Joint Strike Fighter

Accelerating Procurement before Completing Development Increases the Government's Financial Risk Gao ID: GAO-09-303 March 12, 2009

The Joint Strike Fighter (JSF) is the Department of Defense's (DOD) most complex and ambitious aircraft acquisition, seeking to simultaneously produce and field three different versions of the aircraft for the Air Force, Navy, Marine Corps, and eight international partners. The total investment required now exceeds $1 trillion--more than $300 billion to acquire 2,456 aircraft and $760 billion in life cycle operating and support costs, according to program estimates. The Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 requires GAO to review the JSF program annually for 5 years. This is the fifth and final report under the mandate in which GAO (1) determines the program's progress in meeting cost, schedule, and performance goals; (2) assesses manufacturing results and schedule risks; and (3) evaluates development test plans, progress, and risks. GAO's work included analyses of a wide range of program documents, cost data and interviews with defense and contractor officials.

JSF development will cost more and take longer than reported to the Congress last year, and DOD wants to accelerate procurement. Two recent estimates project additional costs ranging from $2.4 billion to $7.4 billion and 1 to 3 more years to complete development. Despite cost and schedule troubles, DOD wants to accelerate JSF procurement by 169 aircraft from fiscal years 2010 through 2015; this could require up to $33.4 billion in additional procurement funding for those 6 years. DOD plans to procure hundreds of aircraft on cost-reimbursement contracts, magnifying the financial risk to the government. Ongoing manufacturing inefficiencies and parts problems have significantly delayed the delivery of test assets. The prime contractor has extended manufacturing schedules three times and delivered 2 of 13 test aircraft. The program is still recovering from earlier problems that resulted in design changes, late parts deliveries, and inefficient manufacturing. The contractor is taking positive steps to improve operations, the supplier base, and schedule management. Schedule risk analyses could further enhance management insight into problem areas and inform corrective actions. Officials expect to deliver all test aircraft and fix many problems by 2010. By then, DOD plans to have purchased 62 operational aircraft and will be ramping up procurement. Procuring large numbers of production jets while still working to deliver test jets and mature manufacturing processes does not seem prudent, and looming plans to accelerate procurement will be difficult to achieve cost effectively. DOD's revised test plan adds a year to the schedule, better aligns resources and availability dates, and lessens the overlap between development and operational testing, but it still allows little time for error discovery and rework. DOD's decision late in 2007 to reduce test aircraft and flight tests adds to risks while any additional delays in delivering test aircraft will further compress the schedule. The revised plan relies on state-of-the-art simulation labs, a flying test bed, and desk studies to verify nearly 83 percent of JSF capabilities. Only 17 percent is to be verified through flight testing. Despite advances, the ability to so extensively substitute for flight testing has not yet been demonstrated. Significant overlap of development, test, and procurement results in DOD making substantial investments before flight testing proves that the JSF will perform as expected. Under the accelerated procurement plan, DOD may procure 360 aircraft costing an estimated $57 billion before completing development flight testing.

Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director: Team: Phone:


GAO-09-303, Joint Strike Fighter: Accelerating Procurement before Completing Development Increases the Government's Financial Risk This is the accessible text file for GAO report number GAO-09-303 entitled 'Joint Strike Fighter: Accelerating Procurement before Completing Development Increases the Government's Financial Risk' which was released on March 12, 2009. This text file was formatted by the U.S. Government Accountability Office (GAO) to be accessible to users with visual impairments, as part of a longer term project to improve GAO products' accessibility. Every attempt has been made to maintain the structural and data integrity of the original printed product. Accessibility features, such as text descriptions of tables, consecutively numbered footnotes placed at the end of the file, and the text of agency comment letters, are provided but may not exactly duplicate the presentation or format of the printed version. The portable document format (PDF) file is an exact electronic replica of the printed version. We welcome your feedback. Please E-mail your comments regarding the contents or accessibility features of this document to Webmaster@gao.gov. This is a work of the U.S. government and is not subject to copyright protection in the United States. It may be reproduced and distributed in its entirety without further permission from GAO. Because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately. Report to Congressional Committees: United States Government Accountability Office: GAO: March 2009: Joint Strike FighteR: Accelerating Procurement before Completing Development Increases the Government's Financial Risk: Joint Strike Fighter: GAO-09-303: GAO Highlights: Highlights of GAO-09-303, a report to congressional committees. Why GAO Did This Study: The Joint Strike Fighter (JSF) is the Department of Defense‘s (DOD) most complex and ambitious aircraft acquisition, seeking to simultaneously produce and field three different versions of the aircraft for the Air Force, Navy, Marine Corps, and eight international partners. The total investment required now exceeds $1 trillion”more than $300 billion to acquire 2,456 aircraft and $760 billion in life cycle operating and support costs, according to program estimates. The Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 requires GAO to review the JSF program annually for 5 years. This is the fifth and final report under the mandate in which GAO (1) determines the program‘s progress in meeting cost, schedule, and performance goals; (2) assesses manufacturing results and schedule risks; and (3) evaluates development test plans, progress, and risks. GAO‘s work included analyses of a wide range of program documents, cost data and interviews with defense and contractor officials. What GAO Found: JSF development will cost more and take longer than reported to the Congress last year, and DOD wants to accelerate procurement. Two recent estimates project additional costs ranging from $2.4 billion to $7.4 billion and 1 to 3 more years to complete development. Despite cost and schedule troubles, DOD wants to accelerate JSF procurement by 169 aircraft from fiscal years 2010 through 2015; this could require up to $33.4 billion in additional procurement funding for those 6 years. DOD plans to procure hundreds of aircraft on cost-reimbursement contracts, magnifying the financial risk to the government. Ongoing manufacturing inefficiencies and parts problems have significantly delayed the delivery of test assets. The prime contractor has extended manufacturing schedules three times and delivered 2 of 13 test aircraft. The program is still recovering from earlier problems that resulted in design changes, late parts deliveries, and inefficient manufacturing. The contractor is taking positive steps to improve operations, the supplier base, and schedule management. Schedule risk analyses could further enhance management insight into problem areas and inform corrective actions. Officials expect to deliver all test aircraft and fix many problems by 2010. By then, DOD plans to have purchased 62 operational aircraft and will be ramping up procurement. Procuring large numbers of production jets while still working to deliver test jets and mature manufacturing processes does not seem prudent, and looming plans to accelerate procurement will be difficult to achieve cost effectively. DOD‘s revised test plan adds a year to the schedule, better aligns resources and availability dates, and lessens the overlap between development and operational testing, but it still allows little time for error discovery and rework. DOD‘s decision late in 2007 to reduce test aircraft and flight tests adds to risks while any additional delays in delivering test aircraft will further compress the schedule. The revised plan relies on state-of-the-art simulation labs, a flying test bed, and desk studies to verify nearly 83 percent of JSF capabilities. Only 17 percent is to be verified through flight testing. Despite advances, the ability to so extensively substitute for flight testing has not yet been demonstrated. Significant overlap of development, test, and procurement results in DOD making substantial investments before flight testing proves that the JSF will perform as expected. Under the accelerated procurement plan, DOD may procure 360 aircraft costing an estimated $57 billion before completing development flight testing. Table: Procurement Investments and Progress of Flight Testing: Cumulative procurement (billions of dollars); 2007: $0.9; 2008: $3.6; 2009: $7.4; 2010: $15.4; 2011: $28.2; 2012: $42.5; 2013: $57.0; 2014: $72.3; 2015: $89.0. Cumulative aircraft procured; 2008: 14; 2009: 30; 2010: 62; 2011: 132; 2012: 241; 2013: 360; 2014: 506; 2015: 684. Percent flight tests completed; 2007: