Defense Acquisitions
Strategic Airlift Gap Has Been Addressed, but Tactical Airlift Plans Are Evolving as Key Issues Have Not Been Resolved
Gao ID: GAO-10-67 November 12, 2009
Department of Defense (DOD) used nearly 700 aircraft, as well as commercial and leased aircraft, to carry about 3 million troops and 800,000 tons of cargo in support of wartime, peacetime, and humanitarian efforts in 2008. C-5s and C-17s move troops and cargo internationally (strategic airlift) and C-130s are the primary aircraft that moves them within a theater of operation (tactical airlift). Over the next 4 years, DOD plans to spend about $12 billion to modernize and procure airlifters and is currently studying how many it needs. The Government Accountability Office (GAO) was asked to (1) identify the status of DOD's modernization and acquisition efforts and (2) determine how well DOD is addressing any capability gaps and redundancies. In conducting this work, GAO identified the cost, schedule, and performance of airlift programs, as well as DOD's plan for addressing gaps and redundancies. GAO also discussed mobility study efforts with DOD, Institute for Defense Analysis (IDA), and RAND Coporation officials.
DOD has recently revamped airlift investments due to modernization cost increases and requirement changes. For strategic airlift, the number of C-5s that will be fully modernized were cut in half because of substantial reengining cost increases and C-17 quantities were increased from 180 to 213 aircraft. These twin changes resulted in a net cost increase of about$3 billion. Additional costs and force structure changes are possible pending decisions on C-5 retirements, other modifications, the potential need for more C-17s to meet tactical airlift needs, and the planned shutdown of C-17 production. For tactical airlift, substantial cost increases for modernizing C-130 avionics tripled unit costs, delayed its schedule, and resulted in almost 60 percent fewer aircraft being modernized. There have been large increases in the C-130J quantity to replace older C-130s, but modest increases in unit costs. The joint Army-Air Force C-27J program was recently transferred to the Air Force and quantities were cut from 78 to 38 aircraft, with an uncertain effect on the Army's airlift missions. The Army and Air Force must also resolve fundamental differences in operating requirements and employment strategy for the Joint Future Theater Lift (JFTL). DOD appears to have addressed its strategic airlift gap, but there is a potential future tactical airlift gap for moving medium weight equipment. Also, questions regarding how the Air Force will meet the Army's direct support mission have not been resolved. DOD is using $5.5 billion appropriated by Congress to procure 23 additional C-17s, which DOD officials believe more than offsets the strategic airlift gap associated with the restructured C-5 modernization program. However, there is a potential gap in the tactical airlift of medium weight loads beyond the capability of the C-130s. The C-17 is the only aircraft capable of moving this type of Army equipment within a theater of operation, although not to austere, short, or unimproved landing areas. The JFTL is envisioned to provide this capability, but will not be available for 15 years or more under the current acquisition strategy. While the various mobility studies acknowledge the C-17's significant dual role, they did not comprehensively evaluate the expanded use of the C-17 to transport medium weight equipment in theater and how this could impact the force structure, the C-17's service life, and decisions related to when to shut down the production line. In addition, questions remain about the number of C-130s and C-27Js needed to fulfill Army direct support missions. Two studies reached somewhat different conclusions about the cost effectiveness of using C-130Js and C-27Js for this mission. The Air Force and Army have not completed a plan for meeting Army direct support requirements, which could affect future decisions on both the C-27J and the C-130J. DOD's recently established portfolio management structure is supposed to provide a useful forum to address the broad range of airlift investment decisions. However, efforts so far have primarily focused on new programs rather than addressing gaps and making other airlift decisions such as when and how many C-5s to retire or the appropriate mix of C-130s and C-27Js needed to perform Army missions.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-10-67, Defense Acquisitions: Strategic Airlift Gap Has Been Addressed, but Tactical Airlift Plans Are Evolving as Key Issues Have Not Been Resolved
This is the accessible text file for GAO report number GAO-10-67
entitled 'Defense Acquisitions: Strategic Airlift Gap Has Been
Addressed, but Tactical Airlift Plans Are Evolving as Key Issues Have
Not Been Resolved' which was released on November 12, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Subcommittee on Air and Land Forces, Committee on Armed
Services, House of Representatives:
United States Government Accountability Office:
GAO:
November 2009:
Defense Acquisitions:
Strategic Airlift Gap Has Been Addressed, but Tactical Airlift Plans
Are Evolving as Key Issues Have Not Been Resolved:
GAO-10-67:
GAO Highlights:
Highlights of GAO-10-67, a report to Subcommittee on Air and Land
Forces, Committee on Armed Services, House of Representatives.
Why GAO Did This Study:
DOD used nearly 700 aircraft, as well as commercial and leased
aircraft, to carry about 3 million troops and 800,000 tons of cargo in
support of wartime, peacetime, and humanitarian efforts in 2008. C-5s
and C-17s move troops and cargo internationally (strategic airlift) and
C-130s are the primary aircraft that moves them within a theater of
operation (tactical airlift). Over the next 4 years, DOD plans to spend
about $12 billion to modernize and procure airlifters and is currently
studying how many it needs.
GAO was asked to (1) identify the status of DOD‘s modernization and
acquisition efforts and (2) determine how well DOD is addressing any
capability gaps and redundancies. In conducting this work, GAO
identified the cost, schedule, and performance of airlift programs, as
well as DOD‘s plan for addressing gaps and redundancies. GAO also
discussed mobility study efforts with DOD, Institute for Defense
Analysis (IDA), and RAND officials.
What GAO Found:
DOD has recently revamped airlift investments due to modernization cost
increases and requirement changes. For strategic airlift, the number of
C-5s that will be fully modernized were cut in half because of
substantial reengining cost increases and C-17 quantities were
increased from 180 to 213 aircraft. These twin changes resulted in a
net cost increase of about $3 billion. Additional costs and force
structure changes are possible pending decisions on C-5 retirements,
other modifications, the potential need for more C-17s to meet tactical
airlift needs, and the planned shutdown of C-17 production. For
tactical airlift, substantial cost increases for modernizing C-130
avionics tripled unit costs, delayed its schedule, and resulted in
almost 60 percent fewer aircraft being modernized. There have been
large increases in the C-130J quantity to replace older C-130s, but
modest increases in unit costs. The joint Army-Air Force C-27J program
was recently transferred to the Air Force and quantities were cut from
78 to 38 aircraft, with an uncertain effect on the Army‘s airlift
missions. The Army and Air Force must also resolve fundamental
differences in operating requirements and employment strategy for the
Joint Future Theater Lift (JFTL).
DOD appears to have addressed its strategic airlift gap, but there is a
potential future tactical airlift gap for moving medium weight
equipment. Also, questions regarding how the Air Force will meet the
Army‘s direct support mission have not been resolved. DOD is using $5.5
billion appropriated by Congress to procure 23 additional C-17s, which
DOD officials believe more than offsets the strategic airlift gap
associated with the restructured C-5 modernization program. However,
there is a potential gap in the tactical airlift of medium weight loads
beyond the capability of the C-130s. The C-17 is the only aircraft
capable of moving this type of Army equipment within a theater of
operation, although not to austere, short, or unimproved landing areas.
The JFTL is envisioned to provide this capability, but will not be
available for 15 years or more under the current acquisition strategy.
While the various mobility studies acknowledge the C-17‘s significant
dual role, they did not comprehensively evaluate the expanded use of
the C-17 to transport medium weight equipment in theater and how this
could impact the force structure, the C-17‘s service life, and
decisions related to when to shut down the production line. In
addition, questions remain about the number of C-130s and C-27Js needed
to fulfill Army direct support missions. Two studies reached somewhat
different conclusions about the cost effectiveness of using C-130Js and
C-27Js for this mission. The Air Force and Army have not completed a
plan for meeting Army direct support requirements, which could affect
future decisions on both the C-27J and the C-130J. DOD‘s recently
established portfolio management structure is supposed to provide a
useful forum to address the broad range of airlift investment
decisions. However, efforts so far have primarily focused on new
programs rather than addressing gaps and making other airlift decisions
such as when and how many C-5s to retire or the appropriate mix of C-
130s and C-27Js needed to perform Army missions.
What GAO Recommends:
GAO recommends, among other things, that DOD broaden the scope of its
portfolio discussions, determine if additional C-17s are needed, and
determine how Army direct support requirements will be met. DOD
partially concurred with the recommendations, citing they have ongoing
plans or processes to address the issues raised. As discussed in the
report, GAO believes DOD needs to take additional steps to fully
respond to the recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-10-67] or key
components. For more information, contact Michael J. Sullivan (202) 512-
4841or sullivanm@gao.gov.
[End of section]
Contents:
Letter:
Background:
Airlift Acquisition and Modernization Programs Have Been Restructured
to Address Rising Costs and Changes in Airlift Needs:
Strategic Airlift Gap Has Been Addressed, but a Potential Tactical
Airlift Gap for Moving Medium Weight Equipment and Other Questions Have
Not Been Resolved:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: A Summary of Strategic and Tactical Airlift Systems--
Ongoing and Future Efforts:
Appendix II: Comments from the Department of Defense:
Related GAO Products:
Tables:
Table 1: Cost and Quantity Changes for Strategic Airlift Programs:
Table 2: Cost and Quantity Remaining for Strategic Airlift Programs as
of July 2009:
Table 3: Cost and Quantity Changes for Tactical Airlift Programs:
Table 4: Cost and Quantity Remaining for Tactical Airlift Programs as
of July 2009:
Table 5: Changes in Strategic Airlift Force Structure and Capabilities:
Table 6: C-5 Funding:
Table 7: C-17 Funding:
Table 8: Comparison of C-130H, C-130J-30, and C-27J Capabilities and
Characteristics:
Table 9: C-130 Funding:
Table 10: C-27J Funding:
Table 11: JFTL-Related RDT&E Funding:
Figures:
Figure 1: DOD Logistics Portfolio Management Structure:
Figure 2: Comparison of C-5 and C-17 Capabilities and Characteristics:
Figure 3: C-5 Galaxy:
Figure 4: C-17 Globemaster:
Figure 5: C-130 Hercules:
Figure 6: C-27J Spartan:
Figure 7: Joint Future Theater Lift:
Abbreviations:
AMP: Avionics Modernization Program:
DOD: Department of Defense:
IDA: Institute for Defense Analysis:
JFTL: Joint Future Theater Lift:
RAND: RAND Corporation:
RERP: Reliability Enhancement and Reengining Program:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
November 12, 2009:
The Honorable Neil Abercrombie:
Chairman:
The Honorable Roscoe Bartlett:
Ranking Member:
Subcommittee on Air and Land Forces:
Committee on Armed Services:
House of Representatives:
The Department of Defense (DOD) employs over 700 aircraft to move
troops and cargo in support of wartime operations, peacetime missions,
and humanitarian aid efforts. In 2008, these airlifters along with
commercial and leased aircraft flew more than 160,000 sorties, moving
about 800,000 tons of cargo and 3 million troops. The Air Force's C-5s
and C-17s perform the intertheater movement of troops and cargo,
referred to as strategic airlift, and its C-130s provide most
intratheater transport, referred to as tactical airlift.
The department plans to spend about $12 billion over the next 4 years
to modernize and recapitalize its airlift fleets. This includes
upgrading the avionics on C-5s and selected C-130 models, replacing
engines on about half of the C-5 fleet, and acquiring additional C-17s
and C-130Js. DOD is also procuring C-27J Joint Cargo Aircraft and has
begun initial planning efforts on the Joint Future Theater Lift (JFTL),
both slated for tactical airlift. Growing fiscal pressures, however,
may cause DOD to reexamine or restructure programs that exceed cost and
schedule targets. Because of the costs, complexities, and
interrelationships of airlift programs and the need for greater
insight, we examined, at your request (1) the cost, schedule, and
performance status of modernization efforts and new airlift programs
and (2) how well DOD is managing the airlift portfolio to make
investment decisions that address any capability gaps and redundancies.
This report builds and expands upon information reported to you on
strategic airlift issues in November 2008[Footnote 1] and provides new
information on tactical airlift programs and issues.
In conducting our work, we interviewed and obtained documentation from
officials within the Office of the Secretary of Defense and U.S.
Transportation Command related to the ongoing Mobility Capabilities and
Requirements Study 2016 and portfolio management activities. DOD
officials did not provide a copy of or detailed information about the
study results because the analysis had not been completed. Instead,
officials provided status updates and answered questions about
potential gaps and redundancies. We met with officials from each of the
weapon system program offices[Footnote 2] to obtain current cost,
schedule, and performance information. When appropriate, we discussed
reasons for variances from cost, schedule, and performance targets and
upcoming acquisition, modernization, or retirement decisions related to
their particular program. In addition, we met with Institute for
Defense Analysis (IDA) and RAND Corporation (RAND) officials to discuss
the results of their DOD-sponsored mobility studies. We also relied on
our previous reports related to portfolio management, DOD mobility
studies, and various weapon systems for information. A list of these
reports is included in the Related GAO Products section at the end of
this report. We conducted this performance audit from January 2009 to
November 2009 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
Background:
DOD uses a variety of aircraft to move weapons, equipment, and troops
from the United States to and within theaters of operation. C-5s and C-
17s are used for strategic airlift. They carry weapons and equipment
too large for any other DOD aircraft from the United States to staging
locations throughout the world. The family of C-130 aircraft, which
includes the C-130E, C-130H, and C-130J aircraft, is then the primary
asset used to move weapons, equipment, and troops within a theater of
operation.[Footnote 3] The C-17 is dually capable of performing both
strategic and tactical airlift missions and supplements the C-130 for
tactical airlift. All of these aircraft are owned and operated by the
Air Force and are considered part of the common user pool of aircraft
that can be used to support any of the services' missions. DOD also
relies on the Air Force's aerial refueling tankers (KC-10 and KC-135),
commercial aircraft, and leased aircraft to supplement airlift
capabilities. Officials at the U.S. Transportation Command and its Air
Force component, the Air Mobility Command, decide on how best to use
the assets on a daily basis. Often, these aircraft are scheduled for
departure when they have a full load, to ensure assets are used cost-
effectively. The services may also use their own airplanes and
helicopters that are not in the common user pool to move people and
cargo within a theater of operation. For example, these assets include
the Army's C-23 Sherpas and the Marine Corps' V-22 Osprey aircraft.
These aircraft are used to perform time-sensitive, mission-critical
requirements and may take off without full loads since urgency is the
primary driver for the mission, not efficiency or cost-effectiveness.
The Air Force is in the process of modernizing its C-5 and C-130H
aircraft and acquiring C-17s, C-130Js, and C-27Js to meet its future
strategic and tactical airlift requirements and improve aircraft
availability. It plans to retire C-130Es from the tactical airlift
fleet by 2014. C-5s are being modernized in two phases. During the
first phase, known as the Avionics Modernization Program (AMP),
aircraft receive upgraded avionics capabilities and an all-weather
flight control system. During the second phase, known as the
Reliability Enhancement and Reengining Program (RERP), aircraft engines
are replaced and electrical, fuel, and other subsystems are modified.
Together, the two modifications will help improve the C-5s wartime
mission capable rate. C-130H aircraft are also receiving an AMP
modification and will undergo a center wing box replacement because of
severe cracking discovered in that area.
DOD periodically assesses global threats, the national military
strategy, and its force structure to determine future airlift
requirements and to judge the sufficiency of its acquisition and
modernization plans. The analytical basis for DOD's current airlift
requirements is the Mobility Capabilities Study completed in December
2005.[Footnote 4] Officials used the study results to report in the
2006 Quadrennial Defense Review that 180 C-17s and 112 fully modernized
C-5s (those that received the AMP and RERP modifications) would be
sufficient to meet the national military strategy for strategic airlift
with acceptable risk. This could change pending the completion of the
ongoing DOD Mobility Capabilities and Requirements Study 2016, two
other DOD-sponsored airlift studies conducted by IDA and RAND, the 2010
Quadrennial Defense Review, and potential changes in threat assumptions
and the national security strategy. The IDA study has already been
completed and the remaining studies are expected to be completed by
January 2010.
Airlift Acquisition and Modernization Programs Have Been Restructured
to Address Rising Costs and Changes in Airlift Needs:
Over the last 2 years, DOD has restructured its airlift investments,
primarily due to sharp cost increases for modernization programs and
changes in requirements. The Air Force now intends to fully modernize
less than one-half of the C-5s it originally planned and will procure
additional C-17s. C-130 avionics modernization quantities were also cut
more than half and the schedule was delayed due to cost increases. The
Air Force is procuring more C-130J models than planned, due in part to
a decision to retire the older C-130E model. Pending decisions on
aircraft retirements, additional modifications, and new acquisitions
could further affect future costs and the force structure. Furthermore,
changing needs and uncertain strategies could lead to cost, schedule
and performance variances on two new airlift programs, the C-27J and
the JFTL. Appendix 1 contains more in-depth cost, schedule, and
performance information on the department's strategic and tactical
airlifters that we reviewed.
Strategic Airlift: DOD Is Modernizing Fewer C-5s, but Acquiring More C-
17s:
DOD has cut its C-5 modernization efforts by more than half and is
acquiring additional C-17s. Significant cost increases on the C-5 RERP
and AMP programs drove up unit costs and delayed schedules. These
problems, along with additional congressional appropriations that DOD
is using to procure more C-17s, led to a decision to fully modernize
only 52 C-5 aircraft instead of the entire fleet. Congress has provided
enough funding for DOD to procure 33 more C-17s. The last one will be
delivered in March 2011.
Substantial C-17 production line shutdown costs--ranging from about
$465 million to about $1 billion by Air Force and Boeing estimates,
respectively--have yet to be determined, but will need to be funded
soon. Table 1 summarizes changes in cost and quantities from original
estimates.
Table 1: Cost and Quantity Changes for Strategic Airlift Programs:
C-17;
Total cost: (then-year dollars in millions): Initial estimate: $39,754;
Total cost: Current estimate: (July 2009): $67,799;
Total cost: Percentage change: 71;
Quantity: Initial estimate: 211;
Quantity: Current estimate: (July 2009): 213;
Quantity: Percentage change: 1;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $188.4;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $318.3;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: 69.
C-5 RERP;
Total cost: (then-year dollars in millions): Initial estimate: $11,094;
Total cost: Current estimate: (July 2009): $7,694;
Total cost: Percentage change: -31;
Quantity: Initial estimate: 126;
Quantity: Current estimate: (July 2009): 52;
Quantity: Percentage change: -59;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $88;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $148.0;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: 68.
C-5 AMP;
Total cost: (then-year dollars in millions): Initial estimate: $911;
Total cost: Current estimate: (July 2009): $1,405;
Total cost: Percentage change: 54;
Quantity: Initial estimate: 112;
Quantity: Current estimate: (July 2009): 112;
Quantity: Percentage change: 0;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $8.1;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $12.5;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: 54.
Total;
Total cost: (then-year dollars in millions): Initial estimate: $51,759;
Total cost: Current estimate: (July 2009): $76,898;
Total cost: Percentage change: 49.
Source: GAO analysis and DOD selected acquisition and program baseline
reports. C-17 data were adjusted to include funding and quantities
included in supplemental budgets.
Notes: DOD plans to AMP a total of 112 C-5s. One aircraft that had
already received the AMP modification crashed.
[End of table]
DOD has nearly completed its C-17 acquisition program and is about
midway through the C-5 AMP modernization program. According to program
officials, 24 C-17s are yet to be delivered and 57 C-5s still need the
AMP modification. The C-5 RERP modernization program is just beginning
the low rate initial production phase. Only 3 of 52 C-5s have received
the RERP modification as part of the development program. DOD has
already spent about $69.2 billion on research, development, test and
evaluation (RDT&E) and procurement funds on these programs and program
officials project they will need to invest about $7.7 billion to
complete the programs as currently planned (see table 2).
Table 2: Cost and Quantity Remaining for Strategic Airlift Programs as
of July 2009:
C-17;
Investments (then-year dollars in millions): Prior: $65,995;
Investments (then-year dollars in millions): To go: $1,804;
Quantity: Delivered: 190;
Quantity: To go: 23.
C-5 RERP;
Investments (then-year dollars in millions): Prior: $2,138;
Investments (then-year dollars in millions): To go: $5,557;
Quantity: Delivered: 3;
Quantity: To go: 49.
C-5 AMP;
Investments (then-year dollars in millions): Prior: $1,062;
Investments (then-year dollars in millions): To go: $343;
Quantity: Delivered: 55;
Quantity: To go: 57.
Total;
Investments (then-year dollars in millions): Prior: $69,195;
Investments (then-year dollars in millions): To go: $7,703.
Source: GAO analysis and DOD selected acquisition reports.
Note: The C-17 quantity delivered figure includes one aircraft that is
dedicated to provide airlift capability to a consortium of European
nations.
[End of table]
The department planned to spend about $12 billion to make AMP and RERP
modifications to the fleet of C-5 aircraft by 2020. However, the Air
Force declared a Nunn-McCurdy cost breach[Footnote 5] in the RERP
program in September 2007, due to increased labor and parts costs. The
AMP effort required additional software development to address
deficiencies found during developmental testing. Development costs
would have been higher except that the Air Force decided not to address
250 deficiencies and 14 operational requirements in this program. These
events resulted in revised plans to provide the AMP upgrade to all C-5
aircraft and the RERP modification to 52 aircraft. The combined cost
for both modifications was reduced to $9.1 billion, but now less than
one-half of the fleet will be fully modernized and at a much higher
unit cost than originally estimated--$160.5 million for both
modifications versus $96.1 million. The portion of the fleet that does
not get both modifications will continue to experience mission capable
rates of around 50 percent compared to about 75 percent for the portion
that does get both modifications. The last modifications are supposed
to be finished in 2015.
Additional costs and changes in the force structure for the C-5 and C-
17 are possible pending decisions on future modifications and
retirements of older C-5s. For example, program officials said that
many of the deficiencies and requirements dropped from the current C-5
AMP effort will be addressed in annual AMP software upgrades, the C-5
RERP, or a new block upgrade program that is scheduled to begin in
fiscal year 2010. The C-17 is also addressing modernization through a
series of aircraft upgrades designed to address emerging issues such as
international airspace access requirements and critical operational/
safety issues.
Significant C-5 cost growth and further delays are possible if the RERP
program is not adequately funded. We previously reported that,
according to the department's Cost Analysis Improvement Group, the RERP
program was underfunded by about $294 million, with additional funding
needed in fiscal years 2012 and 2013.[Footnote 6] Replacement engines
are the costliest portion of the RERP upgrade, and DOD officials said
if funding is insufficient to meet yearly production quantities in
existing purchase agreements, anticipated price breaks will not occur
and could likely result in another Nunn-McCurdy unit cost breach and
program restructure. Department officials said the Air Force is
committed to fully funding the RERP modification of 52 aircraft, but
did not provide us with new budget data for fiscal years 2011 and
beyond.
Planned quantities of C-17s have fluctuated over the years. C-17
procurement began in 1988 and the Air Force initially planned to
acquire 210 aircraft. Following a major acquisition review in 1990, the
program was reduced to 120 aircraft because of technical problems and
funding shortfalls during the full-scale development program, which
resulted in higher than expected cost increases and schedule delays.
[Footnote 7] In subsequent years, DOD expanded the program from 120
aircraft to 180 aircraft and, in the past 3 fiscal years, Congress has
provided funding that would allow DOD to procure 33 additional
aircraft: 10 in fiscal year 2007,[Footnote 8] 15 in fiscal year 2008,
[Footnote 9] and 8 in fiscal year 2009.[Footnote 10] This would bring
the total number of C-17s DOD plans to procure to 213. As of July 2009,
DOD had taken delivery of 190 aircraft. The program is expected to end
with the delivery of the 213th aircraft in March 2011, at which time
the production line could be shut down if Boeing does not receive
additional international orders for the aircraft. The Air Force's
fiscal year 2010 budget includes $91.4 million to fund some of the
shutdown costs and a DOD official stated that additional funding would
be included in future budgets. However, final shutdown costs have not
been negotiated between the Air Force and Boeing, the prime contractor.
Last year we reported that the Air Force estimated the costs to be
around $465 million and Boeing's estimate was about $1 billion.
[Footnote 11]
Tactical Airlift: C-130 AMP Modernization Program Has Been Cut and
Uncertainty Surrounds New Programs:
DOD's tactical airlift investments have also experienced cost and
schedule fluctuations and continue to experience significant
uncertainty. The AMP program to modernize the C-130H fleet has been
substantially reduced, although officials are examining a possible
follow-on effort to include more aircraft. Procurement quantities for
the C-130J have increased to replace retiring C-130E models and plans,
quantities, and employment strategies for the newest tactical aircraft,
the C-27J, have yet to be finalized following a decision to transfer
the joint program entirely to the Air Force. Table 3 summarizes changes
in cost and quantity for current tactical aircraft. The JFTL, expected
to augment the C-130 fleets, is in concept development and cost and
quantity estimates are unavailable.
Table 3: Cost and Quantity Changes for Tactical Airlift Programs:
C-130 AMP;
Total cost (then-year dollars in millions): Initial estimate: $3,965;
Total cost: Current estimate: (July 2009): $5,800;
Total cost: Percentage change: 46;
Quantity: Initial estimate: 519;
Quantity: Current estimate: (July 2009): 221;
Quantity: Percentage change: -57;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $7.6;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $26.3;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: 244.
C-130J;
Total cost (then-year dollars in millions): Initial estimate: $840;
Total cost: Current estimate: (July 2009): $15,018;
Total cost: Percentage change: 1689;
Quantity: Initial estimate: 11;
Quantity: Current estimate: (July 2009): 168;
Quantity: Percentage change: 1,427;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $76.3;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $89.4;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: 17.
C-27J;
Total cost (then-year dollars in millions): Initial estimate: $4,088;
Total cost: Current estimate: (July 2009): $1,912;
Total cost: Percentage change: -53;
Quantity: Initial estimate: 78;
Quantity: Current estimate: (July 2009): 38;
Quantity: Percentage change: -51;
Program acquisition unit cost (then-year dollars in millions): Initial
estimate: $52.4;
Program acquisition unit cost (then-year dollars in millions): Current
estimate: (July 2009): $50.3;
Program acquisition unit cost (then-year dollars in millions):
Percentage change: -4.
Total;
Total cost (then-year dollars in millions): Initial estimate: $8,893;
Total cost: Current estimate: (July 2009): $22,731;
Total cost: Percentage change: 156.
Source: GAO analysis of DOD selected acquisition reports for the C-130
AMP program. GAO analysis of selected acquisition reports for the
initial estimates on the C-130J and C-27J programs and Air Force
updates for the current estimates.
Notes: Numbers may not add due to rounding. C-27J current cost estimate
does not include military construction funding.
[End of table]
DOD has not yet begun its C-130 AMP production program and has only
taken delivery of 2 C-27Js as of July 2009. The department has more
than half of its C-130J acquisitions--95 aircraft--yet to procure. DOD
has already spent $10.1 billion in RDT&E and procurement funds on these
programs. Program officials project it will cost about $12.6 billion to
complete the programs as currently planned (see table 4).
Table 4: Cost and Quantity Remaining for Tactical Airlift Programs as
of July 2009:
C-130 AMP;
Investments (then-year dollars in millions): Prior: $1,796;
Investments (then-year dollars in millions): To go: $4,004;
Quantity: Delivered: 3;
Quantity: To go: 218.
C-130J;
Investments (then-year dollars in millions): Prior: $7,739;
Investments (then-year dollars in millions): To go: $7,280;
Quantity: Delivered: 73;
Quantity: To go: 95.
C-27J;
Investments (then-year dollars in millions): Prior: $584;
Investments (then-year dollars in millions): To go: $1,329;
Quantity: Delivered: 2;
Quantity: To go: 36.
Total;
Investments (then-year dollars in millions): Prior: $10,118;
Investments (then-year dollars in millions): To go: $12,613.
Source: GAO analysis of C-130 AMP selected acquisition reports for
investments and quantity information. GAO analysis of C-130J and C-27J
selected acquisition reports for prior investment and quantity
information and Air Force updates for to go investment and quantity
information.
Note: Numbers may not add due to rounding. C-130J quantities include
orders for all U.S. military customers.
[End of table]
The C-130 AMP entered system development in 2001, but funding
instability and problems integrating hardware and software, as well as
an Air Force decision to exclude C-130E aircraft from the program,
triggered a Nunn-McCurdy unit cost breach in February 2007. The program
was subsequently restructured to include far fewer aircraft--221
instead of 519--at a cost $1.8 billion greater than the original
program estimate. In spite of the restructuring, incomplete production
decision documentation and software integration problems, as well as
senior leadership concerns about the acquisition strategy, have delayed
a low-rate production decision by more than a year from the revised
baseline--a slip of more than 4 years from the initial estimate. As of
July 2009, the program was still awaiting approval from the Under
Secretary for Acquisition, Technology and Logistics to award a
production contract. The Air Force is considering another program
restructure as well as a follow-on effort to modernize avionics on
additional C-130 aircraft, but officials did not provide us an estimate
of costs and quantities.
The department is now procuring more C-130J aircraft than originally
expected, in part because of a decision to retire C-130Es. Production
quantities for J-model aircraft have grown significantly over the last
several years, from an initial baseline of 11 aircraft in 1996 to a
current estimate of 168 aircraft, but according to program estimates,
program unit costs have remained relatively stable. Program officials
estimate a total program cost of $15 billion. As of July 2009, 73 C-
130Js have been delivered.
Recently, the department took delivery of the first two C-27J
airlifters as part of the Joint Cargo Aircraft program to provide
direct support for Army time-sensitive, mission-critical troop
resupply. In June of 2007, the Under Secretary for Acquisition,
Technology and Logistics approved an acquisition program baseline for
the joint program of 78 aircraft, with the Army planning to buy 54
aircraft, and the Air Force 24. However, as part of its fiscal year
2010 budget request, the department transferred the program, along with
the resupply mission it supports, exclusively to the Air Force and
reduced the program from 78 to 38 aircraft. Air Force operational plans
for the fleet and employment concepts for meeting Army direct support
requirements have not been finalized.
The Army and the Air Force are jointly pursuing the JFTL to replace the
C-130H airlifter and augment the rest of the C-130 fleet. The joint
concept development effort was initiated in January 2008 following a
decision by the Army and Air Force Chiefs of Staff to merge
requirements for separate heavy lift efforts in progress at the time.
The JFTL is anticipated to have a payload capacity of up to 36 tons,
with a combat mission radius of 500 nautical miles. However, the
services have different concepts for the aircraft. The Army concept is
for a vertical take-off and landing tiltrotor that could provide
sustainment of forces at the point of need and enable the maneuver of a
mounted force (i.e., forces deployed with combat vehicles) by air. The
Air Force is pursuing a fixed wing concept that would address the need
to operate on short, soft, or rough airfields and the need for greater
speed. Officials from both services stated they would like to have the
JFTL initial capabilities document validated and begin work on an
analysis of alternatives[Footnote 12] in the late summer of 2009, to
help ensure a sufficient basis for budget deliberations in March 2010.
As of July 2009, this had not occurred. Documents provided by these
officials indicate that system development for whichever concept is
selected is not expected to begin until at least 2014, with the new
system to be fielded beginning around 2024.
Strategic Airlift Gap Has Been Addressed, but a Potential Tactical
Airlift Gap for Moving Medium Weight Equipment and Other Questions Have
Not Been Resolved:
Additional funds provided by Congress for C-17 procurement more than
offset the strategic airlift gaps associated with reduced C-5
modernization plans. However, there is a potential future gap in
tactical airlift capabilities for transporting medium weight Army
equipment that cannot fit on C-130 aircraft. The C-17 fleet, in its
dual role of providing both strategic and tactical airlift, currently
provides this capability and is anticipated to continue to do so for
many years. The JFTL is envisioned to eventually replace the C-130H and
perform this and other roles, but will not be available for 15 years or
more under the current acquisition strategy. While the various mobility
studies acknowledge the C-17s' significant dual role, they did not
comprehensively evaluate an expanded future use of the C-17 for the
transport of medium weight equipment and how this could affect the
force structure, the C-17s' service life, and when to shut down the C-
17 production line. For example, the studies do not quantify current
and anticipated future use of the C-17 for tactical airlift. This is
because DOD officials do not consider the C-17 to be a suitable
substitute for the JFTL. In addition, there are differing opinions
about the transport of small loads in direct support of Army units,
which could call into question the quantity of C-27Js needed to perform
the Army mission. Two studies reached somewhat different conclusions
about the cost effectiveness of using C-130Js and C-27Js for this
mission. The Air Force and Army are working on a plan for how the Air
Force will meet Army direct support requirements, but the details have
not been finalized. DOD's recently established portfolio management
structure is supposed to provide a useful forum to address the broad
range of airlift investment decisions. However, efforts so far have
been primarily focused on new programs rather than addressing gaps and
redundancies across the current portfolio, as well as making other
airlift decisions, such as when and how many C-5s to retire or the
appropriate mix of C-130s and C-27Js needed to perform Army missions.
Acquisition of Additional C-17s Addresses Strategic Airlift Gap:
Following DOD's decision to reduce the number of C-5s that will be
fully modernized from 111 to 52 aircraft, Congress has appropriated
around $5.5 billion that DOD plans to use to procure up to 23
additional C-17s. This would bring the total number of C-17s the Air
Force now plans to acquire to 213 aircraft. DOD and Air Force officials
believe this current quantity of C-17s more than adequately addresses
their strategic airlift requirements in terms of the number of aircraft
needed and the collective delivery capabilities. Table 5 shows the
changes in the strategic airlift mix since the time the 2005 Mobility
Capabilities Study was completed and the impact the different mixes
have had on DOD's ability to meet strategic airlift requirements for
the timely inter-theater transport of required equipment and supplies.
Table 5: Changes in Strategic Airlift Force Structure and Capabilities:
Event:
December 2005: Mobility Capability Study released;
September 2006: Congressional appropriation for additional C-17s;
February 2008: C-5 RERP program is restructured;
June 2008: Congressional appropriation for additional C-17s;
June 2009: Congressional appropriation for additional C-17s.
Number of C-17s:
December 2005: 180;
September 2006: 190;
February 2008: 190;
June 2008: 205;
June 2009: 213.
Number of C-5s:
December 2005: 112 fully modernized;
September 2006: 112 fully modernized;
February 2008: 59 avionics only;
52 fully modernized;
June 2008: 59 avionics only;
52 fully modernized;
June 2009: 59 avionics only;
52 fully modernized.
Estimated million ton-miles per day capability:
December 2005: 33.09;
September 2006: 33.95;
February 2008: 32.17;
June 2008: 33.79;
June 2009: 34.79.
Source: GAO analysis of DOD budget and program data.
Note: The million ton-mile measure is a common metric included in prior
capability studies that describes the daily capacity of a specified
fleet of strategic airlifters.
[End of table]
A recent IDA study concluded that 316 strategic airlifters, which
include 205 C-17s, 52 fully modernized C-5s, and 59 partially
modernized C-5s, meets DOD's strategic airlift requirements established
in the 2005 Mobility Capability Study.[Footnote 13] Further, if
additional airlift capacity is needed above what the current mix of
aircraft can deliver, it could be achieved without procuring additional
C-17s or modernizing C-5s. Specifically, IDA found that additional
capacity could be obtained by:
* using C-5s at Emergency Wartime Planning levels:
* transporting some small oversize as well as bulk cargo using Civil
Reserve Air Fleet aircraft:
* making use of host nation airlifters to the maximum extent possible
and:
* using tankers not involved in tanker missions to carry cargo in
theater.
In the event that even more capacity is needed, the IDA study states
that it would be more cost-effective to provide the RERP modification
to more C-5s than to procure additional C-17s because the near-term
acquisition costs are offset by reduced operation and support costs.
IDA also concluded that retiring older C-5As to free up funds to buy
and operate more C-17s would result in a less capable force at
comparable overall cost and thus would not be cost-effective.
Potential Tactical Airlift Gap Exists in Movement of Medium Weight
Equipment on the Battlefield:
A potential future capability gap exists in the deployment and
redeployment of Army medium weight weapon systems within a theater of
combat. The C-17 is the only aircraft currently capable of transporting
heavier equipment, such as combat configured armored Strykers and Mine
Resistant Ambush Protected vehicles, within a theater of operations as
these are too large and bulky for C-130s to carry. However, the C-17
cannot transport this equipment into austere, short, or unimproved
landing areas. DOD's long-term plan is to use the JFTL, the planned C-
130H replacement, to transport these vehicles in theater, including to
such access-challenged locations. However, it will not be available for
at least 15 years as currently planned. While the various mobility
studies acknowledge the C-17 can perform both strategic and tactical
airlift missions, none of the three recently completed or ongoing
studies comprehensively considered the C-17 in the tactical force
structure, even though about 20 percent of the tactical sorties flown
by the C-17 fleet in fiscal year 2007 were for missions where loads
were too large for C-130s. As such, DOD has not evaluated the impact
the increasing tactical heavy lift mission will have on future tactical
airlift requirements, the C-17's service life, its availability to
perform strategic airlift and other tactical airlift missions, and the
impact it could have on C-17 production shutdown plans.
DOD officials do not believe that the C-17 is a suitable substitute for
the JFTL mission. A DOD official stated that preliminary results of the
Mobility Capabilities and Requirements Study 2016 show that in the
worst case planning scenario there would be enough C-17s to perform its
primary role as a strategic airlifter, as well as some tactical
missions through 2016. This is because the study analysis shows the
peak demand for the C-17 and the C-130 occurs at different times and
the C-17 is aging as planned. However, officials indicated that none of
the current mobility studies analyzed the need for the C-17 to perform
additional tactical heavy lift missions for the 8-year period between
2016 and 2024, when the JFTL is expected to be fielded. Furthermore,
because we were not granted access to the preliminary study
information, we could not ascertain the extent to which the C-17's
heavy lift mission had been considered in DOD's analysis through 2016.
C-17 production is scheduled to end in March 2011. As we previously
reported a well-reasoned, near-term decision on the final C-17 fleet
size could help DOD avoid substantial future costs from ending
production prematurely and later restarting production.[Footnote 14]
For example, the Air Force has estimated that restoring the production
line could cost $2 billion. Costs and challenges associated with such a
course include hiring and training a workforce of nearly 3,100 people,
reinstalling and restoring production tooling, and identifying
suppliers and qualifying their parts and processes.
Although it is too early to comment on JFTL program outcomes, we
believe DOD officials will need to exercise caution to avoid pitfalls
we have previously identified in connection with developing new weapon
systems so the new system will be delivered on time and within cost
estimates.[Footnote 15] These pitfalls include taking a revolutionary
versus an evolutionary approach for weapon system development, over
promising performance capabilities; increasing requirements; and
understating expected costs, schedules, and risks associated with
developing and producing the weapon. DOD understands many of the
problems that affect acquisition programs and has revised its
acquisition policy as a foundation for establishing sound, knowledge-
based business cases for individual acquisition programs.[Footnote 16]
For example, the policy recommends the completion of key systems
engineering activities before the start of development, including a
requirement for early prototyping, and establishes review boards to
evaluate the effect of potential requirements changes on ongoing
programs. The policy also supports evolutionary acquisitions and states
that increments should be fully funded, include mature technologies,
and normally be developed in less than 5 years. However, to improve
outcomes, DOD must ensure that its policy changes are consistently
implemented and reflected in decisions on individual programs.
Both Air Force and Army science and technology officials indicated that
no new technology invention is needed for either of their concepts.
However, tiltrotor technology has never been applied to a system of the
size needed to carry all the Army's ground vehicles (excluding the M-1
tank). In fact, the Army envisions the JFTL's payload capacity will be
nearly 5 times that of the V-22, the world's first production tiltrotor
aircraft and nearly 3 times that of the CH-47 Chinook, a heavy lift
helicopter used to transport ground forces, supplies, and other
critical cargo. In addition, the Senate Armed Services Committee
recently noted that to support the JFTL initial operational capability,
a prototype would need to be flying by 2015.[Footnote 17] Yet, the
committee could not identify any DOD funds budgeted for accomplishing
this objective, and further observed that waiting to conduct a
competitive prototyping effort as part of an acquisition program would
take years to begin. As such, the committee requested the Under
Secretary for Acquisition, Technology and Logistics to, among other
things, assess the merits of initiating a low-cost, highly streamlined
competitive prototyping effort immediately, determine whether cost and
performance goals can be met, help define requirements, and sustain the
industrial base.
Mix of C-130s and C-27Js Needed to Support Army Missions Has Not Been
Determined:
Questions remain about the number of C-130s and C-27Js needed to
support Army direct support missions. As stated earlier, as part of its
fiscal year 2010 budget request, the department transferred the C-27J
program, along with the resupply mission it supports, exclusively to
the Air Force and reduced the program from 78 to 38 aircraft. In a
recent hearing, congressional leaders questioned the Secretary of
Defense about how the Air Force will fulfill this mission with fewer
aircraft than initially anticipated.[Footnote 18] In response, the
Secretary of Defense stated that the reduced number of C-27Js was based
on the number needed to recapitalize the Army's fleet of C-23 Sherpas
and that uncommitted C-130 aircraft can be used to complement the C-
27Js to fulfill the Army's mission. In addition, he said there needs to
be a change in the Air Force's culture with respect to how the direct
support mission is accomplished.
The Air Force and Army are in the process of developing plans on how
the Air Force intends to fulfill the direct support mission, which
would include important decisions on employment concepts, basing, and
life-cycle support. The plans are in various stages of development and
are expected to be completed by October 2012. However, congressional
concerns remain regarding the service's commitment to that mission.
This concern is based on historical instances in which the Air Force
assigned lesser priority to direct delivery missions compared with
traditional airlift operations, most notably during the Vietnam War
when the Air Force assumed ownership of the Army's C-7 Caribou aircraft
and subsequently dropped some missions. It is also unclear what effect
this program change will have on the Air Force's C-130 fleet
operations.
In recent studies, IDA and RAND assessed the use and roles of the C-
130s and C-27Js in performing tactical missions. Although the study
parameters were different, they both looked at the tactical movement of
cargo. IDA's analysis focused on the use of these aircraft within the
context of major combat operations as well as persistent global
involvement in numerous smaller operations. IDA found that the tactical
fleets they examined were equally cost-effective at transporting cargo
in major combat operations. Whereas C-130s are more cost effective than
the C-27Js in specific missions that demand full loads, the opposite is
true when missions require small loads. Further, in non-major combat
operations, IDA found that the global demand for small loads on numbers
of aircraft in different locations made additional C-27Js more cost-
effective than additional C-130s.
According to RAND officials, RAND work on this topic has been underway
for several years. The first RAND study focused on determining the most
cost-effective way to recapitalize the C-130 fleet in order to meet the
official wartime requirement. This study concluded that acquisition of
the extended version of the C-130J was the most cost effective option
to perform tactical missions defined in the officially approved wartime
requirement. The C-27J provides about 40 percent of the cargo capacity
(in terms of pallets) as the extended C-130J at about two-thirds the
cost, based on net present value total life cycle costs. In addition,
the study also concluded that the extended C-130J and the C-27J were
equally cost-effective at conducting the ongoing resupply missions in
Iraq and Afghanistan. RAND was then asked to consider the cost-
effectiveness of the C-27J in eight additional missions that were not
part of the official requirement. The study concluded that the C-27J
was not cost-effective or appropriate for five of those missions and
was comparable to the C-130J in three of the missions. RAND also found
that the C-130J and the C-27J have comparable performance under
operationally consistent circumstances of delivering the same amount of
cargo at the same distances.
It should be noted that neither of these studies addressed recent C-27J
program decisions that resulted in the transfer of the program to the
Air Force and a reduction in aircraft quantities. Likewise, neither of
the studies considered the number of C-130s that may be necessary to
supplement these missions or the impact the missions may have on the C-
130 fleet. Furthermore, because the C-27J was not initially considered
part of the common user pool, the ongoing DOD Mobility Capabilities and
Requirements Study 2016 did not include the C-27J in the common user
pool in its analysis. Following the restructuring, an Air Force
official told us that, while the C-27J's primary use is expected to be
for direct support of the Army, it would also be available for movement
of cargo in the common user pool.
New Portfolio Management Initiative Offers Opportunities to Better
Manage Airlift Investments:
In September 2008, the department instituted a new process for helping
senior leaders make investment decisions, including those for
airlift.[Footnote 19] Known as capability portfolio management, the new
process enables the department to develop and manage capabilities, as
opposed to simply individual programs, and enhance the integration and
interoperability within and across sets of capabilities. Previously we
reported that leading commercial companies use portfolio management to
collectively address all of their respective investments from an
enterprise level rather than as independent and unrelated initiatives.
[Footnote 20] This approach, among other things, allows the companies
to weigh the relative costs, benefits, and risks of potential new
products and helps the companies balance near-and future-term market
opportunities.
According to DOD officials, airlift issues fall under the purview of
the logistics portfolio and are included in the deployment and
distribution subgroup, along with sealift and ground transportation.
Figure 1 shows the major capability areas included in the logistics
portfolio.
Figure 1: DOD Logistics Portfolio Management Structure:
[Refer to PDF for image: illustration]
Top level:
Logistics portfolio.
Second level:
Supply;
Maintain;
Deployment and distribution;
Logistic services.
Third level:
Operational contract support;
Engineering;
Installation and support;
Force health protection.
Source: DOD.
[End of figure]
The new capability portfolio management directive states that DOD shall
use capability portfolio management to advise the Deputy Secretary of
Defense and the heads of DOD components on how to optimize capability
investments across the defense enterprise and minimize risk in meeting
the department's capability need in support of strategy. The Under
Secretary of Defense for Acquisition, Technology and Logistics and the
Commander of U.S. Transportation Command share responsibilities for
managing the logistics portfolio. They are expected to identify airlift
issues, priorities, and capability resources and mismatches (gaps,
shortfalls, and redundancies). According to officials that assist with
logistics capability portfolio management activities, logistics
portfolio managers now have access to the Deputy's Advisory Working
Group that they may not have had access to before to discuss unresolved
logistics issues, including the Deputy Secretary of Defense and the
Vice Chairman of the Joint Chiefs of Staff.
We believe portfolio management offers DOD an opportunity to address
the full range of airlift issues, but DOD's implementation thus far has
not had a big impact on the way airlift assets are managed. Officials
we spoke with stated that the Under Secretary of Defense for
Acquisition, Technology and Logistics and U.S. Transportation Command
continue to focus on activities they were already performing prior to
the establishment of the portfolio, mainly concerned with new weapon
system programs and future capabilities but not as much on modification
programs on legacy aircraft. For example, the U.S. Transportation
Command has been and continues to be responsible for developing an
integrated priorities list that details the top new capabilities needed
and identifying capability gaps and shortfalls for airlift. The Under
Secretary of Defense for Acquisition, Technology and Logistics
continues to play an advisory role for addressing these gaps and
shortfalls.
Officials stated that to date, the logistics portfolio managers have
not provided input to recent or upcoming airlift decisions related to
the appropriate mix of strategic and tactical airlifters, changes in
modernization programs, C-5 retirements, C-17 production shutdown, and
changes in the Air Force's roles and missions for airlift. In addition,
no airlift issues have been brought to the working group for
resolution. Given this approach, we believe the department is still at
risk of continuing to develop and acquire new airlift systems and
modernization programs without knowing whether adequate resources are
available to complete programs within cost and schedule estimates.
Conclusions:
Growing fiscal pressures are forcing DOD leaders to look closely at
weapon system investments. DOD has to make tough investment and
programmatic decisions regarding strategic and tactical airlift in the
near future. However, the path forward is not clear because recently
completed and ongoing mobility studies lack some crucial information
that would help department officials make sound airlift investment
decisions. Namely, the studies do not quantitatively account for the
increasing tactical role of the C-17, especially in light of the fact
that C-130s are not capable of delivering heavier equipment demanded by
our warfighters and that the JFTL, which is envisioned to perform this
mission, will not be available for 15 years. Further, the studies do
not explore the possible use of C-27Js in a common user role or the
impact on the fleet and number of C-130s needed to support Army time-
sensitive, mission-critical requirements.
While Congress and DOD appear to have addressed the strategic airlift
capability gap, some fundamental questions remain: Can the Air Force
adequately fund the C-5 RERP modification program over the next 5
years? When should C-5s be retired and how many? And how many C-5s
would need the AMP modification if some of the aircraft are retired?
Even larger questions exist for tactical airlift: Are 213 C-17s enough
to perform both strategic and tactical missions? What are the potential
impacts on C-17 service life, maintenance, and availability from its
expected increased use in the future for the tactical airlift of
heavier and bulkier Army equipment? How will the Air Force meet the
Army's time-sensitive mission-critical requirements with 40 fewer C-27J
aircraft? Will there be a fundamental shift in the Air Force's roles
and mission that would require the Air Force to assume more Army-
specific missions? Can the department set technically realistic
requirements for the JFTL and follow an evolutionary acquisition
strategy that includes selecting mature technologies, normally
developing increments in less than 5 years and fully funding each
increment?
More information is needed to help the department address these
questions and avoid the unnecessary expenditure of billions of dollars
on redundant capabilities or a potentially premature C-17 production
line shutdown. The airlift portfolio management team has the requisite
authority to address these questions and influence budget decisions,
but greater attention must be paid to all facets of the airlift life
cycle--from cradle to grave. Making sound modernization and retirement
decisions is just as important as deciding when and what type of new
programs to start. Moreover, approaching these decisions from a
portfolio perspective rather than on a weapon system by weapon system
basis and considering new roles and missions for the Air Force may help
the department strike the right balance for its airlift investments.
Recommendations for Executive Action:
We are making five recommendations to help improve DOD's management of
strategic and tactical airlift assets. We recommend that the Secretary
of Defense direct:
* the portfolio management team, consisting of U.S. Transportation
Command and the Under Secretary of Defense for Acquisition, Technology
and Logistics, to provide more comprehensive advice to senior leaders
on the full range of airlift investment decisions, including new
program starts, modernization efforts, and retirement decisions. This
would also include identifying alternatives for using existing common
user aircraft to meet service-specific missions and considering new
roles and missions for the Air Force;
* the Office of the Secretary of Defense (Cost Assessment and Program
Evaluation) and Commander, U.S. Transportation Command to develop a
specific airlift plan that would identify when C-5s will be retired and
identify the total number of additional C-17s, if any, that would be
needed to replace C-5s or perform tactical heavy lift missions until
the time the JFTL is fielded;
* the Commander, Air Mobility Command, to determine the appropriate mix
of C-27Js and C-130s that are needed to meet Army time-sensitive,
mission-critical requirements and common user pool requirements;
* the Air Force and Army to reach agreement on plans detailing how Army
time-sensitive, mission-critical requirements will be addressed and
prioritized against other Air Force priorities; and:
* the joint Air Force and Army program office to develop a plan to
follow an evolutionary approach for developing the JFTL based on DOD
acquisition policy that includes selecting mature technologies,
normally developing increments in less than 5 years, and fully funding
each increment.
Agency Comments and Our Evaluation:
DOD provided us with written comments on a draft of this report; these
are included in appendix II. DOD partially concurred with all five
recommendations, stating that it either has plans and processes in
place or ongoing efforts to address our concerns. During the course of
our review, DOD officials explained the steps they were taking to make
strategic and tactical airlift decisions, but in some cases did not
provide us with supporting documentation and, in other cases, the plans
were in the initial stages of development and there was not yet
sufficient detail for us to determine the extent to which they
addressed our concerns. Despite the positive actions DOD described, we
believe that the department's efforts in some cases still fall short
and that our recommendations are warranted to help guide subsequent
actions and transition plans to effective implementation. DOD officials
also provided technical comments on our draft and we revised our report
where appropriate.
In response to our first recommendation about the portfolio management
team providing more comprehensive advice to senior leaders on the full
range of investment decisions, DOD says it has a structured process in
place for assessing its mobility capabilities and requirements that
includes strategic and tactical airlift decisions. We understand that
DOD has a process in place to make airlift decisions, but they are not
being made from a comprehensive portfolio management perspective, per
DOD regulation. DOD officials could not provide us with any evidence
that the portfolio management team had even discussed airlift issues
from a portfolio perspective, even though the logistics portfolio began
as a pilot program for portfolio management 2 years ago. We believe DOD
portfolio managers need to take a broader perspective on airlift issues
to ensure that the appropriate amount of attention and resources are
available to address the most pressing issues for new and legacy
programs and to avoid unnecessary expenditure of funds for
modernizations or acquisitions. Therefore, we do not believe that DOD's
response adequately addresses our recommendation.
The department agreed with our second recommendation on the need to
develop a plan for strategic airlift that identifies the number of C-5s
that will be retired and the number of additional C-17s, if any that
might be needed. In its comments, DOD stated that the Secretary of the
Air Force, in coordination with the Office of the Secretary of Defense
(Cost Assessment and Program Evaluation) and U.S. Transportation
Command has already developed this plan based on the current level of
congressional funding for the C-17 and preliminary results of the
Mobility Capabilities Requirements Study 2016 and the Quadrennial
Defense Review. Specifically, DOD officials believe an adequate number
of C-17s have been procured to cover all necessary missions to satisfy
the National Defense Strategy and will retire some C-5s. We were not
provided any details about this plan for strategic airlift, the ongoing
mobility study or the Quadrennial Defense Review to comment on the
adequacy of the analysis, but believe that a thorough analysis is
needed for senior leaders to make sound investment decisions. We are
concerned about the adequacy of the plan because during the course of
our review, DOD officials told us that the Mobility Capabilities
Requirements Study 2016 does not specifically quantify the use of the C-
17 in a tactical role or evaluate the impact on its service life
resulting from the increased use in that regard. In 2007, over 20
percent of the C-17 missions were for tactical missions and this could
grow given that it is the only aircraft that is capable of moving
certain types of equipment within a theater of operations that are too
large or bulky for the C-130. Further, it is unclear whether DOD has
identified how many C-5s need the AMP modification since additional C-
17s are being procured or when and how many C-5s will be retired. In
addition, we previously reported on deficiencies in how DOD conducted
its previous mobility capabilities study and we do not know if DOD has
addressed these flaws in the current study.[Footnote 21] As a result,
we do not know the extent to which the new study will provide clear
answers for senior leaders regarding strategic and tactical airlift or
engender more questions.
DOD commented that it believes it has fulfilled the requirements for
our third and fourth recommendations by recently tasking the Air Force
and Army to determine the appropriate mix of C-27Js and C-130s to
perform Army time-sensitive, mission-critical requirements and common
user pool requirements, as well as develop plans detailing how Army
requirements will be prioritized against Air Force priorities. These
are good first steps. However, the plans are still in development and,
according to an Air Force briefing to the Deputy's Advisory Working
Group, more work needs to be done. Critical details, including a
concept for employment, a final basing plan, and a decision on the
maintenance concept will have to be worked out over the next several
years. These issues have also generated much debate within the
department and in Congress concerning aircraft quantities and
employment strategies. As we stated earlier, the Air Force has
historically had trouble balancing Army priorities with its own and,
according to the Secretary of Defense, the Air Force will need to
change its culture to successfully meet both requirements. In addition
to completing the plans, we believe DOD may need to exert sustained
oversight by senior leaders, including the portfolio management team,
to ensure the Air Force is able to perform these missions over the long-
term.
Finally, DOD believes that it has fulfilled the requirement for our
fifth recommendation related to using an evolutionary approach for
developing the JFTL that includes selecting mature technologies,
developing increments in less than 5 years, and fully funding each
increment. DOD stated that the Air Force and Army are currently engaged
in approving a JFTL initial capabilities document and commencing with a
formal analysis of alternatives to consider all viable options for
addressing capability gaps. We believe these start-up actions are
appropriate and, if accomplished according to policy, should provide a
solid foundation to inform subsequent decisions for a new weapon system
acquisition program. Our recommendation, however, is geared not only to
these initial planning steps but also looking forward to the smooth
transition to system development and effective acquisition program
management. This recommendation will take several steps and years to
complete, and we believe senior leaders, including the portfolio
management team, need to ensure that the JFTL program has a solid
business case at the start of development with mature technologies,
adequate funding, and an incremental plan for development. Our previous
work on many other weapon systems programs[Footnote 22] has shown that
without these, programs are likely to encounter significant cost and
schedule growth that will, if realized on the JFTL program, impact the
department's ability to move medium weight equipment within a theater
of operations directly to the warfighter. It may also have an impact on
the C-17 program as these aircraft may be used more frequently than
planned for tactical missions. We therefore believe that DOD will need
to take additional steps to be fully responsive to this recommendation.
We are sending copies of this report to the Secretary of Defense and
interested congressional committees. The report is also available at no
charge on the GAO Web site at [hyperlink, http://www.gao.gov].
If you have any questions about this report or need additional
information, please contact me at (202) 512-4841 or sullivanm@gao.gov.
Contact points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. Key contributors
to this report were Bruce Fairbairn, Assistant Director; Cheryl Andrew;
Marvin Bonner; Andrew Redd; Kristine Heuwinkel; and Robert Swierczek.
Signed by:
Michael Sullivan:
Director Acquisition and Sourcing Management:
[End of section]
Appendix I: A Summary of Strategic and Tactical Airlift Systems--
Ongoing and Future Efforts:
This appendix provides more details on strategic and tactical airlift
new and modernization programs to expand upon summary information
provided in the body of this report. We include a brief description of
each aircraft's mission, program status, and our observations on
upcoming program decisions. Where applicable, we highlight our recent
work on some systems. The appendix also includes a funding table for
each aircraft. Because the fiscal year 2010 budget did not include
funding projections beyond fiscal year 2010, we used information from
the Fiscal Year 2010 Defense Budget for funding data related to fiscal
years 2008 through 2010 and the Fiscal Year 2009 Defense Budget for
fiscal years 2011 through 2013 when possible. Since the C-5 Reliability
Enhancement and Reengining Program (RERP) and C-27J programs were
restructured, we relied on information from the Air Force for fiscal
years 2011 through 2013 data. The budget information in each table is
expressed in current (then year) dollars and the totals may not add
exactly because of rounding.
Strategic Airlifters:
The Department of Defense (DOD) uses a mix of modernized C-5s, which
were manufactured 30 to 40 years ago, and newer C-17s to complete the
strategic airlift mission. Both strategic airlifters possess
intercontinental range with aerial refueling and can carry weapons and
equipment too large for any other DOD aircraft. Each also has some
complementary characteristics that favor a mixed fleet. The larger C-5
can carry more cargo than the C-17 and is the only aircraft capable of
handling some equipment, such as the Army's 74-ton mobile scissors
bridge. The C-17 is more modern, has a higher mission capable
rate,[Footnote 23] and is more flexible in that it also provides
tactical airlift to forward-deployed bases. Figure 2 compares the two
strategic airlifters.
Figure 2: Comparison of C-5 and C-17 Capabilities and Characteristics:
[Refer to PDF for image: illustrated table]
Loads:
C-5: 270,000 pounds of cargo (36 pallets), 81 troops;
C-17: 170,900 pounds of cargo (18 pallets), 102 troops.
Wingspan:
C-5: 223 feet;
C-17: 170 feet.
Length:
C-5: 247 feet;
C-17: 174 feet.
Maximum take-off weight:
C-5: 840,000 pounds;
C-17: 585,000 pounds.
Range:
C-5: 6,320 miles (unrefueled); Unlimited (air refueled);
C-17: 2,700 miles (unrefueled); Unlimited (air refueled).
Speed:
C-5: 518 mph;
C-17: 572 mph.
Minimum runway length:
C-5: 6,000 feet;
C-17: 3,500 feet.
Crew:
C-5: 7;
C-17: 3.
Mission capable rate (2008):
C-5: 52 percent;
C-17: 86 percent.
Cost per flying hour (2008):
C-5: $20,947.
C-17: $12,014.
Source: GAO analysis of DOD data; graphics by Lockheed Martin
Corporation.
[End of figure]
C-5 Galaxy:
Figure 3: C-5 Galaxy:
[Refer to PDF for image: photograph]
Source: U.S. Air Force photo/Jason Minto.
[End of figure]
Mission:
The C-5 is one of the largest aircraft in the world and is used by DOD
for strategic airlift purposes. It can carry outsize and oversize cargo
over intercontinental ranges and can take off or land in relatively
short distances. With aerial refueling, the aircraft's range is limited
only by crew endurance. The C-5 can carry nearly all of the Army's
combat equipment, including large heavy items such as the 74-ton mobile
scissors bridge. Ground crews can load and off-load the C-5
simultaneously at the front and rear cargo openings. The landing gear
system permits lowering of the parked aircraft so the cargo floor is at
truck bed height to facilitate vehicle loading and unloading.
Program Status:
The Air Force acquired a total of 126 C-5s in two production batches.
Aircraft designated C-5A were built between 1969 and 1974 and given new
wings in the 1980s.[Footnote 24] Aircraft designated C-5B were built in
a second production run in the 1980s. Since then, the Air Force has
retired 14 C-5As and 1 C-5B crashed, leaving a total of 111 C-5
aircraft (60 C-5As, 49 C-5Bs, and 2 C-5Cs).
In 1999, the Air Force began modernizing its C-5 aircraft.
Modifications are intended to improve operational capability while
improving flight safety, reliability, and maintainability. The two
primary modifications are as follows[Footnote 25]
* The Avionics Modernization Program (AMP), which upgrades
capabilities, including Global Air Traffic Management, navigation and
safety equipment, modern digital equipment, and an all-weather flight
control system.
* The Reliability Enhancement and Reengining Program (RERP), which
replaces engines and modifies over 70 electrical, fuel, and other
subsystems.
Together, these two upgrades were expected to improve the fleet's
wartime mission capable rate to at least 75 percent, thereby increasing
payload capability and transportation throughput, and to reduce total
ownership costs over the life cycle through 2040 by about $14 billion
in 2008 dollars.[Footnote 26]
DOD initially expected to spend about $12 billion on the C-5 AMP and
RERP efforts. However, both modernization efforts experienced cost and
schedule problems since going into development. AMP development costs
increased by approximately 20 percent and would have been higher had
the Air Force not reduced requirements and deferred some development
activities to other programs. Officials waived 14 operational
requirements and deferred the correction of 250 deficiencies identified
during testing, many of which will be addressed and funded in RERP or
future efforts. In addition, the C-5 RERP experienced a Nunn-McCurdy
cost breach. The program was restructured and the Air Force now plans
to RERP 52 aircraft--47 C-5 B aircraft, both C-5 Cs, and 3 aircraft
that had already been modified during system development and
demonstration (two C-5Bs and one C-5A). While the Air Force is expected
to spend $3.4 billion (then-year dollars) less under the restructured
RERP program, ultimately, less than one-half of the aircraft will be
modernized and at a much higher unit cost than originally estimated--
$160.5 million for both modifications versus $96.1 million originally
estimated in then-year dollars. DOD now expects that the C-5 AMP
modification of 112 aircraft and the C-5 RERP modification of 52
aircraft will reduce total ownership costs over the life cycle through
2040 by about $8.9 billion base year 2000 dollars.
According to program officials, as of July 2009, 55 of the C-5s have
received the AMP modification. The last B model received the
modification in August 2009. All focus is now on the A models. Many of
the deficiencies found during testing have been corrected. Other
deficiencies and waivers will be addressed in the RERP program or a
planned block upgrade that is slated to begin in fiscal year 2010.
According to program officials, only 3 C-5 aircraft used during systems
development and demonstration have received the RERP modification thus
far. The first production aircraft will enter modification in August
2009. The Air Force has received low rate initial production approval
for the first 3 lots, totaling 9 aircraft. The full rate production
decision is scheduled for December 2010.
GAO Observations:
It is unclear whether the Air Force is going to adequately fund the
restructured C-5 RERP program because the fiscal year 2010 budget does
not include funding details for the program through 2015. Further,
program officials could only comment on the fiscal year 2010 budget. On
the basis of the fiscal year 2009 budget however, DOD's Cost Analysis
Improvement Group concluded that the restructured C-5 RERP program was
underfunded by about $294 million then-year dollars across the Future
Years Defense Plan for fiscal years 2009 through 2013. Approximately
$250 million then-year dollars less is needed in fiscal years 2009
through 2011, and $544 million then-year dollars more is needed in
fiscal years 2012 and 2013. DOD officials stated that if the budget is
not sufficient to meet agreed-upon quantities, then anticipated price
breaks would not occur, resulting in increased cost to the program and
government.
In June 2009, the Air Force was granted authority by Congress to begin
retiring C-5A aircraft.[Footnote 27] Air Mobility Command officials
told us that fiscal and personnel demands require that the command
limit overall fleet size once warfighting risk is reduced to a
reasonable level. Therefore, the Air Mobility Command will consider
retiring C-5s, as the law and requirements allow, on a one-for-one
basis after 205 C-17s have been procured, to ensure the right
combination of aircraft and capability is balanced against cost and
risk. According to program officials, operational testing for an A
model will take place between October 2009 and January 2010. The final
report will be issued in July 2010. A decision on whether and when to
retire C-5s will not likely be made until after the Mobility
Capabilities and Requirements Study 2016 has been completed.
If DOD decides to retire C-5A aircraft, it may not need to provide the
AMP modification to all of its C-5 fleet. The Air Force plans to have
40 of the 60 C-5A AMP modification kits on contract by the end of 2009
and at least 8 C-5A models will have actually received the modification
by that time.
Table 6: C-5 Funding (Then-year dollars in millions):
FY 2009 budget:
C-5 AMP; RDT&E;
2008: $10.2;
2009: $4.2;
2010: $3.9;
2011: $0;
2012: $0;
2013: $0.
C-5 AMP; Modification;
2008: $84.4;
2009: $94.9;
2010: $79.9;
2011: $75.3;
2012: $77.5;
2013: $75.3.
Total C-5 AMP;
2008: $94.6;
2009: $99.1;
2010: $83.8;
2011: $75.3;
2012: $77.5;
2013: $75.3.
C-5 RERP: RDT&E;
2008: $163.8;
2009: $122.9;
2010: $71.7;
2011: $35.6;
2012: $15.6;
2013: $0.
C-5 RERP: Modification;
2008: $148;
2009: $280.1;
2010: $502.3;
2011: $891.4;
2012: $1,154.6;
2013: $1242.7.
Total C-5 RERP;
2008: $311.8;
2009: $403;
2010: $574;
2011: $927;
2012: $1,170.2;
2013: $1,242.7.
Other programs;
2008: $60.5;
2009: $126;
2010: $101.9;
2011: $6.2;
2012: $6.4;
2013: $6.5.
Total;
2008: $466.8;
2009: $628.1;
2010: $759.7;
2011: $1,008.5;
2012: $1,254.1;
2013: $1,324.5.
Source: For fiscal years 2008-2010, DOD's Fiscal Year 2010 President's
Budget; for fiscal years 2011-2013, DOD's Fiscal Year 2009 President's
Budget for AMP and Other programs and the June 2008 Selected
Acquisition Report for RERP. Numbers may not add due to rounding.
[End of table]
C-17 Globemaster:
Figure 4: C-17 Globemaster:
[Refer to PDF for image: photograph]
Source: C-17 Program Office.
[End of figure]
Mission:
The C-17 is a multi-engine, turbofan, wide-body aircraft that improves
the overall capability of the United States Air Force to rapidly
project, reinforce, and sustain combat forces worldwide. It is used by
DOD for both strategic and tactical missions. For example, the C-17 is
capable of rapid strategic delivery of troops and all types of cargo to
main operating bases or directly to forward bases in the deployment
area. The aircraft can perform tactical airlift and airdrop missions
and can also transport ambulatory patients during aeromedical
evacuations when required. The inherent flexibility and performance of
the C-17 force improve the ability of the total airlift system to
fulfill the worldwide air mobility requirements of the United States.
Program Status:
The Air Force originally planned to procure 120 C-17s, with the last
one being delivered in November 2004. The Air Force's current plans are
to acquire a total of 213 C-17s for $68 billion, with the last one
being delivered in March 2011. The Air Force has taken delivery of 190
aircraft through July 2009. This includes one aircraft that is
dedicated to provide airlift capability to a consortium of European
nations, effectively setting the Air Force's operational force at 212.
The Air Force has a number of ongoing improvement efforts for the C-17,
including:
* improving C-17 airdrop system operations,
* integrating an advanced situational awareness and countermeasures
system,
* upgrading mission planning by integrating a new joint precision
airdrop system,
* replacing the core integrated computer processor, and:
* providing advanced defensive capability.
GAO Observations:
In recent years, the two prominent issues surrounding the C-17 program
have been determining how many C-17s are needed to meet strategic
airlift requirements as well as determining when to begin shutting down
the C-17 production line. Following a C-5 RERP restructuring in 2008,
the U.S. Transportation Command identified a need for 205 C-17s, 25
more than were authorized at the time the 2005 Mobility Capabilities
Study was completed. Subsequent to the study, Congress provided
additional funding that the Air Force used to procure 10 more C-17s in
2007, 15 more in 2008, and 8 more in 2009, bringing the total that will
now be procured to 213. According to Air Mobility Command officials,
the command will consider retiring C-5s, as the law and requirements
allow, on a one-for-one basis after 205 C-17s have been procured, to
ensure the right combination of aircraft and capability is balanced
against cost and risk.
According to program officials, a decision when to shut down the C-17
production line along with the associated costs has not been finalized.
In our November 2008 report we reported that plans called for the C-17
production line to shut down in September 2010.[Footnote 28] This was
based on the Air Force acquiring 205 aircraft. Now that the Air Force
will be acquiring 213 aircraft, the last delivery is now expected to be
in March 2011. We also reported that the total cost to shut down the
line has not been determined. The Air Force estimated the costs to shut
down production to be $465 million whereas Boeing (the prime
contractor) estimated $1 billion. Officials reported that while the Air
Force and Boeing continue to negotiate the final cost to shut down the
C-17 production line, the Air Force did include $91 million in its
fiscal year 2010 President's budget submission to begin these
activities.
According to a DOD official, the C-17s are currently being employed to
fill a capability gap existing in the department's ability to airlift
medium-weight vehicles within a theater of operations using dedicated
tactical airlifters. DOD officials do not consider the C-17 to be a
viable long-term solution as it cannot access short, austere, or
unimproved landing areas in close proximity to combat operations. The
JFTL is expected to provide this long-term solution; however, the JFTL
is not expected to be available until 2024.
Table 7: C-17 Funding (Then-year dollars in millions(:
FY 2009 budget:
RDT&E;
2008: $166.2;
2009: $235.4;
2010: $161.9;
2011: $206.5;
2012: $222.6;
2013: $223.2.
Procurement;
2008: $244;
2009: $317.9;
2010: $88.5;
2011: $214.1;
2012: $216.1;
2013: $196.3.
Modifications;
2008: $194.8;
2009: $315.4;
2010: $469.7;
2011: $469.4;
2012: $415.8;
2013: $628.
Supplemental;
2008: $3,387.9;
2009: $2,187.2;
2010: $132.3;
2011: $0;
2012: $0;
2013: $0.
Total;
2008: $3,992.9;
2009: $3, 055.9;
2010: $852.4;
2011: $890.0;
2012: $854.5;
2013: $1,047.5.
Source: For fiscal years 2008-2010,DOD's Fiscal Year 2010 President's
Budget; fiscal years 2011-2013, DOD's Fiscal Year 2009 President's
Budget.
[End of table]
Tactical Airlifters:
As of April 2009, DOD's tactical airlift fleet consisted of 92 C-130E
aircraft, 268 C-130Hs, 53 C-130Js, and 2 C-27Js--a total of 415
aircraft. DOD plans to retire its aging C-130E fleet by the end of
fiscal year 2014, and according to its Air Mobility Master Plan, looks
to meet its tactical airlift needs with a mix of approximately 406 C-
130H and C-130J airlifters through the end of the next decade. The Army
and Air Force are working on concepts for the Joint Future Theater Lift
(JFTL)--an eventual replacement for the C-130H that is projected to be
capable of carrying most of the Army's large vehicles into forward
operating locations, which C-130s currently cannot do. Additionally,
the Joint Requirements Oversight Council has validated the Army's time-
sensitive, mission-critical resupply requirements that provide the
basis for the Joint Cargo Aircraft program to procure 38 C-27Js. These
missions are comprised of relatively small payloads that are needed in
forward locations within tight time frames. Table 8 compares the
capabilities of the C-130H, C-130J-30, and C-27J airlifters.
Table 8: Comparison of C-130H, C-130J-30, and C-27J Capabilities and
Characteristics:
Loads:
C-130H: 42,000 pounds; 6 pallets, or; 92 combat troops;
C-130J-30: 44,000 pounds; 8 pallets, or; 128 combat troops;
C-27J: 14,190 pounds; 3 pallets, or; 46 combat troops.
Wingspan;
C-130H: 133 feet;
C-130J-30: 133 feet;
C-27J: 94 feet.
Length;
C-130H: 98 feet;
C-130J-30: 113 feet;
C-27J: 75 feet.
Maximum take-off weight;
C-130H: 155,000 pounds;
C-130J-30: 164,000 pounds;
C-27J: 67,241 pounds.
Range[A];
C-130H: 1,720 miles;
C-130J-30: 2,780 miles;
C-27J: 2,645 miles.
Average speed;
C-130H: 345 mph;
C-130J-30: 368 mph;
C-27J: 288 mph.
Minimum runway length;
C-130H: 3000 ft.;
C-130J-30: 3,000 ft.;
C-27J: 2,000 ft.
Crew;
C-130H: 5;
C-130J-30: 3;
C-27J: 3.
Mission capable rate (2008);
C-130H: 74;
C-130J-30: 80[B];
C-27J: Not available[C].
Cost per flying hour (2008);
C-130H: $7,500;
C-130J-30: $5,000[B];
C-27J: $3,871[C].
Source: GAO analysis and DOD data.
Notes: All values are rounded to the nearest whole number. Cost per
flying hour includes fuel costs. The C-130J-30 has an additional 15
feet of fuselage length compared to the base C-130J. Most combat
delivery aircraft the Air Force is procuring will be this extended
model.
[A] Range is based on a 35,000 pound payload for the C-130H and C-130J-
30 and a 13,000 pound payload for the C-27J, based on contractor data.
[B] Figure includes rates/costs for C-130J fleet, which includes both
base C-130J as well as C-130J-30 models.
[C] Only 2 C-27J aircraft have been delivered thus far and are being
used for training and developmental testing. Average cost per flying
hour is the 2008 estimate.
[End of table]
C-130 Hercules:
Figure 5: C-130 Hercules:
[Refer to PDF for image: photograph]
Source: C-130J Program Office.
[End of figure]
Mission:
The C-130 is the principal combat delivery aircraft for the U.S.
military and is employed primarily as a tactical airlift aircraft for
the transport of cargo and personnel within a theater of operation. C-
130s also have the capability to augment strategic airlift forces, as
well as support humanitarian, peacekeeping, and disaster relief
operations. The C-130J is the latest addition to DOD's fleet of C-130
aircraft, providing performance improvements over legacy aircraft in
the series. Variants of the C-130J are being acquired by the Air Force,
Marine Corps, Coast Guard, and several foreign militaries to perform
their respective missions.
Program Status:
The C-130E and C-130H fleets are nearly 30 years old and have serious
reliability, maintainability, and supportability issues, and some are
reaching the end of their service life. For example, aircraft
maintainers discovered severe cracking in the center wing box on some
aircraft early in fiscal year 2005. The program office recommended
retiring or grounding aircraft with more than 45,000 flying hours, and
restricting aircraft with more than 38,000 hours from flying with cargo
or performing tactical maneuvers. In response to these recommendations,
the Air Force is using some operations and maintenance funding to
extend the service life of some C-130 aircraft by 3 to 5 years,
including part of the C-130E fleet, which the Air Force plans to retire
by the end of fiscal year 2014. In addition, the Air Force is currently
funding the replacement of the center wing box on older C-130 aircraft,
and plans to replace the wing structure on the remainder of the C-130H
fleet in a later phase of the program. The cost of the replacement is
approximately $6.5 million per aircraft, and according to Air Force
officials, the program is meeting all cost, schedule, and performance
goals.
The Air Force also has several other modification efforts underway for
the C-130H fleet that will address known capability shortfalls. Efforts
include a Large Aircraft Infrared Countermeasures program, a Surface-
to-Air Fire Look-out Capability modification, and a number of
communications upgrades. The largest modernization effort is the
Avionics Modernization Program (AMP) to standardize cockpit
configurations and avionics, as well as provide for increased
reliability, maintainability, and sustainability. Initially, the Air
Force planned to upgrade all C-130E and C-130H aircraft, including
special operations aircraft. However, after the program entered system
development in 2001, it experienced funding instability and hardware
and software integration issues. These problems, as well as an Air
Force decision to retire C-130E aircraft, triggered a Nunn-McCurdy cost
breach in February 2007. The program was subsequently restructured to
include far fewer aircraft--221 instead of 519--and assume less
developmental risk. Under the revised plan, only a portion of the C-
130H fleet would receive the modification. Since that time, the
program's production decision has been delayed 13 months because of
documentation and software integration problems and senior leadership
concerns about the program's acquisition strategy. A low rate
production decision has not been scheduled as the department is
considering another program restructure. Program officials further
stated that a second phase of the AMP is now being considered that will
modernize C-130s not included in the first phase.
DOD is in the process of procuring 168 C-130J airlifters to replace the
retiring C-130E fleet. According to program officials, as of July 2009,
73 C-130J aircraft have been delivered of 117 on contract.[Footnote 29]
One program official said all C-130J aircraft currently being purchased
by the Air Mobility Command are the C-130J-30 model which, compared to
the base model, has an extended fuselage and is capable of carrying 2
additional cargo pallets, for a total of 8 pallets. The C-130J fleet is
also receiving a number of upgrades to meet communications, navigation,
and surveillance, as well as air traffic management requirements. These
efforts are being funded and developed in partnership with other
countries as part of the International Cooperative Block Upgrade
Program.[Footnote 30] A C-130J program official reports that aircraft
availability rates continue to exceed the fleet standard and are better
than rates for C-130H models.
GAO Observations:
Recently, the Secretary of Defense testified that DOD could use
"uncommitted" C-130 aircraft to complement C-27Js in order to fulfill
Army time-sensitive, mission-critical requirements. However, according
to an Air Force official, the impact to the C-130 fleet of
supplementing C-27Js in direct support missions is not clear, including
how it would affect C-130 availability for other missions. The Air
Force has drafted a concept of employment for direct support of Army
time-sensitive, mission-critical missions that addresses a number of
coordination issues between the services, but the potential impact of
these missions on the C-130 fleet has not been assessed, such as fuel
costs, maintenance to address potential wear on landing gear and other
components, and addressing flight restrictions for runway length.
Table 9: C-130 Funding (Then-year dollars in millions):
FY 2009 budget:
C-130 budget: RDT&E;
2008: $233.3;
2009: $179.3;
2010: $201.3;
2011: $47.5;
2012: $12.9;
2013: $9.9.
C-130 budget: Modifications;
2008: $216.9;
2009: $434.6;
2010: $354.5;
2011: $471.7;
2012: $412.7;
2013: $429.2.
C-130 budget: Supplemental;
2008: $140.7;
2009: $0;
2010: $0;
2011: $0;
2012: $0;
2013: $0.
C-130 budget: Total;
2008: $590.9;
2009: $613.9;
2010: $555.8;
2011: $519.2;
2012: $425.6;
2013: $439.1.
C-130J: RDT&E;
2008: $62.1;
2009: $27.3;
2010: $30.0;
2011: $59.9;
2012: $59.9;
2013: $58.3.
C-130J: Procurement;
2008: $681.4;
2009: $120.7;
2010: $393.6;
2011: $632.9;
2012: $637.5;
2013: $557.8.
C-130J: Modifications;
2008: $58.3;
2009: $34.3;
2010: $13.6;
2011: $115.8;
2012: $129.3;
2013: $105.7.
C-130J: Supplemental;
2008: $1,100.7;
2009: $9;
2010: $72;
2011: $0;
2012: $0;
2013: $0.
C-130J: Total;
2008: $1,902.5;
2009: $191.3;
2010: $509.3;
2011: $808.6;
2012: $826.7;
2013: $721.8.
Source: For fiscal years 2008-2010, DOD's Fiscal Year 2010 President's
Budget and Fiscal Year 2009 Overseas Contingency Operations
Supplemental; fiscal years 2011-2013, DOD's Fiscal Year 2009
President's Budget.
[End of table]
C-27J Joint Cargo Aircraft:
Figure 6: C-27J Spartan:
[Refer to PDF for image: photograph]
Source: L-3 Communications.
[End of figure]
Mission:
The C-27J Spartan is a mid-range, multifunctional aircraft. Its primary
mission is to provide on-demand transport of time-sensitive, mission-
critical supplies and key personnel to forward deployed Army units,
including those in remote and austere locations. It can also be used
for humanitarian relief and homeland security efforts. The aircraft is
capable of carrying up-armored High Mobility Multipurpose Wheeled
Vehicles and heavy, dense loads such as aircraft engines and
ammunition.
Program Status:
The Joint Cargo Aircraft program began in late 2005 when the Under
Secretary for Acquisition, Technology and Logistics directed the Army
and Air Force to merge their requirements for small intra-theater
airlifters.[Footnote 31] In June 2007 the Under Secretary of Defense
for Acquisition, Technology and Logistics issued an Acquisition
Decision Memorandum certifying the program with approval to proceed to
low rate initial production. This memorandum set the acquisition
program baseline at 78 aircraft: 54 for the Army and 24 for the Air
Force. The Army primarily viewed the C-27J as on-call airlift directly
tied to the tactical needs of ground commanders, sometimes referred to
as transporting cargo the "last tactical mile." The Air Force planned
to use its C-27J assets to provide "general support" airlift for all
users, but also views the delivery of time-sensitive, mission-critical
Army cargo as its role.
The joint Army/Air Force program office selected the C-27J as the Joint
Cargo Aircraft in a full and open competition and awarded a firm-fixed
price contract to L-3 Communications, Integrated Systems in June 2007.
Two aircraft of a total of 13 the Army has ordered through fiscal year
2009 have been delivered and according to program officials are being
used to conduct training and developmental testing. In May 2009, as
part of budget deliberations, the Army and Air Force Chiefs of Staff
agreed to transfer responsibility for the C-27J program to the Air
Force, along with the task of fulfilling the Army's time-sensitive,
mission-critical resupply mission. As part of this restructuring,
program quantities were reduced by about 50 percent, from 78 to 38
aircraft. The 13 ordered aircraft, including the 2 already delivered,
will be transferred to the Air Force, who will procure an additional 25
aircraft between 2010 and 2012.
C-27J aircraft are currently built in Turin, Italy. Manufacturer Alenia
Aeronautica (primary sub contractor to L-3 Communications, Integrated
Systems) had planned to break ground on a manufacturing facility in
Jacksonville, Florida, in April 2009, but according to an Alenia
Aeronautica official, this decision has been presently postponed.
According to program officials, Alenia Aeronautica had planned to
assemble C-27J aircraft 16 through 78 at the Jacksonville facility, in
addition to those ordered by foreign customers. With DOD's decision to
procure fewer aircraft, it is unclear whether Alenia will proceed with
construction of the facility.
GAO Observations:
The Air Force has offered some insight into how it will meet the Army's
time-sensitive, mission-critical resupply requirement and is in the
process of further developing concepts of operation and employment for
the C-27J. Although the service is buying only 38 C-27J aircraft, it is
investigating possibilities for fulfilling the direct support mission
requirement at least in part from a common user pool fleet construct.
For example, an Air Force official said C-130s are already used for
some time-sensitive, mission-critical operations. The Secretary of
Defense has indicated that the 38 C-27Js can be complemented by any of
about 200 "uncommitted" C-130s, which he noted can access 99 percent of
the landing strips that C-27Js can access.[Footnote 32] However, it is
unclear if or how such an approach will affect the number of C-130Js
the service plans to buy, or the availability of C-130 aircraft to meet
other requirements associated with major combat operations. The
Mobility Capabilities and Requirements Study 2016 may help shed light
on this issue.
There is also concern about the Air Force's commitment to direct
support of the time-sensitive, mission-critical requirement. Over the
past several decades, the Air Force has retired its direct support
assets, including the Vietnam-era C-7 Caribou and an earlier version of
the C-27. At issue are basic roles and missions philosophies which DOD
recognizes need to be updated to reflect lessons learned in ongoing
combat operations. The Secretary of Defense testified in May 2009 that
there needs to be a change in the Air Force's culture with respect to
how the direct support mission is accomplished. Similarly, the
department's Quadrennial Roles and Missions Review Report for January
2009 notes that the services need to standardize the airlift process by
sharing aircraft employment and availability data and adjust concepts
of operations to allow traditionally general support assets to be used
for direct support and vice versa. However, the Quadrennial Roles and
Missions Review Report also determined that the service
responsibilities for intratheater airlift operations were appropriately
aligned and the option that provided the most value to the joint force
was to assign the C-27J to both the Air Force and the Army. An Air
Force official said the service has drafted a platform-neutral concept
of employment for direct support of the time-sensitive, mission-
critical mission. The vision is to use the capabilities of the entire
mobility airlift fleet (i.e., C-130, C-17, C-5, Operational Support
Airlift) to supplement the 38 C-27Js as required in time-sensitive,
mission-critical operations abroad.
While the Mobility Capabilities and Requirements Study 2016 and other
studies consider tactical airlift requirements into the future,
officials involved with the study have not indicated that they address
the impact of potential departures from traditional roles and missions
constructs--such as changing how the services will approach time-
sensitive, mission-critical resupply. As such, it is not known how
these changes may affect overall requirements for tactical airlifters.
Moreover, there is speculation that the 2010 Quadrennial Defense Review
will establish priorities based on one major combat operation, rather
than two simultaneous ones. Considered together, these points raise the
question of how many C-27Js DOD needs.
Table 10: C-27J Funding (Then-year dollars in millions):
FY 2009 budget:
RDT&E;
2008: $26.8;
2009: $19.7;
2010: $9.4;
2011: $26.5;
2012: $19.2;
2013: $6.8.
Procurement;
2008: $156.0;
2009: $263.4;
2010: $319.1;
2011: $371.3;
2012: $576.5;
2013: $0.
Total;
2008: $182.8;
2009: $283.1;
2010: $328.4;
2011: $397.8;
2012: $595.7;
2013: $6.8.
Source: For fiscal years 2008-2010, DOD's fiscal year 2010 President's
Budget; for fiscal years 2011-2013, Air Force revised program
estimates.
[End of table]
Joint Future Theater Lift:
Figure 7: Joint Future Theater Lift:
[Refer to PDF for image: 2 photographs]
Source: Contractor‘s rendering, Lockheed Martin.
Source: Contractor‘s rendering © 2008 Karem Aircraft/Lockheed Martin.
[End of figure]
Mission:
DOD plans to replace C-130H aircraft and augment the remaining C-130s
with the Joint Future Theater Lift (JFTL). Currently, it is still at
the conceptual stage and is not yet a formal acquisition program. The
Army and Air Force have independently engaged in laboratory efforts to
develop competitive technology solutions including a large tiltrotor,
vertical takeoff and landing aircraft, and a versatile fixed wing,
short takeoff and landing aircraft, respectively.[Footnote 33] A draft
Initial Capabilities Document notes that the JFTL must be capable of
transporting current and future medium-weight armored vehicles into
austere locations with unprepared landing areas. According to an Army
official, another capability under investigation is the ability to
operate from naval vessels (seabasing) to enhance access to remote
areas and to reduce predictability. The JFTL is anticipated to have a
payload capacity of 20 to 36 tons and a combat mission radius of 500
nautical miles. The Air Force Air Mobility Command expects the JFTL to
be fielded sometime around 2024.
Program Status:
JFTL concept development became a joint effort in January 2008
following a decision by the Army and Air Force Chiefs of Staff to merge
requirements for separate heavy lift efforts in progress at the time.
[Footnote 34] The Air Force was designated as the administrative lead
for the development of the Initial Capabilities Document for the JFTL,
and submitted a draft into DOD's Joint Capability Integration and
Development System earlier this year; however, the Army did not agree
with the draft, citing critical disagreements. According to an Army
program official, a recent general officer meeting between the two
services appears to have resolved the Army's remaining critical
comments, and the services could potentially seek approval of the
Initial Capabilities Document at the Joint Requirements Oversight
Council by late summer 2009. Both Army and Air Force officials stated
they would like to have the Initial Capabilities Document validated and
begin work on the analysis of alternatives in the summer of 2009, to
provide a sufficient basis for budget deliberations in March 2010.
Disparate views on requirements are at the heart of the disagreement
between the services. According to an Army official, there were
foundational differences in anticipated usage of the aircraft that led
to initial disagreements between the services. The land component
(i.e., the Army, Marine Corps, and special operations forces) saw a
critical need for an airlift capability that would enable
expeditionary, mounted (i.e. forces deployed with combat vehicles)
ground operations into access-challenged environments. The airlift
community was pursuing a larger, longer range transport to better meet
the current set of traditional airlift missions. The Army official said
the two perspectives resulted in different technologies and system
investigations. The land component, led by the Army, has been pursuing
vertical takeoff and landing concepts that are less infrastructure-
constrained, allow faster force buildup, and can more easily sustain
maneuvering forces from either land or sea bases. The Air Force has
been pursuing advanced lift system technology for turbofan fixed wing
aircraft to improve operations on short, soft, or rough airfields while
increasing cruise speed over current tactical transports. However, the
Army official said development of the JFTL Initial Capabilities
Document has combined these perspectives into one requirements document
and served to converge the services into a more cohesive vision of
future operations.
Both the Army and Air Force have continued to fund technology
development efforts that support their previously separate programs.
Army technology development efforts are focused on a high-efficiency
tiltrotor concept that could become a candidate for the JFTL once
requirements are established. According to an Army lab official, the
aircraft would be nearly as aerodynamically efficient as a fixed wing
aircraft and would have about the same fuel efficiency as a C-130J.
While the concept is still "all on paper," the official said no new
inventions are needed--that the component technologies all have an
existing lineage and could be practically implemented on an aircraft of
the size anticipated (the maximum payload would be 36 tons). The Army
has three contractors or contractor teams working on different
tiltrotor configurations that could potentially meet the joint
capability needs. A number of technology development/risk reduction
efforts, including a tiltrotor test rig and a number of specialized
studies, have been funded by the Army, Special Operations Command,
National Aeronautics and Space Administration, Defense Advanced
Research Projects Agency, and Office of Naval Research.
An Air Force official said the service's technology development efforts
are focused on a fixed wing concept that combines speed and agility to
provide enhanced lift for short takeoffs. According to the Air Force
official, three contractors have done work on this speed agile concept,
with one--Lockheed Martin--on contract to develop a demonstrator model.
The Air Force Research Laboratory has also, in partnership with
Lockheed Martin, developed the Advanced Composite Cargo Aircraft, which
utilizes composite materials in the fuselage and tail, and which
completed a successful test flight in June 2009. An Air Force Research
Lab official said this technology significantly reduces the number of
parts needed, as well as tooling and touch labor needs in the
manufacturing process. He said these processes and materials could
potentially be used for the JFTL.
GAO Observations:
A potential capability gap exists in the department's ability to
airlift medium-weight vehicles to access-challenged areas within a
theater of operations using dedicated tactical airlifters. C-17
aircraft have been employed to transport medium weight vehicles in
theater, but cannot access austere, short, or unimproved landing areas.
In 2007 C-17s flew 15,436 tactical sorties, 3,102 of which--
approximately 20 percent--involved carrying objects too large for a C-
130 to carry. Nevertheless, DOD officials do not consider the C-17 to
be a viable long-term solution given access issues noted above. JFTL is
expected to provide this long-term solution.
We believe the JFTL effort presents the department an opportunity to
address a critical capability gap using the evolutionary, knowledge-
based approach outlined in DOD acquisition policy. However, DOD
officials will need to exercise caution to avoid pitfalls we have
identified in connection with developing new weapon systems, including
taking a revolutionary versus an evolutionary approach for weapon
system development; overpromising performance capabilities; and
understating expected costs, schedules, and risks associated with
developing and producing the weapon.
Fielding the new capability may be a challenge for two reasons. First,
although the services have reached agreement on operational
requirements in developing the Initial Capabilities Document, the
potential exists for future disagreements that could adversely affect
program outcomes. The Army would like a tiltrotor aircraft that can be
used in direct support of its maneuver and sustainment operations, and
the Air Force favors a fixed wing aircraft to support common-user needs
as well as the Army's direct support mission. An Army official said the
decision to pursue a tiltrotor or a fixed wing aircraft will be made
during the analysis of alternatives, and that he expected a more
cooperative relationship between the services once that is decided.
However, we feel that if such a relationship does not emerge or
continue throughout system development, program outcomes could be
jeopardized. Our previous work has found that unstable requirements in
conjunction with long development cycles can lead to considerable cost
growth and schedule delays.
Second, the JFTL was intended to transport medium-weight vehicles,
including Future Combat Systems vehicles; however, DOD recently
canceled the manned ground vehicle portion of the program with plans to
re-launch a new vehicle modernization program incorporating lessons
learned in recent operations in Iraq and Afghanistan. We believe the
design of the new vehicles, including size and weight, could be an
important factor in determining the type of aircraft best suited for
the JFTL mission, primarily because the Army's tiltrotor concept
already envisions a rotorcraft much larger than any ever produced.
However it could be several years before the Army has a good
understanding of the size and weight of the new vehicles.
Table 11: JFTL-Related RDT&E Funding (Then-year dollars in millions):
Air Force:
2008: $38.5;
2009: $22.6;
2010: $26.0;
2011: $49.0;
2012: $44.0;
2013: $40.2.
Army:
2008: $22.5;
2009: $24.5;
2010: n/a;
2011: n/a;
2012: n/a;
2013: n/a.
Total:
2008: $61.0;
2009: $47.1.
Source: For the Air Force, figures for fiscal years 2008 and 2009
represent funding that has been obligated on contract; figures for
fiscal years 2010 through 2013 represent burdened dollars--funds that
include personnel and other programmatic elements--as projected in the
fiscal year 2009 President's Budget request. For the Army, funds are a
combination of Army, Special Operations Command, Defense Advanced
Research Projects Agency, Navy, and National Aeronautics and Space
Administration funding applied directly to Joint Heavy Lift activities.
[End of table]
[End of section]
Appendix II: Comments from the Department of Defense:
Office Of The Under Secretary Of Defense:
Acquisition, Technology And Logistics:
3000 Defense Pentagon:
Washington, DC 20301-3000:
November 3, 2009:
Mr. Michael J. Sullivan:
Director, Acquisition and Sourcing Management:
U.S. Government Accountability Office:
441 G Street, N.W.
Washington, DC 20548:
Dear Mr. Sullivan:
This is the Department of Defense (DoD) response to the GAO Draft
Report, GAO-10-67, "Defense Acquisitions: Strategic Airlift Gap Has
Been Addressed, but Tactical Airlift Plans Are Evolving as Key Issues
Have Not Been Resolved," dated September 9, 2009 (GAO Code 120800).
DoD's responses to the report's recommendations are enclosed.
The Department partially concurs with all five recommendations. In
general, the Department is already taking actions outlined in the
report and does not believe additional directives from the Secretary
are required at this time. A list of technical comments is also
provided separately to ensure report accuracy.
The Department's goal remains to provide the Warfighter with the most
capable and cost-effective strategic and tactical airlift fleets to
meet our global requirements.
Sincerely,
Signed by:
David G. Ahern
Director:
Portfolio Systems Acquisition:
Enclosure: As stated:
[End of letter]
GAO Draft Report Dated September 9, 2009:
GAO-10-67 (GAO Code 120800):
"Defense Acquisitions: Strategic Airlift Gap Has Been Addressed, But
Tactical Airlift Plans Are Evolving As Key Issues Have Not Been
Resolved"
Department Of Defense Comments To The GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretary of Defense
direct the portfolio management team to provide more comprehensive
advice to senior leaders on the full range of airlift investment
decisions, including new program starts, modernization efforts, and
retirement decisions. This would also include identifying alternatives
for using existing common user aircraft to meet service-specific
missions and considering new roles and missions for the Air Force. (p.
20/GAO Draft Report)
DOD Response: Partially Concur. The Department has structured processes
in place for assessing mobility capabilities and requirements that
include strategic and tactical airlift decisions. AT&L, CAPE,
USTRANSCOM and other DoD Components participate in these decisions.
Recommendation 2: The GAO recommends that the Secretary of Defense
direct the Office of the Secretary of Defense (Cost Assessment and
Program Evaluation) and Commander, U.S. Transportation Command to
develop a strategic airlift plan that would identify when C-5s will be
retired and identify the total number of additional C-17s that would be
needed to replace C-5s or perform tactical heavy lift missions until
the time the Joint Future Theater Lift (JFTL) is fielded. (p. 20/GAO
Draft Report)
DOD Response: Partially Concur. The Department agrees on the need to
develop a strategic airlift plan with the details as listed in the
recommendation. Accordingly, the Secretary of the Air Force, in
coordination with OSD CAPE and USTRANSCOM, has already developed a
strategic airlift plan that identifies the retirement of C-5 aircraft
based on congressional funding of additional C-17s not requested by the
Department and preliminary findings from the Mobility Capability
Requirements Study ” 2016 and the Quadrennial Defense Review. The
Department remains confident that it has procured adequate C-17s to
cover all necessary missions to satisfy requirements of the National
Defense Strategy. Recapitalization of the C-5 fleet is decades away.
Prior to determining the C-5's replacement, the Department will conduct
a comprehensive Analysis of Alternatives to fully assess viable
options.
Recommendation 3: The GAO recommends that the Secretary of Defense
direct the Commander, Air Mobility Command, determine the appropriate
mix of C-27Js and C-130s that are needed to meet Army time-sensitive,
mission-critical requirements and common user pool requirements. (p.
20/GAO Draft Report)
DOD Response: Partially Concur. The Department agrees on the need to
determine the appropriate mix of C-27Js and C-130s. Accordingly, the
Secretary of Defense has already tasked the Air Force and the Army to
determine the appropriate mix of C-27Js and C-130s that are needed to
meet Army time-sensitive, mission-critical requirements and common user
pool requirements, thus fulfilling the requirement of this
recommendation.
Recommendation 4: The GAO recommends that the Secretary of Defense
direct the Air Force and Army reach agreement on plans detailing how
Army time-sensitive, mission-critical requirements will be addressed
and prioritized against other Air Force priorities. (p. 21/GAO Draft
Report)
DOD Response: Partially Concur. The Secretary of Defense has already
tasked the Air Force and the Army to develop plans detailing how Army
time-sensitive, mission-critical requirements will be addressed and
prioritized against other Air Force priorities, thus fulfilling the
requirement of this recommendation. An agreement was reached in the
plan for USAF Direct Support of US Army Time Sensitive/Mission Critical
Concept of Employment, approved and signed by Army and Air Force Vice
Chiefs of Staff effective 13 Sep 09.
Recommendation 5: The GAO recommends that the Secretary of Defense
direct the joint Air Force and Army program office develop a plan to
follow an evolutionary approach for developing the JTFL based on DoD
acquisition policy that includes selected mature technologies, normally
developing increments in less than 5 years, and fully funding each
increment. (p. 21 /GAO Draft Report)
DOD Response: Partially Concur. The AF and Army are currently engaged in
approving a JFTL Initial Capabilities Document and commencing with a
formal JCIDS Analysis of Alternatives (AOA) to consider all viable
options for addressing capability gaps, thus fulfilling the requirement
of this recommendation.
[End of section]
Related GAO Products:
Defense Acquisitions: Charting a Course for Lasting Reform. [hyperlink,
http://www.gao.gov/products/GAO-09-663T]. Washington, D.C.: April 30,
2009.
Defense Acquisitions: Assessments of Selected Weapon Programs.
[hyperlink, http://www.gao.gov/products/GAO-09-326SP]. Washington,
D.C.: March 30, 2009.
Defense Acquisitions: Timely and Accurate Estimates of Costs and
Requirements Are Needed to Define Optimal Future Strategic Airlift Mix.
[hyperlink, http://www.gao.gov/products/GAO-09-50]. Washington, D.C.:
November 21, 2008.
Defense Transportation: DOD Should Ensure that the Final Size and Mix
of Airlift Force Study Plan Includes Sufficient Detail to Meet the
Terms of the Law and Inform Decision Makers. [hyperlink,
http://www.gao.gov/products/GAO-08-704R]. Washington, D.C.: April 28,
2008.
Best Practices: An Integrated Portfolio Management Approach to Weapon
System Investments Could Improve DOD's Acquisition Outcomes.
[hyperlink, http://www.gao.gov/products/GAO-07-388]. Washington, D.C.:
March 30, 2007.
Defense Transportation: Study Limitations Raise Questions about the
Adequacy and Completeness of the Mobility Capabilities Study and
Report. [hyperlink, http://www.gao.gov/products/GAO-06-938].
Washington, D.C.: September 20, 2006.
[End of section]
Footnotes:
[1] GAO, Defense Acquisitions: Timely and Accurate Estimates of Costs
and Requirements Are Needed to Define Optimal Future Strategic Airlift
Mix, [hyperlink, http://www.gao.gov/products/GAO-09-50] (Washington,
D.C.: Nov. 21, 2008).
[2] Program offices we visited included the C-130 Avionics
Modernization Program, C-130J, C-17, C-27J, and C-5. We also met with
science and technology officials that are working on the Joint Future
Theater Lift.
[3] DOD began using the C-130Es in 1962 and the C-130Hs, which included
more powerful engines in 1974. DOD added the C-130J to the C-130 family
in 1999. It includes a new propeller design and engines. A stretch
version, the C-130J-30, which includes a 15-foot fuselage extension,
has also been introduced.
[4] Other studies were completed in 1992, 1994, and 2001.
[5] 10 U.S.C. § 2433 establishes the requirement for unit cost reports.
If certain cost thresholds are exceeded (known as unit cost or Nunn-
McCurdy breaches), DOD is required to report to Congress and, in
certain circumstances, certify the program to Congress.
[6] [hyperlink, http://www.gao.gov/products/GAO-09-50].
[7] GAO, Military Airlift: Status of the C-17 Development Program,
[hyperlink, http://www.gao.gov/products/GAO-T-NSIAD-93-6] (Washington,
D.C.: Mar. 10, 1993).
[8] Title III of the Department of Defense Appropriations Act, 2007,
provided funds for Air Force aircraft procurement. Pub. L. No. 109-289.
The Conference Report related to this legislation reflected $2 billion
for the Air Force to procure ten C-17 aircraft. H.R. Conf. Rep. No. 109-
676, at 372 (2006).
[9] Title IX of the Supplemental Appropriations Act, 2008, provided
funds for Air Force aircraft procurement. Pub. L. No. 110-252. The
Congressional Record related to this legislation reflects that both the
House of Representatives and the Senate recommended $3.6 billion for
the Air Force to procure 15 C-17 aircraft. 154 Cong. Rec. H3953, 3971,
3979, 3981 (daily ed. May 15, 2008) (statement of Rep. Obey); 154 Cong.
Rec. S4302, 4329, 4330 (daily ed. May 19, 2008) (statement of Sen.
Byrd).
[10] Title III of the Supplemental Appropriations Act, 2009, provided
funds for Air Force aircraft procurement. Pub. L. No. 111-32. The
Conference Report related to this legislation reflected $2.17 billion
for the Air Force to procure eight C-17 aircraft. H.R. Conf. Rep. No.
111-151, at 93 (2009).
[11] [hyperlink, http://www.gao.gov/products/GAO-09-50].
[12] The analysis of alternatives is an analytical study that is
intended to compare the operational effectiveness, cost, and risks of a
number of alternative potential solutions to address valid needs.
Department of Defense Instruction 5000.02, Operation of the Defense
Acquisition System Enclosure 2, section 4(c), paragraphs 5 and 6 (Dec.
8, 2008); Interim Defense Acquisition Guidebook chapter 3.3.1 (June 15,
2009).
[13] Institute for Defense Analyses, Study on Size and Mix of Airlift
Force, February 2009.
[14] [hyperlink, http://www.gao.gov/products/GAO-09-50].
[15] GAO, Defense Acquisition: DOD Must Balance Its Needs with
Available Resources and Follow an Incremental Approach to Acquiring
Weapon Systems, [hyperlink, http://www.gao.gov/products/GAO-09-431T]
(Washington, D.C.: Mar. 3, 2009).
[16] Department of Defense Directive 5000.01, The Defense Acquisition
System (May 12, 2003); Department of Defense Instruction 5000.02,
Operation of the Defense Acquisition System (Dec. 8, 2008).
[17] S. Rep. No. 111-35, at 52-54 (2009).
[18] Department of Defense Budget Request for Fiscal Year 2010: Hearing
Before the H. Armed Services Comm., 111th Cong. (2009) (statements of
Rep. Bartlett, Ranking Member, H. Armed Services Comm., and Robert
Gates, Secretary of Defense).
[19] Department of Defense Directive 7045.20, Capability Portfolio
Management (Sept. 25, 2008).
[20] GAO, Best Practices: An Integrated Portfolio Management Approach
to Weapon System Investments Could Improve DOD's Acquisition Outcomes,
[hyperlink, http://www.gao.gov/products/GAO-07-388] (Washington, D.C.:
Mar. 30, 2007).
[21] GAO, Defense Transportation: Study Limitations Raise Questions
about the Adequacy and Completeness of the Mobility Capabilities Study
and Report, [hyperlink, http://www.gao.gov/products/GAO-06-938]
(Washington, D.C.: Sept. 20, 2006).
[22] GAO, Defense Acquisitions: Charting a Course for Lasting Reform,
[hyperlink, http://www.gao.gov/products/GAO-09-663T] (Washington, D.C.:
Apr. 30, 2009).
[23] DOD uses mission capable rate as a measure of an aircraft's
readiness to perform at least one assigned mission.
[24] Two C-5As were later modified to carry National Aeronautics and
Space Administration components and other outsized cargo and were re-
designated C-5Cs.
[25] Other modifications include replacing Aft crown skins, the on-
board monitoring system, and floor panels and troop compartments
impacted by corrosion; installing the Large Aircraft Infrared
Countermeasures System and other defensive systems; and updating
trainer configurations.
[26] According to DOD, throughput is defined as the amount of work that
can be performed or the amount of output that can be produced by a
system or component in a given period of time. For airlifters, it
refers to the amount of freight or passengers that can be carried by an
aircraft during a specified time period.
[27] Supplemental Appropriations Act, 2009, Pub. L. No. 111-32, § 311
(2009).
[28] GAO, Defense Acquisitions: Timely and Accurate Estimates of Costs
and Requirements Are Needed to Define Optimal Future Strategic Airlift
Mix, [hyperlink, http://www.gao.gov/products/GAO-09-50] (Washington,
D.C.: Nov. 21, 2008).
[29] The program of record includes orders for all U.S. military
customers.
[30] Partner nations include Italy, Denmark, United Kingdom, Australia,
Canada, and Norway.
[31] These similar Army and Air Force efforts were designated the
Future Cargo Aircraft and Light Cargo Aircraft, respectively.
[32] Army officials said this statement assumed that if the C-130J
could access an airfield within 50 nautical miles of the point of need,
then this was sufficient, even if there were landing zones or surfaces
accessible by the C-27J closer to the point of need.
[33] The Army is partnered with the Navy, Special Operations Command,
Defense Advanced Research Projects Agency, and the National Aeronautics
and Space Administration. A tiltrotor aircraft, such as the V-22, is
one that operates as a helicopter for takeoffs and landings and, once
airborne, converts to a turboprop aircraft.
[34] The Army and Air Force programs were known as Joint Heavy Lift and
Advanced Joint Air Combat System, respectively.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: