Joint Strike Fighter
Strong Risk Management Essential as Program Enters Most Challenging Phase
Gao ID: GAO-09-711T May 20, 2009
The F-35 Joint Strike Fighter (JSF) program is the Department of Defense's (DOD's) most costly acquisition, seeking to simultaneously develop, produce, and field three aircraft variants for the Air Force, Navy, Marine Corps, and eight international partners. The total expected U.S. investment is now more than $300 billion to develop and procure 2,456 aircraft over the next 25 years. GAO's most recent report in March of this year discussed increased development costs and schedule estimates, plans to accelerate procurement, manufacturing performance and delays, and development test strategy. A recurring theme in GAO's work has been concern about what GAO believes is undue concurrency of development, test, and production activities and the heightened risks it poses to achieving good cost, schedule, and performance outcomes. This testimony discusses: (1) current JSF cost and schedule estimates; (2) engine development; (3) manufacturing performance; (4) contracting issues for procurement of aircraft; (5) and test plans. This statement draws from GAO's March 2009 report, updated to the extent possible with new budget data and a recently revised procurement profile directed by the Secretary of Defense.
JSF development will cost more and take longer to complete than reported to the Congress in April 2008, primarily because of contract cost overruns and extended time needed to complete flight testing. DOD is also significantly increasing annual procurement rates and plans to buy some aircraft sooner than reported last year. Total development costs are projected to increase between $2.4 billion and $7.4 billion and the schedule for completing system development extended from 1 to 3 years. The department has not asked for funding for the alternate engine program in the budgets since 2007 arguing that an alternate engine is not needed as a hedge against the failure of the main engine program and that the savings from competition would be small. Nonetheless, the Congress has added funding each year since then to sustain its development. Our prior analysis indicates that competitive pressures could yield enough savings to offset the costs of competition over the JSF program's life. To date, the two contractors have spent over $8 billion on engine development--over $6 billion with the main engine contractor and over $2 billion with the second source contractor. Manufacturing of development test aircraft is taking more time, money, and effort than planned, but officials believe that they can still deliver the 9 remaining test aircraft by early 2010. The contractor has not yet demonstrated mature manufacturing processes, or an ability to produce at currently planned rates. It has taken steps to improve manufacturing; however, given the manufacturing challenges, DOD's plan to increase procurement in the near term adds considerable risk and will be difficult to achieve. DOD is procuring a substantial number of JSF aircraft using cost reimbursement contracts. Cost reimbursement contracts place most of the risk on the buyer--DOD in this case--who is liable to pay more than budgeted should labor, material, or other incurred costs be more than expected when the contract was signed. JSF flight testing is still in its infancy and continues to experience flight testing delays. Nonetheless, DOD is making substantial investments before flight testing proves that the JSF will perform as expected. DOD may procure 273 aircraft costing an estimated $42 billion before completing flight testing.
GAO-09-711T, Joint Strike Fighter: Strong Risk Management Essential as Program Enters Most Challenging Phase
This is the accessible text file for GAO report number GAO-09-711T
entitled 'Joint Strike Fighter: Strong Risk Management Essential as
Program Enters Most Challenging Phase' which was released on May 20,
2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Testimony:
Before the Subcommittee on Air and Land Forces, Committee on Armed
Services, House of Representatives:
United States Government Accountability Office:
GAO:
For Release on Delivery:
Expected at 2::30 p.m. EDT:
Wednesday, May 20, 2009:
Joint Strike Fighter:
Strong Risk Management Essential as Program Enters Most Challenging
Phase:
Statement of Michael Sullivan, Director: Acquisition and Sourcing
Management:
GAO-09-711T:
GAO Highlights:
Highlights of GAO-09-711T, a testimony before the Subcommittee on Air
and Land Forces, Committee on Armed Services, House of Representatives.
Why GAO Did This Study:
The F-35 Joint Strike Fighter (JSF) program is the Department of
Defense‘s (DOD‘s) most costly acquisition, seeking to simultaneously
develop, produce, and field three aircraft variants for the Air Force,
Navy, Marine Corps, and eight international partners. The total
expected U.S. investment is now more than $300 billion to develop and
procure 2,456 aircraft over the next 25 years.
GAO‘s most recent report in March of this year discussed increased
development costs and schedule estimates, plans to accelerate
procurement, manufacturing performance and delays, and development test
strategy. A recurring theme in GAO‘s work has been concern about what
GAO believes is undue concurrency of development, test, and production
activities and the heightened risks it poses to achieving good cost,
schedule, and performance outcomes.
This testimony discusses:
* current JSF cost and schedule estimates;
* engine development;
* manufacturing performance;
* contracting issues for procurement of aircraft; and;
* test plans.
This statement draws from GAO‘s March 2009 report, updated to the
extent possible with new budget data and a recently revised procurement
profile directed by the Secretary of Defense.
What GAO Found:
JSF development will cost more and take longer to complete than
reported to the Congress in April 2008, primarily because of contract
cost overruns and extended time needed to complete flight testing. DOD
is also significantly increasing annual procurement rates and plans to
buy some aircraft sooner than reported last year. Total development
costs are projected to increase between $2.4 billion and $7.4 billion
and the schedule for completing system development extended from 1 to 3
years.
The department has not asked for funding for the alternate engine
program in the budgets since 2007 arguing that an alternate engine is
not needed as a hedge against the failure of the main engine program
and that the savings from competition would be small. Nonetheless, the
Congress has added funding each year since then to sustain its
development. Our prior analysis indicates that competitive pressures
could yield enough savings to offset the costs of competition over the
JSF program‘s life. To date, the two contractors have spent over $8
billion on engine development”over $6 billion with the main engine
contractor and over $2 billion with the second source contractor.
Manufacturing of development test aircraft is taking more time, money,
and effort than planned, but officials believe that they can still
deliver the 9 remaining test aircraft by early 2010. The contractor has
not yet demonstrated mature manufacturing processes, or an ability to
produce at currently planned rates. It has taken steps to improve
manufacturing; however, given the manufacturing challenges, DOD‘s plan
to increase procurement in the near term adds considerable risk and
will be difficult to achieve.
DOD is procuring a substantial number of JSF aircraft using cost
reimbursement contracts. Cost reimbursement contracts place most of the
risk on the buyer”DOD in this case”who is liable to pay more than
budgeted should labor, material, or other incurred costs be more than
expected when the contract was signed.
JSF flight testing is still in its infancy and continues to experience
flight testing delays. Nonetheless, DOD is making substantial
investments before flight testing proves that the JSF will perform as
expected. DOD may procure 273 aircraft costing an estimated $42 billion
before completing flight testing.
Table: Procurement Investments and Progress of Flight Testing:
Cumulative procurement (billions of dollars): 2007: $0.9;
2008: $3.6;
2009: $6.9;
2010: $13.7;
2011: $20.6;
2012: $31.1;
2013: $41.9;
2014: $54.3.
Cumulative aircraft procured:
2007: 2;
2008: 14;
2009: 28;
2010: 58;
2011: 101;
2012: 183;
2013: 273;
2014: 383.
Percentage of flight test program completed: 2007: