Defense Logistics
Actions Needed to Improve Implementation of the Army Logistics Modernization Program
Gao ID: GAO-10-461 April 30, 2010
The Logistics Modernization Program (LMP) is an Army business system that is intended to replace the aging Army systems that manage inventory and depot repair operations. Through 2009, the Army obligated more than $1 billion for LMP. LMP was originally scheduled to be completed by 2005, but after the first deployment in July 2003, the Army delayed fielding because of significant problems. The Army has since decided to field the system in two additional deployments: the second deployment occurred in May 2009, and the third deployment is scheduled to occur in October 2010. GAO was asked to evaluate the effectiveness of the Army's management processes in enabling the second deployment sites to realize the full benefits of LMP.
The Army's management processes that were established prior to the second deployment of LMP were not effective in enabling the second deployment sites to realize the full benefits of LMP. When LMP becomes fully operational at the second deployment locations, the Army expects that it will significantly enhance depot operations. However, the Army was unable to ensure that the data used by LMP were of sufficient quality to enable the depots to perform their day-to-day missions after LMP became operational. As a result of these data quality issues, depot personnel had to develop and use manual work-around processes until they could correct the data in LMP, which prevented the Army from achieving the expected benefits from LMP. Data quality issues occurred despite improvements made by the Army to address data issues experienced during the first deployment of LMP because the Army's testing strategy did not provide reasonable assurance that the data being used by LMP were accurate and reliable. Instead, the Army's testing efforts focused on whether the software was functioning, but did not assess whether the data used by the depots to perform their repair missions were of sufficient quality to work in LMP. According to depot officials, the data problems are being corrected as they are identified. Additionally, the Army's training strategy did not effectively provide LMP users the skills necessary to perform their new tasks. Users at the depots stated that the training they received did not provide a realistic environment that showed them how to perform their expected duties, and did not always match their new responsibilities. However, users at the depots also stated that they had received additional training that resolved the issue. The Army also lacked a comprehensive set of metrics with which to measure the success of LMP implementation. GAO's previous work has shown that successful performance measures should be aligned throughout the organization and cover the activities that an entity is expected to perform. However, the Army did not have common metrics with which to measure success during the second deployment, and the Army's scorecard for measuring LMP implementation focused on the software, but did not assess whether the depots were able to perform their work using LMP as envisioned. Despite these challenges, LMP has provided the Army some benefits, and officials at the second deployment sites provided examples of how LMP had improved their day-to-day operations, for example, through the increased visibility of assets. The third deployment of LMP is scheduled to occur in October 2010, and will involve more commands, occur at locations across the globe, and affect more users than the previous deployments. LMP program management officials stated that they are taking steps to address the issues discussed in this report for the third deployment and are adjusting plans related to data testing and training. However, because these plans are being developed, GAO was unable to verify that the problems have been resolved. Without correcting these issues prior to the third deployment, the Army is likely to face similar, or potentially greater, problems that prevent it from realizing the full benefits of LMP.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
William M. Solis
Team:
Government Accountability Office: Defense Capabilities and Management
Phone:
(202) 512-8365
GAO-10-461, Defense Logistics: Actions Needed to Improve Implementation of the Army Logistics Modernization Program
This is the accessible text file for GAO report number GAO-10-461
entitled 'Defense Logistics: Actions Needed to Improve Implementation
of the Army Logistics Modernization Program' which was released on
April 30, 2010.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to the Chairman, Subcommittee on Readiness, Committee on Armed
Services, House of Representatives:
United States Government Accountability Office:
GAO:
April 2010:
Defense Logistics:
Actions Needed to Improve Implementation of the Army Logistics
Modernization Program:
GAO-10-461:
GAO Highlights:
Highlights of GAO-10-461, a report to the Chairman, Subcommittee on
Readiness, Committee on Armed Services, House of Representatives.
Why GAO Did This Study:
The Logistics Modernization Program (LMP) is an Army business system
that is intended to replace the aging Army systems that manage
inventory and depot repair operations. Through 2009, the Army
obligated more than $1 billion for LMP. LMP was originally scheduled
to be completed by 2005, but after the first deployment in July 2003,
the Army delayed fielding because of significant problems. The Army
has since decided to field the system in two additional deployments:
the second deployment occurred in May 2009, and the third deployment
is scheduled to occur in October 2010. GAO was asked to evaluate the
effectiveness of the Army‘s management processes in enabling the
second deployment sites to realize the full benefits of LMP.
What GAO Found:
The Army‘s management processes that were established prior to the
second deployment of LMP were not effective in enabling the second
deployment sites to realize the full benefits of LMP. When LMP becomes
fully operational at the second deployment locations, the Army expects
that it will significantly enhance depot operations. However, the Army
was unable to ensure that the data used by LMP were of sufficient
quality to enable the depots to perform their day-to-day missions
after LMP became operational. As a result of these data quality
issues, depot personnel had to develop and use manual work-around
processes until they could correct the data in LMP, which prevented
the Army from achieving the expected benefits from LMP. Data quality
issues occurred despite improvements made by the Army to address data
issues experienced during the first deployment of LMP because the Army‘
s testing strategy did not provide reasonable assurance that the data
being used by LMP were accurate and reliable. Instead, the Army‘s
testing efforts focused on whether the software was functioning, but
did not assess whether the data used by the depots to perform their
repair missions were of sufficient quality to work in LMP. According
to depot officials, the data problems are being corrected as they are
identified. Additionally, the Army‘s training strategy did not
effectively provide LMP users the skills necessary to perform their
new tasks. Users at the depots stated that the training they received
did not provide a realistic environment that showed them how to
perform their expected duties, and did not always match their new
responsibilities. However, users at the depots also stated that they
had received additional training that resolved the issue. The Army
also lacked a comprehensive set of metrics with which to measure the
success of LMP implementation. GAO‘s previous work has shown that
successful performance measures should be aligned throughout the
organization and cover the activities that an entity is expected to
perform. However, the Army did not have common metrics with which to
measure success during the second deployment, and the Army‘s scorecard
for measuring LMP implementation focused on the software, but did not
assess whether the depots were able to perform their work using LMP as
envisioned. Despite these challenges, LMP has provided the Army some
benefits, and officials at the second deployment sites provided
examples of how LMP had improved their day-to-day operations, for
example, through the increased visibility of assets.
The third deployment of LMP is scheduled to occur in October 2010, and
will involve more commands, occur at locations across the globe, and
affect more users than the previous deployments. LMP program
management officials stated that they are taking steps to address the
issues discussed in this report for the third deployment and are
adjusting plans related to data testing and training. However, because
these plans are being developed, GAO was unable to verify that the
problems have been resolved. Without correcting these issues prior to
the third deployment, the Army is likely to face similar, or
potentially greater, problems that prevent it from realizing the full
benefits of LMP.
What GAO Recommends:
In order to improve the third deployment of LMP, GAO is recommending
that the Secretary of the Army direct the Commanding General, Army
Materiel Command, to (1) improve testing activities to obtain
reasonable assurance that the data used by LMP can support the LMP
processes, (2) improve training for LMP users, and (3) establish
performance metrics to enable the Army to assess whether the
deployment sites are able to use LMP as intended. The Army concurred
with our recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-10-461] or key
components. For more information, contact William M. Solis at (202)
512-8365 or solisw@gao.gov or Asif A. Khan at (202) 512-9869 or
khana@gao.gov or Nabajyoti Barkakati at (202) 512-4499 or
barkakatin@gao.gov.
[End of section]
Contents:
Letter:
Background:
Army's Management Processes Not Effective in Enabling Second
Deployment Sites to Achieve LMP Benefits:
Conclusion:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Scope and Methodology:
Appendix II: Comments from the Department of Defense:
Tables:
Table 1: LMP Deployment Summary:
Table 2: Post Go-Live Scorecard:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
April 30, 2010:
The Honorable Solomon P. Ortiz:
Chairman:
Subcommittee on Readiness:
Committee on Armed Services:
House of Representatives:
Dear Mr. Chairman:
For decades, the Department of Defense (DOD) has been challenged in
modernizing its business systems.[Footnote 1] In 1995, we designated
DOD's business system modernization program as high risk, and continue
to do so because these systems are fundamental to addressing long-
standing weaknesses related to the management of contracts, finance,
and the supply chain.[Footnote 2] Moreover, we continue to report on
business system investments that fail to effectively deliver promised
benefits and capabilities on time and within budget.[Footnote 3]
Organizations that implement enterprise resource planning systems have
faced substantial challenges because of the complexity of the
endeavor, and the Army is no exception. In 1998, the Army initiated
the Logistics Modernization Program (LMP) in order to replace two
aging Army systems used to manage its inventory and its repair
operations at the depots. LMP was originally scheduled to be completed
by 2005, but the Army delayed fielding LMP because of the significant
problems faced by the first deployment sites--the Communications-
Electronics Command and Tobyhanna Army Depot--in July 2003, which we
detailed in several reports.[Footnote 4] The Army has since determined
that fielding of LMP would occur in two additional phases of
deployment: the Aviation and Missile Command in 2009, which includes
Corpus Christi Army Depot and Letterkenny Army Depot, and the Tank-
automotive and Armaments Command, the Joint Munitions and Lethality
Command, and the Army Sustainment Command in October 2010. Through
2009, the Army has obligated more than $1 billion to implement LMP,
and estimates a total life cycle cost in excess of $2.6 billion to
procure and operate the system. The Army expects that LMP will reduce
redundant and stove piped information technology investments and
assist in driving business transformation across the Army, which will
enable the Army to supply and service the warfighter more quickly and
cost effectively.
We previously assessed the Army's preparation for the second
deployment of LMP and reported that the Army had begun to implement
our prior recommendations related to past issues on data conversion,
billing and collection, requirements management and testing, and
independent verification and validation.[Footnote 5] We also reported
that the Army had implemented critical project management processes
and controls that enabled the Army to identify and understand the
risks associated with making a deployment decision. We further noted
that these critical management processes--which addressed data
conversion from legacy systems to LMP, training LMP users, and the
ability to rapidly evaluate and respond to potential issues--were
absent during the first deployment of LMP at Tobyhanna Army Depot.
However, the effectiveness of the Army's management processes could
not be evaluated until the second deployment had occurred on May 14,
2009.
You asked us to continue monitoring the Army's efforts to deploy LMP
and evaluate the Army's progress in addressing the issues that are
critical to successful implementation. You also asked us to monitor
the actions taken by the Army after the system has been deployed to
ensure that its stated processes are adequate and have been
effectively implemented. Accordingly, the objective of this review was
to evaluate the effectiveness of the Army's management processes in
enabling the second deployment sites to realize the full benefits of
LMP.
To address this objective, we reviewed and analyzed the Army plans and
policies that governed LMP implementation. We obtained briefings from
the LMP program management office on the intended purpose of LMP, as
well as information related to the execution of the second deployment.
We also monitored the second deployment of LMP as it occurred and had
personnel observing operations at Corpus Christi Army Depot, Texas;
Letterkenny Army Depot, Pennsylvania; and the LMP program management
office's command center in Marlton, New Jersey. We met with officials
at each location to discuss how they were using LMP to perform their
missions and attended and observed daily meetings held by each
location and among the locations where they discussed issues that had
arisen and the actions they were taking to resolve the issues. After
the initial deployment, we conducted follow-up visits to Corpus
Christi Army Depot and Letterkenny Army Depot to monitor the progress
of implementation. We also met with officials at the Army Materiel
Command, the Aviation and Missile Command, and the LMP program
management office to discuss how the Army was managing the
implementation and using the system. Lastly, we met with LMP program
management officials to discuss plans for the third deployment of LMP
scheduled to occur in October 2010.
We conducted this performance audit from May 2009 through March 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
Background:
In February 1998, the Army Materiel Command began an effort to replace
its existing materiel management systems--the Commodity Command
Standard System and the Standard Depot System--with LMP. The Army has
used these existing systems for over 30 years to manage inventory and
depot maintenance operations. LMP is intended to transform the Army's
logistics operations in six core processes: order fulfillment, demand
and supply planning, procurement, asset management, materiel
maintenance, and financial management. If effectively implemented, LMP
is expected to provide the Army benefits associated with commercial
best practices, such as inventory reduction, improved repair cycle
time, and increased response time. Additionally, LMP is intended to
improve supply and demand forecast planning and maintenance workload
planning and to provide a single source of data for decision making.
LMP became operational at the Army Communications-Electronics Command
and Tobyhanna Army Depot in July 2003, and was originally expected to
be fully deployed by fiscal year 2005. However, because of problems
experienced at Tobyhanna Army Depot, the Army delayed implementation
until the operational problems were resolved. In May 2009, LMP became
operational at the Army Aviation and Missile Command and Corpus
Christi and Letterkenny Army Depots, and the third and final
deployment of LMP is expected to occur in October 2010 at the Army
Sustainment Command, the Joint Munitions and Lethality Command, the
Tank-automotive and Armaments Command, and Anniston and Red River Army
Depots. When LMP is fully implemented, it is expected to include
approximately 21,000 users at 104 locations across the globe (see
table 1), and it will be used to manage more than $40 billion worth of
goods and services, such as inventory managed at the national level
and repairs at depot facilities.
Table 1: LMP Deployment Summary:
Number of sites:
Communications-Electronics Command: 14;
Aviation and Missile Command: 7;
Army Sustainment Command, Joint Munitions and Lethality Command, and
Tank-automotive and Armaments Command: 83;
Total at full operational capability: 104.
Approximate number of users:
Communications-Electronics Command: 4,000;
Aviation and Missile Command: 6,000;
Army Sustainment Command, Joint Munitions and Lethality Command, and
Tank-automotive and Armaments Command: 11,000;
Total at full operational capability: 21,000.
Source: U.S. Army.
[End of table]
According to LMP program management officials, preparations for the
third deployment of LMP began in December 2008. In September 2009,
leaders from the third deployment sites formally established the
Executive Steering Committee to ensure a successful implementation of
LMP during the third deployment. The committee's responsibilities
include reviewing plans and schedules, exchanging lessons learned,
performing ongoing assessments of readiness to implement LMP, and
making decisions on important issues. As of January 2010, LMP program
management officials told us that several education courses had been
completed and that the third deployment sites were in the process of
completing their initial data conversion activities.
Army's Management Processes Not Effective in Enabling Second
Deployment Sites to Achieve LMP Benefits:
The Army's management processes that were established prior to the
second deployment of LMP were not effective in enabling the second
deployment sites to realize the full benefits of LMP. Based on our
observations, we found that data quality issues prevented personnel at
Corpus Christ and Letterkenny Army Depots from using LMP as
envisioned. The Army acknowledged that data quality was one of the
most important and challenging success factors in deriving the optimal
business benefits from LMP. At both depots, LMP users were unable to
use LMP to conduct depot operations and inventory management functions
immediately following the second deployment. Although the depots were
able to continue to repair items and support the warfighter, LMP users
had to rely on manual work-around processes, which are not part of how
LMP is intended to function and hinder the Army's ability to realize
the benefits expected from LMP. The depots experienced data quality
issues, despite improvements the Army made to address data quality
issues experienced during the first deployment of LMP at Tobyhanna
Army Depot, because the Army's testing strategy did not provide
reasonable assurance that the data being used by LMP were accurate and
reliable. Specifically, the Army's testing strategy focused on
determining whether the software worked as designed, but did not
assess whether LMP was capable of functioning in a depot environment
using the actual data from the depots. Additionally, the Army's
training strategy did not effectively provide users the skills
necessary to perform all of their tasks in LMP. Users at the depots
stated that the training they received before LMP became operational
was not conducted in a realistic environment that showed them how to
perform their expected duties. However, users at both depots also
stated that the LMP program management office had provided additional
training after LMP became operational to address their concerns.
Additionally, when monitoring LMP implementation at the second
deployment sites, the Army lacked a comprehensive set of metrics with
which to accurately assess whether LMP was delivering the intended
functionality. Instead, the metrics used by the LMP program management
office focused on whether the software was working but did not measure
whether the deployment sites were performing their day-to-day
operations using LMP as envisioned. Despite these challenges, the
second deployment sites reported achieving some benefits through the
use of LMP, such as increased visibility over assets.
Data Quality Issues Prevented Depots from Realizing the Full Benefits
of LMP:
The Army was unable to realize the full benefits of LMP at the second
deployment sites because of data quality issues. The benefits that LMP
was expected to provide the depots included reducing the amount of
time to repair items, automatically calculating the material
requirements for repair projects, and improving the management of
maintenance capacity. However, the ability of the second deployment
sites to realize these benefits depended on data quality, which
according to the Army, is one of the most important and challenging
success factors in deriving optimal business benefits from an
enterprise resource planning system like LMP.
In preparation for the second deployment, the Army focused on
addressing systemic data quality problems associated with the first
deployment of LMP at Tobyhanna Army Depot. As we reported in June
2005,[Footnote 6] LMP did not always contain the correct unit price or
unit of issue[Footnote 7] for certain materials, resulting in excess
material being ordered and incorrect prices being charged to jobs. To
avoid similar problems during the second deployment of LMP, the Army
developed processes to ensure that the unit of issue and unit of
measure values shown for a given item were appropriate for that item.
According to LMP program management office officials, out of a target
population of more than 12 million data records, 99.9 percent were
loaded into LMP (12.40 million out of 12.41 million data records)
before the system became operational at the second deployment sites.
Although the Army's processes addressed some of the data issues from
the first deployment of LMP, according to LMP program management
office officials, these processes did not assess whether the overall
quality of the data that the system would use was sufficient to
support the LMP processes.
Both Corpus Christi and Letterkenny Army Depots experienced data
quality issues that prevented the Army from realizing the full
benefits of LMP. For example, during our visit to Corpus Christi Army
Depot shortly after LMP became operational in May 2009, we observed
that personnel at the depot could not use LMP to induct a helicopter
for repair because of data quality issues. As a result, LMP could not
automatically identify the materials needed to support the repair and
ensure that parts would be available in time to support the repairs.
Furthermore, labor rates were also missing for some stages of repair,
thereby precluding LMP from computing the expected labor costs for a
repair project. Users at Corpus Christi Army Depot addressed the data
quality problems as they arose. However, because of these data quality
problems, some of the enterprise processes that LMP can perform had to
be conducted using manual work-around processes to ensure that the
depot accomplished its repair mission and thereby continued to meet
the needs of the warfighter. Furthermore, these manual work-around
processes are labor intensive and prevent the Army from achieving the
benefits that LMP is expected to provide, such as increasing the
efficiency in ordering parts, determining whether sufficient funds are
available to perform the expected work, and determining whether the
production schedule could be achieved with existing resources.
Letterkenny Army Depot also experienced issues with data quality. For
example, when we visited Letterkenny Army Depot shortly after LMP
became operational, depot officials told us that they had identified
data quality errors when they attempted to induct a ground vehicle for
the Patriot system for repair. Letterkenny Army Depot officials also
stated that prior to LMP becoming operational, they spent about 18
months rebuilding the data that were needed to perform repair and
supply functions in LMP. However, after LMP became operational, they
realized that the data were not of sufficient quality to enable the
depot to use LMP as envisioned, so Letterkenny Army Depot officials
took steps to correct the data. During our subsequent visit to
Letterkenny Army Depot in August 2009, depot officials stated that
they were continuing to refine the data, and that they had nearly
completed doing so for their most common repair item--the High
Mobility Multi-Purpose Wheeled Vehicle. This refinement would then
serve as a template for the remaining repair items. Officials at
Letterkenny Army Depot noted, however, that they had pre-positioned
materials prior to the transition to LMP to ensure that the depot
could perform its repair mission if difficulties arose, which enabled
the depot to perform its day-to-day operations despite the data
shortcomings. Nonetheless, officials at Letterkenny Army Depot
acknowledged that they were not using the preferred automated LMP
processes as intended, and needed to use manual work-around processes
to complete their tasks.
Army's Testing Strategy Did Not Evaluate Data Quality:
The Army's testing strategy, as illustrated by the problems
experienced at the second deployment locations, was not comprehensive
enough to provide reasonable assurance that the data being used by LMP
were accurate and reliable. As we have previously reported,[Footnote
8] testing is a critical process utilized by organizations with the
intent of finding errors before a system is implemented. According to
the Army's Master Test Plan for LMP implementation, the objective of
system testing was to ensure that LMP operated as intended. However,
the Army's testing efforts focused on determining whether the software
worked as designed. Army officials stated that Army testing efforts
for the second deployment of LMP had incorporated lessons learned from
the first deployment of LMP. With respect to testing data conversion,
the Army noted two improvements in its testing process: the use of
data-specific scenario testing and engaging users in critical business
process tests. According to the Army's test plan, data-specific
scenario tests were designed to assess the quality, validity, and
integrity of the data to be migrated into LMP, as well as to validate
that data migration processes function as designed. Additionally,
critical business process tests, which were performed by users,
involved the execution of business process-oriented scenarios using
the data loaded into LMP with the intent of assessing the functional
readiness of the software.
In order to assess the functional readiness of the software, the Army
used simulated test data to test the system. For example, when
assessing the functional readiness of the software to perform an
induction of an item for repair, Army officials told us that they did
not attempt to induct an item for repair using the data loaded into
LMP. Instead, the Army tested whether LMP could perform an induction,
and performed these tests using simulated data so that developers
would know whether LMP could provide the intended capability. While
this approach is useful and desirable to determine whether the
software can operate as expected, it does not assess whether the data
are of sufficient quality to work in LMP. Thus, the first attempt to
perform a process in LMP using actual data during the second
deployment occurred when the depots attempted to use the system.
Consequently, the Army's testing strategy did not detect problems with
the quality of the data at the deployment sites.
During lessons learned sessions held in June 2009, Army officials at
the LMP program management office and at the second deployment sites
acknowledged these weaknesses in their testing strategy. Army
officials we interviewed also stated that testing needed to address
whether the deployment sites could perform their work using the system
as intended. For example, officials at Corpus Christi Army Depot
agreed that a better strategy to test whether LMP could perform as
intended would be to induct a representative number of items at each
depot using actual data from each deployment site. By attempting to
induct several items into the depot repair processes that are
representative of the majority of their workloads prior to
transitioning to LMP, the Army would have likely detected problems
related to data quality, which could have provided reasonable
assurance that LMP could operate as intended if the tests were
successful. Furthermore, by incorporating the use of actual data into
its testing strategy, the Army could have obtained reasonable
assurance that the data loaded into LMP were of sufficient quality to
be used and increased user confidence in the system. For example,
officials at Letterkenny Army Depot told us that testing the system in
a simulated environment with actual data would not only assess whether
the system would work but also would gauge the effectiveness of
training. Had the Army's testing strategy used the actual data at the
deployment locations, the Army could have identified issues related to
data quality prior to the transition to LMP.
Army's Training Strategy Did Not Fully Meet Needs of LMP Users:
Although the Army's training strategy was designed to provide LMP
users the skills and knowledge to successfully perform their new
roles, LMP users we interviewed at Corpus Christi and Letterkenny Army
Depots stated that the training they received prior to LMP becoming
operational did not fully meet their needs. LMP users we interviewed
at Corpus Christi and Letterkenny Army Depots stated that the training
focused on what LMP was supposed to do rather than on how they were to
use the system to perform their day-to-day missions. Additionally,
because the duties of some LMP users at the depots were changing, the
training users received was not always commensurate with the
responsibilities they were assigned. Consequently, some LMP users told
us that they did not always understand the actions they needed to
perform in order to accomplish their assigned tasks. Furthermore,
since the timeline for implementing the various LMP processes differed
at each location, the training sometimes occurred weeks before it
could be actually used, which resulted in users needing additional
training after the system became operational. Despite these issues,
LMP users at both depots stated that the additional training they
received after LMP became operational was effective and addressed
their needs.
According to the Army's LMP End-User Training and Development Delivery
Plan dated January 30, 2009, most implementation failures are caused
by poor end user training, which is the transfer of knowledge to the
end users who will run the enterprise with the new solution. To
prevent poor end user training, the Army's plan stated that end user
training must provide users not only with the transactions and tasks
performed in LMP, but also with the ability to recognize the
underlying flow of information through LMP. To meet this goal, the
Army used a blended learning solution designed to provide LMP users
with the skills, process knowledge, and performance support to
successfully perform their new roles after the transition to LMP. The
Army's plan also stated that training should occur as close as
possible to the date of implementation because the user's ability to
retain information diminishes each day the user is not able to put
into practice the training he or she has received.
The Army experienced challenges with the quality and timing of its
education and training efforts. According to the Army, education
focused on LMP concepts, while training demonstrated how the system
should be utilized by the user. However, according to Army lessons
learned documents, users received education on LMP concepts too far in
advance of training, which limited the ability of LMP users to
understand how the changes in the business processes that were to
occur as a result of LMP implementation affected their job
responsibilities. Additionally, LMP users we met at the depots
questioned the overall quality of the training they received. For
example, these users stated that the instruction focused too much on
concepts, rather than providing them the skills necessary to perform
their day-to-day operations. Users also noted that they had limited
opportunities to enhance their knowledge of the system by actually
using the system in a training environment.
The Army was also unable to deliver the correct training to some users
because of challenges in properly assigning roles. The Army's plan for
implementing LMP required not only the adoption of a new technological
solution, but also required changes to the duty descriptions for some
LMP users. For example, prior to LMP implementation, production
controllers at Letterkenny Army Depot were responsible for tracking
the flow of a repair item; however, after LMP implementation,
production controllers became asset managers, who were responsible not
only for tracking the flow of the item through the repair process but
also for ordering parts. Additionally, supervisors were generally
responsible for assigning roles to their personnel, and based on these
roles, users would receive training. However, as noted in Army lessons
learned documents, the process for determining roles sometimes
occurred before supervisors received any notable LMP education. As a
result, some users did not receive the correct training.
The Army also faced challenges in its ability to deliver training as
close as possible to the date of implementation because of the
decentralized execution strategy at each deployment site. In order to
prepare users, the Army used a master training calendar and standard
training curriculum. Although this training was standardized across
the second deployment sites, execution of LMP implementation was
decentralized. For example, after LMP implementation occurred on May
14, 2009, Letterkenny Army Depot consolidated all of its production
controllers into one area and began performing LMP functions in a
phased approach. In contrast, Corpus Christi Army Depot executed LMP
implementation by attempting to perform all tasks shortly after the
transition. Although each approach has merit, the approach used by
Letterkenny Army Depot did not match the Army's approach to training.
That is, LMP users at Letterkenny Army Depot only performed some of
the LMP processes immediately after LMP became operational.
Accordingly, some of the users at Letterkenny Army Depot had to
receive refresher training before they could perform their assigned
duties.
Despite the concerns that LMP users expressed about training, LMP
users also stated that the Army was able to successfully provide
refresher training and ad hoc coursework to address their issues. For
example, LMP users we met with at both Corpus Christi and Letterkenny
Army Depots stated that these courses were effective because the
content was focused and specific. Officials at both depots also stated
that the contractor support personnel that the LMP program management
office provided to assist each depot were also effective in providing
information.
Army Lacked Comprehensive Metrics to Assess LMP Implementation:
The Army was unable to determine whether the second deployment sites
had achieved the envisioned functionality of LMP because the Army
lacked a comprehensive set of metrics to measure the success of LMP
implementation. Our previous work has shown that successful
performance measures should be aligned throughout the organization and
cover the activities that an entity is expected to perform to support
the intent of the program.[Footnote 9] However, based on our review of
the second deployment of LMP, we determined that the Army did not
develop a comprehensive set of metrics. As a result, the scorecards
that the LMP program management office used to measure the progress of
LMP implementation did not measure whether the deployment sites were
performing their day-to-day operations using LMP as envisioned.
The LMP program management office assessed the progress of LMP
implementation using a scorecard that was agreed to by the deployment
sites and the LMP program management office. This scorecard focused on
four elements: (1) validating user access, (2) critical business
processes validated by sites,[Footnote 10] (3) production support and
infrastructure readiness, and (4) training readiness. Table 2 provides
an explanation of each area.
Table 2: Post Go-Live Scorecard:
Element: Validating user access;
Definition: End user access will be determined by end user ability to
(1) log on to the LMP solution and (2) perform assigned duties with
assigned security roles;
Metric:
Green: 90 percent access;
Yellow: 80 percent access;
Red: 70 percent access.
Element: Critical business process validation (CBPV);
Definition: Assess the expected outcomes as defined in the CBPV
template for each critical business process after implementation;
Metric:
Green: End users executed processes, documented issues, and assessed
and recommended actions with assistance of CBPV team with no issues;
Yellow: Issues identified, but work-around(s) in place;
Red: No work-around(s) in place.
Element: Production support and infrastructure;
Definition: Real-time monitoring of key performance parameters,
including system response time, system availability, and system
capacity;
Metric:
Green: All key performance parameters within tolerance;
Yellow: Some key performance parameters not met, but work-around in
place;
Red: Some key performance parameters not met, but no work-around in
place.
Element: Validate expert user and end user education and training
effectiveness;
Definition: Delivery of end user training, refresher workshops, and ad
hoc training;
Metric:
Green: Delivery of all scheduled end user training, refresher
workshops, and ad hoc courses to identified end users and end user
completion of exercise assessments;
Yellow: Schedules missed, but work-around in place;
Red: Schedules missed, but no work-around in place.
Source: U.S. Army.
[End of table]
As noted above, in addition to the criteria for each element, the LMP
program management office's measurements included a legend that
provided detail on the color coding used to assess progress. According
to this scorecard, a "green" rating was assigned if the element was
"on track," a "yellow" rating if the element had "issues being
worked," a "red" rating if the element had "significant
problems/issues," and a "white" rating if the element had not been
started. Of the elements on the scorecard, the only category that
assessed whether LMP could be used as intended was critical business
process validation. However, as stated in the critical business
process validation reports submitted by the Aviation and Missile
Command, Corpus Christi Army Depot, and Letterkenny Army Depot, this
validation allowed the use of manual work-around processes that were
not part of the envisioned LMP processes. Accordingly, the Army did
not have an assessment in place to determine whether LMP was
delivering the envisioned capability to the second deployment sites.
Based on our observations at Corpus Christi and Letterkenny Army
Depots, we found that the elements on the LMP program management
office's scorecard did not accurately reflect the activities that the
depots were expected to perform. One of the primary purposes of
implementing LMP was to gain the capability and efficiencies through
automated processes associated with the software. Accordingly, while
the scorecard measured the functionality of the software after LMP
became operational, the scorecard did not assess whether the depots
were able to perform their work using LMP as envisioned.
In addition to its scorecard, the LMP program management office
provided periodic briefings regarding LMP implementation that
identified problems as "What's Important Now" items. The briefings
described each problem, the impact of the problem, steps being taken
to mitigate the problem, and an estimated date for when the problem
would be resolved. However, despite the presence of these items, the
LMP program management office's scorecard reflected the status of LMP
implementation as "green." For example, a May 28, 2009, briefing that
was provided to senior Army management contained 17 "What's Important
Now" items that identified problems related to missing data, the
ability of the depots to fill customer requisitions, the ability to
correct data in LMP, and challenges related to issuing materials to
the shop floor to support repairs. Additionally, in the same briefing,
the LMP program management office reported that Corpus Christi Army
Depot had inducted an aircraft for repair using LMP. In actuality, as
discussed earlier, the aircraft was inducted by depot personnel using
manual work-around processes that were similar to legacy processes
rather than the envisioned LMP processes. Although the depot was
unable to induct a helicopter using LMP as intended, the LMP program
management office's scorecard reflected a "green" rating for all of
the elements.
We also found that the LMP program management office's scorecard did
not accurately reflect the internal assessment of LMP implementation
at the depots. For example, Letterkenny Army Depot developed and used
a scorecard to measure progress of LMP implementation, which included
more than 50 processes that end users had to perform in LMP covering
areas such as supply, maintenance, and finance. According to officials
at Letterkenny Army Depot, a process was identified as "green" once
the user had successfully performed the task in LMP using the
envisioned processes. However, the progress as tracked by the depot
did not match the progress as reported on the LMP program management
office's scorecard. For example, on May 26, 2009, Letterkenny Army
Depot had identified 48 of its processes as "red" because the depot
either had not yet performed the function in LMP or was unable to
perform it successfully in LMP using the envisioned processes.
However, on the same day, the LMP program management office reported
that LMP was "green" in all elements measured by the LMP program
management office's scorecard. These differences reflect the lack of a
comprehensive set of metrics for measuring the success of LMP
implementation, because while the LMP program management office was
measuring whether the software was working, Letterkenny Army Depot had
identified that it was unable to conduct its daily operations using
LMP as envisioned.
LMP Has Provided the Army Some Benefits:
Although data quality and training issues prevented the second
deployment sites from using the full capabilities of LMP as
envisioned, the use of LMP at the second deployment sites has provided
the Army some benefits that were not available in legacy systems, such
as increased visibility. For example, officials at Corpus Christi Army
Depot stated that LMP has provided them the ability to track and trace
individual transactions to specific end users. With this tool,
officials at Corpus Christi Army Depot stated that they are able to
research individual actions, as well as ensure that individuals are
following the procedures at the depot. Corpus Christi Army Depot
officials also stated that LMP provided them increased visibility over
contractor-managed inventories, which was not available in the legacy
systems.
The Army has also achieved benefits through the common picture
provided by LMP. For example, when explaining how the life cycle
management commands were using LMP, an item manager from the Aviation
and Missile Command showed us how the common view provided by LMP
improved communication with the depots. When attempting to find the
location of an item for repair, the item manager stated that both the
depot and the item manager saw that the item to be repaired had
already arrived at the depot, so the depot could then begin the repair
process. According to the item manager, this visibility was not
available in the legacy systems, and the lack of a common picture
sometimes delayed induction of items for repair. The item manager
stated that the delays occurred because the item manager's system
showed that an item was located at a depot, but the depot's system did
not show the item as received, so personnel at the depot had to locate
the item before it could be inducted for repair. Furthermore, the item
manager demonstrated how the common view provided by LMP helped locate
a critical part for the Patriot missile system of a deployed unit. In
this case, the item manager was able to identify where the part was
stored in order to support the deployed unit. The item manager stated
that this capability was not available in legacy systems.
Preparations for Third Deployment of LMP Are Under Way:
The Army has taken steps to address some of the concerns we identified
during the second deployment of LMP. LMP program management officials
told us that preparations for the third deployment of LMP had begun in
December 2008, but that the Army had adjusted its plans--specifically
in the areas of testing and training--based on lessons learned from
the second deployment. For example, LMP program management officials
told us that the third deployment sites had already begun data
preparation activities in early 2009, and that these activities would
continue through September 2010. Additionally, LMP program management
officials stated that they had developed changes to their testing
strategy and that tests are scheduled to begin in May 2010. LMP
program management officials also stated that they intended to conduct
selective testing using actual depot-specific data and that this
testing is scheduled to begin in August 2010. However, according to
LMP program management officials, the exact processes to be tested and
the materials associated with supporting the tests have yet to be
developed.
With respect to training, LMP program management officials told us
that the training for the third deployment will be conducted by a
cadre of personnel from each of the major deployment sites, and that
members of this cadre would both serve as instructors to users at the
locations as well as assist sites with implementing LMP. LMP program
management officials stated that they were in the process of
completing instruction for the cadre of trainers, and that LMP users
had already begun receiving instruction on the LMP process. During a
meeting with DOD and Army officials, a representative from one of the
sites preparing for the third deployment stated that while the
instructors had changed from contractors to the cadre of trainers, LMP
users were still being taught with the same training materials from
the second deployment. Additionally, according to the Army's schedule
for the third deployment of LMP, the Army plans to update training for
users in June 2010 and begin delivery of training to users in July
2010. Accordingly, because these events have yet to occur, we were
unable to determine whether they adequately addressed the issues we
identified during the second deployment related to data testing and
training.
Conclusion:
Implementation of enterprise resource planning systems, like LMP, is a
complex endeavor, and based on the second LMP deployment, the Army has
improved its ability to manage implementation. Because the Army
improved its management processes based on lessons learned during the
first deployment of LMP at Tobyhanna Army Depot, the Army was
successful in mitigating some of the previous issues. Furthermore, the
second deployment of LMP also demonstrated the potential to provide
benefits for the Army, such as providing better visibility of
inventory and asset management. However, despite the improvements and
the benefits that were achieved, the deployment sites still faced
challenges related to data quality and training, which limited their
ability to use LMP as intended. Additionally, the Army's lack of a
comprehensive set of performance metrics prevented it from measuring
whether the intended LMP functionality had been achieved at the
depots. Although the Army was effective in addressing these challenges
after they had arisen at the second deployment sites, applying these
lessons learned to the Army's plans as it prepares to support the
third phase of deployment in October 2010 is critical. Unless the Army
addresses these challenges, the third deployment locations are likely
to face the same, or even greater, problems, since the third
deployment of LMP will occur at more locations and affect more users
than the previous deployments.
Recommendations for Executive Action:
To improve the third deployment of LMP, we are recommending that the
Secretary of the Army direct the Commanding General, Army Materiel
Command, to take the following three actions:
* Improve testing activities to obtain reasonable assurance that the
data used by LMP can support the LMP processes.
* Improve training for LMP users by:
- providing training on actual job processes in a manner that allows
the users to understand how the new processes support their job
responsibilities and the types of work they are expected to perform
and:
- providing training at the individual deployment sites to match
deployment timelines.
* Establish performance metrics that will enable the Army to assess
whether the deployment sites are able to use LMP as intended.
Agency Comments and Our Evaluation:
In written comments on a draft of this report, DOD stated that the
Army concurred with our recommendations and highlighted the corrective
actions it is taking to (1) improve testing activities to obtain
reasonable assurance that the data used by LMP can support the LMP
processes, (2) improve training for LMP users, and (3) establish
performance metrics that will enable the Army to assess whether the
deployment sites are able to use LMP as intended. Regarding our first
recommendation, the Army commented that the third deployment of LMP
involves two new test activities--the Process and Data Integration
Test and the Business Operational Test--that are designed to address
lessons learned from the second deployment of LMP. The Army commented
that the Process and Data Integration Test will evaluate business
processes using migrated business data from critical weapon systems,
and that the Business Operational Test will require expert and select
end users to perform transactions in LMP using local data. According
to the Army, these tests will bring together data, business processes,
standard operating procedures, and end user training materials to
ensure success. While we have not evaluated the effectiveness or
sufficiency of these two new tests in correcting the data testing
issues we discuss in this report, we believe that the steps the Army
is taking appropriately address the intent of our recommendation. With
respect to our second recommendation, the Army commented that it began
role mapping and development of the training calendar earlier in the
deployment process, and that training will be delivered to end users
in a just-in-time method to ensure that the training is timely and
focused to meet the needs of the users. The Army also commented that
it will continue to provide refresher training after deployment. We
have not reviewed these new training initiatives, but we believe that
they are a step in the right direction toward addressing the intent of
our recommendation and improving LMP user training. Finally, regarding
our third recommendation, the Army commented that it is working to
improve standard performance measures, and that the metrics will
reflect lessons learned from previous LMP deployments. The Army
commented that the expected date of completion for development of
these measures is July 1, 2010. The Army's written comments are
reprinted in appendix II.
We are sending copies of this report to interested congressional
committees; the Secretary of Defense; the Secretary of the Army; and
the Director, Office of Management and Budget. The report also is
available at no charge on the GAO Web site at [hyperlink,
http://www.gao.gov].
Please contact William M. Solis at (202) 512-8365 or solisw@gao.gov,
Asif A. Khan at (202) 512-9869 or khana@gao.gov, or Nabajyoti
Barkakati at (202) 512-4499 or barkakatin@gao.gov if you or your staff
have questions on matters discussed in this report. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. Key contributors to this report were
J. Chris Martin, Senior-Level Technologist; David Schmitt, Assistant
Director; Evelyn Logue; Darby Smith; and Jim Melton.
Sincerely yours,
Signed by:
William M. Solis:
Director, Defense Capabilities and Management:
Signed by:
Asif A. Khan:
Director, Financial Management and Assurance:
Signed by:
Nabajyoti Barkakati:
Chief Technologist:
Applied Research and Methods Center for Technology and Engineering:
[End of section]
Appendix I: Scope and Methodology:
In order to evaluate the effectiveness of the Army's management
processes in enabling the second deployment sites to realize the full
benefits of the Logistics Modernization Program (LMP), we reviewed and
analyzed Army plans and policies that governed LMP implementation.
Specifically, we reviewed plans created by the LMP program management
office related to data conversion and migration, system testing, the
training curriculum, and how the Army intended to monitor the
implementation of LMP. We also held several meetings with LMP program
management office officials and received briefings related to LMP
implementation. During these briefings, we also received information
on how LMP is intended to function, as well as the benefits that the
Army expects to receive by using the system.
We also monitored the second deployment of LMP as it occurred and had
personnel observing operations at Corpus Christi Army Depot, Texas;
Letterkenny Army Depot, Pennsylvania; and the LMP program management
office's command center at Marlton, New Jersey. During our initial
visits to Corpus Christi Army Depot and Letterkenny Army Depot, we met
with depot officials to discuss how they were using LMP and any
problems or successes that had arisen from their usage. We also
observed how personnel at the depots were performing certain processes
using LMP and received documents related to those actions.
Additionally, we reviewed how each of the depots was assessing the
progress of LMP implementation, and attended several of the daily
internal meetings held at Corpus Christi Army Depot and Letterkenny
Army Depot. To assess how the Army was managing the overall progress
of implementation, we also attended daily meetings held by the LMP
program management office, the Aviation and Missile Command, Corpus
Christi Army Depot, and Letterkenny Army Depot.
After the initial deployment, we attended a lessons learned discussion
hosted by the LMP program management office. We conducted follow-up
visits to Letterkenny Army Depot in June 2009 and August 2009 and to
Corpus Christi Army Depot in September 2009 to monitor the progress of
implementation. We also met with officials at the Army Materiel
Command, the Aviation and Missile Command, and the LMP program
management office to discuss how the Army was managing the
implementation, and received documents that were used to inform senior
leaders at the Army Materiel Command on the status of LMP
implementation. We also met with the Army Deputy Chief of Staff for
Logistics in January 2010 to discuss our initial observations.
During meetings we held with officials in the Army Materiel Command
and the LMP program management office, we discussed the steps that the
Army was taking to support the third phase of deployment for LMP. We
received copies of Army briefings assessing the progress of
implementation, as well as revisions to Army plans and drafts of new
plans based on the lessons learned from the second deployment of LMP.
Because of the timing of this review, we did not assess the Army's
plans for the third deployment locations, nor were we able to observe
actions taken by the third deployment locations to prepare for LMP
implementation.
We conducted this performance audit from May 2009 through March 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
[End of section]
Appendix II: Comments from the Department of Defense:
Office Of The Deputy Chief Management Officer:
9010 Defense Pentagon:
Washington, DC 20301-9010:
April 21, 2010:
Mr. William M. Solis:
Director, Defense Capabilities and Management:
United States Government Accountability Office:
441 G Street, NW:
Washington, DC 20548:
Dear Mr. Solis:
The Department of Defense response to the Government Accountability
Office's (GAO) draft report 10-461, "Defense Logistics: Actions Needed
to Improve Implementation of the Army Logistics Modernization
Program," dated March 22, 2010, (GAO Code 351366) is attached and
provides detailed comments on the draft report.
Sincerely,
Signed by:
Elizabeth A. McGrath:
Assistant Deputy Chief Management Officer:
Attachment: As stated:
[End of letter]
Government Accountability Office (GAO) Draft Report Dated March 22,
2010:
GA0-10-461 (GAO CODE 351366):
"Defense Logistics: Actions Needed To Improve Implementation Of The
Army Logistics Modernization Program"
Department Of Defense (DoD) Comments To GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretary of the Army
direct the Commanding General, Army Materiel Command [AMC] to improve
testing activities to obtain reasonable assurance that the data used
by [Logistics Modernization Program] LMP can support the LMP processes
(Page 23/GAO Draft Report.)
DoD Response: The Army concurs with the recommendation. The third
deployment of LMP to the Tank-automotive and Armaments Life Cycle
Management Command, Joint Munitions & Lethality Life Cycle Management
Command and the Army Sustainment Command involves two new test
activities designed to address lessons learned from the second
deployment. During the Process and Data Integration Test activity, End-
to-End business processes will be tested using migrated, validated
business data from critical weapon systems. During the Business
Operational Test, expert and select end users will perform
transactions in the LMP system using local data, from their home
station, bringing data, business process, standard operating
procedures and end user training materials together to ensure success.
AMC also improved data quality processes to supplement LMP data trial
loads, with monthly data quality tests against local site data and
established business rules. Under the AMC Data Audit Strategy, records
failing validation tests will be corrected and reviewed for accuracy,
and AMC will also take a random sampling of records passing the tests
to review accuracy of those records.
Recommendation 2: The GAO recommends that the Secretary of the Army
direct the Commanding General, Army Materiel Command to improve
training for LMP users by:
* Providing training on actual job processes in a manner that allows
the user to understand how the new processes support their job
responsibilities and the types of work they are expected to perform.
* Providing training at the individual deployment sites to match
deployment timelines (Page 23/GAO Draft Report.)
DoD Response: The Army concurs with the recommendation. The third
deployment of LMP utilizes an organic cadre of instructors and subject
matter experts drawn from different levels and backgrounds at AMC.
Together, this cadre has expertise in different areas of AMC
operations, and is responsible for the business transformation
activities at depots, arsenals and commands; participating in the LMP
Process and Data Integration Test and Business Operational Test
activities; tailoring training materials for end users; developing
local Standard Operating Procedures and desktop guides; training
expert users; and delivering end user training. Training materials
leverage experience from deployed sites, and will be demonstrated
during expert user training and Business Operation Test, with any
required changes being made prior to end user training. Cadre and
expert users work collaboratively with current LMP sites to gain
experience and insight into business processes and organizational
change in order to develop the expertise necessary for training end
users.
AMC and the LMP Project Management Office began role mapping and
training calendar development earlier in the deployment process to
determine the number of course offerings necessary at each site. To
the extent possible, training will be delivered at end user locations
in a "just in time" method to ensure the training is timely and
focused to the needs of users. Training activities will continue
following deployment to provide refresher training, and provide
training on monthly and quarterly business processes before the
processes are performed. Desk side ad-hoc training will be delivered
by expert users to answer questions from end users.
Recommendation 3: The GAO recommends that the Secretary of the Army
direct the Commanding General, Army Materiel Command to establish
performance metrics that will enable the Army to assess whether the
deployment sites are able to use LMP as intended. (See pages 23-24/GAO
Draft Report.)
DoD Response: The Army concurs with the recommendation. AMC and the
LMP Program Management Office are working across the third deployment
and deployed sites and commands to improve standard performance
measures for business process effectiveness and the ability to meet
mission requirements using the LMP system. The expected date of
completion for development of Post Go-Live metrics is July 1, 2010.
LMP's Pre Go-Live Scorecard monitors readiness of third deployment
sites to go live across 13 elements, which relate to data,
organization, process, technology and application. Development of
LMP's Post Go-Live metrics is monitored as part of a Pre Go-Live
activity under the process element, "Prepare for Post Go-Live
Support." Post Go-Live metrics will reflect lessons learned from
previous LMP deployments and monitor LMP deployed sites' status and
readiness to transition to "steady state" sustainment, based on
completion of dependent activities and events captured and aligned
against several major areas to include critical business process
validation, data, training, security role mapping and production
support.
[End of section]
Footnotes:
[1] Business systems are information systems that support DOD business
operations, such as civilian personnel, finance, health, logistics,
military personnel, procurement, and transportation.
[2] GAO, High-Risk Series: An Update, [hyperlink,
http://www.gao.gov/products/GAO-09-271] (Washington, D.C.: January
2009).
[3] See, for example, GAO, DOD Business Systems Modernization: Navy
Implementing a Number of Key Management Controls on Enterprise
Resource Planning System, but Improvements Still Needed, [hyperlink,
http://www.gao.gov/products/GAO-09-841] (Washington, D.C.: Sept. 15,
2009), and DOD Business Systems Modernization: Key Marine Corps System
Acquisition Needs to Be Better Justified, Defined, and Managed,
[hyperlink, http://www.gao.gov/products/GAO-08-822] (Washington, D.C.:
July 28, 2008).
[4] GAO, DOD Business Systems Modernization: Billions Continue to Be
Invested with Inadequate Management Oversight and Accountability,
[hyperlink, http://www.gao.gov/products/GAO-04-615] (Washington, D.C.:
May 27, 2004); Army Depot Maintenance: Ineffective Oversight of Depot
Maintenance Operations and System Implementation Efforts, [hyperlink,
http://www.gao.gov/products/GAO-05-441] (Washington, D.C.: June 30,
2005); and DOD Business Transformation: Lack of an Integrated Strategy
Puts the Army's Asset Visibility System Investments at Risk,
[hyperlink, http://www.gao.gov/products/GAO-07-860] (Washington, D.C.:
July 27, 2007).
[5] GAO, Defense Logistics: Observations on Army's Implementation of
the Logistics Modernization Program, [hyperlink,
http://www.gao.gov/products/GAO-09-852R] (Washington, D.C.: July 8,
2009).
[6] [hyperlink, http://www.gao.gov/products/GAO-05-441].
[7] DOD defines unit of issue as the quantity of an item, such as each
number, dozen, gallon, pair, pound, ream, set, or yard.
[8] [hyperlink, http://www.gao.gov/products/GAO-04-615].
[9] GAO, Tax Administration: IRS Needs to Further Refine Its Tax
Filing Season Performance Measures, [hyperlink,
http://www.gao.gov/products/GAO-03-143] (Washington, D.C.: Nov. 22,
2002).
[10] According to the Aviation and Missile Command, critical business
process validation is an element used to verify that LMP has
immediately restored the ability to meet critical business process
needs and satisfy mandatory regulations and requirements.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: