Defense Acquisitions
Rapid Acquisition of MRAP Vehicles
Gao ID: GAO-10-155T October 8, 2009
As of July 2008, about 75 percent of casualties in combat operations in Iraq and Afghanistan were attributed to improvised explosive devices. To mitigate the threat from these weapons, the Department of Defense (DOD) initiated the Mine Resistant Ambush Protected (MRAP) program in February 2007, which used a tailored acquisition approach to rapidly acquire and field the vehicles. In May 2007, the Secretary of Defense affirmed MRAP as DOD's most important acquisition program. To date, about $22.7 billion has been appropriated for the procurement of more than 16,000 MRAP vehicles. This testimony today describes the MRAP acquisition process, the results to date, lessons learned from that acquisition, and potential implications for improving the standard acquisition process. It is mostly based on the work we have conducted over the past few years on the MRAP program. Most prominently, in 2008, we reported on the processes followed by DOD for the acquisition of MRAP vehicles and identified challenges remaining in the program. To describe DOD's approach for and progress in implementing its strategy for rapidly acquiring and fielding MRAP vehicles, we reviewed DOD's plans to buy, test, and field the vehicles and discussed the plans with cognizant department and contractor officials. To identify the remaining challenges for the program, we reviewed the results of testing and DOD's plans to upgrade and sustain the vehicles
DOD use of a tailored acquisition approach to rapidly acquire and field MRAP vehicles was successful. The program relied only on proven technologies and commercially available products; established minimal operational requirements; and undertook a concurrent approach to producing, testing, and fielding the vehicles. To expand limited production capacity, indefinite delivery, indefinite quantity contracts were awarded to nine commercial sources, with DOD agreeing to buy at least 4 vehicles from each. Subsequent orders were based on a concurrent testing approach with progressively more advanced vehicle test results and other assessments. To expedite fielding of the vehicles, the government retained the responsibility for final integration in them of mission equipment packages including radios and other equipment. DOD also made MRAP its highest priority acquisition, which helped contractors and others more rapidly respond to the need and meet production requirements, in part by early investing of their own capital to purchase steel and other critical components in advance of orders. Schedule and performance results for MRAP were very good overall. In July 2008, nearly all testing was completed; the Marine Corps had placed orders for 14,173 MRAPs; and, as of May 2008, 9,121 vehicles had been delivered. As of July 2009, 16,204 vehicles have been produced and 13,848 vehicles fielded in two theaters of operation. Total MRAP production funding was about $22.7 billion, mostly through supplemental appropriations. In terms of lessons learned, MRAP's success was driven by several factors, including quick action to declare its acquisition DOD's highest priority and giving it a DX rating, which allowed access to more critical materials than was otherwise available. The availability of supplemental appropriations was also essential. However, while neither of these factors are practically transferable to other programs, decisions to 1) use only proven technologies, 2) keep requirements to a minimum, 3) infuse significant competition into contracting, and 4) keep final integration responsibility with the government all led to positive outcomes and may be transferable. Challenges to MRAP remain in its reliability, mobility, and safety, which required some modifying of designs and postproduction fixes, and adapting how vehicles were used. Also, long term sustainment costs are not understood and the services are only now deciding how MRAP fits them in the longer term. GAO's multiple best practices reports have underscored the need for the use of mature technologies, well understood requirements, systems engineering knowledge, and incremental delivery of capabilities to enable quicker deliveries. Finally, a broader lesson learned is that it is time to invest the time, money, and management skills in the science and technology community to enable the effectiveness we expect from the acquisition community.
GAO-10-155T, Defense Acquisitions: Rapid Acquisition of MRAP Vehicles
This is the accessible text file for GAO report number GAO-10-155T
entitled 'Defense Acquisitions: Rapid Acquisition of MRAP Vehicles'
which was released on October 8, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the House Armed Services Committee, Defense Acquisition Reform
Panel:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 8:00 a.m. EDT:
Thursday, October 8, 2009:
Defense Acquisitions:
Rapid Acquisition of MRAP Vehicles:
Statement of Michael J. Sullivan, Director:
Acquisition and Sourcing Management:
GAO-10-155T:
GAO Highlights:
Highlights of GAO-10-155T, a testimony before the House Armed Services
Committee, Defense Acquisition Reform Panel.
Why GAO Did This Study:
As of July 2008, about 75 percent of casualties in combat operations in
Iraq and Afghanistan were attributed to improvised explosive devices.
To mitigate the threat from these weapons, the Department of Defense
(DOD) initiated the Mine Resistant Ambush Protected (MRAP) program in
February 2007, which used a tailored acquisition approach to rapidly
acquire and field the vehicles. In May 2007, the Secretary of Defense
affirmed MRAP as DOD‘s most important acquisition program. To date,
about $22.7 billion has been appropriated for the procurement of more
than 16,000 MRAP vehicles.
My testimony today describes the MRAP acquisition process, the results
to date, lessons learned from that acquisition, and potential
implications for improving the standard acquisition process. It is
mostly based on the work we have conducted over the past few years on
the MRAP program. Most prominently, in 2008, we reported on the
processes followed by DOD for the acquisition of MRAP vehicles and
identified challenges remaining in the program. To describe DOD‘s
approach for and progress in implementing its strategy for rapidly
acquiring and fielding MRAP vehicles, we reviewed DOD‘s plans to buy,
test, and field the vehicles and discussed the plans with cognizant
department and contractor officials. To identify the remaining
challenges for the program, we reviewed the results of testing and DOD‘
s plans to upgrade and sustain the vehicles.
What GAO Found:
DOD use of a tailored acquisition approach to rapidly acquire and field
MRAP vehicles was successful. The program relied only on proven
technologies and commercially available products; established minimal
operational requirements; and undertook a concurrent approach to
producing, testing, and fielding the vehicles. To expand limited
production capacity, indefinite delivery, indefinite quantity contracts
were awarded to nine commercial sources, with DOD agreeing to buy at
least 4 vehicles from each. Subsequent orders were based on a
concurrent testing approach with progressively more advanced vehicle
test results and other assessments. To expedite fielding of the
vehicles, the government retained the responsibility for final
integration in them of mission equipment packages including radios and
other equipment. DOD also made MRAP its highest priority acquisition,
which helped contractors and others more rapidly respond to the need
and meet production requirements, in part by early investing of their
own capital to purchase steel and other critical components in advance
of orders.
Schedule and performance results for MRAP were very good overall. In
July 2008, nearly all testing was completed; the Marine Corps had
placed orders for 14,173 MRAPs; and, as of May 2008, 9,121 vehicles had
been delivered. As of July 2009, 16,204 vehicles have been produced and
13,848 vehicles fielded in two theaters of operation. Total MRAP
production funding was about $22.7 billion, mostly through supplemental
appropriations.
In terms of lessons learned, MRAP‘s success was driven by several
factors, including quick action to declare its acquisition DOD‘s
highest priority and giving it a DX rating, which allowed access to
more critical materials than was otherwise available. The availability
of supplemental appropriations was also essential. However, while
neither of these factors are practically transferable to other
programs, decisions to 1) use only proven technologies, 2) keep
requirements to a minimum, 3) infuse significant competition into
contracting, and 4) keep final integration responsibility with the
government all led to positive outcomes and may be transferable.
Challenges to MRAP remain in its reliability, mobility, and safety,
which required some modifying of designs and postproduction fixes, and
adapting how vehicles were used. Also, long term sustainment costs are
not understood and the services are only now deciding how MRAP fits
them in the longer term.
GAO‘s multiple best practices reports have underscored the need for the
use of mature technologies, well understood requirements, systems
engineering knowledge, and incremental delivery of capabilities to
enable quicker deliveries. Finally, a broader lesson learned is that it
is time to invest the time, money, and management skills in the science
and technology community to enable the effectiveness we expect from the
acquisition community.
View [hyperlink, http://www.gao.gov/products/GAO-10-155T] or key
components. For more information, contact Michael J. Sullivan at (202)
512-4841 or sullivanm@gao.gov.
[End of section]
Mr. Chairman and Members of the Panel:
I am pleased to be here today to discuss rapid acquisition programs
within the Department of Defense (DOD), with a focus on our work on the
Mine Resistant Ambush Protected (MRAP) vehicles as a case study
example. As of July 2008, about 75 percent of casualties in combat
operations in Iraq and Afghanistan were attributed to improvised
explosive devices. To mitigate the threat from these weapons, the DOD
initiated the MRAP program in February 2007, which used a tailored
acquisition approach to rapidly acquire and field the vehicles. In May
2007, the Secretary of Defense affirmed MRAP as DOD's single most
important acquisition program. To date, about $22.7 billion has been
appropriated for the procurement of more than 16,000 MRAP vehicles.
My statement today describes the MRAP acquisition process, the results
to date, lessons learned from that acquisition, and potential
implications for improving the standard acquisition process. It is
mostly based on the work we have conducted over the past few years on
the MRAP program. Most prominently, in 2008, we reviewed and reported
on the processes followed by DOD for the acquisition of MRAP vehicles
and identified challenges remaining in the program. [Footnote 1] In
that report, to describe DOD's approach for and progress in
implementing its strategy for rapidly acquiring and fielding MRAP
vehicles, we reviewed DOD's plans to buy, test, and field the vehicles
and discussed the plans with cognizant department and contractor
officials. To identify the remaining challenges for the program, we
reviewed the results of testing and DOD's plans to upgrade and sustain
the vehicles. We conducted that performance audit from June 2007 to
July 2008 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
Background:
In February 2005, Marine Corps combatant commanders identified an
urgent operational need for armored tactical vehicles to increase crew
protection and mobility of Marines operating in hazardous fire areas
against improvised explosive devices, rocket-propelled grenades, and
small arms fire. In response, the Marine Corps identified the solution
as the up-armored high-mobility multi-purpose wheeled vehicle. Over the
next 18 months, however, combatant commanders continued to identify a
requirement for more robust mine-protected vehicles. According to the
acquisition plan, in November 2006, the Marine Corps awarded a sole
source indefinite delivery, indefinite quantity (IDIQ) contract
[Footnote 2] and subsequently placed orders for the first 144 vehicles
to respond to the urgent requirement while it conducted a competitive
acquisition for the balance of the vehicles. In February 2007, the
Assistant Secretary of the Navy for Research, Development, and
Acquisition approved MRAPs entry into production as a rapid acquisition
capability. In September of 2007, the Undersecretary of Defense for
Acquisition, Technology, and Logistics designated MRAP as a major
defense acquisition program[Footnote 3] with the Marine Corps Systems
Command as the Joint Program Executive Officer. Quantities to be
fielded quickly grew from the initial 1,169 vehicles for the Marine
Corps identified in the 2005 urgent need statement to the current
approved requirement of over 16,000 vehicles split among the Army,
Marine Corps, Navy, Air Force, and Special Operations Command, plus
others for ballistic testing.
Three versions of the MRAP vehicle were acquired for different
missions:
* Category I, the smallest version of MRAP, is primarily intended for
operations in the urban combat environment, and can carry up to 7
personnel.
* Category II is a multi-mission platform capable of supporting
security, convoy escort, troop or cargo transport, medical, explosive
ordnance disposal, or combat engineer operations, and carries up to 11
personnel.
* Category III, the largest of the MRAP family, is primarily intended
for the role of mine and IED clearance operations, and carries up to 13
personnel.[Footnote 4]
MRAP vehicles were purchased without mission equipment--such as
communications and situational awareness subsystems--that must be added
before the vehicles can be fielded to the user. The military services
buy the subsystems for their vehicles and provide them as government
furnished equipment to be installed at a government integration
facility located at the Space and Naval Warfare Systems Command in
Charleston, South Carolina.
Acquisition Strategy Was Tailored and Had Special Priority:
DOD used a tailored acquisition approach to rapidly acquire and field
MRAP vehicles. The program established minimal operational
requirements, decided to rely on only proven technologies, and relied
heavily on commercially available products. The program also undertook
a concurrent approach to producing, testing, and fielding the most
survivable vehicles as quickly as possible. To expand limited existing
production capacity, the department expanded competition by awarding
IDIQ contracts to nine commercial sources. To evaluate design,
performance, producibility, and sustainability, DOD committed to buy at
least 4 vehicles from each vendor. According to program officials,
subsequent delivery orders were based on a phased testing approach with
progressively more advanced vehicle test results and other assessments.
To expedite the fielding of the vehicles, the government retained the
responsibility for final integration of mission equipment packages
including radios and other equipment into the vehicles after they were
purchased. DOD also designated the MRAP program as DOD's highest
priority acquisition, which helped contractors and other industry
partners to more rapidly respond to the urgent need and meet production
requirements. Finally, some of the contractors involved in the
acquisition responded to the urgency communicated by the department by
investing their own capital early to purchase needed steel and other
critical components in advance of orders. The decision on the part of
the contractors to purchase components in advance of orders was not
required under their contracts and was done at their own risk.
DOD leadership took several steps to communicate the importance of
producing survivable vehicles as quickly as possible, for example:
* In May 2007, the Secretary of Defense designated MRAP as DOD's single
most important acquisition program and established the MRAP Task Force
to integrate planning, analysis, and actions to accelerate MRAP
acquisition.
* The Secretary also approved a special designation for MRAP--a DX
rating--that requires related contracts to be accepted and performed on
a priority basis over other contracts without this rating.
* The Secretary of the Army waived a restriction on armor plate steel,
which expanded the countries from which DOD could procure steel.
* DOD allocated funds to increase steel and tire production capacity
for MRAP vehicles as these materials were identified as potential
limiting factors for the MRAP industrial base.
DOD recognized that no single vendor could provide all of the vehicles
needed to meet requirements quickly enough and invited vendors to offer
their non-developmental[Footnote 5] solutions. The request for proposal
made clear that the government planned to award one or more IDIQ
contracts to those vendors that were determined to be the best value to
the government. The Marine Corps awarded IDIQ contracts to nine vendors
and issued the first delivery orders in early 2007 for 4 vehicles from
each vendor for initial limited ballistic and automotive testing. One
vendor could not deliver test articles in the time required and the
Marine Corps terminated that contract at no cost to the government.
According to program officials, vehicles from another vendor did not
meet minimum requirements and the Marine Corps terminated the contract
for convenience.
Conventional DOD acquisition policy dictates that weapons be fully
tested before they are fielded to the user. However, the need to begin
fielding survivable vehicles as quickly as possible resulted in a
phased approach designed to quickly identify vehicles that met the
requirement for crew protection so they could be rapidly fielded. This
approach resulted in a high degree of overlap between testing and
fielding of the MRAP vehicles; orders for thousands of vehicles were
placed before operational testing began and orders for thousands more
were placed before it was completed. Figure 1 shows the concurrent
nature of the overall test plan.
Figure 1: MRAP Developmental and Operational Test Plan:
[Refer to PDF for image: illustration]
Phase I: Mid-2nd quarter, 2007 through end of 3rd quarter, 2007;
Phase II: Mid-3rd quarter, 2007 through early 3rd quarter, 2008;
Phase III: Early 4th quarter, 2007 through end of 4th quarter, 2008;
IOT&E: Early 1st quarter, 2008 through end of 4th quarter, 2008.
Source: GAO based on DOD information.
[End of figure]
The Director, Operational Test & Evaluation approved the MRAP Test and
Evaluation Master Plan in 2007. Candidate vehicles underwent ballistic
and automotive testing beginning in March 2007. The test plan included
three phases of developmental tests (DT) of increasing scope as well as
initial operational test and evaluation (IOT&E). Phase I included a
limited evaluation by users. Phase II further evaluated vehicles at the
desired level of performance against the ballistic threat, added more
endurance miles to the automotive portion of the test, and included
mission equipment such as radios and other electronic systems. Phase
III raised the bar for ballistic performance to the emerging threat and
assessed non-ballistic protection to include near-lightning strikes,
high-altitude electromagnetic pulse, and nuclear, biological, and
chemical decontamination tests. The automotive portion of the test
increased endurance to 12,000 miles per vehicle.
Developmental and operational tests were conducted from March 2007
through June 2008. Each of the six MRAP variants have also undergone
IOT&E. All vehicles were rated operationally survivable and
operationally effective with limitations by the Army Evaluation Center.
These limitations were comprised of vehicle size, weight, mobility, and
weapon dead space. All vehicles were also rated operationally suitable
with limitations. These limitations were due to logistic shortfalls,
payload restrictions, and restricted fields of view.
MRAP Schedule and Performance Results Have Been Very Good:
Schedule and performance results for the MRAP have been very good
overall. At the time of our review in July 2008, nearly all of the
developmental and operational testing had been completed; the Marine
Corps, the buying command for the MRAP, had placed orders for 14,173
MRAPs; and, as of May 2008, a little more than a year after the first
contracts were awarded, 9,121 vehicles had been delivered. As of July
2009, 16,204 vehicles have been produced and 13,848 vehicles have been
fielded in two theaters of operation. Total procurement funding for the
MRAP vehicles, mostly through supplemental appropriations, was about
$22.7 billion. According to DOD officials, the MRAP is providing safe,
sustainable, and survivable transport for troops in the theater. It
recognizes that MRAPs have limitations, particularly in the area of off-
road mobility and transportability. Nonetheless, MRAPs are considered
outstanding vehicles for specific missions.
Twenty-one months elapsed from the time the need was first identified
in February 2005 until the sole source IDIQ contract was awarded and
subsequent orders were placed for the first 144 vehicles in November
2006. Three months elapsed between the award of the sole source
contract and the delivery of vehicles under the orders placed pursuant
to the contract in February 2007--about the same time the IDIQ
contracts were awarded to multiple vendors for more vehicles. Testing
of vehicles delivered under orders placed pursuant to the newly awarded
contracts began one month later in March 2007. Initial operational
capability was accomplished in October 2007 or about 33 months after
the need was first identified.
Ultimately, MRAP vendors have successfully increased their production
rates to meet the delivery requirement (see fig. 2). Production began
in February 2007 with one vendor producing 10 vehicles. By March 2008--
a little more than a year after the contracts were awarded--6,935
vehicles had been produced.
Figure 2: Actual Versus Planned Production (monthly):
[Refer to PDF for image: vertical bar graph]
Month: February, 2007;
Vehicles produced, planned: 10;
Vehicles produced, actual: 10.
Month: March, 2007;
Vehicles produced, planned: 29;
Vehicles produced, actual: 29.
Month: April, 2007;
Vehicles produced, planned: 75;
Vehicles produced, actual: 77.
Month: May, 2007;
Vehicles produced, planned: 138;
Vehicles produced, actual: 137.
Month: June, 2007;
Vehicles produced, planned: 227;
Vehicles produced, actual: 200.
Month: July, 2007;
Vehicles produced, planned: 373;
Vehicles produced, actual: 349.
Month: August, 2007;
Vehicles produced, planned: 548;
Vehicles produced, actual: 517.
Month: September, 2007;
Vehicles produced, planned: 810;
Vehicles produced, actual: 825.
Month: October, 2007;
Vehicles produced, planned: 1,243;
Vehicles produced, actual: 1,278.
Month: November, 2007;
Vehicles produced, planned: 2,155;
Vehicles produced, actual: 2,118.
Month: December, 2007;
Vehicles produced, planned: 3,231;
Vehicles produced, actual: 3,305.
Month: January, 2008;
Vehicles produced, planned: 4,496;
Vehicles produced, actual: 4,233.
Month: February, 2008;
Vehicles produced, planned: 5,795;
Vehicles produced, actual: 5,658.
Month: March, 2008;
Vehicles produced, planned: 6,834;
Vehicles produced, actual: 6,935.
Month: April, 2008;
Vehicles produced, planned: 7,994;
Vehicles produced, actual: 7,970.
Month: May, 2008;
Vehicles produced, planned: 9,068;
Vehicles produced, actual: 9,049.
Month: June, 2008;
Vehicles produced, planned: 9,987;
Vehicles produced, actual: 9,946.
Month: July, 2008;
Vehicles produced, planned: 11,017;
Vehicles produced, actual: 10,925.
Month: August, 2008;
Vehicles produced, planned: 11,997;
Vehicles produced, actual: 12,028.
Month: September, 2008;
Vehicles produced, planned: 12,922;
Vehicles produced, actual: 12,959.
Month: October, 2008;
Vehicles produced, planned: 13,481;
Vehicles produced, actual: 13,577.
Month: November, 2008;
Vehicles produced, planned: 14,148;
Vehicles produced, actual: 14,186.
Month: December, 2008;
Vehicles produced, planned: 14,498;
Vehicles produced, actual: 14,700.
Month: January, 2009;
Vehicles produced, planned: 14,900;
Vehicles produced, actual: 14,923.
Month: February, 2009;
Vehicles produced, planned: 15,185;
Vehicles produced, actual: 15,261.
Month: March, 2009;
Vehicles produced, planned: 15,459;
Vehicles produced, actual: 15,575.
Month: April, 2009;
Vehicles produced, planned: 15,766;
Vehicles produced, actual: 15,775.
Source: GAO analysis of Joint Program Office data.
[End of figure]
According to DOD officials, the MRAP provides survivable, safe, and
sustainable vehicles for troops in theater. It is recognized that MRAPs
have limitations, particularly in the area of off-road mobility and
transportability. Nevertheless, MRAPs met minimum requirements for
specific missions. Based on an earlier survey of over 300 soldiers
interviewed in the field, warfighters were satisfied with MRAP overall,
which offers significant improvement in survivability. MRAP vehicles
were seen as well suited for combat logistics patrols, route clearance
missions, raids, quick reaction forces, and other missions requiring
large, dismounted force. MRAP vehicles were seen as not well suited for
mounted patrols in constrained urban areas or extensive operations in
off-road operations.
Many Lessons Learned, Many Challenges Remain:
As with any acquisition of this nature, there are lessons to be
learned. On the positive side, it appears that quick action by the
Secretary of Defense to declare the MRAP program DOD's highest priority
and give it a DX rating allowed the government and the contractors
access to more critical materials than otherwise would have been
available. The availability of funding mostly through supplemental
appropriations was essential. In addition, the decisions to 1) use only
proven technologies, 2) keep requirements to a minimum, 3) infuse
significant competition into the contracting strategy, and 4) keep
final integration responsibility with the government are all practices
that led to positive outcomes. Challenges remain in the form of
reliability, mobility, and safety, which have required some modifying
of the designs, postproduction fixes, and adapting how vehicles were to
be used. Also, long term sustainment costs for MRAP are not yet well
understood and the services are only now deciding how MRAP will fit
into their longer term organizations. This combination of actions
executed to address the urgent need for accelerating the delivery of
MRAP vehicles to theater was innovative and effective.
Major vendors and key subcontractors responded to the urgency
communicated by the department. According to vendor officials from four
of the companies, they collectively invested a substantial amount of
their own capital in anticipation of MRAP work. For example, some
vendors purchased steel and other critical components in advance of
delivery orders for MRAP vehicles in order to meet projected time
lines. In other cases, vendors purchased or developed new facilities
for MRAP production. Multiple vendors also formed teaming arrangements
to meet the increase in vehicle delivery demands. As stated above,
these actions on the part of the contractors were not required under
their contracts and were done at their own risk.
On the down side, because of unique designs, operating procedures, and
maintenance for multiple vehicles from multiple vendors, vehicle
maintenance and support has been somewhat complicated. To ease
maintenance and support concerns in the near term, the MRAP program
office established a centralized training entity where maintainers
would be cross-trained on multiple vendors' vehicles. Longer term, a
key challenge for DOD will be to effectively manage maintenance
personnel and vehicle repair parts without sacrificing vehicle
operational availability. Also, long term sustainment costs for MRAP
are not yet projected and budgeted. The Services are only now deciding
how to fit MRAP vehicles into their organizational structures. Another
lesson, based on operational use of the MRAP vehicles, was their lack
of maneuverability and off-road capability. As a result, DOD is in the
process of acquiring an all terrain version of the MRAP to address the
more difficult terrain and road conditions in Afghanistan. While most
of the vehicles met ballistic requirements, other issues were
identified (reliability, mobility and handling, and safety). These
issues required some modifying of the designs, postproduction fixes, or
adapting how vehicles were to be used. Testing of proposed solutions to
more advanced threats continues. The program office continues to
enhance MRAP vehicle system performance through capability insertion
initiatives executed via engineering change proposals. Such changes are
verified through testing. This testing will be an ongoing process as
additional upgrades are applied.
Broader Lessons and Implications from the MRAP Acquisition:
What were the keys in DOD meeting the urgent requirement for fielding
MRAP in a timely manner? First, DOD kept the requirements simple,
clear, and flexible and did not dictate a single acceptable solution.
Second, DOD made sure that only mature technologies and stable designs
were used by setting a very short and inflexible schedule. DOD acting
as integrator of government furnished equipment after initial delivery
eliminated some risk and uncertainty. Third, MRAP was also given the
highest possible acquisition priority and the participating contractors
responded in positive ways to meet the needs. Fourth, full and timely
funding for the acquisition was a definite plus. The question is, can
this formula be applied to all of DOD's major acquisitions and the
broader acquisition process? The first two keys--simple requirements
and mature technologies--certainly can be and, in fact, recent changes
to the department's acquisition policies and acquisition reform
legislation passed by the Congress should enable these practices to be
implemented easier than in the past. However, the MRAP program also
owes it success to the third and fourth key practices as well--a DX
rating as the highest priority acquisition in the department and nearly
unlimited funding to meet the urgent need--that are not scalable to the
broader acquisition process. Not every program can be a highest
priority and acquisition funds are constrained.
While the MRAP acquisition benefited from all of the practices
mentioned above, the biggest differentiator between that rapid
acquisition and other more common acquisitions in DOD was that it
established requirements that could be achieved with existing
technologies. Recent studies by the Defense Science Board[Footnote 6],
the Defense Acquisition Performance Assessment Panel (DAPA),[Footnote
7] and GAO all indicate that the department can and should acquire and
deliver weapon systems that fulfill urgent warfighter needs to the
field much more quickly. The DSB study recommends a dual acquisition
path that allows for a "rapid" acquisition process for urgent needs and
"deliberate" acquisition processes for others. It recommends a new
agency, proposed as the Rapid Acquisition and Fielding Agency, that
would be focused on speed, utilizing existing technologies, and
acquisition flexibility to achieve the "75 percent solution" quickly.
The DAPA Panel report, among other things, recommended that the
acquisition process should never exceed 6 years from its beginning to
initial operational capability of the acquired weapon system. It stated
that mature technologies and achievable requirements are critical to
the success of such time certain development efforts.
GAO has issued multiple reports under our "best practices" body of work
that underscore the need for faster development cycles and the need for
mature technologies, well understood requirements, systems engineering
knowledge, and incremental delivery of capabilities to enable quicker
deliveries. As early as 1999[Footnote 8], we concluded that successful
product developments separated technology development from product
development, invested time and money in ensuring that their technology
base was vibrant and cutting edge, and eliminated technology risk from
acquisitions. We noted that the DOD's science and technology (S&T)
organization would need to be organized and structured differently,
provided more funding to take new technologies to higher levels of
maturity, and would have to coordinate better with the department's
acquisition community to achieve the synergies necessary to reduce
cycle times. We made recommendations along those lines. We believe that
the "game changer" today in achieving rapid acquisition is the
technology base. Finally, a broader lesson learned is that it may be
time to invest the time, money, and management skills in the S&T
community to enable the effectiveness we expect from the acquisition
community.
Mr. Chairman, that concludes my prepared statement. I will be happy to
answer any of your questions.
Contacts and Staff Acknowledgements:
For future questions about this statement, please contact me on (202)
512-4841 or sullivanm@gao.gov. Individuals making key contributions to
this statement include William R. Graveline, Paul Williams, Dayna
Foster, Danny Owens,
[End of section]
Footnotes:
[1] Rapid Acquisition of Mine Resistant Ambush Protected Vehicles.
[hyperlink, http://www.gao.gov/products/GAO-08-884R]; July 15, 2008.
[2] An IDIQ contract is a type of indefinite delivery contract that
provides for an indefinite quantity of supplies or services within
stated limits, during a fixed period. The government places orders for
individual requirements. Federal Acquisition Regulation (FAR) 16.504.
[3] Major defense acquisition programs are those estimated to require
eventual total research, development, test and evaluation expenditures
of more than $365 million or procurement expenditures of more than
$2.19 billion in fiscal year 2000 constant dollars.
[4] Only the Marine Corps acquired these vehicles. The Army is pursuing
a separate acquisition program to replace its current fleet of vehicles
that perform this mission.
[5] A non-developmental item means any previously developed item of
supply used exclusively for government purposes by a federal agency, a
state or local government, or a foreign government with which the
United States has a mutual defense cooperation agreement; any item
described above that requires only minor modifications or modifications
of a type customarily available in the commercial marketplace in order
to meet the requirements of the procuring department or agency, or any
item of supply being produced that does not meet the requirements
described above solely because the item is not yet in use. FAR 2.101.
[6] Report of the Defense Science Board Task Force on the Fulfillment
of Urgent Operational Needs, July 2009.
[7] A Report by the Assessment Panel of the Defense Acquisition
Performance Assessment Project "Defense Acquisition Performance
Assessment, January 2006.
[8] Best Practices: Better Management of Technology Development Can
ImproveWeapo System Outcomes [hyperlink,
http://www.gao.gov/products/GAO/NSIAD-99-162], July 30, 1999.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: