Joint Strike Fighter
Accelerating Procurement before Completing Development Increases the Government's Financial Risk
Gao ID: GAO-09-303 March 12, 2009
The Joint Strike Fighter (JSF) is the Department of Defense's (DOD) most complex and ambitious aircraft acquisition, seeking to simultaneously produce and field three different versions of the aircraft for the Air Force, Navy, Marine Corps, and eight international partners. The total investment required now exceeds $1 trillion--more than $300 billion to acquire 2,456 aircraft and $760 billion in life cycle operating and support costs, according to program estimates. The Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 requires GAO to review the JSF program annually for 5 years. This is the fifth and final report under the mandate in which GAO (1) determines the program's progress in meeting cost, schedule, and performance goals; (2) assesses manufacturing results and schedule risks; and (3) evaluates development test plans, progress, and risks. GAO's work included analyses of a wide range of program documents, cost data and interviews with defense and contractor officials.
JSF development will cost more and take longer than reported to the Congress last year, and DOD wants to accelerate procurement. Two recent estimates project additional costs ranging from $2.4 billion to $7.4 billion and 1 to 3 more years to complete development. Despite cost and schedule troubles, DOD wants to accelerate JSF procurement by 169 aircraft from fiscal years 2010 through 2015; this could require up to $33.4 billion in additional procurement funding for those 6 years. DOD plans to procure hundreds of aircraft on cost-reimbursement contracts, magnifying the financial risk to the government. Ongoing manufacturing inefficiencies and parts problems have significantly delayed the delivery of test assets. The prime contractor has extended manufacturing schedules three times and delivered 2 of 13 test aircraft. The program is still recovering from earlier problems that resulted in design changes, late parts deliveries, and inefficient manufacturing. The contractor is taking positive steps to improve operations, the supplier base, and schedule management. Schedule risk analyses could further enhance management insight into problem areas and inform corrective actions. Officials expect to deliver all test aircraft and fix many problems by 2010. By then, DOD plans to have purchased 62 operational aircraft and will be ramping up procurement. Procuring large numbers of production jets while still working to deliver test jets and mature manufacturing processes does not seem prudent, and looming plans to accelerate procurement will be difficult to achieve cost effectively. DOD's revised test plan adds a year to the schedule, better aligns resources and availability dates, and lessens the overlap between development and operational testing, but it still allows little time for error discovery and rework. DOD's decision late in 2007 to reduce test aircraft and flight tests adds to risks while any additional delays in delivering test aircraft will further compress the schedule. The revised plan relies on state-of-the-art simulation labs, a flying test bed, and desk studies to verify nearly 83 percent of JSF capabilities. Only 17 percent is to be verified through flight testing. Despite advances, the ability to so extensively substitute for flight testing has not yet been demonstrated. Significant overlap of development, test, and procurement results in DOD making substantial investments before flight testing proves that the JSF will perform as expected. Under the accelerated procurement plan, DOD may procure 360 aircraft costing an estimated $57 billion before completing development flight testing.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-09-303, Joint Strike Fighter: Accelerating Procurement before Completing Development Increases the Government's Financial Risk
This is the accessible text file for GAO report number GAO-09-303
entitled 'Joint Strike Fighter: Accelerating Procurement before
Completing Development Increases the Government's Financial Risk' which
was released on March 12, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Committees:
United States Government Accountability Office:
GAO:
March 2009:
Joint Strike FighteR:
Accelerating Procurement before Completing Development Increases the
Government's Financial Risk:
Joint Strike Fighter:
GAO-09-303:
GAO Highlights:
Highlights of GAO-09-303, a report to congressional committees.
Why GAO Did This Study:
The Joint Strike Fighter (JSF) is the Department of Defense‘s (DOD)
most complex and ambitious aircraft acquisition, seeking to
simultaneously produce and field three different versions of the
aircraft for the Air Force, Navy, Marine Corps, and eight international
partners. The total investment required now exceeds $1 trillion”more
than $300 billion to acquire 2,456 aircraft and $760 billion in life
cycle operating and support costs, according to program estimates. The
Ronald W. Reagan National Defense Authorization Act for Fiscal Year
2005 requires GAO to review the JSF program annually for 5 years. This
is the fifth and final report under the mandate in which GAO (1)
determines the program‘s progress in meeting cost, schedule, and
performance goals; (2) assesses manufacturing results and schedule
risks; and (3) evaluates development test plans, progress, and risks.
GAO‘s work included analyses of a wide range of program documents, cost
data and interviews with defense and contractor officials.
What GAO Found:
JSF development will cost more and take longer than reported to the
Congress last year, and DOD wants to accelerate procurement. Two recent
estimates project additional costs ranging from $2.4 billion to $7.4
billion and 1 to 3 more years to complete development. Despite cost and
schedule troubles, DOD wants to accelerate JSF procurement by 169
aircraft from fiscal years 2010 through 2015; this could require up to
$33.4 billion in additional procurement funding for those 6 years. DOD
plans to procure hundreds of aircraft on cost-reimbursement contracts,
magnifying the financial risk to the government.
Ongoing manufacturing inefficiencies and parts problems have
significantly delayed the delivery of test assets. The prime contractor
has extended manufacturing schedules three times and delivered 2 of 13
test aircraft. The program is still recovering from earlier problems
that resulted in design changes, late parts deliveries, and inefficient
manufacturing. The contractor is taking positive steps to improve
operations, the supplier base, and schedule management. Schedule risk
analyses could further enhance management insight into problem areas
and inform corrective actions. Officials expect to deliver all test
aircraft and fix many problems by 2010. By then, DOD plans to have
purchased 62 operational aircraft and will be ramping up procurement.
Procuring large numbers of production jets while still working to
deliver test jets and mature manufacturing processes does not seem
prudent, and looming plans to accelerate procurement will be difficult
to achieve cost effectively.
DOD‘s revised test plan adds a year to the schedule, better aligns
resources and availability dates, and lessens the overlap between
development and operational testing, but it still allows little time
for error discovery and rework. DOD‘s decision late in 2007 to reduce
test aircraft and flight tests adds to risks while any additional
delays in delivering test aircraft will further compress the schedule.
The revised plan relies on state-of-the-art simulation labs, a flying
test bed, and desk studies to verify nearly 83 percent of JSF
capabilities. Only 17 percent is to be verified through flight testing.
Despite advances, the ability to so extensively substitute for flight
testing has not yet been demonstrated. Significant overlap of
development, test, and procurement results in DOD making substantial
investments before flight testing proves that the JSF will perform as
expected. Under the accelerated procurement plan, DOD may procure 360
aircraft costing an estimated $57 billion before completing development
flight testing.
Table: Procurement Investments and Progress of Flight Testing:
Cumulative procurement (billions of dollars); 2007: $0.9; 2008: $3.6;
2009: $7.4;
2010: $15.4;
2011: $28.2;
2012: $42.5;
2013: $57.0;
2014: $72.3;
2015: $89.0.
Cumulative aircraft procured;
2008: 14;
2009: 30;
2010: 62;
2011: 132;
2012: 241;
2013: 360;
2014: 506;
2015: 684.
Percent flight tests completed;
2007:
The Justia Government Accountability Office site republishes public reports retrieved from the U.S. GAO These reports should not be considered official, and do not necessarily reflect the views of Justia.