and support after launch, this brings the program life cycle
cost to $12.5 billion.
[10] The European Organization for the Exploitation of Meteorological
Satellites' MetOp program is a series of three polar-orbiting
satellites dedicated to operational meteorology. MetOp satellites are
planned to be launched sequentially over 14 years. The first of these
satellites was launched in 2006 and is currently operational.
[11] GAO-07-498.
[12] NPP is to include the Visible/infrared imager radiometer suite,
Cross-track infrared sounder, Advanced technology microwave sounder,
Ozone mapper/profiler suite (nadir and limb), and the Clouds and the
earth's radiant energy system.
[13] The three sensors included the flight unit for the Advanced
technology microwave sounder and engineering design units for the
Visible/infrared imager radiometer suite and the Cross-track infrared
sounder.
[14] NOAA officials have stated that they believe the program should be
built to a "high" security level per Federal Information Processing
Standards Publication 199.
[15] National Research Council, Options to Ensure the Climate Record
from the NPOESS and GOES-R Spacecraft: A Workshop Report (Washington,
D.C.: 2007), and the Office of the Federal Coordinator for
Meteorological Services and Supporting Research, Impacts of NPOESS Nunn-
McCurdy Certification and Potential Loss of ACE Spacecraft Solar Wind
Data on National Space Environmental Monitoring Capabilities.
(Washington, D.C.: January 2008). The report committee was co-chaired
by the director of the Space Weather Prediction Center (NOAA) and the
chief of the Integration, Plans, and Requirements division within the
U.S. Air Force Directorate for Weather. Agency partners in the
Department of Commerce, DOD, NASA, the National Science Foundation, and
the Office of the Federal Coordinator for Meteorology concurred with
the report.
[16] GAO-08-518.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Mail or Phone:
The first copy of each printed report is free. Additional copies are $2
each. A check or money order should be made out to the Superintendent
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or
more copies mailed to a single address are discounted 25 percent.
Orders should be sent to:
U.S. Government Accountability Office:
441 G Street NW, Room LM:
Washington, D.C. 20548:
To order by Phone:
Voice: (202) 512-6000:
TDD: (202) 512-2537:
Fax: (202) 512-6061:
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: