Missile Defense
European Phased Adaptive Approach Acquisitions Face Synchronization, Transparency, and Accountability Challenges
Gao ID: GAO-11-179R December 21, 2010
This report formally transmits our briefing on acquisition management for the European Phased Adaptive Approach (EPAA). This is one of two products we are issuing in response to congressional October 13, 2009 request that we evaluate the Department of Defense's (DOD) plans for implementing EPAA. We provided congressional staff a draft copy of this briefing in a meeting with them on September 22, 2010. We do not make any recommendations in the briefing. We will issue a final report on broader issues of European missile defense that will include the material in the briefing. That final product will have recommendations, as appropriate. For the briefing we sought to answer two questions: (1) What key acquisition planning and management practices are in place for EPAA? (2) Are there near-term development risks for EPAA?
In response to changing threats in the region and new opportunities created by advances in missile defense technology, in September 2009 the President announced a new policy for missile defense of Europe, called the European Phased Adaptive Approach, or EPAA. DOD has emphasized the benefits of a policy of regional phased adaptive approaches, stating that it does not require a globally integrated missile defense architecture and that it relies on proven solutions. According to DOD, because EPAA is a policy, not a separate missile defense acquisition program, DOD intends to use the department's existing processes for managing missile defense acquisitions and the existing BMDS element-based acquisition approach for missile defense system elements---not one specific to EPAA--to approve system acquisitions. However, we found that DOD has not fully implemented a management process that synchronizes EPAA acquisition activities and ensures transparency and accountability. DOD has made progress in acquisition planning for technology development and systems engineering and testing and partial progress in defining requirements and identifying stakeholders but has not yet developed an EPAA acquisition decision schedule or an overall EPAA investment cost. The limited visibility into the costs and schedule for EPAA and the lack of some key acquisition management processes we found reflect the oversight challenges with the acquisition of missile defense capabilities that we have previously reported. The consequences of these issues have included: (1) limited means of independently assessing progress and a limited basis for oversight and (2) going into production before fully demonstrating system performance, leading to rework, cost increases, delays, and uncertainties about delivered capabilities. The flexibility desired by DOD is not incompatible with appropriate visibility into key aspects of acquisition management. As DOD proceeds with the EPAA acquisition activities, it is important for Congress and the President to have assurance that the EPAA policy is working as intended and that acquisition activities are cost-effective.
GAO-11-179R, Missile Defense: European Phased Adaptive Approach Acquisitions Face Synchronization, Transparency, and Accountability Challenges
This is the accessible text file for GAO report number GAO-11-179R
entitled 'Missile Defense: European Phased Adaptive Approach
Acquisitions Face Synchronization, Transparency, and Accountability
Challenges' which was released on December 21, 2010.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
GAO-11-179R:
United States Government Accountability Office:
Washington, DC 20548:
December 21, 2010:
The Honorable James R. Langevin:
Chairman:
The Honorable Michael R. Turner:
Ranking Member:
Subcommittee on Strategic Forces:
Committee on Armed Services:
House of Representatives:
Subject: Missile Defense: European Phased Adaptive Approach
Acquisitions Face Synchronization, Transparency, and Accountability
Challenges:
This report formally transmits our briefing on acquisition management
for the European Phased Adaptive Approach (EPAA) (see enclosure I).
This is one of two products we are issuing in response to your October
13, 2009 request that we evaluate the Department of Defense's (DOD)
plans for implementing EPAA. We provided your staff a draft copy of
this briefing in a meeting with them on September 22, 2010. We do not
make any recommendations in the briefing. We will issue a final report
on broader issues of European missile defense that will include the
material in the briefing. That final product will have
recommendations, as appropriate.
Objectives, Scope and Methodology:
For the briefing we sought to answer two questions: (1) What key
acquisition planning and management practices are in place for EPAA?
(2) Are there near-term development risks for EPAA?
To answer the first question on acquisition management practices, we
synthesized management and oversight criteria from the Office of
Management and Budget, DOD, the Missile Defense Agency (MDA), and GAO
best acquisition practices for large acquisition to determine key
management principles. We then compared EPAA acquisition efforts to
these principles. To determine the status of DOD's efforts, we
reviewed DOD and MDA documentation related to EPAA, including the
Ballistic Missile Defense Review Report and MDA's Ballistic Missile
Defense System (BMDS) Accountability Report. We met with MDA and
Office of the Secretary of Defense officials. We also visited U.S.
European Command and U.S. Strategic Command to understand their needs.
To answer the second question on near-term development risks, we
reviewed MDA's BMDS acquisition documentation, including the
integrated master test plan and budget documents. We met with
officials from MDA directorates and element program offices as well as
the Office of the Under Secretary of Defense for Policy and the Under
Secretary of Defense for Acquisition, Technology and Logistics, and
visited contractor facilities. We also used prior GAO work regarding
best acquisition practices to assess those risks.
We conducted this performance audit from March 2010 to November 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
Summary of Results:
In response to changing threats in the region and new opportunities
created by advances in missile defense technology, in September 2009
the President announced a new policy for missile defense of Europe,
called the European Phased Adaptive Approach, or EPAA.DOD has
emphasized the benefits of a policy of regional phased adaptive
approaches, stating that it does not require a globally integrated
missile defense architecture and that it relies on proven solutions.
According to DOD, because EPAA is a policy, not a separate missile
defense acquisition program, DOD intends to use the department's
existing processes for managing missile defense acquisitions and the
existing BMDS element-based acquisition approach for missile defense
system elements---not one specific to EPAA--to approve system
acquisitions.
However, we found that DOD has not fully implemented a management
process that synchronizes EPAA acquisition activities and ensures
transparency and accountability. DOD has made progress in acquisition
planning for technology development and systems engineering and
testing and partial progress in defining requirements and identifying
stakeholders but has not yet developed an EPAA acquisition decision
schedule or an overall EPAA investment cost. The limited visibility
into the costs and schedule for EPAA and the lack of some key
acquisition management processes we found reflect the oversight
challenges with the acquisition of missile defense capabilities that
we have previously reported. The consequences of these issues have
included:
* limited means of independently assessing progress and a limited
basis for oversight and:
* going into production before fully demonstrating system performance,
leading to rework, cost increases, delays, and uncertainties about
delivered capabilities.
The flexibility desired by DOD is not incompatible with appropriate
visibility into key aspects of acquisition management. As DOD proceeds
with the EPAA acquisition activities, it is important for Congress and
the President to have assurance that the EPAA policy is working as
intended and that acquisition activities are cost-effective.
Agency Comments and Our Evaluation:
DOD provided us written comments on a draft of this briefing. These
comments are reprinted in enclosure II.
In its comments, the department stated that it disagreed with GAO's
approach to assess EPAA as what it termed a "near-distinct" element of
the Ballistic Missile Defense System, rather than DOD's decision to
employ the department's existing processes. As we have consistently
reported, the department's existing processes for developing and
acquiring missile defense have transparency and accountability issues
that limit oversight and preclude assessing overall progress as well
as limiting opportunities for constructive action to put programs in a
better position to succeed. The six key principles we used in our
review to assess the department's planning and management of
acquisition processes for EPAA are embedded in the department's
acquisition guidance as well as the Office of Management and Budget's
guidance for capital programming across federal agencies, particularly
as it relates to bringing together and synchronizing multiple
development efforts. Although we understand that EPAA is a policy
approach, not an acquisition program, it nonetheless represents an
arrangement of significant investments, it requires a high degree of
coordination and technical integration, and the progress implementing
EPAA continues to be of congressional interest. Thus, we continue to
believe these acquisition management principles serve as a useful,
appropriate and beneficial standard by which to assess the
department's approach to managing EPAA acquisitions.
The department also stated that GAO inaccurately portrayed DOD's
acquisition plans as inadequate to making capability available to the
warfighter should requests for deployment come from combatant
commanders. The acquisition issues with individual systems reported in
the briefing are risks, not certainties. As we have stated in the
briefing and throughout our body of work on acquisition of missile
defense capabilities, the department does not take a knowledge-based
approach toward missile defense development--which involves developing
firm requirements, ensuring a resource requirements match, and
starting with mature technologies, among other steps. We have found
that attaining high levels of knowledge at key junctures in
development is an attribute of successful acquisitions. Instead, the
highly concurrent development, production and deployment effort DOD is
undertaking in the BMDS increases risks that the capability eventually
provided will not meet the warfighter's needs, with significant
potential cost and schedule growth consequences.
We also received technical comments from DOD, which have been
addressed in the briefing, as appropriate. Our quality standards
require that we solicit technical comments on draft products to ensure
the accuracy of our findings. DOD and MDA submitted two sets of
technical comments for our review. We were only able to make
relatively small adjustments to the briefing because the department
was unable to substantiate most of the comments with sufficient
documentation.
The changes we did make to the briefing include additional context on
EPAA as well as additions that reflect the oversight and management
processes in place to guide decisions on EPAA. We also made minor text
changes at various locations throughout the briefing. Our conclusions,
however, remain the same.
We are sending copies of this report to the appropriate congressional
committees; the Secretary of Defense; the Under Secretaries of Defense
for Policy and for Acquisition, Technology and Logistics; and the
Director of the Missile Defense Agency. The report also is available
at no charge on the GAO Web site at [hyperlink, http://www.gao.gov].
Should you or your staff have any questions concerning this report,
please contact me at (202) 512-4841 or chaplainc@gao.gov. Contact
points for our Offices of Congressional Relations and Public Affairs
may be found on the last page of this report Key contributors to this
report include David Best, Assistant Director; Gwyneth Woolwine,
Analyst-in-Charge; Nick Cornelisse; Tana Davis; Meredith Kimmett;
Marie Mak; Wiktor Niewiadomski; John Pendleton; Robert Swierczek;
James P. Tallon; and Edwin Yuen.
Signed by:
Cristina Chaplain:
Director:
Acquisition and Sourcing Management:
Enclosures - 2:
[End of section]
Enclosure I:
Missile Defense European Phased Adaptive Approach:
Acquisitions Face Synchronization, Transparency, and Accountability
Challenges:
Prepared for the Subcommittee on Strategic Forces of the House
Committee on Armed Services:
Overview:
* Summary;
* Scope and Methodology;
* Background - European Phased Adaptive Approach;
* Objective 1 ” Managing EPAA Acquisitions;
* Objective 2 ” Near-Term EPAA System Development Risks;
* Concluding Observations.
Introduction:
Meeting the presidential direction to develop and field missile
defenses in Europe in four phases will require addressing significant
acquisition management and system development challenges.
* Acquisition management challenges are inherent to the European
Phased Adaptive Approach (EPAA) because acquisition activities of the
of Ballistic Missile Defense System (BMDS) elements comprising EPAA
must be synchronized to deliver the capabilities desired.
* System development challenges are inherent to EPAA because the EPAA
policy commits to delivering capabilities on a schedule that requires
concurrency among technology, design, testing, and other development
activities; this concurrency introduces risk of increased costs,
schedule delay, or performance shortfalls, which must be addressed.
Objectives:
What key acquisition planning and management practices are in place
for EPAA?
Are there near-term development risks for EPAA?
Summary: Preliminary Findings:
Objective 1:
* The Department of Defense (DOD) has not fully implemented a
management process that synchronizes EPAA acquisition activities and
ensures transparency and accountability. DOD has made progress in
acquisition planning for technology development and systems
engineering and testing and partial progress in defining requirements
and identifying stakeholders, but has not yet developed an EPAA
acquisition decision schedule or an overall EPAA investment cost.
Objective 2:
* The administration's EPAA policy committed DOD to a schedule that
could be challenging to meet based on the technical progress of
missile defense element development and testing programs, and
committed DOD to this schedule before the scope of the development
efforts was fully understood.
Scope and Methodology:
Management process to synchronize acquisitions: We synthesized
management and oversight principles from the Office of Management and
Budget, DOD, the Missile Defense Agency (MDA), and GAO best
acquisition practices for large acquisition efforts similar to EPAA.
We then compared EPAA acquisition efforts to these principles. To
determine the status of those efforts, we reviewed DOD and MDA
documentation related to EPAA, including the Ballistic Missile Defense
Review (BMDR) Report and MDA's BMDS Accountability Report (BAR). We
met with MDA and Office of the Secretary of Defense officials. We also
visited the U.S. European Command and U.S. Strategic Command.
Near-term development risks: To identify risks, we reviewed MDA's BMDS
acquisition documentation, including the integrated master test plan
and budget documents. We met with officials from MDA directorates and
element program offices as well as the Offices of the Under Secretary
of Defense for Policy and the Under Secretary of Defense for
Acquisition, Technology, and Logistics and visited contractor
facilities. We also used prior GAO work regarding best acquisition
practices to assess those risks.
We conducted this performance audit from March 2010 to November 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
Background: The President's EPAA Policy:
In response to changing threats in the region and new opportunities
created by advances in missile defense technology, in September 2009
the President announced a new policy for missile defense of Europe,
called the European Phased Adaptive Approach, or EPAA.
According to DOD, the EPAA policy was based primarily around an Aegis
Standard-Missile 3-based architecture in Europe and the need for a
flexible defense against an uncertain threat.
DOD describes the new approach as more cost effective because the SM-3
is less expensive than the ground-based interceptor that would be used
under the prior approach to the defense of Europe. In addition, DOD
believes the new approach is more resilient to changes in raid size
than the previous plan, which would only have had 10 interceptors in
Europe.
DOD states that EPAA's use of distributed, mobile, and relocatable
systems increases the system's survivability by making the assets more
difficult for an adversary to target.
BMDR Report: New Phased Adaptive Approaches at Core of Defending
against Regional Threats:
EPAA represents the first example of DOD's plan to adopt a new
regionally based approach to delivering missile defense capability; as
outlined in its first BMDR report published February 2010.
DOD has emphasized the benefits of a policy of regional phased
adaptive approaches (PAA), stating that it does not require a globally
integrated missile defense architecture and that it relies on proven
solutions.
According to DOD, the regionally based policy approach reflects the
commitment to significantly accelerate the acquisition and deployment
of mature systems and that the benefits of improving capabilities are
best ensured by tailoring regional deterrence and defense
architectures to the unique requirements of each region.
DOD Officials View Missile Defense Capabilities as a Tool Kit for the
Regional PAAs:
In the BMDR Report's new regional PAA policy context,
DOD views missile defense capabilities as a "tool kit:"
* MDA develops and acquires the systems, that is, the tools;
* The regional combatant commands select from among those tools to
address threats in their areas of responsibility; and;
* According to DOD, a comprehensive Global Force Management process
will be used to make decisions about system allocation and inventory.
DOD Plans to Use Existing Missile Defense Acquisition Management and
Oversight Processes for EPAA:
According to DOD, because EPAA is a policy, not a separate missile
defense acquisition program, DOD intends to use the department's
existing processes for managing missile defense acquisitions and the
existing BMDS element-based acquisition approach for missile defense
system elements-”not one specific to EPAA-”to approve system
acquisitions.
Among the department's existing missile defense acquisition management
roles, responsibilities and processes are the following:
Linking Acquisition to Policy:
* The Under Secretary of, Defense for Policy is responsible to ensure
consistency between missile defense policy and development and
acquisition plans and approaches.
Warfighter Desired Capabilities:
* The Chairman of the Joint Chiefs of Staff provides advice on desired
BMDS capabilities and characteristics.
* The Commander, U.S. Strategic Command, through the Chairman of the
Joint Chiefs of Staff coordinates development of the BMDS operational
architecture and advocates for combatant command-desired missile
defense characteristics and capabilities.
Missile Defense Acquisition Oversight:
* The Under Secretary of Defense for Acquisition, Technology and
Logistics:
- is responsible for overall management oversight of MDA,
- provides acquisition policy direction and program guidance and makes
production decisions,
- periodically determines the applicability of the department's
traditional acquisition process to MDA acquisition management,
[Footnote 1] and,
- chairs the Missile Defense Executive Board.
* The Missile Defense Executive Board (MDEB):
- recommends and oversees implementation of strategic policies and
plans, program priorities, and investment options,
- makes recommendations regarding the MDA comprehensive acquisition
strategy; and,
- oversees the annual preparation of the BMDS portfolio, including
required capabilities and a program plan to meet those requirements.
MDA's Acquisition Process for BMDS Elements:
MDA is responsible for the acquisition of the integrated BMDS,
comprised of individual BMDS elements”for example Aegis Ballistic
Missile Defense, Terminal High Altitude Area Defense, and ANITPY-2
radar.
The individual BMDS program elements have their own development paths
and schedules. According to the Director, MDA, there are several
venues that MDA uses to manage and oversee elements, including monthly
reviews with the Program Executive and quarterly reviews with the
Director.
Most elements are also reviewed annually as part of the preparation of
the BMDS Accountability Report (BAR).
* The BAR presents baseline parameters used to guide and track
development of BMDS capabilities and explains variances from the
established schedule, technical, and resource baselines.
* These baselines are new in the 2010 BAR; GAO will assess them in its
congressionally mandated review of MDA for fiscal year 2010.
Acquisition Activities to Implement EPAA:
The EPAA policy articulates a schedule for delivering four phases of
capability to defend Europe and augment current protection of the U.S.
homeland; Phase 1 in 2011, Phase 2 in 2015, Phase 3 in 2018, and Phase
4 in the 2020 time frames respectively.
The policy is structured around increasingly capable variants of the
Standard Missile 3 interceptor, together with sensors, command and
control, and other capabilities.
It is envisioned that each successive phase will deliver additional
capability with respect to both threat missile range and raid size.
DOD has not yet determined the full set of BMDS system elements that
will participate in EPAA or which of the four phases they will be part
of (see table on the following slide).
Table: Ballistic Missile Defense System Elements That May Comprise
EPAA:
Element: Command and Control, Battle Management, and Communications
(C2BMC);
Capability description: Integrating element provides deliberate
planning, situational awareness, sensor management, communications,
and battle management for the integrated BMDS.
Element: Sensors (AN/TPY-2, ABIR, PTSS);
Capability description: The Army Navy/Transportable Radar Surveillance
(AN/TPY-2) is an X-band, high resolution radar that can detect
missiles early in flight, provide precise tracking information to the
BMDS. Other sensors for EPAA may include the Airborne Infrared (ABIR)
and/or Precision Tracking Space System (PTSS) which would provide
persistent classification and global tracking capability.
Element: Aegis Ballistic Missile Defense (Aegis BMD);
Capability description: Midcourse engagement capability with Standard
Missile 3 to defeat short-, medium- and some intermediate-range
ballistic missiles. Has long range surveillance and track capability
which detects and tracks in early ascent phase, providing forward
based BMDS surveillance. Includes the sea and land-based variant
(known as Aegis Ashore).
Element: Terminal High Altitude Area Defense (THAAD);
Capability description: Ground-based system designed to destroy short-
and medium-range ballistic missiles during the late-midcourse and
terminal phases of flight. A THAAD battery consists of the THAAD
interceptor system and the AN/TPY-2 radar.
Source: GAO summary of MDA data.
[End of table]
[End of Background section]
Objective 1: Managing EPAA Acquisitions:
Key Principles for Synchronizing EPAA Acquisitions and Ensuring
Transparency and Accountability:
Given the range of assets involved (system variety and quantity), the
scale of the presidential policy commitment, and potential costs, a
management process that synchronizes EPAA acquisition activities and
provides enhanced transparency and accountability is important to
delivering the promised capability on time and cost effectively.
The following tables outline key acquisition principles that help
ensure synchronization, transparency and accountability and provide an
assessment of DOD's EPAA acquisition activities.
These principles are derived from prior GAO assessments of DOD systems
acquisition, as well as DOD and governmentwide acquisition guidance,
such as Office of Management and Budget Circular A-11's Capital
Program Guidance.
Key principles are as follows:
1. Defining the capability desired.
2. Identifying stakeholders and roles.
3. Developing integrated schedules and decision reviews.
4. Developing integrated plans for technology development and systems
engineering.
5. Establishing integrated test plans.
6. Estimating the total integrated investment.
Table: Defined Requirements:
Key principle: Well-defined requirements;
* Warfighter needs are the basis of the decision for developing and
producing a capability and for deciding the optimal type and quantity
of systems;
* A system's business case, as called for by best acquisition
practices, should provide demonstrated evidence that needs are real
and necessary and can best be met by the chosen concept.
Assessment of EPAA acquisition efforts: Ongoing;
* EPAA was generated by presidential direction versus the process for
warfighter involvement as laid out in MDA policies and directives for
missile defense acquisition;
* EPAA effectively started the acquisition process for European
capabilities; more detailed determination of desired capabilities is
in progress;
* Although DOD has begun to plan and implement EPAA, it has not yet
established architectures with systems and quantities for the
phases.
Source: GAO analysis of DOD data.
[End of table]
Table: Stakeholders and Roles:
Key principle: Stakeholders and decision makers identified and roles
defined;
* All elements of the business case should be agreed upon by major
stakeholders across the requirements, funding, acquisition, and
warfighting communities;
* Formal agreements among program managers, their acquisition
executives, and the user community setting forth common program goals.
Assessment of EPAA acquisition efforts: Ongoing;
* DOD and MDA policies identify stakeholders at various levels for
BMDS system element acquisitions;
* It is unclear how the responsibilities for EPAA acquisition as a
whole are divided and how those responsibilities will be executed.
Source: GAO analysis of DOD data.
[End of table]
Table: Integrated Schedule:
Key principle: Integrated schedule and decision reviews;
* Reviews of demonstrated progress and follow-on plans at defined
major decision points;
* Exit and entry criteria to show components ready to move from one
phase to next and component baseline is integrated within itself and
with the greater (BMDS) baseline.
Assessment of EPAA acquisition efforts: Not present;
* The MDEB, responsible for overseeing missile defense portfolio
capability developments, has focused its attention solely at the
element, not EPAA, level. DOD has not formally or fully aligned
acquisition programming to support EPAA or set acquisition decision
points for each phase;
* Decisions about production of systems do not appear to be fully
linked to the phases;
* EPAA policy defines the year a phase may deliver capability, but
MDA/DOD acquisition managers, stakeholders and Congress currently lack
an integrated EPAA-level view. According to DOD an integrated schedule
is being developed.
Source: GAO analysis of DOD data.
[End of table]
Table: Integrated Technology Development and System Engineering:
Key principle: Integrated planning for technology development and
systems engineering;
* Systems engineering activities”requirements analysis, design, and
testing”are needed to ensure that a weapon system program's
requirements are achievable and designable given available resources,
such as technologies;
* Systems engineering is to provide for integrating technical
processes and define and balance performance, cost, schedule, and risk
within a family of systems or system of systems.
Assessment of EPAA acquisition efforts: Present;
* In March 2010, MDA system engineering activities explicitly
incorporated EPAA as a "system" and included it in existing
engineering integration activities within the BMDS;
* MDA Systems Engineering has established a Master Integration Plan
that addresses EPAA and is coordinated with integrated testing.a
8We assessed this plan only for its alignment with EPAA, not for any
other purpose.
Source: GAO analysis of DOD data.
[End of table]
Table: Integrated Testing:
Key principle: Integrated planning for testing;
* Test and Evaluation Master Plan should contain integrated master
schedule;
* Major defense acquisition programs subject to interoperability
evaluations throughout life cycle to ensure validity to support
mission accomplishment.
Assessment of EPAA acquisition efforts: Present;
* We reported in February 2010 that MDA revised its testing approach
to better align tests with modeling and simulation needs;
* MDA's Integrated Master Test Plan has been updated to explicitly
align with DOD's new PAA and MDA is preparing an Integrated Master
Assessment Plan that is expected to further articulate testing and
assessment efforts.[A]
[A] We assessed this plan only for its alignment with EPAA, not for
any other purpose.
Source: GAO analysis of DOD data.
[End of table]
Table: Integrated View of Financial Commitment:
Key principle: Integrated investment view (costs);
* Baseline for total cost is a fundamental marker used to measure
progress, identify cost growth, and ensure that full resource
commitment is understood;
* The BMDR commits to develop and field capability that is "fiscally
sustainable over long-term."
Assessment of EPAA acquisition efforts: Not present;
* There is currently no basis for an accurate acquisition cost
estimate because DOD has not determined which BMDS elements will
comprise EPAA or their quantities, and the scope of technology
development for new and existing systems remains unclear;
* According to DOD, it is difficult to determine an accurate long-term
acquisition cost estimate because the EPAA describes a flexible versus
rigid architecture.
Source: GAO analysis of DOD data.
[End of table]
Previously Reported Transparency and Accountability Issues May
Continue with EPAA:
DOD emphasizes that EPAA is a policy, not a separate acquisition
program, and that the department's existing processes for managing
missile defense acquisition are sufficient for EPAA.
The acquisition activity required to meet the President's direction
poses complex synchronization, transparency, and accountability
challenges for the existing DS system element acquisition process.
These challenges are of particular concern in light of our past
findings regarding that process. Since our first report in 2004,
following the establishment of MDA, we have consistently found that:
* DOD has not taken a knowledge-based approach to missile defense
acquisition;
* DOD has used an approach for building cost, schedule, and
performance goals that yielded limited transparency and
accountability; and;
* DOD's decisions to manufacture, produce, and field missile defense
systems are outpacing testing, modeling, and validation, resulting in
decisions being made with limited understanding of system
effectiveness.
While DOD has worked to address some of our concerns, in February 2010
we reported that DOD continues to face challenges regarding
transparency and accountability, and that DOD is still proceeding with
production and fielding of BMDS despite developmental problems and
test delays.
[End of Objective 1 section]
Objective 2: System Development Risks:
Near-Term EPAA Development Risks:
* Compressed schedule for all assets;
* Interoperability for all assets;
* System-specific risks.
EPAA Policy Compresses Development Schedule:
A sound/executable acquisition has firm requirements, mature
technologies, and a strategy that provides sufficient time and money
for design activities before making the decision to start system
development and demonstration or to transition to production.
The administration's EPAA policy committed DOD to a schedule before
the scope of system development effort was fully understood.
DOD is working to develop plans for implementation within the
constraints of policy time frames; however, system schedules are
highly optimistic in technology development, testing, production, and
integration, leaving little room for potential delays.
As efforts to meet near-term commitments unfold, the schedule for
delivering capabilities may be difficult to achieve and resources
needed may grow.
System Interoperability and Assessment of Integrated System
Performance:
As a system of systems, the BMDS is expected to perform as a whole,
not just as the sum of its individual parts; thus technical
interoperability and integration among BMDS elements is key to whole
system performance.
The ability of testing and assessment plans to fully demonstrate BMDS
capabilities in a regional context is constrained by existing
limitations in models and simulations. These limitations include
incorrect representations of how BMDS elements are linked in the real
world and can result in overstating integrated system performance.
Interoperability with friends and allies is uncertain; who will
contribute, how, and the degree of technical feasibility and
investment to interoperate with other nations has yet to be determined.
C2BMC Development:
As the BMDS integrating element, C2BMC is expected to provide
planning, situational awareness, sensor management, and battle
management. Integration is a key feature”and because of C2BMC's role”
also a risk.
The system may not accurately group threat missile tracks to reduce
multiple cues from sensors about the tracks, and may present an
incorrect picture of the battlespace to BMDS "shooters." Data fusion
issues may delay the multiradar capability of the next version of the
system, while degrading sensor tasking, track forwarding, and
situational awareness. Execution of the current ground test campaign
is expected to provide additional data with which to assess these
risks.
Aegis Ashore: Development Uncertainties:
According to the Director, MDA, Aegis Ashore development is not a high
risk because it is based on the existing Aegis BMD system. Aegis BMD
version 3.6.1 is currently in service on BMD-capable cruisers and
destroyers.
However, a significant degree of uncertainty remains:
* While Aegis BMD has demonstrated performance at sea, a series of
changes are required to modify it for use on land with Aegis Ashore.
* Changes to existing Aegis BMD technologies that will be reused for
Aegis Ashore may reduce their maturity in the context of the new Aegis
Ashore program, and new features will require testing and assessment
to demonstrate their performance. MDA plans both ground and flight
tests prior to deployment.
* In addition, there are dependencies on next-generation versions of
Aegis systems that are still in development.
Modification and development planned for Aegis Ashore includes:
* Deckhouse: Reconfiguration of design, integration, and fabrication
of new enclosures.
* Operating system configurations:
- Integrated Aegis Combat System architecture includes 32 sensors,
communications, weapons, and countermeasures. Only 11 of these will be
reused for Aegis Ashore; the remaining 21 will need to be suppressed
or otherwise disabled.
- Upgraded new Multi-Mission Signal Processor and BMD 5.0 software.
Suppress certain features for use with Aegis Ashore, such as the
software that accounts for a ship's pitch and yaw.
* Radar: It is currently unclear whether the SPY-1 radar's spectrum
supportability in its intended environment is fully understood or
accounted for.
* Vertical launching system: Modifications planned for environmental
control as well as safety and survivability.
* Standard Missile 3 block IB: Interceptor's design may need changes
to meet location requirements of Aegis Ashore.
Aegis Ashore: Design Stability:
According to program officials, detail design for Aegis Ashore has not
yet begun.
The contract for Aegis Ashore deckhouse fabrication is scheduled for
award prior to preliminary or critical design reviews for the whole
Aegis Ashore system.
We have previously reported that starting fabrication prior to
achieving design stability can lead to costly modifications later in
the process.
Aegis Ashore: BMDS Integration and Testing:
Integration: The Aegis Ashore capability depends on successful
integration within the BMDS via its C2BMC command and control node. It
is C2BMC that links Aegis Ashore to its cueing forward sensors, and as
such, demonstrating quality of service and connectivity of Aegis
Ashore with C2BMC is a vital piece of integration if Aegis Ashore is
to provide the type of coverage envisioned for its operation in Europe.
Testing: The scope of testing planned for Aegis Ashore has reduced
since the program began and may not be timed to provide needed
knowledge prior to production.
* Some knowledge points for Aegis Ashore remain undefined.
* While Aegis Ashore was previously scheduled to participate in four
Aegis Ashore specific flight test intercepts, it is now scheduled to
participate in only two, though MDA believes this will not affect
testing objectives.
* We have previously reported that repetition of intercept related
objectives is important to build confidence in intercept capability.
* The first intercept flight test with a target is scheduled for the
second half of fiscal year 2014, at which point contracts for
component production and construction will be well under way.
Standard Missile 3 Block IB Interceptor: Development:
Technology development of the throttleable divert attitude control
system is following a high-risk path.
According to the Director, MDA the first intercept flight test was
just moved into the third quarter 2011 to allow time to complete all
qualification tests before the flight test.
Standard Missile 3 Block IB Interceptor: Testing and Production:
The test schedule is not synchronized with planned production and
financial commitments. Investments are planned prior to demonstrating
system performance.
* Two flight tests needed to demonstrate interceptor knowledge points
are scheduled after the manufacturing readiness review and contract
awards for 38 missiles (plus four "pathfinders").
* In all, 104 of 320 interceptors-”estimated at a cost of $1.2 billion
to $1.6 billion”-are expected to be under contract before all major
knowledge points have been demonstrated.
While MDA characterized the first 30 interceptors as being test
rounds, half remain unassigned to a specific test. Of those assigned
to a test, some interceptors may be produced earlier than necessary
since they deliver 1 to 2 years prior to the scheduled test.
Existing issues with subcontractor manufacturing performance for
missile components introduce risk that the transition to manufacturing
IB missiles may not go as smoothly as planned.
THAAD Production:
Some production risks identified for THAAD batteries including
incomplete system and some component qualification, potential design
changes, and demonstrated production rates for interceptor components
not supporting production needs have caused more than a 6-month delay
in production. The program has now addressed most of these risks and
has mitigation plans in place for those remaining.
* An Army safety review board identified the requirement to install an
optical block for the initiation system in 2003, but MDA did not
modify the development contract to include this requirement until
2006. In addition MDA awarded a production contract in December 2006
although a design was not yet selected.
* To date, 7 years after the optical block requirement was identified,
program officials told us that full recurring costs have not been
determined and the requirement has not been defined on the production
contract. This late requirement has since delayed interceptor
production and, subsequently, Battery 1 and 2 full deliveries more
than 6 months. The program recently completed efforts to redesign and
requalify the optical block component.
* The program also has yet to demonstrate necessary production rates
for a component of the interceptor (the flight sequencing assembly);
according to the program office there is a mitigation strategy in
place that may successfully address this issue.
* Contract award for Battery 3 (with an option for Battery 4)
interceptor production was delayed from second to fourth quarter
fiscal year 2010. However, most THAAD subcontractors have already
identified gaps in production-”some of more than a year”-which may
require the contractor to recertify and requalify production processes.
[End of Objective 2 section]
Concluding Observations:
According to DOD, one of the benefits of DOD's new concept for
regional phased adaptive approaches is that it provides DOD with
flexibility and will be more cost effective.
We did not review the viability of the new regional policy; rather we
focused on its acquisition executability. Thus our conclusions are not
about what is the right policy, but about the right way to execute its
acquisitions
Limited visibility into costs and schedule for EPAA and the lack of
some key acquisition management processes reflect oversight challenges
we have previously reported with the acquisition of missile defense
capabilities.
Consequences have included the following:
* Limited means of independently assessing progress and limited basis
for oversight.
* Going into production before fully demonstrating system performance
has led to rework, cost increases, delays and uncertainties about
delivered capabilities.
The flexibility desired by DOD is not incompatible with appropriate
visibility into key aspects of acquisition management. As DOD proceeds
with the EPAA acquisition activities, it is important for Congress and
the President to have assurance that the EPAA policy is working as
intended and that acquisition activities are cost-effective.
We plan to issue a broader report on European missile defense issues.
That final product will have recommendations, as appropriate.
[End of Enclosure I]
Office Of The Under Secretary Of Defense:
Acquisition, Technology and Logistics:
3000 Defense Pentagon:
Washington, DC 20301-3000:
December 15, 2010:
Ms. Christina T. Chaplain:
Director, Acquisition and Sourcing Management:
U.S. Government Accountability Office
441 G Street, NW:
Washington, DC 20548:
Dear Ms. Chaplain:
This is the Department of Defense (DoD) response to the GAO Draft
Report, GAO-11-179R, Defense Acquisitions: European Phased Adaptive
Approach (EPAA) Acquisitions Face Synchronization, Transparency, and
Accountability Challenges', dated October 29, 2010 (GAO Code 120900).
The Department understands this brief was provided to Congress prior
to addressing the Departments concerns, but that there will be a final
report which will include the information from the subject document.
Although I would have preferred an opportunity for Department review
and comment prior to presentation to Congress, the Department
appreciates the opportunity to provide technical comments to address
areas of potential misunderstandings or to clarify the facts for
inclusion into the brief and the final report. I have enclosed a copy
of the Departments critical and substantive technical comments that
was provided on November 30, 2010.
In general, the Department disagrees with the GAO's approach to assess
the EPAA in Europe as a near-distinct element of the Ballistic Missile
Defense System rather than recognizing the Department's approach to
employ missile defense capability in defense of Europe using existing
Departmental processes. We believe the assessment described in this
report inaccurately portrays the Departments acquisition plans as
inadequate to making capability available to the warfighter
should requests for deployment be generated by the combatant
commanders.
I recommend that a technical comment resolution meeting be held in the
near term with the Missile Defense Agency. I am willing to host that
meeting, if desired.
My point of contact for this effort is Colonel David Arrieta,
David.Arrieta@osd.mil, 703-695-7328.
Sincerely,
Signed by:
David G. Ahern:
Deputy Assistant Secretary of Defense:
Portfolio Systems Acquisition:
Enclosure: As stated.
[End of Enclosure II]
Footnote:
[1] Pursuant to 2002 direction from the Secretary of Defense, BMDS
elements do not follow DOD's traditional acquisition processes until
they enter production and are transferred to the services.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: