Polar-Orbiting Environmental Satellites
With Costs Increasing and Data Continuity at Risk, Improvements Needed in Tri-agency Decision Making
Gao ID: GAO-09-564 June 17, 2009
The National Polar-orbiting Operational Environmental Satellite System (NPOESS) is a tri-agency acquisition--managed by the Department of Commerce's National Oceanic and Atmospheric Administration (NOAA), the Department of Defense (DOD), and the National Aeronautics and Space Administration (NASA)--that has experienced escalating costs, schedule delays, and technical difficulties. As the often-delayed launch of its demonstration satellite draws closer, these problems continue. GAO was asked to (1) identify the status and risks of key program components, (2) assess the NPOESS Executive Committee's ability to fulfill its responsibilities, and (3) evaluate efforts to identify an alternative system integrator for later NPOESS satellites. To do so, GAO analyzed program and contractor data, attended program reviews, and interviewed agency officials.
While selected components of the NPOESS program have made progress over the past year, the program is once again over budget and behind schedule. In terms of progress, three of the five instruments slated for a demonstration satellite (called the NPOESS Preparatory Project--NPP) have been delivered and integrated on the spacecraft; the ground-based satellite data processing system has been installed and tested at both of the locations that are to receive NPP data; and the satellites' command, control, and communications system has passed acceptance testing. However, the program's approved cost and schedule baseline are not achievable, and problems with two critical sensors continue to drive the program's cost and schedule. Costs could grow by $1 billion over the current $13.95 billion estimate, and the schedules for NPP and the first two NPOESS satellites are expected to be delayed by 7, 14, and 5 months, respectively. These delays increase the risk of a gap in satellite continuity. An independent review team established to assess key program risks recently reported that the constellation of satellites is extremely fragile, and that there could be a 3 to 5 year gap in satellite coverage if NPP, NPOESS, or other DOD satellites fail on launch. The NPOESS Executive Committee responsible for overseeing the program has made improvements over the last several years, but still has not effectively fulfilled its responsibilities. Responding to past concerns expressed by GAO and the Department of Commerce's Inspector General, the Committee now meets on a regular basis, and has sought and reacted to advice from external advisors to mitigate specific risks. However, the Committee lacks the membership and leadership needed to effectively and efficiently oversee and direct the program. Specifically, the DOD Committee member with acquisition authority does not attend Executive Committee meetings--and sometimes contradicts the Committee's decisions, the Committee does not track its action items to closure, and many of the Committee's decisions do not achieve desired outcomes. Program officials and external independent reviewers explained that it is extremely difficult for the Committee to navigate three agencies' competing requirements and priorities. Until these shortfalls are addressed, the Committee will remain ineffective. The NPOESS program has conducted two successive studies of alternatives to using the existing system integrator for the last two NPOESS satellites, but neither identified a viable alternative to the current contractor. Both studies assessed a variety of alternatives, including re-competing the entire prime contract, obtaining an independent system integrator while having the existing prime contractor continue to develop space and ground components, and having the government take over responsibility for the system's integration. The first study identified strengths and weaknesses and the second study identified high-level costs and benefits. Neither study identified an alternative that is viable. Program officials plan to conduct a final study prior to the June 2010 decision on whether to proceed with the existing prime contractor.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Team:
Phone:
GAO-09-564, Polar-Orbiting Environmental Satellites: With Costs Increasing and Data Continuity at Risk, Improvements Needed in Tri-agency Decision Making
This is the accessible text file for GAO report number GAO-09-564
entitled 'Polar-Orbiting Environmental Satellites: With Costs
Increasing and Data Continuity at Risk, Improvements Needed in Tri-
agency Decision Making' which was released on June 17, 2009.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as part
of a longer term project to improve GAO products' accessibility. Every
attempt has been made to maintain the structural and data integrity of
the original printed product. Accessibility features, such as text
descriptions of tables, consecutively numbered footnotes placed at the
end of the file, and the text of agency comment letters, are provided
but may not exactly duplicate the presentation or format of the printed
version. The portable document format (PDF) file is an exact electronic
replica of the printed version. We welcome your feedback. Please E-mail
your comments regarding the contents or accessibility features of this
document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Requesters:
United States Government Accountability Office:
GAO:
June 2009:
Polar-Orbiting Environmental Satellites:
With Costs Increasing and Data Continuity at Risk, Improvements Needed
in Tri-agency Decision Making:
GAO-09-564:
GAO Highlights:
Highlights of GAO-09-564, a report to congressional requesters.
Why GAO Did This Study:
The National Polar-orbiting Operational Environmental Satellite System
(NPOESS) is a tri-agency acquisition-”managed by the Department of
Commerce‘s National Oceanic and Atmospheric Administration (NOAA), the
Department of Defense (DOD), and the National Aeronautics and Space
Administration (NASA)”-that has experienced escalating costs, schedule
delays, and technical difficulties. As the often-delayed launch of its
demonstration satellite draws closer, these problems continue.
GAO was asked to (1) identify the status and risks of key program
components, (2) assess the NPOESS Executive Committee‘s ability to
fulfill its responsibilities, and (3) evaluate efforts to identify an
alternative system integrator for later NPOESS satellites. To do so,
GAO analyzed program and contractor data, attended program reviews, and
interviewed agency officials.
What GAO Found:
While selected components of the NPOESS program have made progress over
the past year, the program is once again over budget and behind
schedule. In terms of progress, three of the five instruments slated
for a demonstration satellite (called the NPOESS Preparatory Project”
NPP) have been delivered and integrated on the spacecraft; the ground-
based satellite data processing system has been installed and tested at
both of the locations that are to receive NPP data; and the satellites‘
command, control, and communications system has passed acceptance
testing. However, the program‘s approved cost and schedule baseline are
not achievable, and problems with two critical sensors continue to
drive the program‘s cost and schedule. Costs could grow by $1 billion
over the current $13.95 billion estimate, and the schedules for NPP and
the first two NPOESS satellites are expected to be delayed by 7, 14,
and 5 months, respectively. These delays increase the risk of a gap in
satellite continuity. An independent review team established to assess
key program risks recently reported that the constellation of
satellites is extremely fragile, and that there could be a 3 to 5 year
gap in satellite coverage if NPP, NPOESS, or other DOD satellites fail
on launch.
The NPOESS Executive Committee responsible for overseeing the program
has made improvements over the last several years, but still has not
effectively fulfilled its responsibilities. Responding to past concerns
expressed by GAO and the Department of Commerce‘s Inspector General,
the Committee now meets on a regular basis, and has sought and reacted
to advice from external advisors to mitigate specific risks. However,
the Committee lacks the membership and leadership needed to effectively
and efficiently oversee and direct the program. Specifically, the DOD
Committee member with acquisition authority does not attend Executive
Committee meetings”and sometimes contradicts the Committee‘s decisions,
the Committee does not track its action items to closure, and many of
the Committee‘s decisions do not achieve desired outcomes. Program
officials and external independent reviewers explained that it is
extremely difficult for the Committee to navigate three agencies‘
competing requirements and priorities. Until these shortfalls are
addressed, the Committee will remain ineffective.
The NPOESS program has conducted two successive studies of alternatives
to using the existing system integrator for the last two NPOESS
satellites, but neither identified a viable alternative to the current
contractor. Both studies assessed a variety of alternatives, including
re-competing the entire prime contract, obtaining an independent system
integrator while having the existing prime contractor continue to
develop space and ground components, and having the government take
over responsibility for the system‘s integration. The first study
identified strengths and weaknesses and the second study identified
high-level costs and benefits. Neither study identified an alternative
that is viable. Program officials plan to conduct a final study prior
to the June 2010 decision on whether to proceed with the existing prime
contractor.
What GAO Recommends:
GAO is making recommendations to the Secretaries of Commerce and
Defense and to the Administrator of NASA to improve the effectiveness
and efficiency of the Executive Committee. In commenting on a draft of
this report, NASA and Commerce officials concurred with the
recommendations; DOD concurred with one and partially concurred with
the other recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-09-564] or key
components. For more information, contact David A. Powner at (202) 512-
9286 or pownerd@gao.gov.
[End of section]
Contents:
Letter:
Background:
Progress Made, but Continued Instrument Problems Are Driving Costs
Upward, Forcing Launch Delays, and Endangering Satellite Continuity:
Executive Committee Has Not Effectively Fulfilled Its Responsibilities:
Program Has Assessed Alternatives, but Has Not Yet Identified a Viable
Alternative for Acquiring the Last Two NPOESS Satellites:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: Summary of the Fall 2008 Independent Review Team's
Findings and Recommendations:
Appendix III: Comments from the Department of Commerce:
Appendix IV: Comments from the Department of Defense:
Appendix V: Comments from the National Aeronautics and Space
Administration:
Appendix VI: GAO Contact and Staff Acknowledgments:
Tables:
Table 1: Expected NPOESS Instruments as of August 31, 2004:
Table 2: Major Changes to the NPOESS Program by the Nunn-McCurdy
Certification Decision:
Table 3: Changes to NPOESS Instruments, as of June 2006:
Table 4: Configuration of Instruments Planned for NPP and NPOESS
Satellites, as of May 2008:
Table 5: Status and Risk Level of Key Space and Ground Components, as
of April 2009:
Table 6: Changes in Key Program Milestones over Time:
Figures:
Figure 1: Configuration of Operational Polar Satellites:
Figure 2: Stages of Satellite Data Processing:
Figure 3: Examples of Weather Products:
Figure 4: NPOESS Program Roles and Responsibilities:
Figure 5: Nunn-McCurdy Certified Satellite Constellation:
Figure 6: Potential Gaps in the Continuity of Current and Planned Polar
Satellites:
Abbreviations:
CrIS: Cross-track Infrared Sounder:
DMSP: Defense Meteorological Satellite Program:
DOD: Department of Defense:
EDR: Environmental Data Record:
MetOp: Meteorological Operational (satellite):
NASA: National Aeronautics and Space Administration:
NOAA: National Oceanic and Atmospheric Administration:
NPOESS: National Polar-orbiting Operational Environmental Satellite
System:
NPP: NPOESS Preparatory Project:
POES: Polar-orbiting Operational Environmental Satellites:
VIIRS: Visible/infrared imager radiometer suite:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
June 17, 2009:
Congressional Requesters:
The planned National Polar-orbiting Operational Environmental Satellite
System (NPOESS) program is expected to be a state-of-the-art,
environment-monitoring satellite system that will replace two existing
polar-orbiting environmental satellite systems. Polar-orbiting
satellites provide data and imagery that are used by weather
forecasters, climatologists, and the military to map and monitor
changes in weather, climate, the oceans, and the environment. The
NPOESS program is considered critical to the United States' ability to
maintain the continuity of data required for weather forecasting
(including severe weather events such as hurricanes) and global climate
monitoring through the year 2026.
Three agencies share responsibility for the NPOESS acquisition: the
Department of Commerce's National Oceanic and Atmospheric
Administration (NOAA), the Department of Defense (DOD)/United States
Air Force, and the National Aeronautics and Space Administration
(NASA). These agencies established a tri-agency office to manage the
NPOESS program. The program is overseen by an Executive Committee made
up of senior executives from each of the agencies. Since its inception,
NPOESS costs have doubled, launch schedules have been repeatedly
delayed, and significant functionality was cut from the program. Even
after a major restructuring, the program is still encountering
technical issues, schedule delays, and the likelihood of further cost
increases. More importantly, delays in launching the satellites have
put the program's mission at risk.
This report responds to your request that we (1) identify the status
and risks of key program components, (2) assess the NPOESS Executive
Committee's ability to fulfill its responsibilities, and (3) evaluate
efforts to identify an alternative system integrator for later NPOESS
satellites. To identify the status and risks to the program, we
reviewed program documentation including status briefings, monthly
program management documents, and contractor-provided earned value
data. We compared the contractor's earned value management data to cost
and schedule estimates and evaluated reasons for variances in the
contractor's performance. To assess the NPOESS Executive Committee's
ability to fulfill its responsibilities, we reviewed Executive
Committee documentation, including meeting minutes. We compared the
Committee's actions to its documented responsibilities, as well as to
best practices in investment management and oversight.[Footnote 1] To
evaluate the efforts to develop an alternative system integrator for
NPOESS, we compared the requirement for a study of alternatives to the
results of two successive studies. We also interviewed relevant agency
officials from NOAA, NASA, and DOD. In addition, this report builds on
work we have done on environmental satellites over the last several
years.[Footnote 2]
We conducted our work at the NPOESS Integrated Program Office
headquarters and at NOAA, NASA, and DOD facilities in the Washington,
D.C., metropolitan area. In addition, we conducted work at contractors'
facilities in the Los Angeles, California, area because of the
importance of these sites to development of the sensors for the program
and to the satellites' integration. We conducted this performance audit
from October 2008 to June 2009 in accordance with generally accepted
government auditing standards. Those standards require that we plan and
perform the audit to obtain sufficient, appropriate evidence to provide
a reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a reasonable
basis for our findings and conclusions based on our audit objectives.
Additional details on our objectives, scope, and methodology are
provided in appendix I.
Background:
Since the 1960s, the United States has operated two separate
operational polar-orbiting meteorological satellite systems: the Polar-
orbiting Operational Environmental Satellite (POES) series, which is
managed by NOAA, and the Defense Meteorological Satellite Program
(DMSP), which is managed by the Air Force. These satellites obtain
environmental data that are processed to provide graphical weather
images and specialized weather products. These satellite data are also
the predominant input to numerical weather prediction models, which are
a primary tool for forecasting weather 3 or more days in advance--
including forecasting the path and intensity of hurricanes. The weather
products and models are used to predict the potential impact of severe
weather so that communities and emergency managers can help prevent and
mitigate its effects. Polar satellites also provide data used to
monitor environmental phenomena, such as ozone depletion and drought
conditions, as well as data sets that are used by researchers for a
variety of studies such as climate monitoring.
Unlike geostationary satellites, which maintain a fixed position
relative to the earth, polar-orbiting satellites constantly circle the
earth in an almost north-south orbit, providing global coverage of
conditions that affect the weather and climate. Each satellite makes
about 14 orbits a day. As the earth rotates beneath it, each satellite
views the entire earth's surface twice a day. Currently, there is one
operational POES satellite and two operational DMSP satellites that are
positioned so that they can observe the earth in early morning,
midmorning, and early afternoon polar orbits. In addition, the
government is also relying on a European satellite, called the
Meteorological Operational (MetOp) satellite, in the midmorning orbit.
[Footnote 3] Together, they ensure that, for any region of the earth,
the data provided to users are generally no more than 6 hours old.
Figure 1 illustrates the current operational polar satellite
configuration. Besides the four operational satellites, six older
satellites are in orbit that still collect some data and are available
to provide limited backup to the operational satellites should they
degrade or fail. The last POES satellite was launched in February 2009
and declared operational in early June 2009. The Air Force plans to
continue to launch its three remaining DMSP satellites every few years,
with the final launch planned for 2014.
Figure 1: Configuration of Operational Polar Satellites:
Polar Satellite Data and Products:
Polar satellites gather a broad range of data that are transformed into
a variety of products. Satellite sensors observe different bands of
radiation wavelengths, called channels, which are used for remotely
determining information about the earth's atmosphere, land surface,
oceans, and the space environment. When first received, satellite data
are considered raw data. To make them usable, the processing centers
format the data so that they are time-sequenced and include earth
location and calibration information. After formatting, these data are
called raw data records. The centers further process these raw data
records into channel-specific data sets, called sensor data records and
temperature data records. These data records are then used to derive
weather and climate products called environmental data records (EDR).
EDRs include a wide range of atmospheric products detailing cloud
coverage, temperature, humidity, and ozone distribution; land surface
products showing snow cover, vegetation, and land use; ocean products
depicting sea surface temperatures, sea ice, and wave height; and
characterizations of the space environment. Combinations of these data
records (raw, sensor, temperature, and environmental data records) are
also used to derive more sophisticated products, including outputs from
numerical weather models and assessments of climate trends. Figure 2 is
a simplified depiction of the various stages of satellite data
processing, and figure 3 depicts examples of two different weather
products.
Figure 2: Stages of Satellite Data Processing:
[Refer to PDF for image: illustration]
1) Raw data;
2) Raw data records;
3) Sensor data records and temperature data records;
4) Environmental data records;
5) Derived products and output from numerical weather prediction
models.
Source: GAO analysis of NOAA information.
[End of figure]
Figure 3: Examples of Weather Products:
[Refer to PDF for image: illustration]
Note: The figure on the left is a POES Image of Hurricane Katrina in
2005, and the figure on the right is an analysis of ozone concentration
produced from POES satellite data.
Source: NOAA‘s National Environmental Satellite Data and Information
Service.
[End of figure]
NPOESS Overview:
With the expectation that combining the POES and DMSP programs would
reduce duplication and result in sizable cost savings, a May 1994
Presidential Decision Directive required NOAA and DOD to converge the
two satellite programs into a single satellite program capable of
satisfying both civilian and military requirements.[Footnote 4] The
converged program, NPOESS, is considered critical to the United States'
ability to maintain the continuity of data required for weather
forecasting and global climate monitoring. To manage this program, DOD,
NOAA, and NASA formed the tri-agency Integrated Program Office.
Within the program office, each agency has the lead on certain
activities: NOAA has overall program management responsibility for the
converged system and for satellite operations; the Air Force has the
lead on the acquisition; and NASA has primary responsibility for
facilitating the development and incorporation of new technologies into
the converged system. NOAA and DOD share the cost of funding NPOESS,
while NASA funds specific technology projects and studies. In addition,
an Executive Committee--made up of the administrators of NOAA and NASA
and the Under Secretary of Defense for Acquisition, Technology, and
Logistics--is responsible for providing policy guidance, ensuring
agency support and funding, and exercising oversight authority.
[Footnote 5] Figure 4 depicts the organizations that make up the NPOESS
program and lists their responsibilities.
Figure 4: NPOESS Program Roles and Responsibilities:
[Refer to PDF for image: illustration]
NPOESS Integrated Program Office:
Agency: National Oceanic and Atmospheric Administration;
Responsibility: Overall program management and satellite operations;
Funding: Shared funding with U.S. Air Force for NPOESS.
Agency: United States Air Force;
Responsibility: Acquisition;
Funding: Shared funding with NOAA for NPOESS.
Agency: National Aeronautics and Space Administration;
Responsibility: Technologies;
Funding: Specific technology projects and studies.
Source: GAO analysis of NPOESS program office data.
[End of figure]
Acquisition Strategy:
NPOESS is a major system acquisition that was originally estimated to
cost about $6.5 billion over the 24-year life of the program from its
inception in 1995 through 2018. The program is to provide satellite
development, satellite launch and operation, and ground-based satellite
data processing. These deliverables are grouped into four main
categories: (1) the space segment, which includes the satellites and
sensors; (2) the integrated data processing segment, which is the
system for transforming raw data into EDRs and is to be located at the
four processing centers; (3) the command, control, and communications
segment, which includes the equipment and services needed to support
satellite operations; and (4) the launch segment, which includes the
launch vehicle services.
When the NPOESS engineering, manufacturing, and development contract
was awarded in August 2002, the cost estimate was adjusted to $7
billion. Acquisition plans called for the procurement and launch of six
satellites over the life of the program, as well as the integration of
13 instruments--consisting of 10 environmental sensors and 3
subsystems. Together, the sensors were to receive and transmit data on
atmospheric, cloud cover, environmental, climatic, oceanographic, and
solar-geophysical observations. The subsystems were to support
nonenvironmental search and rescue efforts, sensor survivability, and
environmental data collection activities. The program office considered
four of the sensors to be critical because they provide data for key
weather products; these sensors are in bold in table 1, which describes
each of the expected NPOESS instruments.
Table 1: Expected NPOESS Instruments as of August 31, 2004 (critical
sensors are indicated in brackets):
Instrument: Advanced technology microwave sounder [critical sensor];
Description: Measures microwave energy released and scattered by the
atmosphere and is to be used with infrared sounding data from the cross-
track infrared sounder to produce daily global atmospheric temperature,
humidity, and pressure profiles.
Instrument: Aerosol polarimetry sensor;
Description: Retrieves specific measurements of clouds and aerosols
(liquid droplets or solid particles suspended in the atmosphere, such
as sea spray, smog, and smoke).
Instrument: Conical-scanned microwave imager/sounder [critical sensor];
Description: Collects microwave images and data needed to measure rain
rate, ocean surface wind speed and direction, amount of water in the
clouds, and soil moisture, as well as temperature and humidity at
different atmospheric levels.
Instrument: Cross-track infrared sounder (CrIS) [critical sensor];
Description: Collects measurements of the earth‘s radiation to
determine the vertical distribution of temperature, moisture, and
pressure in the atmosphere.
Instrument: Data collection system;
Description: Collects environmental data from platforms around the
world and delivers them to users worldwide.
Instrument: Earth radiation budget sensor;
Description: Measures solar short-wave radiation and long-wave
radiation released by the earth back into space on a worldwide scale to
enhance long-term climate studies.
Instrument: Ozone mapper/profiler suite;
Description: Collects data needed to measure the amount and
distribution of ozone in the earth‘s atmosphere. Consists of two
components (limb and nadir) which can be provided separately.
Instrument: Radar altimeter;
Description: Measures variances in sea surface height/topography and
ocean surface roughness, which are used to determine sea surface
height, significant wave height, and ocean surface wind speed and to
provide critical inputs to ocean forecasting and climate prediction
models.
Instrument: Search and rescue satellite aided tracking system;
Description: Detects and locates aviators, mariners, and land-based
users in distress.
Instrument: Space environmental sensor suite;
Description: Collects data to identify, reduce, and predict the effects
of space weather on technological systems, including satellites and
radio links.
Instrument: Survivability sensor;
Description: Monitors for attacks on the satellite and notifies other
instruments in case of an attack.
Instrument: Total solar irradiance sensor;
Description: Monitors and captures total and spectral solar irradiance
data.
Instrument: Visible/infrared imager radiometer suite (VIIRS) [critical
sensor];
Description: Collects images and radiometric data used to provide
information on the earth‘s clouds, atmosphere, ocean, and land surfaces.
Source: GAO analysis of NPOESS program office data.
Source: GAO analysis of NPOESS program office data.
[End of table]
In addition, a demonstration satellite, called the NPOESS Preparatory
Project (NPP), was planned to be launched several years before the
first NPOESS satellite in order to reduce the risk associated with
launching new sensor technologies and to ensure continuity of climate
data with NASA's Earth Observing System satellites. NPP was to host
three of the four critical NPOESS sensors, as well as one other sensor
and to provide the program office and the processing centers an early
opportunity to work with the sensors, ground control, and data
processing systems.[Footnote 6]
When the NPOESS development contract was awarded, the schedule for
launching the satellites was driven by a requirement that the NPOESS
satellites be available to back up the final POES and DMSP satellites
should anything go wrong during the planned launches of these
satellites.[Footnote 7] Early program milestones included (1) launching
NPP by May 2006, (2) having the first NPOESS satellite available to
back up the final POES satellite launch then planned for March 2008,
and (3) having the second NPOESS satellite available to back up the
final DMSP satellite launch then planned for October 2009. If the
NPOESS satellites were not needed to back up the final predecessor
satellites, their anticipated launch dates would have been April 2009
and June 2011, respectively.
Cost Increases, Schedule Delays, and Technical Problems Led to a
Decision to Restructure the NPOESS Program:
Over several years, we reported that NPOESS had experienced continued
cost increases, schedule delays, and serious technical problems.
[Footnote 8] By November 2005, we estimated that the cost of the
program had grown from $7 billion to over $10 billion. In addition, the
program was experiencing major technical problems with the VIIRS sensor
and expected to delay the launch date of the first satellite by almost
2 years. These issues ultimately required difficult decisions to be
made about the program's direction and capabilities.
The Nunn-McCurdy law requires DOD to take specific actions when a major
defense acquisition program growth exceeds certain cost thresholds.
[Footnote 9] Key provisions of the law require the Secretary of Defense
to notify Congress when a major defense acquisition is expected to
overrun its current baseline by 15 percent or more and to certify the
program to Congress when it is expected to overrun its current baseline
by 25 percent or more.[Footnote 10] In November 2005, NPOESS exceeded
the 25 percent threshold, and DOD was required to certify the program.
Certifying a program entails providing a determination that (1) the
program is essential to national security, (2) there are no
alternatives to the program that will provide equal or greater military
capability at less cost, (3) the new estimates of the program's cost
are reasonable, and (4) the management structure for the program is
adequate to manage and control costs. DOD established tri-agency teams--
made up of DOD, NOAA, and NASA experts--to work on each of the four
elements of the certification process.
In June 2006, DOD (with the agreement of both of its partner agencies)
certified a restructured NPOESS program, estimated to cost $12.5
billion through 2026--an increase of $4 billion more than the prior
life cycle cost estimate.[Footnote 11] This restructuring decision
delayed the launch of NPP and the first 2 satellites by roughly 3 to 5
years--a deviation from NOAA's requirement to have NPOESS satellites
available to back up the final POES and DMSP satellites should anything
go wrong during those launches. The restructured program also reduced
the number of satellites to be produced by relying on European
satellites for the midmorning orbit and planning to use NPOESS
satellites in the early morning and afternoon orbits. In addition, in
order to reduce program complexity, the Nunn-McCurdy certification
decision decreased the number of NPOESS sensors from 13 to 9 and
reduced the functionality of 4 sensors.
In addition, a new executive position--called the Program Executive
Officer--was established to oversee the NPOESS program office and to
report directly to the Executive Committee. The Program Executive
Officer obtains weekly and monthly reports on the program's cost,
schedule, performance, and risks from the System Program Director, and
in turn, provides monthly and quarterly updates to the Executive
Committee. Table 2 summarizes the major program changes made by the
Nunn-McCurdy certification decision, and figure 5 denotes the
configuration of the planned polar-operational satellite program in the
future.
Table 2: Major Changes to the NPOESS Program by the Nunn-McCurdy
Certification Decision:
Key area: Life cycle range;
Program before the Nunn-McCurdy decision: 1995”2020;
Program after the Nunn-McCurdy decision (as of June 2006): 1995”2026.
Key area: Estimated life cycle cost;
Program before the Nunn-McCurdy decision: $8.4 billion;
Program after the Nunn-McCurdy decision (as of June 2006): $12.5
billion.
Key area: Launch schedule;
Program before the Nunn-McCurdy decision:
NPP by October 2006;
First NPOESS (C1) by November 2009;
Second NPOESS (C2) by June 2011;
Program after the Nunn-McCurdy decision (as of June 2006):
NPP by January 2010;
C1 by January 2013;
C2 by January 2016.
Key area: Management structure;
Program before the Nunn-McCurdy decision: System Program Director
reports to a tri-agency steering committee and the tri-agency Executive
Committee. Independent program reviews noted insufficient system
engineering and cost analysis staff;
Program after the Nunn-McCurdy decision (as of June 2006): System
Program Director is responsible for day-to-day program management and
reports to the Program Executive Officer. Program Executive Officer
oversees program and reports to the tri-agency Executive Committee.
Key area: Number of satellites;
Program before the Nunn-McCurdy decision: 6 (in addition to NPP);
Program after the Nunn-McCurdy decision (as of June 2006): 4 (in
addition to NPP).
Key area: Number of orbits;
Program before the Nunn-McCurdy decision: 3 (early morning, midmorning,
and afternoon);;
Program after the Nunn-McCurdy decision (as of June 2006): 2 (early
morning and afternoon; will rely on European satellites for midmorning
orbit data).
Key area: Number and complement of instruments;
Program before the Nunn-McCurdy decision: 13 instruments (10 sensors
and 3 subsystems);
Program after the Nunn-McCurdy decision (as of June 2006): 9
instruments (7 sensors and 2 subsystems); 4 of the sensors are to
provide fewer capabilities.
Key area: Number of EDRs;
Program before the Nunn-McCurdy decision: 55;
Program after the Nunn-McCurdy decision (as of June 2006): 39 (6 are to
be degraded products).
Source: GAO analysis of NPOESS program office data.
[End of table]
Figure 5: Nunn-McCurdy Certified Satellite Constellation:
[Refer to PDF for image: illustration]
This illustration depicts the notional local equatorial crossing times
for the following satellites:
NPOESS: 0530 hours;
MetOp: 0930 hours;
NPOESS: 1330 hours.
Sources: GAO analysis of NPOESS program office data; MapArt (globe).
[End of figure]
While the Nunn-McCurdy certification decision decreased the number of
NPOESS sensors and reduced the functionality of others, it allowed for
the reintegration of the canceled sensors if other parties choose to
fund them. Table 3 describes the changes to NPOESS instruments.
Table 3: Changes to NPOESS Instruments, as of June 2006:
Instrument: Advanced technology microwave sounder;
Status of instrument after Nunn-McCurdy decision: Sensor unchanged; to
be included on NPP and on afternoon satellites.
Instrument: Aerosol polarimetry sensor;
Status of instrument after Nunn-McCurdy decision: Sensor was
canceled[A].
Instrument: Conical-scanned microwave imager/sounder;
Status of instrument after Nunn-McCurdy decision: Sensor was canceled;
program office to procure a less complex microwave imager/sounder for
inclusion beginning on the second NPOESS satellite.
Instrument: Cross-track infrared sounder;
Status of instrument after Nunn-McCurdy decision: Sensor unchanged; to
be included on NPP and on afternoon satellites.
Instrument: Data collection system;
Status of instrument after Nunn-McCurdy decision: No change; subsystem
is to be included on all four NPOESS satellites.
Instrument: Earth radiation budget sensor;
Status of instrument after Nunn-McCurdy decision: Sensor was canceled;
is to be replaced by a legacy sensor on C1 only[A].
Instrument: Ozone mapper/profiler suite;
Status of instrument after Nunn-McCurdy decision: One part of the
sensor (limb) was canceled; remaining part is to be included on NPP and
on all four NPOESS satellites[A].
Instrument: Radar altimeter;
Status of instrument after Nunn-McCurdy decision: Sensor was canceled.
Instrument: Search and rescue satellite aided tracking system;
Status of instrument after Nunn-McCurdy decision: Sensor unchanged;
subsystem is to be included on all four NPOESS satellites.
Instrument: Space environmental sensor suite;
Status of instrument after Nunn-McCurdy decision: Sensor was canceled;
is to be replaced by a less capable, less expensive legacy sensor[A].
Instrument: Survivability sensor;
Status of instrument after Nunn-McCurdy decision: Subsystem was
canceled[A].
Instrument: Total solar irradiance sensor;
Status of instrument after Nunn-McCurdy decision: Sensor was
canceled[A].
Instrument: Visible/infrared imager radiometer suite;
Status of instrument after Nunn-McCurdy decision: Sensor unchanged;
sensor is to be included on NPP and on all four NPOESS satellites.
Source: GAO analysis of NPOESS program office data.
[A] While direct program funding for these sensors was eliminated,
these sensors could be reintegrated should other parties choose to fund
them. The Nunn-McCurdy decision notes that the spacecraft is to include
space for these sensors and funds to integrate them.
[End of table]
The changes in NPOESS sensors affected the number and quality of the
resulting weather and environmental products, called EDRs. In selecting
sensors for the restructured program during the Nunn-McCurdy process,
decision makers placed the highest priority on continuing current
operational weather capabilities and a lower priority on obtaining
selected environmental and climate measuring capabilities. As a result,
the revised NPOESS system has significantly less capability for
providing global climate measures than was originally planned.
Specifically, the number of EDRs was decreased from 55 to 39, of which
6 are of a reduced quality. The 39 EDRs that remain include cloud base
height, land surface temperature, precipitation type and rate, and sea
surface winds. The 16 EDRs that were removed include cloud particle
size and distribution, sea surface height, net solar radiation at the
top of the atmosphere, and products to depict the electric fields in
the space environment. The six EDRs that are of a reduced quality
include ozone profile, soil moisture, and multiple products depicting
energy in the space environment.
Selected Climate Sensors Have Been Added Back to the Program:
After the 2006 Nunn-McCurdy decision, the NPOESS Executive Committee
decided to add selected sensors back to individual satellites in order
to address concerns from the climate community about the loss of key
climate data. In January 2008, the Committee approved plans to include
a replacement for the Earth radiation budget sensor (called the Clouds'
and the earth's radiant energy system sensor) on the NPP satellite. In
addition, in May 2008, the Committee approved plans to include a Total
solar irradiance sensor on the C1 satellite. Table 4 shows which
instruments are currently planned for NPP and the four satellites of
the NPOESS program, called C1, C2, C3, and C4. Program officials
acknowledged that these configurations could change if other parties
decide to develop the sensors that were canceled.
Table 4: Configuration of Instruments Planned for NPP and NPOESS
Satellites, as of May 2008:
Instrument: Advanced technology microwave sounder;
NPP: [A];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [B];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [B].
Instrument: Microwave imager/sounder (replacing the canceled Conical-
scanned microwave imager/sounder);
NPP: [C];
NPOESS C1 (PM): [C];
NPOESS C2 (AM): [A];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [A].
Instrument: Cross-track infrared sounder;
NPP: [A];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [B];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [B].
Instrument: Data collection system;
NPP: [C];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [A];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [A];
Instrument: Clouds‘ and the earth‘s radiant energy system sensor
(replacing selected capabilities of the Earth radiation budget sensor);
NPP: [A];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [C];
NPOESS C3 (PM): [C];
NPOESS C4 (AM): [C].
Instrument: Ozone mapper/profiler suite (nadir);
NPP: [A];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [C];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [C].
Instrument: Ozone mapper/profiler suite (limb);
NPP: [A];
NPOESS C1 (PM): [B];
NPOESS C2 (AM): [C];
NPOESS C3 (PM): [B];
NPOESS C4 (AM): [C].
Instrument: Search and rescue satellite aided tracking system;
NPP: [C];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [A];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [A].
Instrument: Space environment monitor (replacing selected capabilities
of the space environmental sensor suite);
NPP: [C];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [C];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [C].
Instrument: Total solar irradiance sensor;
NPP: [C];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [B];
NPOESS C3 (PM): [C];
NPOESS C4 (AM): [B].
Instrument: Visible/infrared imager radiometer suite;
NPP: [A];
NPOESS C1 (PM): [A];
NPOESS C2 (AM): [A];
NPOESS C3 (PM): [A];
NPOESS C4 (AM): [A].
[A] = Sensor is currently planned for this satellite:
[B] = Canceled but could be restored to this satellite:
[C] = Not applicable--sensor was never planned for this satellite:
Source: GAO analysis of NPOESS program office data.
[End of table]
NPOESS Experienced Schedule Delays and Cost Growth after It Was
Restructured:
After the program was restructured, NPOESS continued to experience
schedule delays and cost growth. In June 2008, we reported that poor
workmanship and testing delays caused an additional 8-month slip to the
expected delivery date of the Visible/infrared imager radiometer suite
(VIIRS) sensor.[Footnote 12] This late delivery caused a corresponding
delay in the expected launch date of the NPP demonstration satellite,
moving it to June 2010. In addition, we reported that the program life
cycle costs, estimated at $12.5 billion, were expected to rise by
approximately $1 billion because of problems experienced in the
development of the VIIRS and Cross-track infrared sounder (CrIS)
sensors, the need to revise outdated operations and support cost
estimates, and the need to modify information security requirements on
ground systems. Program officials subsequently modified their life
cycle cost estimate to $13.95 billion, which included about $1.15
billion for revised pre-and post-launch operations and support costs
and about $300 million to address development issues. The revised cost
estimate did not include funds to modify information security
requirements.
Prior Reports Recommended Steps to Mitigate Program Risks:
In recent years, we have made a series of recommendations to mitigate
risks on the NPOESS program. In April 2007, we reported that the
program lacked a process and plan for identifying and filling key
staffing shortages and that DOD's plans to reassign the Program
Executive Officer would unnecessarily increase risks to an already
risky program.[Footnote 13] We also reported that while the program
office had made progress in restructuring NPOESS after the June 2006
Nunn-McCurdy certification decision, important tasks leading up to
finalizing contract changes remained to be completed. Specifically, the
program had made progress in drafting key acquisition documents,
including the system engineering plan, the test and evaluation master
plan, and the memorandum of agreement between the agencies. However,
executive approval of those documents was about 6 months late at that
time--due in part to the complexity of navigating three agencies'
approval processes. To address these issues, we recommended that NPOESS
program officials develop and implement a written process for
identifying and addressing human capital needs and establish a plan to
immediately fill needed positions; that DOD delay the reassignment of
the Program Executive Officer until all sensors were delivered to NPP;
and that the appropriate agency executives finalize key acquisition
documents by the end of April 2007.
Following up on these recommendations, in May 2008, we reported that
program officials had documented the program's staffing process and
made progress in filling selected budgeting and system engineering
vacancies.[Footnote 14] DOD, however, reassigned the Program Executive
Officer in July 2007 and replaced this person with a new Program
Executive Officer. We also reported that executive approval of key
acquisition documents was more than a year late at that time and
reiterated our prior recommendation that the agencies immediately
complete these activities. The last of these acquisition documents was
approved in December 2008.
Progress Made, but Continued Instrument Problems Are Driving Costs
Upward, Forcing Launch Delays, and Endangering Satellite Continuity:
Over the past year, selected components of the NPOESS program--
including the ground segment and selected sensors--have made progress.
However, the program's approved cost and schedule baseline is not
achievable, and problems with two critical sensors continue to drive
the program's cost and schedule. Costs are expected to grow by about $1
billion from the current $13.95 billion cost estimate, and the
schedules for NPP and the first two NPOESS satellites are expected to
be delayed by 7, 14, and 5 months, respectively. These delays endanger
the continuity of weather and climate satellite data because there will
not be a satellite available as backup should a satellite fail on
launch or in orbit. Program officials reported that they are assessing
alternatives for mitigating risks, and that they plan to propose a new
cost and schedule baseline by June 2009.
Program Made Progress on Selected Components:
With over $4 billion expended on the program through the end of fiscal
year 2008, the program is well under way. Over the past year, selected
components of the NPOESS program have made progress. Specifically,
three of the five instruments slated for NPP have been delivered and
integrated on the spacecraft; the ground-based satellite data
processing system has been installed and tested at both of the
locations that are to receive NPP data; and the satellites' command,
control, and communications system has passed acceptance testing.
Details on the status of key components are provided in table 5.
Table 5: Status and Risk Level of Key Space and Ground Components, as
of April 2009:
Component: Advanced technology microwave sounder;
Program-identified risk level: Low;
Status:
For NPP: The instrument was integrated on the spacecraft in December
2006 and is awaiting delivery of the other sensors in order to complete
integration testing.
For C1: The instrument is currently being built by the prime
contractor. Although the effort is low risk, the effort is taking more
time than originally expected.
Component: Clouds‘ and the earth‘s radiant energy system;
Program-identified risk level: Low;
Status:
For NPP: The instrument was integrated on the spacecraft in November
2008.
For C1: The instrument is on track and expected to go through systems
requirements review in April 2009.
Component: Cross-track infrared sounder (CrIS);
Program-identified risk level: High;
Status: For NPP: The instrument has experienced several issues during
testing and final review, including a faulty calibration target and
overstressed semiconductors. Repairing these issues delayed the
instrument‘s delivery to the NPP integration contractor. That date is
now set for July 2009.
Component: Cross-track infrared sounder (CrIS);
Program-identified risk level: Medium;
Status: For C1: A new calibration target will be needed for the second
flight unit. A simplified design has been chosen that is based on
existing technology. In addition, because the program needs to delay
activities on the second flight unit in 2009, delivery of the unit
could be delayed by a full year.
Component: Microwave imager/sounder;
Program-identified risk level: Low;
Status: For C2: The NPOESS Executive Committee recently directed the
program to review the sensor‘s requirements in order to mitigate
growing program costs. Because the sensor is not yet in development,
the executive committee noted that this is an appropriate time to
consider developing a less complex sensor. The program director stated
that he expects the sensor to undergo a requirements review by the end
of May 2009.
Component: Ozone mapper/profiler suite;
Program-identified risk level: Medium;
Status: For NPP: The instrument was recently integrated on the
spacecraft. However, the program office raised concerns that screws had
been overtorqued and is reviewing the assembly of the instrument.
Component: Ozone mapper/profiler suite;
Program-identified risk level: Low;
Status: For C1: In order to fund problems on VIIRS, work was halted on
the second flight unit”which will lead to a delayed delivery of
approximately 1 year.
Component: Total solar irradiance sensor;
Program-identified risk level: Low;
Status: For C1: Due to a lack of available funds prior to April 2009,
the program office is reassessing the schedule for the first flight
unit of this instrument. The preliminary design review is currently
scheduled for April 2009.
Component: Visible/infrared imager radiometer suite (VIIRS)
Program-identified risk level: High;
Status:
For NPP: The sensor has completed electromagnetic compatibility and
vibration testing, and it began thermal vacuum testing in early May
2009. However, continued slow test execution and problems during
environmental testing have led to further delays in delivering it to
the NPP integration contractor. While the contractor‘s current plan
shows delivery in September 2009, the government estimates a delivery
by December 2009.
For C1: More than 80 percent of the parts for the second VIIRS sensor
have already been acquired.
Component: Spacecraft;
Program-identified risk level: Low;
Status: For NPP: The spacecraft has been completed and three of five
instruments have been integrated on it.
Component: Spacecraft;
Program-identified risk level: Medium;
Status: For C1: The spacecraft recently completed a critical design
audit; however, it is also on the ’critical path“ for C1, which means
that any delays in the spacecraft could delay the launch date.
Component: Command, Control, and Communications;
Program-identified risk level: Low;
Status: The command, control, and communications segment is being
developed in a series of builds.
For NPP: Build 1.4 has been completed.
For C1: Build 2.1 is under development.
Component: Integrated Data Processing System;
Program-identified risk level: Low;
Status: For NPP: Hardware has been deployed to two central data
processing centers (NOAA‘s National Satellite Operations Facility in
Suitland, Maryland and the Air Force Weather Agency) and testing has
begun. Development continues on the next system software build.
Component: Ground stations for receiving satellite data;
Program-identified risk level: Low;
Status: NOAA is working with domestic and foreign authorities to obtain
approval to operate ground stations to receive satellite data. To date,
the program office has reached agreement with 7 of 15 ground station
sites. According to agency officials, only 3 ground stations will be
operational by the launch of the first NPOESS satellite and the full
complement of ground stations will be operational by the launch of the
second NPOESS satellite.
Source: GAO analysis of NPOESS program office data.
[End of table]
Technical Challenges Cause Cost Increases, Delay Schedule, and Risk
Data Continuity; Key Decisions on Program's Next Steps Are Pending:
While the program has made progress, problems with two critical sensors
continue to drive the program's cost and schedule. Specifically,
ongoing challenges with VIIRS development, design, and workmanship have
led to additional cost overruns and delayed the instrument's delivery
to NPP. In addition, problems discovered during environmental testing
on CrIS led the contractor to further delay its delivery to NPP and
added further unanticipated costs to the program. To address these
issues, the program office halted or delayed activities on other
components (including the development of a sensor planned for the C1
satellite) and redirected those funds to fixing VIIRS and CrIS. As a
result, those other activities now face cost increases and schedule
delays.
Program officials acknowledge that NPOESS will cost more than the
$13.95 billion previously estimated, but they have not yet adopted a
new cost estimate. Program officials estimated that program costs will
grow by about $370 million due to recent technical issues experienced
on the sensors and the costs associated with halting and then
restarting work on other components of the program. In addition, the
costs associated with adding new information security requirements to
the program could reach $200 million.[Footnote 15] This estimate also
does not include approximately $410 million for operations and support
costs for the last two years of the program's life cycle (2025 and
2026). Thus, we anticipate that the overall cost of the program could
grow by about $1 billion from the current $13.95 billion estimate--
especially given the fact that difficult integration and testing of the
sensors on the NPP and C1 spacecrafts has not yet occurred.[Footnote
16] Program officials reported that they plan to revise the program's
cost estimate over the next few weeks and to submit it for executive-
level approval in June 2009.
As for the program's schedule, program officials estimate that the
delivery of VIIRS to the NPP contractor will be delayed, resulting in a
further delay in the launch of the NPP satellite to January 2011, a
year later than the date estimated during the program restructuring--
and seven months later than the June 2010 date that was established
last year. In addition, program officials estimated that the first and
second NPOESS satellites would be delayed by 14 and 5 months,
respectively, because selected development activities were halted or
slowed to address VIIRS and CrIS problems. The program's current plans
are to launch C1 in March 2014 and C2 in May 2016. Program officials
notified the Executive Committee and DOD's acquisition authority of the
schedule delays, and under DOD acquisition rules, are required to
submit a new schedule baseline by June 2009. See table 6 for changes in
key program milestones over time.
Table 6: Changes in Key Program Milestones over Time:
Milestones: Final POES launch[A];
As of the August 2002 contract award: March 2008;
As of the June 2006 certification decision: February 2009;
Current program estimates (as of April 2009): February 2009 (actual);
Change from 2006 certification decision: Not applicable.
Milestones: NPP launch;
As of the August 2002 contract award: May 2006;
As of the June 2006 certification decision: January 2010[B];
Current program estimates (as of April 2009): January 2011;
Change from 2006 certification decision: 1-year delay.
Milestones: First NPOESS satellite planned for launch;
As of the August 2002 contract award: April 2009;
As of the June 2006 certification decision: January 2013;
Current program estimates (as of April 2009): March 2014;
Change from 2006 certification decision: 14-month delay.
Milestones: Final DMSP launch[A];
As of the August 2002 contract award: October 2009;
As of the June 2006 certification decision: April 2012;
Current program estimates (as of April 2009): May 2014[C];
Change from 2006 certification decision: 25-month delay.
Milestones: Second NPOESS satellite planned for launch;
As of the August 2002 contract award: June 2011;
As of the June 2006 certification decision: January 2016;
Current program estimates (as of April 2009): May 2016;
Change from 2006 certification decision: 5-month delay[D].
Source: GAO analysis of DOD, NOAA, and NPOESS program office data.
[A] POES and DMSP are not part of the NPOESS program. Their launch
dates are provided to indicate the increased risk of satellite data
gaps between when these systems launch and when the NPOESS satellites
launch.
[B] In February 2008, the launch date for NPP was delayed to June 2010.
[C] DMSP program staff noted that the DMSP launches were delayed due to
the health of existing satellites and to mitigate the impact of NPOESS
delays. The final DMSP could be delayed to as late as 2018, if
required.
[D] This 5-month delay extends from the first day of January 2016 to
the last day of May 2016.
[End of table]
These launch delays have endangered our nation's ability to ensure the
continuity of polar-orbiting satellite data. The final POES satellite,
called NOAA-19, is in an afternoon orbit and is expected to have a 5-
year lifespan. Both NPP and C1 are planned to support the afternoon
orbit. Should the NOAA-19 satellite fail before NPP is launched,
calibrated, and operational, there would be a gap in satellite data in
that orbit. Further, the delays in C1 mean that NPP will not be the
research and risk reduction satellite it was originally intended to be.
Instead, it will have to function as an operational satellite until C1
is in orbit and operational--and if C1 fails on launch or in early
operations, NPP will be needed to function until C3 is available,
currently planned for 2018. The delay in the C2 satellite launch
affects the early morning orbit. There are three more DMSP satellites
to be launched in the early and midmorning orbits. DOD is revisiting
the launch schedules for these satellites to try to extend them as long
as possible. An independent review team, established to assess key
program risks, recently reported that the constellation of satellites
is extremely fragile and that a single launch failure of DMSP or of the
NPP satellite could result in a gap in satellite coverage from 3 to 5
years. Figure 6 shows the current and planned satellites and highlights
gaps where the constellation is at risk.
Figure 6: Potential Gaps in the Continuity of Current and Planned Polar
Satellites:
[Refer to PDF for image: illustrated table]
Orbit: Early morning;
Satellite: DMSP F-17;
Calibration and validation: Not indicated;
Planned spacecraft operations: prior to 2009 through late 2010;
Potential gap in data continuity if satellite fails on launch or in
orbit: not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: late 2010 through late 2012.
Orbit: Early morning;
Satellite: DMSP F-19;
Calibration and validation: Not indicated;
Planned spacecraft operations: late 2012 through late 2017;
Potential gap in data continuity if satellite fails on launch or in
orbit: late 2012 through late 2017;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Early morning;
Satellite: NPOESS C-2;
Calibration and validation: mid-2016 through late 2017;
Planned spacecraft operations: late 2017 through mid-2023;
Potential gap in data continuity if satellite fails on launch or in
orbit: late 2017 through mid-2020;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Early morning;
Satellite: NPOESS C-4;
Calibration and validation: early to mid-2020;
Planned spacecraft operations: mid-2020 through 2026;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Mid-morning;
Satellite: DMSP F-18;
Calibration and validation: Not indicated;
Planned spacecraft operations: mid-2009 through mid-2013;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: mid-2013 through mid-2014.
Orbit: Mid-morning;
Satellite: DMSP F-20;
Calibration and validation: Not indicated;
Planned spacecraft operations: mid-2014 through mid-2019;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Mid-morning;
Satellite: MetOp-A;
Calibration and validation: Not indicated;
Planned spacecraft operations: prior to 2009 through late 2011;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Mid-morning;
Satellite: MetOp-B;
Calibration and validation: Not indicated;
Planned spacecraft operations: early 2011 through early 2016;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Mid-morning;
Satellite: MetOp-C;
Calibration and validation: Not indicated;
Planned spacecraft operations: late 2015 through late 2020;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Afternoon;
Satellite: NOAA-19;
Planned spacecraft operations: Not indicated;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated; early 2009 through late 2012;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Afternoon;
Satellite: NPP;
Calibration and validation: early 2011 through late 2012;
Planned spacecraft operations: late 2012 through late 2015;
Potential gap in data continuity if satellite fails on launch or in
orbit: late 20123 through late 2014;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Afternoon;
Satellite: NPOESS C-1;
Calibration and validation: early through late 2014;
Planned spacecraft operations: late 2014 through early 2021;
Potential gap in data continuity if satellite fails on launch or in
orbit: early 2016 through mid-2018;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Orbit: Afternoon;
Satellite: NPOESS C-3;
Calibration and validation: early through mid-2018;
Planned spacecraft operations: mid-2018 through 2024;
Potential gap in data continuity if satellite fails on launch or in
orbit: Not indicated;
Potential gap in data continuity if satellite does not live beyond its
expected life: Not indicated.
Sources: GAO analysis of DOD, NOAA, and NPOESS program office data.
[End of figure]
Although the program's approved cost and schedule baseline is not
achievable and the polar satellite constellation is at risk, the
Executive Committee has not yet made a decision on how to proceed with
the program. Specifically, the Committee has not approved a new program
schedule and a realistic cost estimate or determined whether it will
mitigate or accept the risk of a potential gap in satellite continuity.
Program officials plan to propose new cost and schedule baselines in
June 2009. However, the Executive Committee does not have an estimate
for when it will make critical decisions on cost, schedule, and risk
mitigation. Program officials reported that they are addressing
immediate funding constraints by deferring selected activities to later
fiscal years in order to pay for VIIRS and CrIS problems, delaying the
launches of NPP, C1, and C2, and assessing alternatives for mitigating
the risk that VIIRS will continue to experience problems--including the
possibility of purchasing a legacy imaging sensor to replace VIIRS on
C1. Without an executive-level decision to do so, the program is
proceeding on a course that is deferring cost growth, delaying
launches, and risking its underlying mission of providing operational
weather continuity to the civil and military communities.
Executive Committee Has Not Effectively Fulfilled Its Responsibilities:
While the NPOESS Executive Committee has made improvements over the
last several years in response to prior recommendations, it has not
effectively fulfilled its responsibilities and does not have the
membership and leadership it needs to effectively or efficiently
oversee and direct the NPOESS program. Specifically, the DOD Executive
Committee member with acquisition authority does not attend committee
meetings--and sometimes contradicts the Committee's decisions, the
Committee does not aggressively manage risks, and many of the
Committee's decisions do not achieve desired outcomes. Independent
reviewers, as well as program officials, explained that the tri-agency
structure of the program makes it very difficult to effectively manage
the program. Until these shortfalls are addressed, the Committee is
unable to effectively oversee the NPOESS program--and important issues
involving cost growth, schedule delays, and satellite continuity will
likely remain unresolved.
Executive Committee Has Responded to Past Recommendations:
In November 2005, we reported that the Executive Committee did not meet
on a regular basis and that most of its meetings did not result in
major decisions, but instead triggered further analysis and review.
[Footnote 17] In addition, in May 2006, the Department of Commerce's
Inspector General reported that the Committee did not effectively
challenge the program's optimistic assessments and recommended that it
provide more vigilant oversight. Since then, the Committee has met
regularly on a quarterly basis and held interim teleconferences as
needed.
The Committee has also sought and reacted to advice from external
advisors by, among other actions, authorizing a government program
manager to reside onsite at the VIIRS contractor's facility to improve
oversight of the sensor's development on a day-to-day basis. More
recently, the Executive Committee sponsored a broad-based independent
review of the NPOESS program and is beginning to respond to its
recommendations. The independent review team's findings and
recommendations are provided in appendix II.
Key Acquisition Executive Does Not Attend Executive Committee Meetings:
As established by the 1995 and 2008 memorandums of agreement signed by
all three agencies, the members of the NPOESS Executive Committee are
(1) the Under Secretary of Commerce for Oceans and Atmosphere; (2) the
Under Secretary of Defense for Acquisition, Technology, and Logistics;
and (3) the NASA Administrator.[Footnote 18] Because DOD has the lead
responsibility for the NPOESS acquisition, the Under Secretary of
Defense for Acquisition, Technology, and Logistics, was also designated
as the milestone decision authority--the individual with the authority
to approve a major acquisition program's progression in the acquisition
process, as well as any changes to the cost, schedule, and
functionality of the acquisition.[Footnote 19] The intent of the tri-
agency memorandums was that acquisition decisions would be agreed to by
the Executive Committee before a final acquisition decision is made by
the milestone decision authority.[Footnote 20]
However, DOD's acquisition authority has never attended an Executive
Committee meeting. This individual delegated the responsibility for
attending the meetings--but not the authority to make acquisition
decisions--to the Under Secretary of the Air Force. Therefore, none of
the individuals who attend the Executive Committee meetings for the
three agencies have the authority to approve the acquisition program
baseline or major changes to the baseline. As a result, agreements
between committee members have been overturned by the acquisition
authority, leading to significant delays. For example, the details of
the program's acquisition program baseline were agreed to by members of
the Executive Committee, but were overruled by the office of the Under
Secretary of Defense for Acquisition, Technology, and Logistics. This
required several months of extensive renegotiation. In addition, after
the Executive Committee members agreed to a revised tri-agency
memorandum of agreement and it was signed by the Secretary of Commerce
and the Administrator of NASA, the Under Secretary of Acquisition,
Technology, and Logistics refused to approve the document, and it took
over a year to finalize it. Crucially, this year-long disagreement
focused on whether the Under Secretary should consult with or
coordinate with members of the Executive Committee on matters related
to NPOESS. In August 2008, the Under Secretary of Commerce for Oceans
and Atmosphere wrote to the Under Secretary of Defense for Acquisition,
Technology, and Logistics, expressing concern that DOD did not
recognize the management role of the tri-agency NPOESS Executive
Committee or its responsibility, authority, and accountability to make
decisions that represent the respective agency positions.
At the conclusion of our review, DOD agency officials stated that the
absence of the Under Secretary of Defense for Acquisition, Technology,
and Logistics at Executive Committee meetings is not the root cause of
the Executive Committee's problems, but acknowledged that this
individual's presence at the meetings could be helpful in streamlining
the flow of information and the decision-making process.
Committee Does Not Aggressively Manage Risks:
Best practices note that oversight of large investments is a critical
part of the investment life cycle and call for oversight boards to take
corrective actions at the first sign of cost, schedule, and performance
problems. They also call for oversight boards to ensure that corrective
actions and related efforts are executed by the project management team
and tracked until the desired outcomes occur.[Footnote 21] To provide
this oversight, the Executive Committee holds quarterly meetings during
which the program's progress is reviewed using metrics that provide an
early warning of cost, schedule, and technical risks.
Although the Executive Committee meets quarterly to review program
progress and risks, and the results of those meetings are recorded in
meeting minutes, the Committee does not routinely document action items
or track those items to closure. Specifically, in the four meetings
held between March 2007 and January 2008, the Committee explicitly
documented 12 action items, but did not explicitly document action
items in the three meetings from May to December 2008. Instead, 5
actions were implied in the text of the meeting minutes and at least 1
action item to proceed with a modified schedule for VIIRS was not
recorded at all. Further, the Executive Committee did not routinely
track the closure of its action items. Some action items were not
discussed in later meetings and in cases where an item was discussed,
it was not always clear what action was taken, whether it was
effective, and whether the item was closed. Specifically, of the 18
action items we identified between March 2007 and December 2008, 7 were
clearly closed and 11 were not.[Footnote 22] For example, in May 2008,
the Executive Committee asked DOD's Cost Analysis Improvement Group and
the program office to reconcile their cost estimates, but it is not
clear from the meetings that took place after this one whether this
action was taken and what the result was. Also in May 2008, the
Committee directed the prime contractor and others to investigate the
root causes of technical issues; again, it is not clear whether this
was completed or what the results were.
According to the Program Executive Officer, the closing of an action
item is not always explicitly tracked because it typically involves
gathering information that is presented during later Committee
meetings. Nonetheless, by not rigorously documenting action items--
including identifying the party responsible for the action, the desired
outcome, and the time frame for completion--and then tracking the
action items to closure, the Executive Committee is not able to ensure
that its actions have achieved their intended results and to determine
whether additional changes or modifications are still needed. This
impedes the Committee's ability to effectively oversee the program,
direct risk mitigation activities, and obtain feedback on the results
of its actions.
Committee Decisions Do Not Achieve Desired Outcomes:
Best practices in investment management call for oversight of large
investments throughout their life cycles.[Footnote 23] Government
guidance calls for oversight boards to take corrective actions at the
first sign of cost, schedule, and performance slippages in order to
mitigate risks and achieve successful outcomes. The NPOESS Executive
Committee generally took immediate action to mitigate the risks that
were brought before them; however, a majority of these actions were not
effective--that is, they did not fully resolve the underlying issues or
result in a successful outcome. Specifically, of 22 significant risks
forwarded to the Executive Committee between January and December 2008,
the Committee took some action to mitigate 17 of the risks and decided
to monitor the other 5 risks. Committee actions included approving
modifications to the VIIRS schedule and directing the program to modify
key acquisition documents to resolve disagreements, to establish an
onsite government manager at a subcontractor's facility, and to develop
a plan for the way forward for the program once it was determined that
the program could not execute its baseline on time within its budget.
However, the Committee's actions either did not result in successful
outcomes or were inefficient in achieving successful outcomes. Of the
22 risks presented to the Executive Committee, 18 involved cost,
schedule, and technical issues on the VIIRS and CrIS sensors, and 4
involved barriers to gaining approval of key acquisition documents. The
Committee's actions on the sensor development risks accomplished
interim successes by improving the government's oversight of a
subcontractor's activities and guiding next steps in addressing
technical issues--but even with committee actions, the sensors'
performance has continued to falter and affect the rest of the program.
Independent reviewers reported that the tri-agency structure of the
program complicated the resolution of sensor risks because any decision
could be revisited by another agency. In addition, while the
government's onsite program manager is responsible for managing
deliverables of a critical sensor, this individual reported that the
plurality of customers with different expectations and priorities made
it difficult to move the sensor development effort forward.
As for the 4 risks involving barriers to gaining approval of key
acquisition documents, by the end of 2008, all of the acquisition
documents had been completed. However, the path to achieving this
successful outcome was inefficient. For example, it took over 2 years
and countless iterations by multiple levels of management in three
different agencies to complete the tri-agency memorandum of agreement.
The leader of an independent review team charged with reviewing key
program risks recently reported that the Executive Committee is "at
best— inefficient." Program officials explained that interagency
disagreements and differing priorities make it difficult to effectively
resolve issues. In addition, two independent advisors noted that the
tri-agency aspect of the program makes it difficult to make decisions
that balance the needs of all three agencies.
The Committee's inability to make effective and efficient decisions is
further complicated when difficult risks are not escalated in a timely
manner. While most risks are raised to the Committee within months of
the time they surface at the program level, selected interagency issues
lingered before being brought before the Executive Committee.
Specifically, an interagency disagreement regarding the appropriate
level of security requirements was discussed and studied for 2 years
before the Committee was notified--and the Committee still has not been
asked to make a decision on this issue.
At the conclusion of our review, DOD officials reported that part of
the problem in escalating risks is that, in violation of interagency
agreements and inconsistent with DOD acquisition policy, two senior
NOAA officials review and limit what the Program Executive Officer
provides to the Executive Committee.[Footnote 24] NOAA officials and
the Program Executive Officer strongly disagreed with this statement.
NASA officials commented that NOAA's enhanced oversight provides a
healthy set of checks and balances to the program.
Program Has Assessed Alternatives, but Has Not Yet Identified a Viable
Alternative for Acquiring the Last Two NPOESS Satellites:
When NPOESS was restructured in June 2006, the program included two
satellites (C1 and C2) and an option to have the prime contractor
produce the next two satellites (C3 and C4). In approving the
restructured program, DOD's decision authority noted that he reserved
the right to use a different satellite integrator for the final two
satellites, and that a decision on whether to exercise the option was
to be made in June 2010. To prepare for this decision, DOD required a
tri-agency assessment of alternative management strategies. This
assessment was to examine the feasibility of an alternative satellite
integrator, to estimate the cost and schedule implications of moving to
an alternative integrator, and within one year, to provide a viable
alternative to the NPOESS Executive Committee.
To address DOD's requirement, the NPOESS Program Executive Officer
sponsored two successive alternative management studies; however,
neither of the studies identified a viable alternative to the existing
satellite integrator. The first study, conducted in 2007, identified
three alternatives to the existing satellite integrator, including (1)
re-competing the entire prime contract, (2) obtaining an independent
system integrator while having the existing prime contractor continue
to develop space and ground components, and (3) having the government
take over responsibility for the system integration. The study
identified the relative strengths and weaknesses of the alternatives
and recommended that the program remain with the existing prime
contractor for C3 and C4 because doing otherwise would increase cost
and schedule risks. It did not quantify these costs or risks. The
second alternative management study, conducted in 2008, identified the
same alternatives to the current system integrator and assessed their
relative cost, schedule, and performance risks to the program. The
study determined that the alternatives to the system integrator were
not viable options because of their potential costs, and because the
prime contractor's performance had been meeting requirements. This
study also recommended staying with the prime contractor for C3 and C4.
Both of these studies also assessed other aspects of program
management--including the government's executive and program management
and the contractors' management--and made recommendations to improve
them.
The Program Executive Officer plans to conduct a final assessment of
alternatives prior to the June 2010 decision on whether to exercise the
option to have the current system integrator produce the next two
NPOESS satellites. Program officials explained that the program's
evolving costs, schedules, and risks could mean that an alternative
that was not viable in the past would become viable. For example, if
the prime contractor's performance no longer meets basic requirements,
an alternative that was previously too costly to be considered viable
might become so.
Conclusions:
Continued problems in the development of critical NPOESS sensors have
contributed to growing costs and schedule delays. Costs are now
expected to grow by as much as $1 billion over the prior life cycle
cost estimate of $13.95 billion, and problems in delivering key sensors
have led to delays in launching NPP and the first two NPOESS
satellites--by a year or more for NPP and the first NPOESS satellite.
These launch delays have endangered our nation's ability to ensure the
continuity of polar-orbiting satellite data. Specifically, if any
planned satellites fail on launch or in orbit, there would be a gap in
satellite data until the next NPOESS satellite is launched and
operational--a gap that could last for 3 to 5 years.
The NPOESS Executive Committee responsible for making cost and schedule
decisions and addressing the many and continuing risks facing the
program has not yet made important decisions on program costs,
schedules, and risks--or identified when it will do so. In addition,
the Committee has not been effective or efficient in carrying out its
oversight responsibilities. Specifically, the individual with the
authority to make acquisition decisions does not attend committee
meetings; corrective actions are not identified in terms of desired
outcomes, resources, and time frames for completion; these actions are
not tracked to closure; and selected risks are not escalated in a
timely manner. Until the Committee's shortfalls are addressed,
important decisions may not be effective and issues involving cost
increases, schedule delays, and satellite continuity may remain
unresolved.
Recommendations for Executive Action:
To improve the timeliness and effectiveness of acquisition decision-
making on the NPOESS program, we recommend that the Secretary of
Defense direct the Under Secretary of Defense for Acquisition,
Technology, and Logistics to attend and participate in NPOESS Executive
Committee meetings.
We also recommend that the Secretaries of Defense and Commerce and the
Administrator of NASA direct the NPOESS Executive Committee to take the
following five actions:
* establish a realistic time frame for revising the program's cost and
schedule baselines;
* develop plans to mitigate the risk of gaps in satellite continuity;
* track the Committee's action items from inception to closure;
* improve the Committee's ability to achieve successful outcomes by
identifying the desired outcome associated with each of the Committee's
actions, as well as time frames and responsible parties, when new
action items are established; and:
* improve the Committee's efficiency by establishing time frames for
escalating risks to the Committee for action so that they do not linger
unresolved at the program executive level.
Agency Comments and Our Evaluation:
We received written comments on a draft of this report from the
Secretary of Commerce (see appendix III), the Deputy Assistant
Secretary of Defense (see appendix IV), and the Associate Deputy
Administrator of NASA (see appendix V). In their comments, NASA and
NOAA agreed with our findings and recommendations and identified plans
to implement them. For example, NASA noted that it would work closely
with DOD and NOAA to ensure that a realistic time frame was established
for cost and schedule baselines and to develop plans to mitigate
program risks. NOAA noted that it planned to mitigate risk, in part by
accelerating the development of environmental products--and planned to
use more data from NPP than it had originally planned. Regarding our
recommendations to track Executive Committee actions and ensure
successful outcomes by identifying the desired outcome associated with
each action as well as time frames and responsible parties, both NASA
and NOAA noted that they would work with the Program Executive Officer
to ensure that these actions happen in a timely and effective manner.
Finally, regarding our recommendation to improve the Executive
Committee's efficiency by establishing time frames for escalating risks
to the Committee, both NASA and NOAA noted that they would work with
the Program Executive Officer to ensure that this was done. NOAA also
provided technical comments on the report, which we incorporated as
appropriate.
In its written comments, DOD concurred with one and partially concurred
with our other recommendations. Regarding our recommendation to have
the appropriate official attend Executive Committee meetings, the
agency partially concurred and noted that the Under Secretary of
Acquisition, Technology, and Logistics would evaluate the necessity of
attending future Executive Committee meetings. DOD also reiterated that
the Under Secretary of the Air Force was delegated the authority to
attend the meetings. While we acknowledge that the Under Secretary
delegated responsibility for attending these meetings, it is an
inefficient way to make decisions and achieve outcomes. In the past,
agreements between Executive Committee members have been overturned by
the Under Secretary, leading to significant delays in key decisions.
In addition, DOD partially concurred with our recommendations that the
Executive Committee establish a realistic time frame for revising the
program's cost and schedule baselines, and develop plans to mitigate
the risk of data gaps. For both recommendations, DOD noted that the
program office should develop the plans, which would then be reviewed
by the Executive Committee. We agree that the program is responsible
for revising the cost and schedule baselines and developing risk
mitigation plans, and that the Executive Committee is responsible for
approving these plans. However, our recommendations focused on
implementing these activities. Until the Committee establishes a time
frame for making decisions on the program's cost and schedule baseline
and endorses risk mitigation plans, there is a continued risk that the
program will encounter further delays or gaps in satellite data
continuity.
DOD concurred with our recommendation that the Executive Committee
track action items and noted that it will recommend that the Program
Executive Officer establish a Web-based tracking system so that all
agencies can review the action items and their status.
Regarding our recommendation to identify the desired outcomes,
responsible parties, and time frames associated with the Committee's
corrective actions, DOD partially concurred and noted that the tri-
agency memorandum of agreement empowers the System Program Director and
Program Executive Officer to achieve successful outcomes. While we
agree that the memorandum establishes these executives'
responsibilities, it is the responsibility of the Executive Committee
to define expectations associated with their directed actions--
including desired outcomes, who is accountable, and time frames for
completion. In past Executive Committee meetings, these expectations
have not been defined.
DOD partially concurred with our recommendation to establish time
frames for escalating risks to the Executive Committee, and noted that
the Program Executive Officer should be able to do so. However, DOD
expressed concern that interference by the other agencies had weakened
the Program Executive Officer's ability to perform as intended. We
acknowledge that there is a disagreement among the three agencies on
the appropriate level of oversight of the program; however, we believe
that one of the roles of the Executive Committee members should be to
ensure that risks are escalated in a timely manner. Until time frames
are established, risks may continue to linger unresolved at the program
level.
We are sending copies of this report to interested congressional
committees, the Secretary of Commerce, the Secretary of Defense, the
Administrator of NASA, the Director of the Office of Management and
Budget, and other interested parties. In addition, this report will be
available on the GAO Web site at [hyperlink, http://www.gao.gov].
If you have any questions about this report, please contact me at (202)
512-9286 or at pownerd@gao.gov. Contact points for our Offices of
Congressional Relations and Public Affairs may be found on the last
page of this report. GAO staff who made major contributions to this
report are listed in Appendix VI.
Signed by:
David A. Powner:
Director, Information Technology Management Issues:
List of Congressional Requesters:
The Honorable Brian Baird:
Chairman:
The Honorable Bob Inglis:
Ranking Member:
Subcommittee on Energy and Environment:
Committee on Science and Technology:
House of Representatives:
The Honorable Brad Miller:
Chairman:
The Honorable Paul Broun, Jr.
Ranking Member:
Subcommittee on Investigations and Oversight:
Committee on Science and Technology:
House of Representatives:
The Honorable F. James Sensenbrenner, Jr.
House of Representatives:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
Our objectives were to (1) identify the status and risks of key
National Polar-orbiting Operational Environmental Satellite System
(NPOESS) program components, (2) assess the NPOESS Executive
Committee's ability to fulfill its responsibilities, and (3) evaluate
efforts to identify an alternative system integrator for later NPOESS
satellites.
To evaluate the status and risks of key program components, we reviewed
briefings and monthly program management reports. We analyzed earned
value management data to assess the contractors' performance against
cost and schedule estimates and evaluated reasons for variances in the
contractors' performance. We obtained adequate assurance that these
agency-provided data had been tested and were sufficient for our
assessment purposes. We reviewed cost reports and program risk
management documents and interviewed program officials to determine
program and program segment risks that could negatively affect the
program's ability to maintain the current schedule and cost estimates.
We also interviewed agency officials from the Department of Defense
(DOD), National Aeronautics and Space Administration (NASA), and
National Oceanic and Atmospheric Administration (NOAA) and the NPOESS
program office to determine the status and risks of the key program
segments. We interviewed senior-level officials representing the prime
contractor and the subcontractor responsible for developing a critical
sensor. We also observed senior-level management review meetings to
obtain information on the status of the NPOESS program.
To assess the NPOESS Executive Committee's ability to fulfill its
responsibilities, we reviewed the presidential directive that
established NPOESS and the 1995 and 2008 memorandums of agreement
signed by all three agencies to determine the responsibilities and
membership of the Executive Committee. We analyzed Executive Committee
meeting minutes to determine the attendees of the meetings, the action
items that were identified, and whether those action items were tracked
to closure. We reviewed monthly briefings from the Program Executive
Officer's Program Management Council to identify the key risks and
issues facing the program. We then compared these risks and issues to
the matters brought to the Executive Committee's attention in monthly
letters and meeting minutes to determine whether those risks were
escalated. In addition, we analyzed the Executive Committee's response
to the identified risks and issues to determine whether and how the
Committee responded. Finally, we interviewed senior officials in the
NPOESS program office and program executive office.
To evaluate efforts to identify an alternative system integrator for
later NPOESS satellites, we reviewed the Acquisition Decision
Memorandum that identified the need for a study of alternatives. We
reviewed briefings from two alternative management studies and analyzed
the alternatives presented in those briefings. We reviewed program
plans and status for addressing the recommendations of those studies.
We interviewed the chair of the 2008 alternative management study and
senior officials from the NPOESS program office regarding steps taken
to close the studies' recommendations. We also interviewed the Program
Executive Officer to understand the next steps to be taken by the
program.
We primarily performed our work at the NPOESS Integrated Program Office
and at DOD, NASA, and NOAA offices in the Washington, D.C.,
metropolitan area. In addition, we conducted work at the Los Angeles,
California, facilities of the prime contractor, the subcontractor
responsible for a critical sensor, and the Defense Contract Management
Agency groups overseeing those contractors. We conducted this
performance audit from October 2008 to June 2009 in accordance with
generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings and
conclusions based on our audit objectives. We believe that the evidence
obtained provides a reasonable basis for our findings and conclusions
based on our audit objectives.
[End of section]
Appendix II: Summary of the Fall 2008 Independent Review Team's
Findings and Recommendations:
To address programwide risks and challenges, the National Polar-
orbiting Operational Environmental Satellite System (NPOESS) Executive
Committee sponsored an independent review of the program in Fall 2008.
In March 2009, the independent review team reported on its findings to
the Executive Committee.[Footnote 25] Its findings were that:
* the program has a low probability of success in its current
configuration;
* the program, as configured after the Nunn-McCurdy certification,
places continuity of data at high risk because of the inability to
recover from a launch or spacecraft failure;
* cost has become the most important parameter, over mission success;
* the Executive Committee is at best inefficient;
* the program office suffers from a lack of space acquisition
infrastructure typically found at space acquisition centers;
* the program is making questionable decisions because of the pressure
put on it by near-term budget needs;
* the highest probability of success is with the current contractor
team for both NPOESS and the Visible/infrared imager radiometer suite;
* the NPOESS Preparatory Project (NPP) satellite is an operational
asset;
* the priorities of the Air Force and the National Oceanic and
Atmospheric Administration are not aligned; and:
* the current budget is inadequate.
To address these findings, the independent review team recommended that
the Committee:
* address the continuity issues by defining the "right" program to meet
the country's weather and climate needs;
* determine how to co-locate the program office at an acquisition
center;
* determine an appropriate budget for the program;
* accelerate the schedule of the third and fourth NPOESS satellites;
* use NPP data operationally;
* assess whether to launch NPP on schedule or on an anticipated need
date for the data;
* change the culture to put mission need first;
* stop looking at options for VIIRS and NPOESS; and:
* either fund the program at an 80 percent confidence level or reduce
the content of the program so that it can be funded at an 80 percent
confidence instead of a 50 percent confidence level.[Footnote 26]
[End of section]
Appendix III: Comments from the Department of Commerce:
United States Department Of Commerce:
The Secretary of Commerce:
Washington, D.C. 20230:
June 1, 2009:
Mr. David A. Powner Director:
Information Technology:
Management Issues:
U.S. Government Accountability Office:
441 G Street, NW:
Washington, DC 20548:
Dear Mr. Powner:
Thank you for the opportunity to review and comment on the Government
Accountability Office's draft report entitled Polar-orbiting
Environmental Satellites: With Costs Increasing and Data Continuity at
Risk Improvements Needed in Tri-agency Decision Making (GAO-09-564). On
behalf of the Department of Commerce, I have enclosed the National
Oceanic and Atmospheric Administration's programmatic comments to the
draft report.
Sincerely:
Signed by:
Gary Locke:
Enclosure:
[End of letter]
Department of Commerce:
National Oceanic and Atmospheric Administration:
Comments on the Draft GAO Report Entitled "Polar-orbiting Environmental
Satellites: With Costs Increasing and Data Continuity at Risk,
Improvements Needed in Tri-agency Decision-Making" (GAO-09-564, June
2009):
General Comments:
The Department of Commerce (DOC) and the National Oceanic and
Atmospheric Administration (NOAA) appreciate the opportunity to review
this report on the National Polarorbiting Operational Environmental
Satellite System (NPOESS) program. The Government Accountability Office
(GAO) makes six recommendations that it anticipates will improve the
effectiveness and efficiency of the tri-agency Executive Committee
(EXCOM). The first recommendation is directed to the Secretary of
Defense, while the remaining five recommendations are directed to DOC
as well as to the Department of Defense (DoD) and the National
Aeronautics and Space Administration (NASA). Overall, the report was
fair and balanced in assessing the status and risks of key program
components. DOC is committed to successfully executing the NPOESS
program.
NOAA Response to GAO Recommendations:
The draft GAO report states, "We are also recommending that the
Secretaries of Defense and Commerce and the Administrator of NASA
direct the NPOESS Executive Committee to take the following five
actions:"
Recommendation 2: "Establish a realistic timeframe for revising the
program's cost and schedule baselines."
NOAA Response: NOAA concurs with this recommendation. The NPOESS
Integrated Program Office is developing an updated program office
estimate for a revised acquisition program baseline as required by DoD
acquisition regulation. However, a revised program cost and schedule
estimate will be established later this year following a robust
independent cost analysis of recommended programmatic and acquisition
alternatives that better reflect a budget with appropriate contingency
funding to reduce risk. The revised program cost and schedule estimates
will be ready for initial EXCOM review in late summer 2009. The updated
acquisition program baseline review process should subsequently be
completed in fall 2009.
Recommendation 3: "Develop plans to mitigate the risk of gaps in
satellite continuity."
NOAA Response: NOAA concurs with this recommendation. The NPOESS
Preparatory Project (NPP) sensors are capable of producing data that
meet or exceed the data provided by NOAA-19, our current operational
satellite. Accordingly, to mitigate the potential gap in polar
environmental satellite data coverage in the afternoon orbit between
NOAA-19 and NPOESS C1, NOAA plans to make operational use of the data
from the NPP spacecraft and increase the number of products NOAA had
planned to generate from the NPP system as a risk reduction mission to
minimize impacts to NOAA's National Weather Service and other users.
Specifically, NOAA will accelerate development of 54 polar legacy
products. Previously, 19 legacy products were expected from NPP, with
an increase to 54 products in the NPOESS C1 era. NOAA will enhance its
NPP data processing ground system with sufficient infrastructure to
support the additional 35 products and 24/7 operations and support.
In the mid-morning orbit, NOAA will continue through the next decade to
process and deliver environmental products to its customers from the
U.S. and European instruments on board the European Organisation for
the Exploitation of Meteorological Satellites (EUMETSAT) MetOp series
of satellites.
NOAA will assess the use of additional international and interagency
assets as well as potential development of spare satellites and
instruments. The cost and schedule details associated with these
contingency options are currently under review. Any alternative
decision will ultimately be made consistent with results of the
Visible/Infrared Imager/Radiometer Suite (VIIRS) instrument testing
that is currently underway.
Recommendation 4: "Track the Committee's action items from inception to
closure."
NOAA Response: NOAA concurs with this recommendation. NOAA will task
the NPOESS Program Executive Officer (PEO) to ensure that Executive
Committee (EXCOM) action items are clearly and completely defined;
assigned to responsible parties for completion within a specific
timeframe; and tracked to completion, including reporting the results
to the EXCOM. NOAA will monitor EXCOM action items through the NOAA
Program Management Council and take corrective actions needed to ensure
action item coordination and closure.
Recommendation 5: "Improve the Committee's ability to achieve
successful outcomes by identifying the desired outcome associated with
each of the Committee actions, as well as timeframes and responsible
parties, when new action items are established."
NOAA Response: NOAA concurs with this recommendation. NOAA will task
the PEO to ensure EXCOM action items and desired outcomes are clearly
and completely defined; assigned to responsible parties for completion
within a specific timeframe; and tracked to completion, including
reporting the results to the EXCOM. NOAA will monitor EXCOM action
items through the NOAA Program Management Council and take corrective
actions needed to ensure successful outcomes.
Recommendation 6: "Improve the Committee's efficiency by establishing
timeframes for escalating risks to the Committee for action so that
they do not linger unresolved at the program executive level."
NOAA Response: NOAA concurs with this recommendation. The PEO will
ensure that resolution plans and schedules are established and tracked
at the PEO's monthly management council. NOAA will work with NASA and
DoD to ensure that the PEO establishes clear criteria and timeframes
for elevating risks to the EXCOM for action. NOAA will monitor PEO
action items and issue resolution through the NOAA Program Management
Council and the tri-agency NPOESS Oversight Council (NOC) to take
corrective actions needed to ensure timeliness in addressing escalating
risks.
Note: The NOC, established in the spring of 2009, is the tri-agency
council that reviews the NPOESS program on a more recurrent basis than
the senior-level EXCOM. The NOC, which reports to the EXCOM, is co-
chaired by NOAA's Deputy Under Secretary of Commerce for Oceans and
Atmosphere, the Deputy Under Secretary of the Air Force, and the Deputy
Administrator of NASA. These members are responsible for representing
their agencies and providing a reasonable representation of their EXCOM
position to ensure that issues and actions are responded to in a timely
manner.
[End of section]
Appendix IV: Comments from the Department of Defense:
Office Of The Assistant Secretary Of Defense:
Networks And Information Integration:
6000 Defense Pentagon:
Washington, DC 20301-6000:
May 28, 2009:
Mr. David A. Powner:
Director, Information Technology and Management Issues:
U.S. Government Accountability Office:
441 G Street, N.W.
Washington, D.C. 20548:
Dear Mr. Powner:
This is the Department of Defense (DoD) response to the Government
Accountability Office (GAO) draft report, GAO-09-564, "Polar-Orbiting
Environmental Satellites: With Costs Increasing and Data Continuity at
Risk, Improvements Needed in Tri-agency Decision Making" dated May 1,
2009 (GAO Code 310890). The DoD acknowledges receipt of the Draft
report.
Sincerely,
Signed by:
Dr. Ronald C. Jost
Deputy Assistant Secretary of Defense (C3, Space and Spectrum):
Enclosure(s): As stated:
[End of letter]
GAO Draft Report Dated May 1, 2009:
GAO-09-564 (GAO Code 310890):
"Polar-Orbiting Environmental Satellites: With Costs Increasing And
Data Continuity At Risk, Improvements Needed In Tri-Agency Decision
Making"
Department Of Defense Comments To The GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretary of Defense
direct the Under Secretary of Defense for Acquisition, Technology and
Logistics to attend and participate in National Polar-orbiting
Operational Environmental Satellite System (NPOESS) Executive Committee
meetings. (p. 32/GAO Draft Report)
DOD Response: Partially concur. The recently confirmed Under Secretary
of Defense for Acquisition, Technology and Logistics (USD AT&L) as the
Milestone Decision Authority for NPOESS, will evaluate the necessity to
attend and participate in all future Executive Committee (EXCOM)
meetings. The Memorandum of Agreement (MOA) between the Department of
Commerce, Department of Defense, and National Aeronautics and Space
Administration clearly defines the responsibilities of the EXCOM,
Integrated Program Office (IPO), Program Executive Officer (PEO), and
System Program Director (SPD). The Under Secretary of the Air Force
attends EXCOM meetings on behalf of USD AT&L as delegated on 03 June
2002. The SecAF is the DoD lead for acquisition execution review,
funding and manpower, as well as the lead service for operational
weather products for the DoD.
Recommendation 2: The GAO recommends that the Secretary of Defense
direct the NPOESS Executive Committee to establish a realistic
timeframe for revising the program's cost and schedule baselines. (p.
32/GAO Draft Report)
DOD Response: Partially concur. Per the Memorandum of Agreement (18 Dec
2008), "The Under Secretary of Commerce for Oceans and Atmosphere, the
Under Secretary of Defense for Acquisition, Technology, and Logistics,
and the NASA Administrator will form the NPOESS EXCOM. Each EXCOM
member will be accountable to the EXCOM for his/her agency's support of
the NPOESS program." The DoD EXCOM member will continue to monitor and
review the NPOESS program cost and schedule updates to the baseline
from the PEO quarterly.
Recommendation 3: The GAO recommends that the Secretary of Defense
direct the NPOESS Executive Committee to develop plans to mitigate the
risk of gaps in satellite continuity. (p. 32/GAO Draft Report)
DOD Response: Partially concur. The EXCOM should direct the program
office to establish plans to mitigate the risk gaps in satellite
continuity as indicated in this report. The EXCOM can review the
program's risk mitigation plan and modify as necessary.
Recommendation 4: The GAO recommends that the Secretary of Defense
direct the NPOESS Executive Committee to track the Committee's action
items from inception to closure. (p. 33/GAO Draft Report)
DOD Response: Concur. To accomplish this, the DOD recommends the PEO
establish a web-based tracking system such that all agencies can review
action items from inception to closure.
Recommendation 5: The GAO recommends that the Secretary of Defense
direct the NPOESS Executive Committee to improve the Committee's
ability to achieve successful outcomes by identifying the desired
outcome associated with each of the Committee actions, as well as
timeframes and responsible parties, when new action items are
established. (p. 33/GAO Draft Report)
DOD Response: Partially concur. The DOD believes the MOA establishes
responsibilities that empower responsible individuals (e.g. PEO, SPD)
to achieve successful outcomes. The MOA states, "The SPD will direct
and manage the NPOESS IPO with immediate oversight of the PEO. The SPD
is ultimately responsible to the EXCOM for the conduct of the NPOESS
program and will be granted the decision authority deemed necessary to
execute the program. The SPD will also coordinate decisions on NPOESS
matters that affect DOC, NASA, and DoD with the PEO to ensure
resolution and coordination of all major decisions." Furthermore, the
EXCOM will "exercise oversight authority over the program through the
PEO ". The DOD EXCOM member will support Committee actions and will be
responsive to the PEO's recommendations.
Recommendation 6: The GAO recommends that the Secretary of Defense
direct the NPOESS Executive Committee to improve the committee's
efficiency by establishing timeframes for escalating risks to the
Committee for action so that they do not linger unresolved at the
program executive level. (p. 33/GAO Draft Report)
DOD Response: Partially concur. The DOD agrees that issues that are
unresolved at the program execution level should be brought to the
EXCOM and efficiently acted upon. As a DOD led acquisition, the PEO
structure is in place to manage program risks. As such, the PEO has the
responsibility to follow the traditional DOD streamlined acquisition
supervision channels between the PEO and MDA. The object of this
streamlined channel is to improve ability of MDA-PEO chain to pass
clear unfiltered information up/subsequent acquisition guidance down.
Impact of additional entities in PEO-MDA chain, contrary to approved
MOA Amendment, has apparently weakened PEO oversight (as highlighted in
the Alternative Management Structure Study of 2008).
[End of section]
Appendix V: Comments from the National Aeronautics and Space
Administration:
National Aeronautics and Space Administration:
Office of the Administrator:
Washington, DC 20546-0001:
May 29, 2009:
Mr. David A. Powner:
Director:
Information Technology Management Issues:
United States Government Accountability Office:
Washington, DC 20548:
Dear Mr. Powner:
NASA appreciates the opportunity to comment on your draft report
entitled, "Polarorbiting Environmental Satellites: With Costs
Increasing and Data Continuity at Risk, Improvements Needed in Tri-
agency Decision Making," (GAO-09-564).
In the draft report, GAO makes a total of six recommendations intended
to improve the timeliness and effectiveness of acquisition decision-
making on the National Polar-orbiting Operational Environmental
Satellite System (NPOESS) program. Below is NASA's response to the five
recommendations which were addressed directly to the Agency:
Recommendations 2 and 3: (1) Establish a realistic timeframe for
revising the program's cost and schedule baselines; and (2) develop
plans to mitigate the risk of gaps in satellite continuity.
Response: Concur. We have been working closely with the National
Oceanic and Atmospheric Administration (NOAA) and the Department of
Defense (DoD) to develop a viable course of action to address both of
these concerns. The NPOESS program continues to struggle with the
impacts of persistent delays caused by the late deliveries of key
instruments. As you know, this has significantly impacted the launch
readiness date for our NPOESS Preparatory Project (NPP) Mission,
causing near-term concerns about data continuity with the on-orbit Aqua
Satellite. NASA has been actively supporting the tri-agency assessment
efforts that are studying the possible options for a path forward for
NPOESS and will continue to do so.
Recommendation 4: Track the Committee's action items from inception to
closure.
Response: Concur. We agree with your recommendation that the Executive
Committee (EXCOM) maintain a status of action items established during
the quarterly EXCOM meetings and track these items from inception to
closure. We will work with the Program Executive Officer for
Environmental Satellites (PEO) to ensure that the necessary controls
and processes are established.
Recommendation 5: Improve the Committee's ability to achieve successful
outcomes by identifying the desired outcome associated with each of the
Committee actions, as well as timeframes and responsible parties, when
new action items are established.
Response: Concur. We agree with your recommendation to establish
desired outcomes, timeframes, and responsible parties for the actions
taken during the EXCOM meetings. Again, we will work with the PEO to
ensure that the actions are fully documented and recorded in the
minutes to the EXCOM meetings.
Recommendation 6: Improve the Committee's efficiency by establishing
timeframes for escalating risks to the Committee for action so that
they do not linger unresolved at the program executive level.
Response: Concur. We agree with your concerns and recommendation
regarding unresolved program risks and the escalation of risks to the
EXCOM. Although many risks can be adequately managed at the PEO or
Systems Program Director (SPD) level, there are some risks that would
benefit from escalation to the EXCOM level for tri-agency adjudication.
We will work with the PEO to ensure that these risks are escalated to
the EXCOM level when necessary.
NASA will continue to work with NOAA and the DoD toward the success of
the NPP and NPOESS programs. If you have any questions or require
additional information, please contact Andrew Carson at (202) 358-1702.
Thank you again for the opportunity to review this draft report, and we
are looking forward to your final report to Congress.
Sincerely,
Signed by
Charles H. Scales:
Associate Deputy Administrator:
[End of section]
Appendix VI: GAO Contact and Staff Acknowledgments:
GAO Contact:
David A. Powner, (202) 512-9286 or pownerd@gao.gov:
Staff Acknowledgments:
In addition to the contact named above, Colleen M. Phillips, Assistant
Director; Kate Agatone; Carol Cha; Neil Doherty; Kaelin P. Kuhn;
Kathleen S. Lovett; and Lee McCracken made key contributions to this
report.
[End of section]
Footnotes:
[1] GAO, Information Technology Investment Management: A Framework for
Assessing and Improving Process Maturity, [hyperlink,
http://www.gao.gov/products/GAO-04-394G] (Washington, D.C.: March
2004).
[2] GAO, Environmental Satellites: Polar-orbiting Satellite Acquisition
Faces Delays; Decisions Needed on Whether and How to Ensure Climate
Data Continuity, [hyperlink, http://www.gao.gov/products/GAO-08-899T]
(Washington, D.C.: June 19, 2008); Environmental Satellites: Polar-
orbiting Satellite Acquisition Faces Delays; Decisions Needed on
Whether and How to Ensure Climate Data Continuity, [hyperlink,
http://www.gao.gov/products/GAO-08-518] (Washington, D.C.: May 16,
2008); Environmental Satellite Acquisitions: Progress and Challenges;
[hyperlink, http://www.gao.gov/products/GAO-07-1099T] (Washington,
D.C.: July 11, 2007); Polar-orbiting Operational Environmental
Satellites: Restructuring Is Under Way, but Challenges and Risks
Remain, [hyperlink, http://www.gao.gov/products/GAO-07-910T]
(Washington, D.C.: June 7, 2007); Polar-orbiting Operational
Environmental Satellites: Restructuring Is Under Way, but Technical
Challenges and Risks Remain, [hyperlink,
http://www.gao.gov/products/GAO-07-498] (Washington, D.C.: Apr. 27,
2007); Polar-orbiting Operational Environmental Satellites: Cost
Increases Trigger Review and Place Program's Direction on Hold,
[hyperlink, http://www.gao.gov/products/GAO-06-573T] (Washington, D.C.:
Mar. 30, 2006); Polar-orbiting Operational Environmental Satellites:
Technical Problems, Cost Increases, and Schedule Delays Trigger Need
for Difficult Trade-off Decisions, [hyperlink,
http://www.gao.gov/products/GAO-06-249T] (Washington, D.C.: Nov. 16,
2005); Polar- orbiting Environmental Satellites: Information on Program
Cost and Schedule Changes, [hyperlink,
http://www.gao.gov/products/GAO-04-1054] (Washington, D.C.: Sept. 30,
2004); Polar-orbiting Environmental Satellites: Project Risks Could
Affect Weather Data Needed by Civilian and Military Users, [hyperlink,
http://www.gao.gov/products/GAO-03-987T] (Washington, D.C.: July 15,
2003); and Polar-orbiting Environmental Satellites: Status, Plans, and
Future Data Management Challenges, [hyperlink,
http://www.gao.gov/products/GAO-02-684T] (Washington, D.C.: July 24,
2002).
[3] The European MetOp program is a series of three polar-orbiting
satellites dedicated to operational meteorology. MetOp satellites are
planned to be launched sequentially over 14 years. The first of these
satellites was launched in 2006 and is currently operational.
[4] Presidential Decision Directive NSTC-2, May 5, 1994.
[5] The Under Secretary of Defense for Acquisition, Technology, and
Logistics delegated the responsibility for attending the meetings--but
not the authority to make acquisition decisions--to the Under Secretary
of the Air Force.
[6] The four sensors are the Visible/infrared imager radiometer suite,
the Cross-track infrared sounder, the Advanced technology microwave
sounder, and the Ozone mapper/profiler suite. NPP will now also host
the Clouds' and earth's radiant energy system sensor.
[7] In general, satellite experts anticipate that roughly 1 out of
every 10 satellites will fail either during launch or during early
operations after launch.
[8] [hyperlink, http://www.gao.gov/products/GAO-06-573T], [hyperlink,
http://www.gao.gov/products/GAO-06-249T], [hyperlink,
http://www.gao.gov/products/GAO-04-1054], [hyperlink,
http://www.gao.gov/products/GAO-03-987T], and [hyperlink,
http://www.gao.gov/products/GAO-02-684T].
[9] 10 U.S.C. § 2433 is commonly referred to as Nunn-McCurdy.
[10] 10 U.S.C. § 2433 has recently been amended by Pub. L. No. 109-163,
§ 802 (Jan. 6, 2006) and Pub. L. No. 109-364, § 213 (a) (Oct. 17,
2006). The law now also includes cost growth thresholds from the
program's original baseline.
[11] DOD estimated that the acquisition portion of the certified
program would cost $11.5 billion. The acquisition portion includes
satellite development, production, and launch, but not operations and
support costs after launch. When combined with an estimated $1 billion
for operations and support after launch, this brings the program life
cycle cost to $12.5 billion.
[12] [hyperlink, http://www.gao.gov/products/GAO-08-899T].
[13] [hyperlink, http://www.gao.gov/products/GAO-07-498].
[14] [hyperlink, http://www.gao.gov/products/GAO-08-518].
[15] These estimates are subject to further refinement because the
Executive Committee has not agreed on a cost estimating methodology and
the agencies have not yet agreed to new information security
requirements.
[16] This cost estimate includes launch vehicle costs of approximately
$329 million, which are funded outside the program's baseline.
[17] [hyperlink, http://www.gao.gov/products/GAO-06-249T].
[18] The 1995 agreement specified that the NASA member would be the
Deputy Administrator. Responsibility was subsequently taken over by the
Administrator of NASA.
[19] According to DOD, the milestone decision authority is the
designated individual who has overall responsibility for an investment.
This person has the authority to approve a major acquisition program's
progression in the acquisition process and is responsible for reporting
cost, schedule, and performance results.
[20] The 1995 and 2008 memorandums of agreement differ slightly in this
regard. The first agreement stated that DOD's milestone decision
authority will make acquisition decisions with concurrence of the other
Executive Committee members while the second agreement states that the
DOD authority must consider committee decisions. The second agreement
takes precedence in the case of a conflict.
[21] [hyperlink, http://www.gao.gov/products/GAO-04-394G].
[22] The program subsequently reported that 12 of the 18 action items
have been closed and that 6 are in progress.
[23] [hyperlink, http://www.gao.gov/products/GAO-04-394G].
[24] DOD directive 5000.55 section E2.1.43 states that a Program
Executive Officer only reports to and receives guidance and direction
from the DOD component acquisition executive. Also, the 2008 tri-agency
memorandum of agreement reiterates that the Program Executive Officer
reports directly to and takes direction from the Executive Committee.
[25] The independent review team has provided briefings on its findings
and recommendations, but as of the first week of June 2009, had not yet
released its final report.
[26] A 50 percent level of confidence indicates that a program has a 50
percent chance that the program will be delivered at the identified
cost.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: