Military Munitions Response Program
Opportunities Exist to Improve Program Management
Gao ID: GAO-10-384 April 9, 2010
The Department of Defense (DOD) established the military munitions response program (MMRP) in 2001 to clean up sites known to be or suspected of being contaminated with military munitions and related hazardous substances. Cleanup of sites on active and base realignment and closure installations is the responsibility of the military service--Air Force, Army, Navy, or Marine Corps--that currently controls the land, and the Army has delegated execution of cleanup of formerly used defense sites (FUDS) to the U.S. Army Corps of Engineers (Corps). GAO was mandated to assess the (1) MMRP staffing and funding levels; (2) progress DOD has made in cleaning up munitions response sites; (3) extent to which DOD has established MMRP performance goals; and (4) extent to which DOD collects data on factors influencing project duration, as well as the accuracy of its cleanup cost estimates. GAO analyzed MMRP data and DOD documents and interviewed officials from DOD, the military services, and the Corps.
The military services and the Corps do not track the time that staff work on MMRP activities separately from the time they spend on another environmental restoration program--the Installation Restoration Program (IRP). Consequently, it is not possible to determine the staffing levels for the MMRP. In addition, obligated funds for the MMRP increased from $95 million in fiscal year 2002 to approximately $284 million in fiscal year 2008, and the military services and the Corps directed 11 percent of their total MMRP and IRP environmental restoration funds to the MMRP during the period--a total of about $1.2 billion to the MMRP compared with $9.7 billion to the IRP. DOD reported to Congress that it had completed its cleanup response for 1,318 of its 3,674 sites by the end of fiscal year 2008; however, for 1,234 of these sites, DOD's response was an investigation that determined cleanup was not necessary. The remaining 84 sites were cleaned up because of such factors as imminent danger to public safety and pressing military mission and land reuse needs. In addition, the military services and the Corps are still in the process of gathering information necessary to prioritize most sites in the MMRP inventory for cleanup. When this process is complete, the military services and the Corps will consider this information along with other factors, such as land reuse plans, to determine which sites to clean up first. However, DOD has not issued guidance on how factors other than risk should be considered when making decisions about which sites to sequence first for cleanup, and the Air Force, the Army, and the Corps have begun to independently develop their own approaches. Using varying approaches could lead to inconsistent sequencing decisions. DOD has not yet established a performance goal for implementing the cleanup remedy (referred to as "remedy in place") or achieving the cleanup objective (referred to as "response complete") at munitions response sites located on FUDS, as required by the fiscal year 2007 National Defense Authorization Act. The act also directs DOD to report on interim goals it determines feasible for achieving the performance goals, but DOD has not yet done so. Performance goals are important because they are used to track progress toward cleaning up munitions response sites. By establishing goals, DOD would have better information with which to measure MMRP progress. DOD gathers data on two of the factors--site size and type of hazard--that can influence project duration at military munitions response sites. As would be expected, these data indicate that the larger the munitions response site and the more complex the type of hazard, the longer it takes to clean up the site. In addition, because data on funds obligated to complete specific phases of the cleanup process are not included in DOD's database for many munitions response sites, it is not possible to assess the accuracy of the military services' and the Corps' cost estimates for the MMRP.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
Anu K. Mittal
Team:
Government Accountability Office: Natural Resources and Environment
Phone:
(202) 512-9846
GAO-10-384, Military Munitions Response Program: Opportunities Exist to Improve Program Management
This is the accessible text file for GAO report number GAO-10-384
entitled 'Military Munitions Response Program: Opportunities Exist to
Improve Program Management' which was released on April 9, 2010.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
Report to Congressional Committees:
United States Government Accountability Office:
GAO:
April 2010:
Military Munitions Response Program:
Opportunities Exist to Improve Program Management:
GAO-10-384:
GAO Highlights:
Highlights of GAO-10-384, a report to congressional committees.
Why GAO Did This Study:
The Department of Defense (DOD) established the military munitions
response program (MMRP) in 2001 to clean up sites known to be or
suspected of being contaminated with military munitions and related
hazardous substances. Cleanup of sites on active and base realignment
and closure installations is the responsibility of the military
service”Air Force, Army, Navy, or Marine Corps”that currently controls
the land, and the Army has delegated execution of cleanup of formerly
used defense sites (FUDS) to the U.S. Army Corps of Engineers (Corps).
GAO was mandated to assess the (1) MMRP staffing and funding levels;
(2) progress DOD has made in cleaning up munitions response sites; (3)
extent to which DOD has established MMRP performance goals; and (4)
extent to which DOD collects data on factors influencing project
duration, as well as the accuracy of its cleanup cost estimates. GAO
analyzed MMRP data and DOD documents and interviewed officials from
DOD, the military services, and the Corps.
What GAO Found:
The military services and the Corps do not track the time that staff
work on MMRP activities separately from the time they spend on another
environmental restoration program”the Installation Restoration Program
(IRP). Consequently, it is not possible to determine the staffing
levels for the MMRP. In addition, obligated funds for the MMRP
increased from $95 million in fiscal year 2002 to approximately $284
million in fiscal year 2008, and the military services and the Corps
directed 11 percent of their total MMRP and IRP environmental
restoration funds to the MMRP during the period”a total of about $1.2
billion to the MMRP compared with $9.7 billion to the IRP.
DOD reported to Congress that it had completed its cleanup response
for 1,318 of its 3,674 sites by the end of fiscal year 2008; however,
for 1,234 of these sites, DOD‘s response was an investigation that
determined cleanup was not necessary. The remaining 84 sites were
cleaned up because of such factors as imminent danger to public safety
and pressing military mission and land reuse needs. In addition, the
military services and the Corps are still in the process of gathering
information necessary to prioritize most sites in the MMRP inventory
for cleanup. When this process is complete, the military services and
the Corps will consider this information along with other factors,
such as land reuse plans, to determine which sites to clean up first.
However, DOD has not issued guidance on how factors other than risk
should be considered when making decisions about which sites to
sequence first for cleanup, and the Air Force, the Army, and the Corps
have begun to independently develop their own approaches. Using
varying approaches could lead to inconsistent sequencing decisions.
DOD has not yet established a performance goal for implementing the
cleanup remedy (referred to as ’remedy in place“) or achieving the
cleanup objective (referred to as ’response complete“) at munitions
response sites located on FUDS, as required by the fiscal year 2007
National Defense Authorization Act. The act also directs DOD to report
on interim goals it determines feasible for achieving the performance
goals, but DOD has not yet done so. Performance goals are important
because they are used to track progress toward cleaning up munitions
response sites. By establishing goals, DOD would have better
information with which to measure MMRP progress.
DOD gathers data on two of the factors”site size and type of hazard”
that can influence project duration at military munitions response
sites. As would be expected, these data indicate that the larger the
munitions response site and the more complex the type of hazard, the
longer it takes to clean up the site. In addition, because data on
funds obligated to complete specific phases of the cleanup process are
not included in DOD‘s database for many munitions response sites, it
is not possible to assess the accuracy of the military services‘ and
the Corps‘ cost estimates for the MMRP.
What GAO Recommends:
GAO recommends that Congress consider requiring DOD to report
separately on sites where response is complete because they needed no
cleanup, and that DOD issue guidance on how factors other than
relative risk should be considered in munitions response site
sequencing decisions, and set FUDS performance goals as required by
law. DOD partially agreed with the recommendations but not with the
matter for congressional consideration.
View [hyperlink, http://www.gao.gov/products/GAO-10-384] or key
components. For more information, contact Anu Mittal at (202) 512-3841
or mittala@gao.gov.
[End of section]
Contents:
Letter:
Background:
The Military Services and the Corps Do Not Track MMRP Staffing Levels,
and the MMRP Receives a Small Share of DOD's Environmental Restoration
Funds:
Most Sites That DOD Has Reported as Response Complete Did Not Require
Cleanup, and Cleanup Priorities Are Still Being Determined for the
Majority of Sites:
DOD Has Not Established a Key Performance Goal for Its MMRP at FUDS,
as Required by Law, and Has Not Determined and Reported on the
Feasibility of Interim Goals:
DOD Collects Limited Data on Factors That Can Affect MMRP Project
Duration, and Incomplete Data Prevent an Assessment of the Accuracy of
Its MMRP Cost Estimates:
Conclusions:
Matter for Congressional Consideration:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Objectives, Scope, and Methodology:
Appendix II: Comments from the Department of Defense:
Appendix III: GAO Contact and Staff Acknowledgments:
Figures:
Figure 1: Unexploded Ordnance Found at a Munitions Response Site:
Figure 2: Location and Number of Munitions Response Sites, as of
Fiscal Year 2008:
Figure 3: Percentage of Munitions Response Sites at Active and BRAC
Installations and FUDS, and Distribution among the Military Services
and the Corps:
Figure 4: Site Inspection at Beale Air Force Base:
Figure 5: IRP and MMRP Obligated Funds, Fiscal Years 2002 through 2008:
Figure 6: MMRP Obligated Funds, Fiscal Years 2002 through 2008:
Figure 7: Sites the Military Services and the Corps Cleaned Up under
the MMRP, as of Fiscal Year 2008:
Figure 8: Sites with Prioritization Protocol Scores Reported to DOD,
as of Fiscal Year 2008:
Figure 9: Percentage of Sites with No Obligated Funds Data, by Phase:
Abbreviations:
BRAC: base realignment and closure:
CERCLA: Comprehensive Environmental Response, Compensation, and
Liability Act:
Corps: U.S. Army Corps of Engineers:
DOD: Department of Defense:
FUDS: formerly used defense sites:
IRP: Installation Restoration Program:
MMRP: Military Munitions Response Program:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
April 9, 2010:
The Honorable Carl Levin:
Chairman:
The Honorable John McCain:
Ranking Member:
Committee on Armed Services:
United States Senate:
The Honorable Ike Skelton:
Chairman:
The Honorable Howard P. McKeon:
Ranking Member:
Committee on Armed Services:
House of Representatives:
The Department of Defense (DOD) has identified over 3,600 sites known
to be, or suspected of being, contaminated with military munitions
from training and other activities. These sites can pose risks to
human health and the environment. Military munitions include
unexploded ordnance (explosives that were fired but did not detonate
as planned), discarded military munitions (munitions that were
abandoned without proper disposal), and munitions constituents
(propellants or other materials originating from munitions).[Footnote
1] Sites that contain munitions (other than operational ranges) that
require a response from DOD are known as munitions response sites.
These sites are located on active installations, base realignment and
closure (BRAC) installations, and formerly used defense sites (FUDS)
across the country. About half of the land on which munitions response
sites are located has been or will be converted to nonmilitary uses,
which may include residential or commercial development and
recreation, according to DOD officials.
Under its Defense Environmental Restoration Program, DOD identifies,
investigates, and cleans up contamination from hazardous substances,
pollutants, and contaminants including military munitions at active,
BRAC, and FUDS locations that were contaminated while under DOD's
jurisdiction.[Footnote 2] To carry out activities under the Defense
Environmental Restoration Program, over time DOD has established three
programs, including the Installation Restoration Program (IRP) and the
Military Munitions Response Program (MMRP).[Footnote 3] Specifically,
in 1985, DOD established the IRP to address the release of hazardous
substances and other contamination, and most of DOD's environmental
remediation work to date has been conducted under this program. In
2001, DOD established the MMRP, which focuses on remediating
unexploded ordnance, discarded military munitions, and munitions
constituents on munitions response sites. Cleanup of munitions
response sites on active and BRAC installations is the responsibility
of the military service--Air Force, Army, or Navy[Footnote 4]--that
currently controls the land, and cleanup of FUDS sites is the
responsibility of the U.S. Army Corps of Engineers (Corps).[Footnote
5] While DOD has overall responsibility for the MMRP, it allows each
of the military services and the Corps to implement and manage their
own munitions response programs, including determining how best to
organize their programs, set program and funding priorities, and track
management information, in accordance with DOD policies and guidance.
The National Defense Authorization Act for fiscal year 2009 mandated
that we review and report to Congress by October 14, 2009, on various
aspects of DOD's organization, operation, and management of the MMRP.
[Footnote 6] We briefed the staffs of the Senate and House Committees
on Armed Services on October 14, 2009. We are following up with this
report, which provides more detail on the topics covered in the
briefing. As agreed with your offices, this report assesses the (1)
MMRP staffing and funding levels; (2) progress DOD has made in
cleaning up munitions response sites; (3) extent to which DOD has
established MMRP performance goals; and (4) extent to which DOD
collects data on factors influencing project duration, as well as the
accuracy of DOD's cleanup cost estimates.
In addressing these objectives, we reviewed each of the individual
MMRPs as implemented by the Air Force, Army, Navy, and the Corps at
active and BRAC installations and FUDS. We analyzed MMRP funding data,
as well as data in DOD's environmental programs management database--
known as the Knowledge-Based Corporate Reporting System--which
includes relative priority scores, project duration, and cost
estimates. We reviewed key documents, such as DOD's Defense
Environmental Programs Annual Report to Congress, which includes
information on program performance goals, and the Munitions Response
Site Prioritization Protocol that is used to assign a relative
priority to sites in order to prioritize sites for cleanup. We visited
one BRAC installation (Fort Ord), one active installation (Beale Air
Force Base), and one FUDS (Camp Beale) to ensure we had the
opportunity to review various types of MMRP activities at active and
BRAC installations, as well as FUDS. We met with and obtained
information and data needed for our review from a key senior DOD
official responsible for the MMRP within DOD's Office of the Deputy
Under Secretary of Defense (Installations and Environment); and we
interviewed senior officials from the Army, Air Force, Navy, and the
Corps. We also interviewed headquarters and regional officials from
the Environmental Protection Agency to discuss the MMRP.
We assessed the reliability of data for certain variables related to
our objectives in DOD's Knowledge-Based Corporate Reporting System, by
electronically testing for obvious errors in accuracy and
completeness, reviewing information about the data and the system that
produced them, and interviewing agency officials knowledgeable about
the data. When we found inconsistencies in the data, we worked with
DOD officials to clarify them before conducting our analyses. We
determined that the data were sufficiently reliable for the purposes
of providing basic descriptive information about the MMRP and for
analyzing the duration of phases of the cleanup process. However, we
found data on funds obligated for cleanup to be incomplete and
therefore not suitable for analysis. We discuss this data reliability
problem in more detail later in the report. We conducted this
performance audit from January 2009 to April 2010 in accordance with
generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings
and conclusions based on our audit objectives. We believe that the
evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives. Appendix I provides
additional detail on our scope and methodology.
Background:
The National Defense Authorization Act for fiscal year 2002 requires
DOD to develop and maintain an inventory of defense sites known or
suspected to contain unexploded ordnance, discarded military
munitions, or munitions constituents and to annually update the
inventory and list prioritizing these sites for cleanup.[Footnote 7]
Figure 1 shows an example of unexploded ordnance found at a munitions
response site on Beale Air Force Base in 2008.
Figure 1: Unexploded Ordnance Found at a Munitions Response Site:
[Refer to PDF for image: photograph]
Source: Air Force.
[End of figure]
As of fiscal year 2008, DOD had identified 3,674 munitions response
sites in the United States and its territories and outlying areas.
[Footnote 8] Figure 2 shows the number of sites in each state and in
United States territories and outlying areas.
Figure 2: Location and Number of Munitions Response Sites, as of
Fiscal Year 2008:
[Refer to PDF for image: map of the U.S. and associated data]
Alabama: 62;
Alaska: 260;
American Samoa: 3;
Arizona: 144;
Arkansas: 25;
California: 526;
Colorado: 66;
Connecticut: 8;
Delaware: 11;
District of Columbia: 36;
Florida: 161;
Georgia: 44;
Guam: 31;
Hawaii: 165;
Idaho: 27;
Illinois: 74;
Indiana: 35;
Iowa: 14;
Kansas: 66;
Kentucky: 16;
Louisiana: 59;
Maine: 47;
Marshall Islands: 1;
Maryland: 111;
Massachusetts: 83;
Michigan: 71;
Minnesota: 11;
Mississippi: 33;
Missouri: 31;
Montana: 22;
Nebraska: 32;
Nevada: 66;
New Hampshire: 15;
New Jersey: 62;
New Mexico: 174;
New York: 95;
North Carolina: 85;
North Dakota: 11;
Northern Mariana Islands: 6;
Ohio: 29;
Oklahoma: 42;
Oregon: 24;
Pennsylvania: 56;
Puerto Rico: 32;
Rhode Island: 19;
South Carolina: 53;
South Dakota: 20;
Tennessee: 45;
Texas: 270;
U.S. Virgin Islands: 3;
Utah: 50;
Vermont: 5;
Virginia: 140;
Wake Island: 1.
Washington: 78;
West Virginia: 4;
Wisconsin: 3;
Wyoming: 11.
Source: GAO analysis of DOD data; Map Resources (map).
[End of figure]
The majority of munitions response sites are located on active
installations (46 percent) and FUDS (45 percent), with the remainder
located on BRAC installations (9 percent). The Corps is responsible
for cleanup at 45 percent (1,661) of the munitions response sites, the
Army for 29 percent (1,080), the Air Force for 18 percent (644), and
the Navy for 8 percent (289), as shown in figure 3.
Figure 3: Percentage of Munitions Response Sites at Active and BRAC
Installations and FUDS, and Distribution among the Military Services
and the Corps:
[Refer to PDF for image: pie-chart]
N = 3,674.
Active installations: 46%;
FUDS: 45%;
BRAC installations: 9%.
Corps: 45%;
Army: 29%
Air Force: 18%;
Navy: 8%.
Source: GAO analysis of DOD data.
[End of figure]
Each of the military services and the Corps have established their own
individual organizational structures to implement the MMRP. These
structures, which are similar to the structures of their respective
IRPs, have various levels of management, but for ease of discussion,
we have identified three broad levels of management. At the
operational level, key responsibilities rest with project managers who
directly oversee MMRP activities at Army, Air Force, and Navy active
and BRAC installations and at FUDS. The project managers'
responsibilities may include planning munitions response actions,
developing cleanup cost estimates, coordinating with stakeholders,
[Footnote 9] and ensuring oversight of program activities, such as
monitoring technical work conducted by the contractors who are
responsible for various aspects of the cleanup process. Next, at the
middle-management level, managers provide direct oversight of MMRP
activities conducted at the operational level and also serve as
liaisons between the operational level and the top leadership level of
the organization. Managers at the middle-management level may be
responsible for monitoring MMRP activities, such as reviewing cleanup
plans developed at the operational level, determining operational
level funding, and ensuring that their munitions response programs are
in compliance with applicable laws and policies. Finally, managers at
the leadership level of the organization may conduct program reviews
to ensure MMRP activities implemented by the operational and middle-
management levels are in compliance with applicable laws, regulations,
and DOD policy and to approve funding requests for munitions response
actions that have been recommended by the levels below them.
Some munitions response sites pose a greater risk to human health or
the environment than others. The National Defense Authorization Act
for fiscal year 2002 requires DOD to develop a protocol for assigning
a relative priority for cleanup for all sites based primarily on
factors relating to safety and environmental hazard potential.
[Footnote 10] Initially, the military services and the Corps used a
process that produced what are known as risk assessment code scores to
rank the relative risk of munitions response sites based on the risk
they pose relative to other sites. However, in 2005, DOD, in
conjunction with the states, tribes, and the Environmental Protection
Agency, established a new process, known as the Munitions Response
Site Prioritization Protocol,[Footnote 11] which establishes a
consistent and transparent approach to evaluating the relative risks
at munitions response sites and prioritizes them for cleanup. The new
process uses three hazard evaluation modules to determine a site's
relative priority score--Explosive Hazard Evaluation, Chemical Warfare
Materiel Hazard Evaluation, and Health Hazard Evaluation. [Footnote
12] After the military service or the Corps has gathered sufficient
data about a site's characteristics to be able to complete at least
one of the protocol's modules, it assigns the site a relative priority
score of one through eight, with one representing the highest priority
or greatest risk and eight the lowest priority or lowest risk. The
military services and the Corps may not assign a relative priority
score to some sites and instead assign one of the following
alternative designations:[Footnote 13]
* Evaluation pending. Indicates that there are known or suspected
hazards present but that sufficient information is not available to
populate the data elements for at least one of the modules and the
site requires further evaluation.
* No longer required. Indicates that the site no longer requires a
priority score because DOD has conducted a response action and
determined that no further action is required.
* No known or suspected hazard. Indicates that the site does not
require an evaluation to determine a relative priority score because
review of the site concluded that no hazards are present.
According to DOD's policy, the military services and the Corps will
clean up munitions response sites with a higher relative priority
score before a site with a lower score. However, the military services
and the Corps also can consider other factors, such as military
mission needs, land reuse plans, and stakeholder concerns, in
determining which sites to clean up first. DOD refers to the process
of deciding which sites to clean up first based on relative priority
scores in combination with other factors as "sequencing" sites for
cleanup.
In deciding what actions, if any, are needed to clean up a site
identified as potentially contaminated with military munitions, DOD
officials told us that the military services and the Corps follow the
process established under the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA) of 1980.[Footnote 14] Key
steps in this process are:[Footnote 15]
* Preliminary assessment. To determine through a review of existing
information whether a potential military munitions hazard is present
and whether further action is needed.
* Site inspection. To determine whether a hazard or potential hazard
exists and the nature of any associated threats to human health or the
environment. The site inspection builds upon the preliminary
assessment and involves sampling, as appropriate, to determine the
nature of contamination and potential pathways of exposure and to
recommend whether further action is warranted. (Figure 4 shows a site
inspection team surveying a munitions response site at Beale Air Force
Base.)
* Remedial investigation/feasibility study. To collect data necessary
to determine the nature and extent of the hazard and to assess risk to
human health and the environment. Also, establish objectives for the
remedial action, and analyze and evaluate cleanup approaches.
According to DOD, cleanup approaches could include limiting public
access by installing controls such as barriers, fences, and signs
coupled with land use controls.
* Remedial design/remedial action. To design, construct, and operate
the cleanup remedy selected by the feasibility study. DOD considers
that it has the "remedy in place" when testing shows that the remedy
will operate as designed. DOD considers that it has attained "response
complete" when the cleanup objective is achieved.[Footnote 16]
Figure 4: Site Inspection at Beale Air Force Base:
[Refer to PDF for image: photograph]
Source: Air Force.
[End of figure]
The National Defense Authorization Act for fiscal year 2007 directs
DOD to establish the following performance goals for defense sites
under the MMRP:
* complete, by September 30, 2007, preliminary assessments of all
munitions response sites on active installations and FUDS;
* complete, by September 30, 2010, site inspections of all munitions
response sites at active installations and FUDS;
* achieve, by September 30, 2009, a remedy in place or response
complete for all munitions response sites at all military
installations realigned or closed prior to 2005; and:
* achieve, by a date to be established by the Secretary of Defense, a
remedy in place or response complete for all munitions response sites
at all active installations, FUDS, and all military installations
realigned or closed under the 2005 round of base closures (BRAC 2005).
[Footnote 17]
In addition, the act requires that DOD report "such interim goals as
the Secretary determines feasible" for the military services and the
Corps to reach their performance goals for remedy in place or response
complete at active, FUDS, and BRAC 2005 munitions response sites.
To track information pertaining to the number, description, and status
of munitions response sites being managed under each of their MMRPs,
the military services and the Corps maintain their own databases.
Twice a year they report information requested by DOD about their
munitions response sites. This information is compiled in a database
DOD calls the Knowledge-Based Corporate Reporting System. DOD uses the
information in this database to help oversee the overall MMRP; track
progress toward the achievement of its program performance goals; and
to support its need to report on the progress of the MMRP to Congress
and others, for example in DOD's Defense Environmental Programs Annual
Report to Congress.
The Military Services and the Corps Do Not Track MMRP Staffing Levels,
and the MMRP Receives a Small Share of DOD's Environmental Restoration
Funds:
According to a senior DOD official, DOD does not require the military
services or the Corps to track the time they spend working on MMRP
activities separately from the time they spend working on other
environmental restoration program activities. As a result, we were
unable to determine the staffing levels dedicated to the MMRP.
According to officials from the Army, Air Force, Navy, and the Corps,
their staff support both the IRP and the MMRP. However, these
officials told us they do not separately track the time that staff
spend working on each of the two programs because Congress does not
appropriate funding for these programs separately and tracking staff
time separately would add no value to accomplishing cleanup of these
sites. Moreover, a senior Army official told us that the extent to
which staff work on the IRP and MMRP varies greatly among employees
from day to day, making it extremely difficult to quantify the time
devoted to each program.
DOD provides the military services and the Corps combined annual
funding for all of their environmental restoration programs.[Footnote
18] It is the responsibility of the military services and the Corps to
make decisions about how to prioritize that funding among their
environmental programs, such as the IRP and MMRP. Between 2002 and
2008, the military services and the Corps directed most of their IRP
and MMRP environmental restoration funds to their respective IRPs--a
total of about $9.7 billion compared with the approximately $1.2
billion they directed to their respective MMRPs (see figure 5).
Figure 5: IRP and MMRP Obligated Funds, Fiscal Years 2002 through 2008:
[Refer to PDF for image: multiple line graph]
Fiscal Year: 2002;
Total IRP: $1,423 million;
Total MMRP: $95.3 million.
Fiscal Year: 2003;
Total IRP: $1,566.5 million;
Total MMRP: $136.1 million.
Fiscal Year: 2004;
Total IRP: $1,334.1 million;
Total MMRP: $119.6 million.
Fiscal Year: 2005;
Total IRP: $1,239.6 million;
Total MMRP: $151.1 million.
Fiscal Year: 2006;
Total IRP: $1,351.5 million;
Total MMRP: $202.8 million.
Fiscal Year: 2007;
Total IRP: $1,301.6 million;
Total MMRP: $244.7 million.
Fiscal Year: 2008;
Total IRP: $1,448.1 million;
Total MMRP: $283.5 million.
Source: GAO analysis of DOD data.
Note: Totals do not include program management and support costs.
[End of figure]
Annual obligations[Footnote 19] for the MMRP have increased from about
$95 million in fiscal year 2002, the program's first full year of
operation, to approximately $284 million in fiscal year 2008 (see
figure 6).
Figure 6: MMRP Obligated Funds, Fiscal Years 2002 through 2008:
[Refer to PDF for image: vertical bar graph]
Fiscal Year: 2002;
Funds obligated: $95.3 million.
Fiscal Year: 2003;
Funds obligated: $136.1 million.
Fiscal Year: 2004;
Funds obligated: $119.6 million.
Fiscal Year: 2005;
Funds obligated: $151.1 million.
Fiscal Year: 2006;
Funds obligated: $202.8 million.
Fiscal Year: 2007;
Funds obligated: $244.7 million.
Fiscal Year: 2008;
Funds obligated: $283.5 million.
Source: GAO analysis of DOD data.
Note: Totals do not include program management and support costs.
[End of figure]
According to DOD officials, the majority of munitions response sites
are still in the investigative phases and are not yet ready for
cleanup. Officials said that the military services and the Corps
obligated more money to the IRP than the MMRP for the following
reasons: (1) most sites in the IRP are being cleaned up or are ready
for cleanup; (2) cleanup is more costly than investigation; and (3)
the IRP was established long before the MMRP. As of the end of fiscal
year 2008, according to DOD's 2008 annual report to Congress, the
military services and the Corps had achieved response complete status
at about 79 percent of their IRP sites. Officials from the military
services and the Corps said they plan to apply more funding to the
MMRP and less to the IRP as they achieve remedy in place or response
complete status for additional IRP sites. For example, a senior Corps
official said that after the Corps meets its IRP goals for FUDS in
fiscal year 2020, FUDS munitions response program funding should
increase. Similarly, Air Force officials told us they are directing
more funding to the IRP to reach its goals. For example, in fiscal
year 2007, the Air Force directed almost $430 million to its IRP,
while directing less than $19 million to its MMRP. Air Force officials
said that after the Air Force achieves remedy in place or response
complete at its IRP sites, it will increase funding to address cleanup
needs at its munitions response sites.
Additionally, Army and Navy officials told us that as they continue to
make progress toward completing IRP cleanups, they have begun to
direct more funding to MMRP sites. For example, according to the
Army's fiscal year 2009 environmental restoration program management
plan, the Army expects MMRP funding for active installations to reach
almost $285 million in fiscal year 2011, compared with about $33
million in fiscal year 2008. Furthermore, Navy officials told us that
over the past few years, the Navy has begun shifting some funding from
its IRP to its MMRP. For example, in fiscal year 2005, the Navy
directed about $20 million to its MMRP, while in 2008, it directed
approximately $71 million.
Most Sites That DOD Has Reported as Response Complete Did Not Require
Cleanup, and Cleanup Priorities Are Still Being Determined for the
Majority of Sites:
DOD reported to Congress that it had achieved response complete at
more than one-third of its munitions response sites by the end of
fiscal year 2008. According to DOD, most of these sites did not
require cleanup under the MMRP. For the small number of sites where
the military services and the Corps have conducted cleanup activities
under the MMRP, a variety of factors influenced the selection of these
sites, including immediate danger to public safety and pressing
military mission needs. However, for the majority of sites in the MMRP
inventory, the military services and the Corps are still in the
process of gathering information necessary to assess the sites'
relative risk levels in order to set cleanup priorities. In some
cases, they have also begun to develop approaches to sequencing their
respective sites for cleanup.
Most Sites DOD Reported as Response Complete Did Not Require Cleanup,
although DOD Has Cleaned Up a Small Number of Sites for Various
Reasons:
DOD reported to Congress having achieved response complete at 1,318 of
a total of 3,674 munitions response sites by the end of fiscal year
2008.[Footnote 20] However, according to our analysis of data provided
by the military services and the Corps, 1,234 of these 1,318 sites did
not require actual cleanup under the MMRP and were instead
administratively closed.[Footnote 21] An administrative closure can
occur for a variety of reasons but does not involve any actual cleanup
under the MMRP.[Footnote 22] One of the most common reasons for an
administrative closure was that the sites were investigated and found
to be free of hazards. Our analysis found more than 700 of the 1,234
administratively closed sites were closed because, during the
preliminary assessment, site inspection, or remedial investigation of
the site, the military services and the Corps concluded that the
threats assumed to be present when the site was included in the MMRP
inventory were actually negligible or did not exist.[Footnote 23] For
example, according to a senior Corps official, the Corps assumed that
all FUDS forts and camps had firing ranges and therefore included all
of them in the MMRP inventory. Upon further study, the Corps found
that many former forts and camps did not have firing ranges, so
cleanup under the MMRP at these sites was not necessary. Corps and
military service officials also told us that some sites were
administratively closed for a variety of reasons, such as (1) they
were not eligible for MMRP (either because the sites were funded under
another program--such as the IRP--or were discovered to be currently
in use by the military);[Footnote 24] (2) they were merged with other
sites and therefore ceased to exist as independent sites; (3) they
never actually existed and were added to the inventory in error; or
(4) the hazard was not of DOD origin and therefore not DOD's
responsibility to clean up.
Since 2001, we have been concerned about the lack of clarity in DOD's
approach for reporting on response complete sites. That year we
recommended that DOD exclude projects from its "completed" list that
did not require actual cleanup and were closed solely as the result of
an administrative action.[Footnote 25] According to DOD's Defense
Environmental Restoration Program Management Guidance, response
complete means, in essence, that the military services or the Corps
have taken and completed remedial actions at a site.[Footnote 26]
Nevertheless, the department disagreed with our recommendation, and
its environmental programs annual reports to Congress since 2001 have
continued to report administratively closed sites as response complete
with very limited explanation. Specifically, in its fiscal year 2008
annual report,[Footnote 27] DOD mentioned in a note to a figure that
the response complete category included both sites it cleaned up and
sites that did not require actual cleanup, which we have defined as
administratively closed. A senior DOD official told us that DOD
reports administratively closed sites and sites that were actually
cleaned up as response complete because in both cases it has completed
its response under the CERCLA process. Nonetheless, because DOD does
not clearly and prominently explain in its reports that many of these
sites were not actually cleaned up under the MMRP, we continue to
believe that the information being provided to Congress and the public
is misleading and overstates the level of progress made cleaning up
sites under the MMRP.
Our analysis indicates that the military services and the Corps have
conducted cleanup activities under the MMRP at 84 of the 1,318 sites
it reported as response complete as of fiscal year 2008, as shown in
figure 7.
Figure 7: Sites the Military Services and the Corps Cleaned Up under
the MMRP, as of Fiscal Year 2008:
[Refer to PDF for image: pie-chart]
N = 84.
Air Force: 54;
FUDS: 27;
Navy: 2;
Army: 1.
Source: GAO analysis of DOD data.
[End of figure]
According to military service and Corps officials, these sites were
selected for cleanup based on an assessment of relative risk and other
factors. These other factors included imminent danger to public
safety, pressing military mission needs, land reuse plans, and
stakeholder concerns, for example:
* Imminent danger. According to a senior Army official, the Corps
cleaned up the Dolly Sods North FUDS, located in the Monongahela
National Forest in West Virginia, for imminent danger reasons. This
site had been assigned a medium risk assessment code score.[Footnote
28] Hikers visiting the site--a wilderness area currently owned by the
U.S. Forest Service and visited by approximately 60,000 people
annually--reported finding military munitions on the ground. For
example, in 1996, a piece of live ordnance was found about 300 feet
from a visitor parking lot. As a result, the Corps took cleanup
actions that involved removing ordnance from trail areas and campsites
because it determined that these items presented an imminent danger to
the public. The Corps completed the cleanup in 2000 and also
implemented an explosives safety education program for visitors to the
site, which is ongoing.
* Mission needs. According to Air Force officials, the Air Force
selected the sole munitions response site at Little Rock Air Force
Base in Arkansas for cleanup in fiscal year 2009 to meet mission
needs, even though it received a low prioritization protocol score.
The factors that drove the decision to clean up this site were that
(1) the site is a possible location for a future Security Forces
Regional Training Center, and (2) by cleaning up the only MMRP site on
the base, it would release the entire base from the program and thus
reduce related administrative costs. The Air Force estimates that site
cleanup will be complete in fiscal year 2010.
* Land reuse plans. According to a senior Army official, the Army
funded cleanup work done by a local redevelopment authority on a
munitions response site at Fort Ord, a BRAC installation near
Monterey, California, to meet land reuse plans, even though the Army
assigned the site a medium risk assessment code score and has not
scored it under the munitions response site prioritization protocol.
The Army initiated cleanup at this site largely in response to the
community's request to implement a land reuse plan to construct a
veterans' cemetery. The central California coast region currently
lacks burial space for the approximately 50,000 veterans residing in
the area, some of whom served in World War II and now wish to be
buried at Fort Ord. According to a senior Army official, as of January
2010, the redevelopment authority had completed cleanup, and the
veterans' cemetery can be developed as soon as funding is available.
* Stakeholder concerns. According to a senior Army official, the Corps
decided to clean up the Torpedo and Bombing Range FUDS at Pyramid Lake
northeast of Reno, Nevada, because of stakeholder concerns, even
though the Corps assigned the site a low risk assessment code score.
[Footnote 29] The Corps responded to concerns expressed by the Pyramid
Lake Paiute Tribe by initiating cleanup using funds from FUDS and
another program managed by the Corps, the Native American Lands
Environmental Mitigation Program. Pyramid Lake covers more than 20
percent of the Pyramid Lake Indian Reservation and is of high cultural
and social value to the tribe. The Corps removed surface bunkers and
debris from the site, as well as over 13 tons of rockets and other
discarded munitions submerged in the lake, and cleanup was completed
in 2006.
The Military Services and the Corps Have Evaluated Few Munitions
Response Sites for Relative Risks and Lack Consistent Approaches for
Sequencing Sites:
Before beginning cleanup at most of their munitions response sites,
the military services and the Corps first gather enough information to
use the prioritization protocol to assign a relative priority score to
each site based on its potential environmental and safety hazards.
Officials from the military services and the Corps told us that data
necessary to derive a reliable priority score are gathered during the
site inspection phase. However, as of the end of fiscal year 2008, the
military services and the Corps had completed the site inspection
phase for only 38 percent of munitions response sites.[Footnote 30]
Consequently, during fiscal year 2007--the year the military services
and the Corps began reporting prioritization protocol scores--and
fiscal year 2008, the military services were only able to report
relative priority scores to DOD for 432 sites, or 19 percent of the
2,333 munitions response sites that needed scoring.[Footnote 31]
Specifically, the Air Force reported scores for 53 sites, or 13
percent of its 417 sites; the Army reported scores for 175 sites, or
29 percent of its 603 sites; and the Navy reported scores for 204
sites, or 89 percent of its 230 sites. The military services and the
Corps assigned the remaining 1,901 sites the alternative rating
"evaluation pending" as of the end of fiscal year 2008, indicating
that they needed more information before they could calculate relative
priority scores.
According to a senior Army official, the Corps has not reported any
prioritization protocol scores for FUDS to DOD because the scores have
not yet been finalized pending an internal review. The same official
said that the Corps will report scores for about 600 sites to DOD by
the end of fiscal year 2010 and will report scores for the remaining
sites by fiscal year 2014. The percentage of sites with reported
scores by military service and the Corps is shown in figure 8.
Figure 8: Sites with Prioritization Protocol Scores Reported to DOD,
as of Fiscal Year 2008:
[Refer to PDF for image: vertical bar graph]
Air Force (N = 53):
Percentage of sites reporting scores: 13.
Army (N = 175):
Percentage of sites reporting scores: 29.
Navy (N = 204):
Percentage of sites reporting scores: 89.
FUDS[A] (N = 0):
Percentage of sites reporting scores: 0.
Source: GAO analysis of DOD data.
[A] The Corps has not reported any prioritization protocol scores for
FUDS.
[End of figure]
After they have assigned prioritization protocol scores to all of
their sites, each of the military services and the Corps are to
determine which sites to sequence and allocate funding to first for
the next phase of the cleanup process.[Footnote 32] However, currently
there is no consistent DOD approach for or guidance on considering
factors other than risk in making sequencing decisions. In the absence
of guidance from DOD that establishes a consistent set of
requirements, we found that the Air Force, Army, and the Corps have
begun to independently develop their own approaches for sequencing,
and the Navy has not yet determined whether it needs to develop such
an approach. Specifically, we found the following:
* The Air Force has developed detailed, written guidance for
incorporating factors other than risk into its site sequencing
decisions. The guidance requires the use of a numerical scoring
process that incorporates prioritization protocol scores, as well as
legal, scheduling, and mission factors, to sequence its sites for
cleanup. According to Air Force officials, the Air Force is applying
this approach to a single pool of both IRP and MMRP sites, which they
believe allows them to fund cleanups of the highest-priority sites
first across both programs. In addition, a senior Air Force official
told us that using the standardized process ensures fairness and
transparency in site sequencing.
* According to a senior Army official, the Army is currently
developing a sequencing policy that it hopes to release by May 2010,
which will apply to sites managed by both the Army and the Corps. The
policy will likely require program managers to document the reasons
for their sequencing decisions to facilitate transparency and allow
for more effective Army oversight. However, the official said that the
Army does not plan to require a particular approach to sequencing and
believes a quantitative approach similar to the Air Force's approach
could be too restrictive and not allow adequate flexibility for
decision making.
* According to a senior Navy official, it is too early to determine
whether the Navy needs to issue additional guidance beyond the
framework that establishes the prioritization protocol and sequencing
considerations currently provided in the DOD regulations. According to
the official, although the Navy has initially prioritized many sites
based on preliminary assessment data, it does not expect to begin
fully sequencing sites until 2011, when it completes site inspections
and applies the data gathered to generate relative priority scores.
The Navy will wait to see if it encounters any difficulties before
deciding on whether to develop additional guidance.
According to a senior DOD official, the department plans to give the
military services and the Corps the flexibility to make sequencing
decisions as they see fit. This official said that the military
services and the Corps have experience making sequencing decisions for
the IRP, and DOD has not encountered any problems with these
decisions. As a result, the official said DOD sees no need to provide
guidance on how factors other than risk should be considered when
making decisions about which sites to sequence first for cleanup.
However, in the absence of such guidance, the military services and
the Corps may not consistently (1) consider the same range of factors
in making their decisions or (2) give the same relative significance
to risk and other factors in making their cleanup sequencing
decisions. As a result, we believe that this could impact the
consistency and transparency of sequencing decisions.
DOD Has Not Established a Key Performance Goal for Its MMRP at FUDS,
as Required by Law, and Has Not Determined and Reported on the
Feasibility of Interim Goals:
DOD has not yet implemented the statutory requirement contained in the
fiscal year 2007 National Defense Authorization Act to establish a key
performance goal for reaching remedy in place or response complete at
munitions response sites on FUDS, although DOD has established the
required performance goals for active and BRAC 2005 sites.[Footnote 33]
According to a senior DOD official, the primary reason DOD has not
established a remedy in place or response complete performance goal
for munitions response sites on FUDS is that the Corps has not
completed site inspections at most of these sites. This official told
us that it is not possible to fully understand each site's cleanup
requirements before the site inspection is complete, and therefore,
establishing a goal at this time is premature. In addition, the
official said that the number of munitions response sites on FUDS is
still changing because the Corps is subdividing munitions response
areas into smaller, more manageable sites. The anticipated increase in
the number of sites is likely to impact cleanup schedules, according
to this official. Finally, the official told us that DOD expects to
establish a performance goal for munitions response sites on FUDS
after the Corps completes site inspections, which is expected at the
end of fiscal year 2010. Until DOD sets the goal, Congress and the
public will have less information with which to monitor the progress
of cleanups at munitions response sites on FUDS.
The fiscal year 2007 National Defense Authorization Act also requires
DOD to report "such interim goals as the Secretary determines
feasible" for the military services and the Corps to reach their
remedy in place or response complete performance goals.[Footnote 34]
However, DOD has not yet determined whether such goals are feasible--
the necessary initial step before reporting interim goals. A senior
DOD official said that DOD will determine whether interim goals are
feasible after the military services and the Corps have completed the
site inspection phase for all munitions response sites, which they
expect to do by the end of fiscal year 2010. The DOD official said
that it is not practical for DOD to establish interim goals without
first understanding the nature and extent of cleanup requirements at
munitions response sites. However, DOD was able to establish its
performance goals for reaching remedy in place or response complete
for munitions response sites at active and BRAC 2005 installations,
and we believe DOD should therefore be able to determine the
feasibility of related interim goals. Furthermore, until DOD
determines whether interim goals are feasible, and if so, reports them
to Congress, DOD will not have addressed this requirement. Moreover,
since DOD's MMRP remedy in place or response complete performance
goals are long-term--2017 for sites at BRAC 2005 installations, 2020
for sites at active installations, and possibly 2060 or later for
FUDS--without this determination and reporting of interim goals,
Congress may have limited information with which to measure progress
of the MMRP over the next decade.
DOD Collects Limited Data on Factors That Can Affect MMRP Project
Duration, and Incomplete Data Prevent an Assessment of the Accuracy of
Its MMRP Cost Estimates:
DOD collects data on two of the many factors that can influence
project duration at munitions response sites.[Footnote 35] Our
analysis of DOD's data on these two factors indicates that the larger
the munitions response site and the more complex the type of hazard
the longer the site takes to clean up. However, we were unable to
assess the accuracy of the military services' and the Corps' estimates
of the costs to complete phases of the cleanup process because DOD's
database does not contain complete data on funds obligated for
completing specific phases of the cleanup process for many munitions
response sites.[Footnote 36]
DOD Collects Information on Two Factors That Can Affect MMRP Project
Duration:
Although a number of factors can affect project duration at a
munitions response site, DOD collects information on two of these
factors--site size and the type of hazard. Specifically, DOD requires
the military services and the Corps to report the acreage of sites and
the type of hazard present, such as unexploded ordnance or munitions
constituents. This information is compiled in DOD's environmental
programs management database, known as the Knowledge-Based Corporate
Reporting System. As would be expected, our analysis of DOD's data
shows a relationship between these two factors and project duration--
that the average project duration for a munitions response site
corresponds with the size of the site and the type of hazard. For
example, small munitions response sites have an average project
duration of 4.3 years, whereas larger sites have an average project
duration of 5.9 years. Additionally, sites with the longest project
duration, 5.8 years, were the ones that had unexploded munitions and
ordnance. In contrast, sites with small arms ranges, had an average
project duration of 5 years.
Officials from the military services and the Corps told us that a
number of other factors can influence project duration, but DOD's
database does not include information on these factors, which include
the following:
* The need to achieve consensus with stakeholders, such as regulators
or community members, can increase project duration. For example,
failure to reach consensus with regulators increased project duration
at the Jackson Park Naval Housing Complex, according to Navy
officials. One area of disagreement between Navy officials and federal
regulators was over the number of detected metal pieces that needed to
be excavated during the remedial investigation phase. Federal
regulators wanted the Navy to excavate a higher percentage of detected
metal pieces than the Navy initially intended to excavate. After a
lengthy process, the Navy and federal regulators were able to reach
consensus on the percentage of metal pieces to excavate.
* Obtaining entry rights from current owners of FUDS properties takes
time and can increase project duration. For example, a senior official
from the Corps told us that a landowner at the Campbell Island, North
Carolina, FUDS refused to grant the Corps access to the site because
of dissatisfaction with the government. The site inspection phase was
scheduled to start sometime after December 2008; however, as of
February 2010, the Corps had not yet initiated the site inspection
because the agency has not yet been able to obtain entry rights from
the current landowner. Corps officials plan to contact the landowner
sometime in 2010 in an effort to resolve the issue.
* Site-specific factors arise that can extend project duration in some
cases. For example, Air Force officials told us that strict
requirements from the New Hampshire State Historic Preservation Office
delayed cleanup at New Boston Air Force Base. It took the Air Force
longer to complete the investigative phases of the cleanup process
because the Historic Preservation Office required that all objects
discovered on the site, that were not unexploded ordnances or
munitions constituents, be left in place to allow an archeologist to
photograph and log each item for the historical record.
Incomplete Data Prevent an Assessment of the Accuracy of MMRP Cleanup
Cost Estimates:
We found that DOD lacks complete site-level data on obligated funds
for the three phases of the cleanup process we examined--preliminary
assessment, site inspection, and remedial investigation/feasibility
study--for fiscal years 2001 through 2008. These are funds that DOD
has legally committed to pay for activities conducted during a
particular phase of the cleanup process. Assessing the extent to which
DOD's estimates of costs for MMRP cleanup phases are accurate requires
both data on the estimated costs and funds obligated so they can be
compared to determine how closely the estimates match the obligations.
Our analysis of the 2,611 munitions response sites where work was
conducted during the preliminary assessment phase in fiscal years 2001
through 2008 found that the database did not contain obligated funds
data for 2,272 (or 87 percent) of the sites.[Footnote 37] According to
a senior DOD official, the military services and the Corps often are
unable to report funds obligated for preliminary assessments for
individual sites because they sometimes conduct preliminary
assessments for all sites on an installation at the same time. In
these instances, obligated funds are reported for the entire
installation as opposed to on a site-by-site basis. Moreover,
according to this official, the preliminary assessment and site
inspection phases are often conducted concurrently and obligated funds
for these two phases are consolidated in the site inspection phase.
However, our analysis of the 2,322 munitions response sites where work
was conducted during the site inspection phase in fiscal years 2001
through 2008--including those sites that had a combined preliminary
assessment and site inspection phase--found that the database did not
have obligated funds data for 488 (or 21 percent) of these sites.
Finally, our analysis of the 283 sites where work was conducted during
the remedial investigation/feasibility study phase in fiscal years
2001 through 2008 found the database did not have obligated funds data
for 116 (or 41 percent) of these sites. Figure 9 summarizes our
analysis of the percentage of sites in these three phases of the
cleanup process that did not have obligated funds data.
Figure 9: Percentage of Sites with No Obligated Funds Data, by Phase:
[Refer to PDF for image: 3 pie-charts]
Preliminary assessment phase (by individual site): N = 2,611;
87%: Had no obligated funds data.
Site inspection phase (combined with preliminary assessment): N =
2,322;
21%: Had no obligated funds data.
Remedial investigation/feasibility study phase: N = 283;
41%: Had no obligated funds data.
Source: GAO analysis of DOD data.
[End of figure]
A senior DOD official told us that in fiscal year 2009, DOD
implemented additional, more rigorous quality assurance and control
processes designed to detect errors and inconsistencies in its MMRP
cost estimates. For example, the official said that one of the new
data checks DOD began performing in 2009 was to examine sites
scheduled to begin a cleanup phase in the future to ensure that the
database also includes an estimate of the cost to complete that phase.
However, the official said DOD is not currently evaluating whether the
military services and the Corps are reporting obligated funds data for
project phases that have been completed. DOD requires the military
services and the Corps to gather obligated funds data and, according
to the DOD official, they should be reporting these data to DOD for
inclusion in the Knowledge-Based Corporate Reporting System. In the
absence of complete site-level information on obligated funds, DOD or
Congress may not be able to determine the accuracy of the military
services' and the Corps' reported cost estimates for completing the
various phases of the cleanup process. Furthermore, DOD or Congress
ultimately may not have sufficient information to assess whether DOD's
estimates of its future cleanup liabilities under the MMRP are
reliable.
Conclusions:
Thousands of munitions response sites that potentially pose risks to
human health and the environment may need to be cleaned up before they
can be reused, often for nonmilitary purposes. While we recognize that
managing the MMRP is a large and complex task for DOD, the military
services, and the Corps, we believe that in several areas there are
opportunities for program management improvements. First, there is a
need for guidance on how to conduct site sequencing in a manner that
is consistent and transparent. While Congress mandated a consistent
and transparent approach to assessing relative risks to assign cleanup
priorities at sites, it did not provide for a process for assessing
other factors, such as stakeholder concerns and military mission
needs, when making site sequencing decisions; and DOD has not provided
guidance to the military services and the Corps on how to conduct such
assessments. Without DOD guidance on how to determine which sites to
sequence first for cleanup, we are concerned that the military
services and the Corps could use inconsistent processes for making
these decisions. Second, we remain concerned about the transparency of
DOD's response complete information provided to Congress. DOD has
categorized 1,234 sites as response complete, but these sites did not
require actual cleanup under the MMRP, and we believe that this fact
is not adequately explained in DOD's annual report to Congress. As a
result, Congress and the public may be misled about the extent to
which actual cleanups have taken place under the MMRP to date. Third,
despite a legal requirement to do so, DOD has not yet established the
remedy in place or response complete goal for FUDS nor determined and
reported any interim goals it finds feasible for the MMRP.
Implementing these requirements would provide DOD, Congress, and the
public better information to track progress toward cleaning up
munitions response sites. Finally, the database that DOD uses to help
manage its MMRP does not contain complete site-level data on obligated
funds for the cleanup phases we examined. As a result, it is not
possible to assess the accuracy of the cost estimates for activities
conducted during these phases. As the MMRP matures and more sites
begin actual cleanups, program costs will continue to increase and it
will be critical for DOD to be able to determine whether its cost
estimates for phases of the cleanup process are accurate, so that
Congress and the public can have reasonable assurance that DOD's
estimates of its future cleanup liabilities under the MMRP are likely
to be reliable.
Matter for Congressional Consideration:
To improve transparency for progress DOD has made in cleaning up MMRP
sites, Congress may wish to consider requiring that DOD report, in a
separate category from its accounting of "response complete" sites in
the Defense Environmental Programs Annual Report to Congress, any
sites that DOD determined did not require actual cleanup under the
MMRP and were administratively closed.
Recommendations for Executive Action:
To improve consistency, transparency, and management of the MMRP, we
recommend that the Secretary of Defense take the following three
actions:
* develop guidance for the military services and the Corps that
establishes a consistent approach for how factors other than relative
risk should be considered in munitions response site sequencing
decisions;
* establish and report to Congress (1) a goal for achieving remedy in
place or response complete for FUDS, as required by law, and (2) such
interim goals as DOD determines feasible for the remedy in place or
response complete goals at munitions response sites on active and BRAC
2005 installations and FUDS; and:
* establish a process to ensure the completeness of site-level
obligated funds data in DOD's Knowledge-Based Corporate Reporting
System database.
Agency Comments and Our Evaluation:
We provided a copy of a draft of this report to the Department of
Defense for its review and comment. DOD partially agreed with two of
our recommendations and disagreed with one recommendation and the
matter for congressional consideration.
DOD said that it partially agreed with our first recommendation that
the Secretary of Defense develop guidance for the military services
and the Corps that establishes a consistent approach for how factors
other than relative risk should be considered in munitions response
site sequencing decisions. DOD said that it will collect and evaluate
information and lessons learned from the military services regarding
their processes for sequencing munitions response sites. If DOD
determines that additional guidance is necessary, DOD said it will
develop specific sequencing protocols and issue further guidance to
ensure consistency across the military services. However, DOD did not
specify what additional information it needs to collect from the
military services and the Corps to determine that they currently are
taking different approaches to sequencing their sites for cleanup. Nor
did DOD explain in its comments the need for providing the military
services and the Corps the flexibility to develop different approaches
to sequencing munitions response sites. Given that this flexibility
could result in inconsistent processes for making sequencing
decisions, we continue to believe that DOD needs to provide guidance
to the military services and the Corps that establishes a consistent
approach to sequencing. This guidance will ensure that the military
services and the Corps not only use the Munitions Response Site
Prioritization Protocol to assign site priorities in a consistent and
transparent fashion, but also ensure that they consider the same range
of other factors, in addition to relative risk, in making their
decisions and assess the significance of those factors in a consistent
way.
DOD also partially concurred with our second recommendation, that DOD
establish a goal of remedy in place or response complete for FUDS, as
required by law, and interim goals at munitions response sites on
active and BRAC 2005 installations and FUDS. DOD said that it did not
concur with what it understood to be a separate part of the
recommendation--to set a date for "completing cleanup" of FUDS.
However, we did not intend to convey a further requirement beyond the
remedy in place or response complete goal for FUDS, and we clarified
the recommendation accordingly. DOD said that it will establish a
remedy in place or response complete goal for munitions response sites
at FUDS and will establish additional short-term interim goals for
active and BRAC 2005 installations and FUDS once it has a better
understanding of the nature and extent of cleanup requirements at
these sites. However, DOD has not committed to a date by which it will
establish these goals. We believe it is important for DOD to set these
goals as soon as possible because, until it does so, Congress and the
public will have less information with which to monitor the progress
of cleanups at munitions response sites.
DOD did not agree with our third recommendation to establish a process
to ensure the completeness of site-level obligated funds data in its
Knowledge-Based Corporate Reporting System database. DOD stated that
it has procedures in place to plan, program, budget, and execute funds
for cleanup actions at munitions response sites. DOD also said that it
has information on obligated funds but that it is not typically
available at the individual site level and is tracked outside of the
Knowledge-Based Corporate Reporting System database. Although we
recognize that DOD has these phase-level data in another database, we
continue to believe that without site-level obligations data, DOD does
not have the ability to compare the corresponding cost estimates to
determine if they are accurate. In the absence of such a comparison,
DOD or Congress may not be able to determine the accuracy of the
military services' and the Corps' estimates of the costs to complete
various phases of the cleanup process.
Finally, DOD did not agree with our matter for congressional
consideration that would require DOD to report in a separate category
from its "response complete" sites in the Defense Environmental
Programs Annual Report to Congress any sites that DOD determined did
not require actual cleanup under the MMRP and were administratively
closed. DOD said that it believes that all sites that complete the
CERCLA process should be considered equal accomplishments whether they
require a removal or remedial action or not. DOD also said that it
believes it is misleading to characterize a site that achieves closure
without an actual cleanup differently from one that has been cleaned
up, and that this undermines the significant work and progress DOD has
made. We recognize that DOD must conduct assessments and
investigations to determine that no physical cleanup actions will be
needed and that this process can require significant time and effort
to complete. Nonetheless, we believe it is misleading to group
administratively closed and actually cleaned up sites together because
the actions DOD took to close those two types of sites are
significantly different. Also, we do not believe that listing these
sites in separate categories undermines the progress DOD has made.
Rather, doing so will improve transparency and more clearly indicate
the nature of the actions that DOD has taken to reach response
complete for its munitions response sites. Consequently, we continue
to believe that Congress may wish to consider requiring DOD to report
sites that were administratively closed in a separate category from
those sites requiring actual, physical cleanup.
DOD also provided technical comments in an enclosure to its letter,
which we have incorporated in this report as appropriate. DOD's letter
is included in appendix II.
We are sending copies of this report to the appropriate congressional
committees, the Secretary of Defense, and other interested parties. In
addition, the report will be available at no charge on the GAO Web
site at [hyperlink, http://www.gao.gov].
If you or your staffs have any questions about this report, please
contact me at (202) 512-3841 or mittala@gao.gov. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. GAO staff who made major
contributions to this report are listed in appendix III.
Signed by:
Anu K. Mittal:
Director, Natural Resources and Environment:
[End of section]
Appendix I: Objectives, Scope, and Methodology:
The National Defense Authorization Act for fiscal year 2009 mandates
that we assess the (1) Military Munitions Response Program's (MMRP)
staffing and funding levels; (2) progress the Department of Defense
(DOD) has made cleaning up munitions response sites; (3) extent to
which DOD has established performance goals for the MMRP; and (4)
extent to which DOD collects data on factors influencing project
duration, as well as the accuracy of its cleanup cost estimates.
In addressing these four objectives, we analyzed MMRP data for fiscal
years 2001 through 2008 in DOD's environmental programs management
database--the Knowledge-Based Corporate Reporting System--and the
Defense Environmental Programs Annual Reports to Congress for fiscal
years 2002 through 2008. We assessed the reliability of the data for
relevant variables in the Knowledge-Based Corporate Reporting System
by electronically testing for obvious errors in accuracy and
completeness. We also reviewed information about data verification,
reporting, and security, and the systems that produced the data, and
interviewed officials knowledgeable about the data. When we found
inconsistencies in the data, we worked with the officials responsible
for the data to clarify these inconsistencies before conducting our
analyses. We determined that the data were sufficiently reliable for
the purposes of providing descriptive information about the MMRP and
for analyzing the duration of phases of the MMRP cleanup process.
However, we found MMRP obligated funds data to be incomplete and
therefore not suitable for analysis. We discuss this data reliability
issue in more detail later in this appendix. In addition, we reviewed
key laws, regulations, policies, and guidance from DOD, the military
services (Army, Air Force, and Navy),[Footnote 38] and the U.S. Army
Corps of Engineers (Corps). We visited one base realignment and
closure (BRAC) installation (Fort Ord), one active installation (Beale
Air Force Base), and one formerly used defense site (FUDS) (Camp
Beale) to ensure we had the opportunity to review MMRP operations at
active and BRAC installations and FUDS. We also interviewed
headquarters and regional officials from the Environmental Protection
Agency to discuss the MMRP.
To assess the military services' and the Corps' MMRP staffing and
funding levels, we spoke with senior officials from the Office of the
Deputy Under Secretary of Defense (Installations and Environment), the
military services, and the Corps who are knowledgeable about how MMRP
staffing and funding levels are determined. In addition, we reviewed
the Defense Environmental Programs Annual Reports to Congress for
fiscal years 2002 through 2008 to determine funding obligated for the
MMRP.
To assess the progress DOD has made in cleaning up munitions response
sites, we identified, as of the end of fiscal year 2008, how many
sites DOD had administratively closed and how many had been actually
cleaned up. We defined a site as administratively closed if after
investigating, DOD determined that it could safely close the site
without taking remedial action. Specifically, we analyzed data in the
Knowledge-Based Corporate Reporting System to identify sites that fit
two criteria: (1) the "response complete"[Footnote 39] date matched
the end date for the three investigative phases during which no
remediation actions are taken (preliminary assessment, site
inspection, and remedial investigation) and (2) no costs were reported
in the remedial action construction or the remedial action operations
phase. Senior officials from DOD, the military services, and the Corps
agreed that these criteria would identify sites that had been closed
without actual cleanup, which we have defined as being
administratively closed. These criteria allowed us to identify 712 of
the 1,318 sites DOD reported as having achieved response complete.
However, we were unable to determine if any of the remaining 606 sites
had been administratively closed because sites may have been
administratively closed without the response complete date matching
the end date of one of the investigative phases. Therefore, we asked
the military services and the Corps to identify which sites they had
administratively closed. The Air Force and the Navy were able to
provide the information for their relatively small number of sites,
but senior Army and Corps officials said they did not keep such
information in a centralized database and it would take them too much
time to gather it for their many sites. Instead, they provided us with
the number of sites they had actually cleaned up and indicated that we
could assume the remaining sites had been administratively closed. In
addition, we assessed the progress the military services and the Corps
have made in applying the Munitions Response Site Prioritization
Protocol to generate relative priority scores for their sites by
reviewing prioritization protocol data in the Knowledge-Based
Corporate Reporting System. We considered a site to be scored if it
was listed in the Knowledge-Based Corporate Reporting System as having
a numerical relative priority score of one through eight or if it had
been given the alternative designation of "no known or suspected
hazard" as of the end of fiscal year 2008. We considered sites to not
be scored if they had a designation of "evaluation pending" because
this designation indicates that the military services or the Corps
need more information to assign the site a relative priority score. We
excluded from our analysis the 1,341 sites for which the military
services and the Corps indicated that scoring was no longer required
because DOD reported that most of these sites had already reached
response complete.
To assess the extent to which DOD has established performance goals
for the MMRP, we reviewed the fiscal year 2007 National Defense
Authorization Act, the Military Munitions Response Program
Comprehensive Plan, and the fiscal year 2008 Defense Environmental
Programs Annual Report to Congress. We also spoke with a senior
official responsible for the MMRP from the Office of the Deputy Under
Secretary of Defense (Installations and Environment) to determine the
progress DOD has made in establishing performance goals.
To assess the extent to which DOD collects data on factors influencing
project duration, we reviewed and analyzed data from the Knowledge-
Based Corporate Reporting System to determine the average length of
time munitions response sites have been in the cleanup process. To
determine project duration, we attempted to identify start and end
dates for phases of the cleanup process for all 3,674 sites in the
Knowledge-Based Corporate Reporting System. We measured project
duration as the length of time between the earliest phase start date
and the latest phase end date, calculated using both month and year
information.[Footnote 40] Using this method, we were able to calculate
project duration for 3,112 sites. We were unable to calculate project
duration for 47 sites because they had no phase dates in the Knowledge-
Based Corporate Reporting System. We did not calculate project
duration for the remaining 515 sites because they had phase start and
end dates prior to fiscal year 2001 (when the MMRP was established)
and were therefore outside the scope of this review. Next, we analyzed
site size and type to assess their relationship to project duration.
To analyze site size, we divided the list of sites into three
similarly sized categories: (1) small (less than 23 acres); (2) medium
(between 23 and 649 acres); (3) large (650 acres or larger). We also
created a fourth category for sites reported as zero acres or those
with missing size data. Once we assigned sites to a category, we were
able to combine this analysis with our analysis on project duration to
calculate the mean and median project duration for small, medium, and
large sites. We reported the mean project duration in the report, and
there was no substantive difference between the mean and median. We
used the site-type data in the Knowledge-Based Corporate Reporting
System to determine the relationship between project duration and type
of hazard. We limited our analysis of site types to categories that
included at least 5 percent of the total number of sites and then
combined the remaining categories into an "other" category. This
allowed us to analyze project duration for six site-type categories:
(1) unexploded munitions and ordnance areas, (2) small arms ranges,
(3) firing ranges, (4) explosive ordnance disposal areas, (5) other,
and (6) unknown (i.e., information on site type was not available).
Once we had determined these categories, we combined this analysis
with our project duration analysis to calculate the mean and median
project duration for each site type. We reported the mean project
duration in the report, and there was no substantive difference
between the mean and median. We also interviewed senior officials from
the military services and the Corps to obtain their views on factors
influencing project duration.
To assess the accuracy of DOD's cleanup cost estimates, we assessed
the reliability of data on obligated funds in the Knowledge-Based
Corporate Reporting System for fiscal years 2001 through 2008. We
analyzed the data to determine the extent to which sites with reported
activities in three phases of the cleanup process also included data
on funds obligated for those activities. We restricted our analysis to
the first three phases of the cleanup process--preliminary assessment,
site inspection, and remedial investigation/feasibility study--because
most munitions response sites are in one of these phases. To determine
if we had a sufficient number of sites to conduct our analysis, we
calculated the number of sites in each of the three phases that had
obligated funds data. We found that over 10 percent of sites for all
three phases were missing obligated funds data. Therefore, we
concluded that the data were not sufficiently reliable to allow us to
compare obligated funds to cost estimates for the sites in all three
phases to determine the accuracy of the estimates.
We conducted this performance audit from January 2009 to April 2010 in
accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
[End of section]
Appendix II: Comments from the Department of Defense:
Office Of The Under Secretary Of Defense:
3000 Defense Pentagon:
Washington, DC 20301-3000:
March 31, 2010:
Ms. Anu K. Mittal:
Director, Natural Resources and Environment:
U.S. Government Accountability Office:
441 G Street, N.W.
Washington, DC 20548:
Dear Ms. Mittal:
This is the Department of Defense (DoD) response to the GAO Draft Report
10-384, "Military Munitions Response Program, Opportunities Exist to
Improve Program Management," dated March 2010, (GAO Code 361041).
DoD's detailed responses to the GAO recommendations and the matter for
Congressional consideration are provided at Enclosure 1. Enclosure 2
provides additional substantive issues DoD has with the GAO draft
report. Additional technical comments have been provided to GAO under
separate cover.
The Department partially concurs with GAO's first recommendation that
the Secretary of Defense develop guidance that establishes a
consistent approach for how the Military Services consider factors
other than relative risk in munitions response site sequencing
decisions. DoD will collect and evaluate information and lessons
learned from the Military Services describing their processes for
sequencing munitions response sites for munitions response activities.
if additional guidance is necessary, DoD will develop specific
sequencing protocols and issue further guidance to ensure consistency
across the Military Services.
The Department partially concurs with GAO's second recommendation that
the Secretary of Defense establish and report to Congress: (1) a
target date for completing cleanup of Formerly Used Defense Sites
(FUDS), as required by law; and (2) such interim goals as DoD
determines feasible for the remedy in place or response complete goals
at munitions response sites on active installations, installations
closed under the 2005 Round of Base Realignment And Closures (BRAC),
and FUDS. The Fiscal Year (FY) 2007 National Defense Authorization Act
(NDAA) requires DoD to establish a remedy in place or response
complete goal for munitions response sites at FUDS; DoD will set
target dates for remedy in place or response complete, not for
completing cleanup. The FY2007 NDAA also requires DoD to establish
interim goals to track remedy in place or response complete
progress at active and BRAC 2005 installations and FUDS properties.
DoD will comply with the requirements outlined in the FY2007 NDAA
establishing additional short- and long-term performance goals once it
has a better understanding of the nature and extent of cleanup
requirements at these sites.
The Department does not concur with GAO's third recommendation that
the Secretary of Defense establish a process to ensure the
completeness of obligated funds data for phases of the Military
Munitions Response Program cleanup process in DoD's Knowledge-Based
Corporate Reporting System database. GAO's suggestion that obligated
funds are incomplete is not correct. Obligated funds data are
available but are not typically reported for individual sites because
contracts are often awarded at the installation-level or for groups of
sites. Further, the Department has procedures in place to plan,
program, budget, and execute funds for cleanup actions by phase at
munitions response sites.
The Department does not concur with GAO's request for Congress to
consider requiring DoD to report separately on sites closed because
they did not require removal or remedial actions. DoD believes that
all sites that complete the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA) process should be considered
equal accomplishments whether they require a removal or remedial
action or not. The Department expends significant resources to conduct
preliminary assessments, site inspections, remedial investigations,
and feasibility studies to determine and document that it has met its
cleanup objectives, and that there is no requirement for removal or
remedial action. When the Department meets the cleanup objectives at a
given site, the response action is complete, regardless of the phase
of the CERCLA process in which the action is completed.
Sincerely,
Signed by:
Dorothy Robyn:
Deputy Under Secretary of Defense (Installations and Environment):
Enclosures: As stated:
GAO Draft Report Dated March 2010:
GAO-10-384 (GAO CODE 361041):
Enclosure 1:
"Military Munitions Response Program, Opportunities Exist to Improve
Program Management"
Department Of Defense Comments To The GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretary of Defense
develop guidance for the Military Services and the Corps that
establishes a consistent approach for how factors other than relative
risk should be considered in munitions response site sequencing
decisions. (p. 33/GAO Draft Report)
DOD Response: DoD partially concurs. OSD believes that it has issued
sufficient guidance on this subject at this time. This guidance
appears in the Final Rule of the Munitions Response Site
Prioritization Protocol (32 CFR Part 179) and is further explained in
OSD's internal publication entitled Munitions Response Site
Prioritization Protocol Primer, dated April 2007. Using the guidance
provided in these documents, the Military Services sequence munitions
response sites based primarily on the priority determined by applying
the Munitions Response Site Prioritization Protocol, but also consider
a range of factors including, but not limited to regulator and
stakeholder concerns, and cultural, social and economic issues. These
site-specific factors may influence the sequencing decision, but do
not alter the priority. In the past three years of implementing this
guidance, the Military Services have tested various sequencing
practices and learned from their experiences in the field. Next year,
after the Military Services begin sequencing their munitions response
sites in earnest, OSD will collect and evaluate information and
lessons learned from the Military Services describing their processes
for sequencing munitions response sites for cleanup action. If we
determine that the current amount of flexibility enjoyed by the
Military Services is causing issues, OSD will consider developing
additional guidance to establish more uniformity across the Military
Services.
Recommendation 2: The GAO recommends that the Secretary of Defense
establish and report to Congress (1) a target date for completing
cleanup of FUDS, as required by law, and (2) such interim goals as DoD
determines feasible for the remedy in place or response complete goals
at munitions response sites on active and BRAC 2005 installations and
FUDS. (p. 33/GAO Draft Report)
DOD Response: DoD partially concurs. The FY2007 National Defense
Authorization Act requires the Secretary to establish a remedy in
place or response complete goal for FUDS. The legislation does not
require DoD to set a target date for completing cleanup of 1,111)S;
therefore, DoD does not concur with this part of the recommendation.
In addition, the law does not require DoD to establish these goals
within any certain timeframe.
The Military Services are currently completing site inspections on a
very aggressive schedule at munitions response sites on active
installations and FUDS properties. The data gathered during the site
inspection phase are critical to informing DoD of cleanup
requirements. Specifically, the site inspection data is necessary to
determine how many sites will require additional response actions
under the Military Munitions Response Program (MMRP) and the potential
scope of the work. Once the site inspections are complete and the
Department has sufficient information about site-specific conditions,
DoD will evaluate performance data to understand the nature and extent
of cleanup requirements. The Department will use this analysis to meet
its statutory requirement to establish a long-term remedy in place or
response complete goal for FUDS. In addition, DoD will establish short-
term interim goals for active and BRAC 2005 installations and FUDS
properties that are both challenging and reasonable.
Recommendation 3: The GAO recommends that the Secretary of Defense
establish a process to ensure the completeness of obligated funds data
for phases of the MMRP cleanup process in DOD's Knowledge Based
Corporate Reporting System database. (p. 33/GAO Draft Report)
DOD Response: DoD does not concur. The Department has procedures in
place to plan, program, budget, and execute funds for cleanup actions
at munitions response sites. The Military Services prepare cost
estimates for future work at the site-level, while obligation data is
often aggregated across multiple sites because contracts arc typically
awarded at the installation-level or for a group of sites. The cost
estimating programs DoD uses are based on ongoing and detailed data
gathering on costs incurred for various types of environmental
restoration work at a very detailed level. The Military Services
report this data in DoD's Knowledge-Based Corporate Reporting System
database. The Department reviews this data for accuracy and
completeness prior to inclusion of the site-level obligations and cost
estimates in the Defense Environmental Programs Annual Report to
Congress. The Military Services also report obligations and cost
estimates at the phase-level in the Select and Native Programming Data
Input System. Because this data is at the phase- rather than site-
level, obligations for contracts awarded at the installation-level or
for a group of sites are captured in the system. this information is
reported in the Defense Environmental Programs Annual Report to
Congress. Thus, complete obligation data is captured and provided to
Congress and the public, but the Knowledge-Based Corporate Reporting
System is not the source of the data.
Congressional Consideration: The GAO recommends a matter for
Congressional Consideration. To improve transparency for progress DoD
has made in cleaning up MMRP sites, Congress may wish to consider
requiring that DoD report in a separate category from its accounting
of "response complete" sites in the Defense Environmental Programs
Annual Report to Congress, any sites that DoD determined did not
require actual cleanup under the MMRP and were administratively
closed. (p.33/GAO Draft Report)
DOD Response: DoD does not concur. DoD believes that sites achieving
all cleanup objectives at any point in the process can be
characterized as response complete under the Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA),
whether they require a removal or remedial action or not. DoD objects
to a separate classification of "administrative closure" to categorize
sites that did not require a removal or remedial action because CERCLA
and the National Oil and Hazardous Substances Pollution Contingency
Plan (NCP) do not distinguish the status of sites where response
complete is determined early in the process from those where response
complete is determined alter active remediation. Furthermore, the NCP
requires that a "no action" alternative be evaluated throughout the
investigative phase and selected in the Record of Decision if the
standards arc already satisfied or there is no risk, so that
unnecessary actions are not taken using taxpayer funds or required by
responsible parties.
In addition, the Department expends significant resources to conduct
preliminary assessments, site inspections, remedial investigations,
and feasibility studies to determine and document that it has met its
cleanup objectives, and that there is no requirement for removal or
remedial action. When the Department meets the cleanup objectives at a
given site, the response action is complete, regardless of the phase
of the CERCLA process in which the action is completed. It is
misleading to characterize a site that achieves closure without a
removal or remedial action differently from sites characterized as
response complete after active remcdiation. This undermines the
significant work and progress, including collaboration and work with
regulators and stakeholders, that the Department is making under the
MMRP.
The term "response complete" is appropriate for the purposes of MMRP
metrics and reporting because it reflects that the necessary CERCLA
response actions for which the Department is responsible have been
completed. "Response complete" is used by DoD to track progress, but
is not used to communicate with the pubic regarding the protectiveness
of the situation at a specific site. Finally, this term is accurate
and does not misrepresent progress because it means that further
response work, other than possibly long-term management, is not
required. This is what DoD is required to report and is an accurate
representation of progress by the program in the completion of
necessary CERCLA response actions under the Defense Environmental
Restoration Program.
In the past, DoD has identified some sites that it believed required
cleanup, but later determined that these sites did not require actions
under CERCLA. For example, some sites were funded under the
Installation Restoration Program, some sites were double counted, and
some sites never existed and were added to the inventory in error. DoD
stopped reporting these sites in its inventory beginning with the
FY2009 Defense Environmental Programs Annual Report to Congress.
[End of section]
Appendix III: GAO Contact and Staff Acknowledgments:
GAO Contact:
Anu K. Mittal, Director, (202) 512-3841 or mittala@gao.gov:
Staff Acknowledgments:
In addition to the individual named above, Stephen D. Secrist,
Assistant Director; Leo G. Acosta; Elizabeth Beardsley; Mark Braza;
Nancy Crothers; Pamela Davidson; Janida Grima; Amanda Leissoo; Laina
Poon; and Kim Raheb made significant contributions to this report.
[End of section]
Footnotes:
[1] For complete definitions, see 10 U.S.C. §§ 2710(e)(2)-(3),
101(e)(5) (2010).
[2] To be eligible for FUDS cleanup under the Installation Restoration
Program and the Military Munitions Response Program, according to the
Defense Environmental Restoration Program Management Guidance (2001)
and FUDS program policy, a property must have been under the
jurisdiction of DOD and owned by, leased to, or otherwise possessed by
the United States at the time of actions leading to contamination by
hazardous substances prior to October 17, 1986. This jurisdiction
extends to governmental entities that are the legal predecessors of
DOD or the components--Army, Navy and Marine Corps, Air Force, and the
Defense Logistics Agency.
[3] DOD also operates the much smaller Building Demolition/Debris
Removal Program to address the demolition and removal of unsafe
buildings or structures at facilities or sites that meet specified
criteria.
[4] The Department of the Navy implements the MMRP at both Navy and
Marine Corps munitions response sites.
[5] The Army is the executive agent for the FUDS program but has
delegated day-to-day program management and execution responsibilities
to the U.S. Army Corps of Engineers.
[6] Duncan Hunter National Defense Authorization Act for Fiscal Year
2009, Pub. L. No. 110-417, § 345, 122 Stat. 4425 (2008).
[7] Pub. L. No. 107-107 §§ 311(a), (c) (2001); 10 U.S.C. § 2710 (2010).
[8] American Samoa, Guam, Puerto Rico, the U.S. Virgin Islands, the
Commonwealth of the Northern Mariana Islands, and Wake Island are all
U.S. territories. The Marshall Islands is associated with the United
States through a Compact of Free Association.
[9] Stakeholders for military munitions cleanups include, but are not
limited to, federal and state environmental protection agencies,
federal land managers, environmental and other advocacy groups, and
members of the general public.
[10] Pub. L. No. 107-107 §§ 311(b)(1) (2001); 10 U.S.C. § 2710(b)(1)
(2010).
[11] 70 Fed. Reg. 58,016 (Oct. 5, 2005) (codified at 32 C.F.R. Pt. 179
(2010)).
[12] The Explosive Hazard Evaluation module provides a single DOD-wide
approach for the evaluation of explosive hazards posed by unexploded
ordnance, discarded military munitions or munitions constituents.
Similarly, the Chemical Warfare Materiel Hazard Evaluation module
provides evaluation of the chemical hazards associated with the
physiological effects of chemical warfare material such as chemical
munitions or toxic chemical agents. Finally, the Health Hazard
Evaluation module provides a process for evaluating the relative risk
to human health and the environment posed by munitions constituents.
[13] For complete definitions, see 32 C.F.R. § 179.6(d)(4)-(5) (2010).
[14] Pub. L. No. 96-510, as amended. A key law amending CERCLA was the
Superfund Amendments and Reauthorization Act of 1986, Pub. L. No. 99-
499 (1986), which provided that federal agencies "shall be subject to,
and comply with, this Act in the same manner and to the same extent,
both procedurally and substantively," as any private party. Id., §
120. See 42 U.S.C. § 9620 (2010).
[15] For complete descriptions, see 40 C.F.R. §§ 300.420, 300.430,
300.435 (2010).
[16] After a site reaches response complete, the military services and
the Corps may conduct long-term management at the site. For example,
they may monitor environmental conditions, enforce land use controls,
and maintain any remedies to ensure continued protection as designed.
Long-term management occurs until no further environmental restoration
response actions are appropriate or anticipated.
[17] John Warner National Defense Authorization Act for Fiscal Year
2007, Pub. L. No. 109-364, § 313, 120 Stat. 2083, 2138 (2006).
[18] For the purpose of this report, the amount of money the military
services and the Corps obligated for MMRP activities is used to
approximate funding received.
[19] The term "obligations" refers to the amount of money the military
services and the Corps legally committed for payment.
[20] DOD, Defense Environmental Programs Annual Report to Congress
(Fiscal Year 2008), pp.16-17.
[21] DOD views "cleanup" as any activity that falls within the CERCLA
process, including studies and investigation. While we acknowledge
that these are critical steps in the CERCLA process, for purposes of
this report we distinguish between these activities conducted during
the earlier phases of the CERCLA process from activities undertaken
during the remedial action phase. Specifically, we refer to activities
undertaken during the remedial action phase as "actual cleanup"
because activities in this phase usually involve physical, on-site
work to remedy hazards. We refer to sites that DOD determined needed
no remedial action as "administratively closed."
[22] Although administratively closed sites did not undergo remedial
actions, according to military service and Corps officials, actions
intended to reduce risk, such as erecting fences or warning signs, may
have been taken at some sites during the investigative phases.
[23] Our analysis of available data indicated the military services
and the Corps investigated 741 sites and found them to be free of
hazards. However, Army and Corps officials believe there were likely
additional response complete sites where no hazard was present, but
they were not able to provide us with a specific number.
[24] The services and the Corps may have cleaned up some munitions
response sites under the IRP before the MMRP was established as a
separate program in 2001. Operational ranges are excluded from the
MMRP. A senior DOD official explained that cleaning up munitions--
beyond normal clearance operations--from past military actions while
new munitions are being deposited by current activities would waste
resources.
[25] GAO, Environmental Contamination: Cleanup Actions at Formerly
Used Defense Sites, [hyperlink,
http://www.gao.gov/products/GAO-01-557] (Washington, D.C.: July 31,
2001).
[26] To reach response complete, any operations required for the
remedial action must also be completed. For example, a groundwater
pump-and-treat system would need to operate for some period of time
before the cleanup objective could be accomplished and the site could
be considered response complete.
[27] DOD's fiscal year 2008 annual report is the most recent report as
of April 2010.
[28] Risk assessment code scores were used to rank sites by relative
risk prior to 2007 when the military services and the Corps began
reporting scores based on the Munitions Response Site Prioritization
Protocol. This site would not have been scored using the
prioritization protocol because it was cleaned up in 2000.
[29] This site would not have been scored using the Munitions Response
Site Prioritization Protocol because cleanup was completed in 2006.
[30] Thirty-eight percent represents the number of sites that had a
site inspection completion date in DOD's Knowledge-Based Corporate
Reporting System database.
[31] The military services and the Corps reported that 1,341 munitions
response sites no longer required scoring using the Munitions Response
Site Prioritization Protocol, primarily because they categorized the
sites as response complete.
[32] DOD's regulation establishing the Munitions Response Site
Prioritization Protocol provides for subsequent sequencing to consider
other factors and provides a nonexclusive list of example factors,
such as mission needs and stakeholder input. The military services and
the Corps are to use their installation-specific management action
plans--plans that describe an integrated, coordinated approach for
conducting all required environmental restoration activities,
including schedules and cost estimates--as a vehicle for sequencing.
The regulation does not, however, establish a methodology for how such
other factors are to be considered.
[33] After a final remedial action has been constructed and is
operating as planned, DOD describes the site status as remedy in
place. While operation of the remedy is ongoing but cleanup objectives
have not yet been met, the site cannot be considered response
complete. DOD categorizes sites as response complete at any point in
the process when it determines no further response is appropriate,
including sites without a remedy in place. According to DOD, such
determinations are made in conjunction with regulators and
stakeholders.
[34] The act requires the reporting of such feasible interim goals in
association with the remedy in place or response complete performance
goals for munitions response sites at active and BRAC 2005
installations, and FUDS.
[35] We measured project duration, which was calculated using both
month and year information, as the length of time between the earliest
phase start date and the latest phase end date. For the purposes of
our analysis, if the most recent phase was still in process, we used
September 2008 as the end date because that was the latest date for
which we had Knowledge-Based Corporate Reporting System data.
[36] The military services and the Corps report funds obligated for
cleanup activities at munitions response sites in a fiscal year to DOD.
[37] We did not conduct a similar analysis on the extent to which DOD
had complete data on cost estimates.
[38] The Department of the Navy (Navy) implements the MMRP at both
Navy and Marine Corps munitions response sites.
[39] After the military services or the Corps completes its response
to potential military munitions hazards, and when no further response
action is appropriate, DOD describes the site's status as "response
complete."
[40] If the latest phase did not have an end date, we used September
2008 as the end date because we assumed that the site was still in
that phase at the end of fiscal year 2008, the year for which we had
Knowledge-Based Corporate Reporting System data.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: