Defense Acquisitions
CH-53K Helicopter Program Has Addressed Early Difficulties and Adopted Strategies to Address Future Risks
Gao ID: GAO-11-332 April 4, 2011
The United States Marine Corps is facing a critical shortage of heavy-lift aircraft. In addition, current weapon systems are heavier than their predecessors, further challenging the Marine Corps's current CH-53E heavy-lift helicopters. To address the emerging heavy-lift requirements, the Marine Corps initiated the CH-53K Heavy Lift Replacement program, which has experienced significant cost increase and schedule delays since entering development in 2005. This report (1) determines how the CH-53K's estimates of cost, schedule, and quantity have changed since the program began development and the impact of these changes and (2) determines how the CH-53K's current acquisition strategy will meet current program targets as well as the warfighter's needs. To address these objectives, GAO analyzed the program's budget, schedules, acquisition reports, and other documents and interviewed officials from the program office, the prime contractor's office, the Marine Corps, the Defense Contract Management Agency, and the Office of the Secretary of Defense.
The CH-53K helicopter mission is to provide combat assault transport of heavy weapons, equipment, and supplies from sea to support Marine Corps operations ashore. Since the program began development in December 2005, its total cost estimate has grown by almost $6.8 billion, from nearly $18.8 billion to over $25.5 billion as a result of a Marine Corps-directed quantity increase from 156 to 200 aircraft and schedule delays. The majority of the program's total cost growth is due to added quantities. Development cost growth and schedule delays resulted from beginning development before determining how to achieve requirements within program constraints, with miscommunication between the program office and prime contractor about systems engineering tasks and with late staffing by both the program office and the contractor. The program has also deferred three performance capabilities and relaxed two maintenance-based technical performance metrics in an effort to defer cost. Delivery of the CH-53K to the warfighter is currently scheduled for 2018--a delay of almost 3 years. The CH-53K program has made progress addressing the difficulties it faced early in system development. It held a successful critical design review in July 2010 and has adopted mitigation strategies to address future program risk. The program's new strategy, as outlined in the President's fiscal year 2012 budget, lengthens the development schedule, increases development funding, and delays the production decision. However, adjustments made to the budget submitted to Congress reduce the program's fiscal year 2012 development funding by $30.5 million (and by a total of $94.6 million between fiscal years 2010 and 2015). According to information contained in the budget, this reduction would result in additional schedule delays to the program of approximately 7 months and a net increase of $69 million to the total development cost estimate. The CH-53K program's new acquisition strategy addresses previous programmatic issues that led to early development cost growth and schedule delays.
GAO-11-332, Defense Acquisitions: CH-53K Helicopter Program Has Addressed Early Difficulties and Adopted Strategies to Address Future Risks
This is the accessible text file for GAO report number GAO-11-332
entitled 'Defense Acquisitions: CH-53K Helicopter Program Has
Addressed Early Difficulties and Adopted Strategies to Address Future
Risks' which was released on April 4, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
Report to the Ranking Member, Subcommittee on Defense, Committee on
Appropriations, House of Representatives:
April 2011:
Defense Acquisitions:
CH-53K Helicopter Program Has Addressed Early Difficulties and Adopted
Strategies to Address Future Risks:
GAO-11-332:
GAO Highlights:
Highlights of GAO-11-332, a report to the Ranking Member, Subcommittee
on Defense, Committee on Appropriations, House of Representatives.
Why GAO Did This Study:
The United States Marine Corps is facing a critical shortage of heavy-
lift aircraft. In addition, current weapon systems are heavier than
their predecessors, further challenging the Marine Corps‘s current CH-
53E heavy-lift helicopters. To address the emerging heavy-lift
requirements, the Marine Corps initiated the CH-53K Heavy Lift
Replacement program, which has experienced significant cost increase
and schedule delays since entering development in 2005.
This report (1) determines how the CH-53K‘s estimates of cost,
schedule, and quantity have changed since the program began
development and the impact of these changes and (2) determines how the
CH-53K‘s current acquisition strategy will meet current program
targets as well as the warfighter‘s needs. To address these
objectives, GAO analyzed the program‘s budget, schedules, acquisition
reports, and other documents and interviewed officials from the
program office, the prime contractor‘s office, the Marine Corps, the
Defense Contract Management Agency, and the Office of the Secretary of
Defense.
What GAO Found:
The CH-53K helicopter mission is to provide combat assault transport
of heavy weapons, equipment, and supplies from sea to support Marine
Corps operations ashore. Since the program began development in
December 2005, its total cost estimate has grown by almost $6.8
billion, from nearly $18.8 billion to over $25.5 billion as a result
of a Marine Corps-directed quantity increase from 156 to 200 aircraft
and schedule delays. The majority of the program‘s total cost growth
is due to added quantities. Development cost growth and schedule
delays resulted from beginning development before determining how to
achieve requirements within program constraints, with miscommunication
between the program office and prime contractor about systems
engineering tasks and with late staffing by both the program office
and the contractor. The program has also deferred three performance
capabilities and relaxed two maintenance-based technical performance
metrics in an effort to defer cost. Delivery of the CH-53K to the
warfighter is currently scheduled for 2018-”a delay of almost 3 years.
The CH-53K program has made progress addressing the difficulties it
faced early in system development. It held a successful critical
design review in July 2010 and has adopted mitigation strategies to
address future program risk. The program‘s new strategy, as outlined
in the President‘s fiscal year 2012 budget, lengthens the development
schedule, increases development funding, and delays the production
decision. However, adjustments made to the budget submitted to
Congress reduce the program‘s fiscal year 2012 development funding by
$30.5 million (and by a total of $94.6 million between fiscal years
2010 and 2015). According to information contained in the budget, this
reduction would result in additional schedule delays to the program of
approximately 7 months and a net increase of $69 million to the total
development cost estimate. The CH-53K program‘s new acquisition
strategy addresses previous programmatic issues that led to early
development cost growth and schedule delays.
Figure: Comparison of the CH-53K‘s Original and New Schedules:
[Refer to PDF for image: time line]
Original schedule:
FY06: Milestone B;
FY07: Preliminary design review;
FY09: Critical design review;
FY09-FY12: Test articles production and delivery;
FY11-FY16: Testing;
FY12: Milestone C;
FY13-14: LRIP Lot 1 (6);
FY14-16: LRIP Lot 2 (9);
FY14-17: LRIP Lot 3 (14);
FY16: Initial operational capacity;
FY16-FY20 and beyond: Full rate production (FRP) Lots 4-9 (127).
New schedule:
FY06: Milestone B;
FY09: Preliminary design review;
FY10: Critical design review;
FY11-FY14: Test articles production and delivery;
FY13: First flight;
FY13-FY19: Testing;
FY15: Milestone C;
FY16-19: LRIP Lot 1 (6);
FY18-19: LRIP Lot 2 (9);
FY19-20: LRIP Lot 3 (14);
FY19: Initial operational capacity;
FY16-FY20 and beyond: Full rate production (FRP) Lots 4-9 (171).
Source: GAO analysis of United States Marine Corps data.
[End of figure]
View [hyperlink, http://www.gao.gov/products/GAO-11-332] or key
components. For more information, contact Michael J. Sullivan at (202)
512-4841 or sullivanm@gao.gov.
[End of section]
Contents:
Letter:
Background:
CH-53K Cost Growth, Schedule Delays, and Deferred Capabilities Will
Affect Delivery to the Warfighter:
CH-53K Program Has Made Progress and Adopted Strategies to Address
Future Risk:
Agency Comments:
Appendix I: Scope and Methodology:
Appendix II: GAO Contact and Staff Acknowledgments:
Table:
Table 1: Changes in Estimated Costs, Quantities, and Major Events:
Figures:
Figure 1: Comparison of CH-53E and CH-53K Capabilities and
Characteristics:
Figure 2: Marine Corps Heavy-Lift Helicopter Force Structure:
Figure 3: Comparison of the CH-53K's Original and New Schedules:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
April 4, 2011:
The Honorable Norman D. Dicks:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
House of Representatives:
Dear Mr. Dicks:
The United States Marine Corps is facing a critical shortage in the
number of Marine expeditionary heavy-lift aircraft, currently its CH-
53E helicopters. Although all available decommissioned CH-53E
helicopters have been overhauled for use, according to program
officials, currently deployed CH-53E aircraft are flying at three
times their planned utilization rate. In addition, current weapon
systems are heavier than their predecessors, further challenging the
Marine Corps‘s current CH-53E heavy-lift helicopters. To address the
emerging heavy-lift requirements, the Marine Corps initiated the CH-
53K Heavy Lift Replacement program. The total program is expected to
cost significantly more than originally planned and deployment has
been significantly delayed. As a result, you asked GAO to (1)
determine how the CH-53K‘s estimates of cost, schedule, and quantity
changed since the program began development and the overall impact of
these changes and (2) determine how the CH-53K‘s current acquisition
strategy will meet current program targets as well as the warfighter‘s
needs.
To determine how the CH-53K‘s estimates of cost, schedule, and
quantity have changed since the program began development, we received
briefings from program and contractor officials and reviewed budget
documents, annual Selected Acquisition Reports, monthly status
reports, performance indicators, and other data. To identify the CH-53K‘
s current acquisition strategy and determine how this strategy will
meet current program targets as well as the warfighter‘s needs, we
reviewed the program‘s original and current acquisition schedules and
test plans. We analyzed the current retirement schedules of the legacy
CH-53E fleet and discussed the impact of these retirements on the
Marine Corps‘s heavy-lift requirement with appropriate officials. We
interviewed officials with the CH-53K program office; Sikorsky
Aircraft Corporation (Sikorsky), the prime contractor; the United
States Marine Corps; the Defense Contract Management Agency; and the
Office of the Secretary of Defense (OSD). We conducted this
performance audit from February 2010 through March 2011 in accordance
with generally accepted government auditing standards. Those standards
require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings
and conclusions based on our audit objectives. We believe that the
evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives. A more detailed description
of our scope and methodology is included in appendix I.
Background:
The CH-53K helicopter mission is to provide combat assault transport
of heavy weapons, equipment, and supplies from sea to support Marine
Corps operations ashore. The CH-53K is a new-build design evolution of
the existing CH-53E and is expected to maintain the same shipboard
footprint, while providing significant lift, reliability,
maintainability, and cost-of-ownership improvements. Its major
improvements include upgraded engines, redesigned gearboxes, composite
rotor blades and rotor system improvements, fly-by-wire flight
controls, a fully integrated glass cockpit, improved cargo handling
and capacity, and survivability and force protection enhancements. It
is expected to be able to transport external loads totaling 27,000
pounds over a range of 110 nautical miles under high-hot conditions
without refueling and to fulfill land-and sea-based heavy-lift
requirements.
Sikorsky was awarded a sole-source contract to develop the CH-53K
helicopter because, according to the program office, as the developer
of the CH-53E, it is the only known qualified source with the ability
to design, develop, and produce the required CH-53 variant. The
program entered the system development and demonstration phase of the
acquisition process in December 2005 and a $3 billion development
contract was awarded to Sikorsky in April 2006. Beginning in 2006, the
program experienced schedule delays that resulted in cost increases to
the development contract. As a result of the schedule delays and cost
growth, in 2009 the program office reported a cost and schedule
deviation to its original cost and acquisition program baselines to
OSD. However, these increases were not significant enough to incur
what is commonly referred to as a Nunn-McCurdy breach.[Footnote 1]
In July 2010, the CH-53K program completed what it deemed a successful
critical design review (CDR), signaling that it had a stable design
and could begin building developmental test aircraft. The program
began building the first of five developmental test aircraft in early
2011, plans to make a decision to enter low-rate initial production
(LRIP) in 2015, and plans to achieve an initial operational capability
(IOC) in 2018.
CH-53K Cost Growth, Schedule Delays, and Deferred Capabilities Will
Affect Delivery to the Warfighter:
Primarily because of decisions to increase the number of aircraft and
other issues, the CH-53K program has experienced approximately $6.8
billion in cost growth and a nearly 3-year delay from original
schedule estimates for delivery of IOC. The program started
development before determining how to achieve requirements within
program constraints, which led to cost growth and schedule delays and
resulted in the program delaying its preliminary design review to
September 2008, nearly 3 years after development start.[Footnote 2] In
addition, the program received permission to defer three performance
capabilities and relax two technical metrics associated with operating
and support costs--which we believe are sound acquisition decisions--
and will deliver the initial capability to the warfighter in 2018,
almost 3 years later than originally planned. In the end, delayed
delivery will require the Marine Corps to rely longer on legacy
aircraft that are more costly to operate and maintain, less reliable,
and less capable of performing the same mission.
The CH-53K program's estimates of cost, schedule, and quantity have
significantly grown since development started in December 2005. The
Marine Corps now plans to buy a total of 200 CH-53K helicopters for an
estimated $25.5 billion, a 36 percent increase over its original
estimates. The majority of this increase is due to added quantities.
The program's schedule delays have increased the development cost
estimate by over $1.7 billion, or more than 39 percent. In 2008, the
Marine Corps directed the program to increase its total quantity
estimate from 156 to 200 aircraft to support an increase in strength
from 174,000 to 202,000 Marines. In February 2011, the Secretary of
Defense testified that the number of Marine Corps troops may decrease
by up to 20,000 Marines beginning in fiscal year 2015. The Marine
Corps has assessed the required quantity of aircraft and determined
that the requirement for 200 aircraft remains valid despite the
proposed manpower decrease. Primarily as a result of the aircraft
quantity increase, the program's procurement cost estimate has also
increased by over $5 billion, or 35 percent, from nearly $14.4 billion
to over $19.4 billion. The program's average procurement unit cost has
increased 4.8 percent. In addition, the program's schedule delays have
delayed its ability to achieve IOC until 2018, nearly 3 years later
than originally planned. Table 1 compares the program's original
baseline estimates of cost, quantity, and major schedule events to
current program estimates.
Table 1: Changes in Estimated Costs, Quantities, and Major Events:
Development quantities:
Development start: 4;
Current status: 4;
Increase since initial estimate: [Empty].
Procurement quantities:
Development start: 152;
Current status: 196;
Increase since initial estimate: [Empty].
Total quantities:
Development start: 156;
Current status: 200;
Increase since initial estimate: 28.2 percent.
Cost estimates (then year dollars in millions):
Development;
Development start: $4,366.4;
Current status: $6,082.9;
Increase since initial estimate: 39.3 percent.
Procurement:
Development start: $14,399.9;
Current status: $19,443.2;
Increase since initial estimate: 35.0 percent.
Total program:
Development start: $18,766.3;
Current status: $25,526.1;
Increase since initial estimate: 36.0 percent.
Unit cost estimates (then year dollars in millions):
Program acquisition:
Development start: $120.3;
Current status: $127.6;
Increase since initial estimate: 6.1 percent.
Average procurement:
Development start: $94.7;
Current status: $99.2;
Increase since initial estimate: 4.8 percent.
Major events:
Preliminary design review:
Development start: June 2007;
Current status: September 2008;
Increase since initial estimate: 15 months.
Critical design review:
Development start: March 2009;
Current status: July 2010;
Increase since initial estimate: 16 months.
Initial operational capability:
Development start: September 2015;
Current status: June 2018;
Increase since initial estimate: 33 months.
Source: GAO analysis of Department of Defense data.
Note: Table does not reflect program changes based on the President's
fiscal year 2012 budget.
[End of table]
CH-53K Program Started Development Before Determining How to Achieve
Requirements and with Late Staffing:
The program started development before determining how to achieve
requirements within program constraints, which led to cost growth and
schedule delays. The CH-53K program originally scheduled its
preliminary design review for June 2007, a year and a half after the
program began development, and later delayed it to September 2008,
nearly 3 years after development start. We have reported that
performing systems engineering reviews--including a system
requirements review, system functional review, and preliminary design
review--before a program is initiated and a business case is set is
critical to ensuring that a program's requirements are defined and
feasible and that the design can meet those requirements within cost,
schedule, and other system constraints.[Footnote 3]
Problems with systems engineering began immediately within the program
because the program and Sikorsky disagreed on what systems engineering
tasks needed to be accomplished. As a result, the bulk of the
program's systems engineering problems related to derived
requirements. According to an OSD official, the contractor did not
account for total design workload, technical reviews, and development
efforts. For example, the program experienced problems defining
software specifications for its Avionics Management System.[Footnote
4] While Marine Corps officials commented that requirements are often
difficult to define early in the engineering process and changes are
expected during design maturation, they noted that in this case the
use of a firm fixed-price contract with the subcontractor made it
difficult to facilitate changes. As a result, completing this task
took longer than the program had estimated and the program's CDR was
delayed. In another example, the program has a requirement that the CH-
53K be transportable by C-5 aircraft. As with the CH-53E, because of
its size, the CH-53K's rotor and main gearbox will be removed from the
aircraft's body in order to fit within the height requirements of a C-
5. The program office interpreted this as requiring that each CH-53K
be shipped in its entirety on a single C-5 aircraft, including the
removed rotor and gearbox. However, the contractor interpreted the
requirement differently and proposed shipping all rotors and main
gearboxes in another C-5 separate from the CH-53K body. Program
officials did not accept this interpretation of the requirement and
required the contractor to propose a solution in which each CH-53K
aircraft would be shipped and arrive in its entirety in a single C-5
aircraft. Marine Corps officials commented that even though this
requirement was interpreted differently, it was identified early in
the systems engineering process and addressed.
The program office and contractor underestimated the time it would
take to hire its workforce, and delays in awarding subcontracts made
it difficult for the program to complete design tasks and maintain its
schedule. According to an OSD official, while the program officially
began development in December 2005, the development contract was not
awarded until 4 months later--in April 2006--delaying development
start. According to program officials, budget-driven hiring
restrictions for government personnel, which included ceilings on the
number of government personnel who could be assigned to the program
management office, affected the program's ability to hire its
workforce at the time the program was initiated. Similarly, program
officials told us that the contractor underestimated the amount of
time required to locate, recruit, train, and assign qualified
personnel to the program. The contractor was also late in awarding
contracts to its major subcontractors. To mitigate the risk of
production cost growth, the contractor established long-term
production agreements with its subcontractors. According to program
officials, in these agreements subcontractors committed in advance to
pricing arrangements for the production of parts and spares. While the
contractor used this strategy to reduce program risk, it resulted in a
delay and the major subcontracts were awarded later than needed to
maintain the program's initially planned schedule.
CH-53K Program Has Deferred Performance Capabilities and Relaxed
Technical Metrics Associated with Operating and Support Costs:
In 2010, the CH-53K program received approval from the Joint
Requirements Oversight Council (JROC) to defer three performance
capabilities that make up a portion of the Net-Ready key performance
parameter, and from the Marine Corps to relax two maintenance-based
technical performance metrics--both of which we believe are sound
acquisition decisions.[Footnote 5] The Department of Defense's (DOD)
decision to defer three performance capabilities was based on
consultation among JROC, Headquarters U.S. Marine Corps, Chief of
Naval Operations staff, and the program office in 2008, which prompted
the CH-53K program office to review the program's requirements and
identify potential areas in which to decrease costs. As part of that
review, the program office identified several areas where costs could
be deferred without decreasing capability, including three
communications-related performance capabilities--Link-16, Variable
Message Format, and Mode V software--that constituted part of the Net-
Ready key performance parameter. Program officials estimated that this
will result in over $100 million in cost deferral. Program officials
explained that these software capabilities were not removed from the
program's road map, but rather have been deferred until after IOC.
Originally, the program's Operational Requirements Document called for
all three capabilities to be fully integrated in fiscal year 2015.
However, one of the capabilities must now be fully integrated no later
than 6 months after IOC, which is currently scheduled to occur in
2018, and the other two capabilities must be fully integrated within 2
years of IOC. Program officials stated that deferment of these
capabilities will not affect aircraft interoperability.
Two technical performance metrics were changed because, according to
program officials, meeting the original maintenance-based technical
performance requirements for Mean Time To Repair[Footnote 6] and Mean
Corrective Maintenance Time for Operational Mission Failures[Footnote
7] was not cost effective. For example, the CH-53K's rotor blades are
designed to have a two-piece design featuring a removable tip.
However, the curing time to adhere the blade tip to the blade was
driving up the time it would take to remove and replace the blade tip.
The contractor proposed meeting the original requirement by moving to
a one-piece blade; however, this would increase the program's
operating and support costs[Footnote 8] by approximately $99 per
flight hour and increase the logistical footprint of the helicopter.
As a result, the program sought and received approval to relax the
performance metric associated with replacing the blade tip instead of
investing the financial resources necessary to obtain the original
metrics or moving to a one-piece blade.
Delayed Delivery of the CH-53K Requires Longer Reliance on Costly and
Less Reliable Legacy Aircraft:
Because of a nearly 3-year delay in initial delivery of the CH-53K,
program officials estimated that it will cost approximately $927
million more to continue to maintain the CH-53E legacy system. Initial
delivery of the CH-53K to the warfighter is currently scheduled for
2018, a delay of almost 3 years that will require the Marine Corps to
rely on legacy aircraft that are less reliable, more costly to operate
and maintain, and less capable of performing the same mission. This
delay, coupled with an increased demand for the CH-53E in foreign
theaters, led the Marine Corps to pull all available assets from
retirement for either reentry into service or to be used for spare
parts. Continued reliance on the CH-53E will be costly, as it is one
of the most expensive helicopters to maintain in the Marine Corps's
fleet. For example, the drive train of the CH-53E costs approximately
$3,000 per flight hour to maintain. In contrast, the program estimates
that the drive train for the CH-53K--its largest dynamic system--will
cost only $1,000 per flight hour to maintain. In addition, the CH-53K
is expected to have improved reliability and maintainability over the
CH-53E legacy system. For example, the CH-53K's engine has 60 percent
fewer parts than that of the CH-53E, which the program office believes
will result in a more reliable engine that is easier and less costly
to maintain. In addition, the CH-53K incorporates an aluminum gearbox
casing, which will decrease the need for replacement resulting from
corrosion.
Delayed delivery of the CH-53K will also affect the ability of the
Marine Corps to carry out future missions that cannot be performed by
the CH-53E. For example, the CH-53E can carry 15,000 pounds internally
compared to 30,000 pounds for the CH-53K. While the CH-53K is expected
to carry up to 27,000 pounds externally for 110 nautical miles at
91.5°F at an altitude of 3,000 feet--a Navy operational requirement
for high-hot conditions--the CH-53E can only carry just over 8,000
pounds under the same conditions. The increased lift capability of the
CH-53K during these conditions may enable it to carry the current and
incoming inventory of up-armored vehicles, which are much heavier than
their less-armored predecessors. For example, the up-armoring of
wheeled military vehicles, such as the High Mobility Multi-purpose
Wheeled Vehicle, and the introduction of the Joint Light Tactical
Vehicle have resulted in a military inventory with weights that are
beyond the weight limits of the CH-53E. According to program
officials, without the addition of the CH-53K, the Marine Corps will
soon no longer be able to carry and deliver the military's new
inventory of wheeled vehicles in high-hot conditions. Figure 1
compares the capabilities and characteristics of the CH-53E and CH-53K.
Figure 1: Comparison of CH-53E and CH-53K Capabilities and
Characteristics:
[Refer to PDF for image: illustrated table]
Average annual operating and maintenance cost per helicopter (FY 2011):
$8 million $5 million.
Internal width:
CH-53E: 8 feet;
CH-53K: 9 feet.
Empty weight:
CH-53E: 37,500 pounds;
CH-53K: 43,750 pounds.
Maximum distance:
CH-53E: 580 nautical miles;
CH-53K: 507 nautical miles.
Maximum speed:
CH-53E: 172.5 miles per hour;
CH-53K: 195.6 miles per hour.
Maximum internal weight:
CH-53E: 15,000 pounds:
CH-53K: 30,000 pounds.
Maximum external weight (high-hot):
CH-53E: 8,265 pounds;
CH-53K: 27,000 pounds.
Maximum gross weight:
CH-53E: 73,500 pounds;
CH-53K: 88,000 pounds.
Source: GAO analysis of Department of Defense data; Marine Aviation
data (CH-53E photo); 2008 Sikorsky Aircraft Corporation data (CH-53K
photo).
[End of figure]
The combination of the increase in the quantity of heavy-lift
helicopters required to support Marine troop levels and the delayed
delivery of the CH-53K to the warfighter has created a requirement gap
for heavy-lift helicopters of nearly 50 helicopters (nearly 25
percent) over the next 7 years and represents an operational risk to
the warfighter. However, the Marine Corps stated that it is accepting
significant risk with the heavy-lift shortfall and will continue to
operate under this gap until the CH-53K becomes available. Figure 2,
which shows the required aircraft quantities, the current CH-53 series
helicopter force structure, and planned CH-53K production, illustrates
the operational risk.
Figure 2: Marine Corps Heavy-Lift Helicopter Force Structure:
[Refer to PDF for image: layer graph]
The graph depicts Aircraft quantity for fiscal years 2009 through
2030. The difference between supplied quantity and the required
quantity of 200 is depicted as Operational Risk. CH-53E quantities
from 2009 through 2020 are at 150 per year, with Operational Risk at
50 until 2016, when quantities of CH-53K begin to decrease the risk.
From 2020 through 2030, quantities of CH-53E steadily decrease as
quantities of CH-53K steadily increase until the Operational Risk in
2030 is zero.
Source: Department of Defense.
[End of figure]
CH-53K Program Has Made Progress and Adopted Strategies to Address
Future Risk:
The CH-53K program has made progress addressing the difficulties it
faced early in system development. The program held CDR in July 2010,
demonstrating that it has the potential to move forward successfully.
The program has also adopted mitigation strategies to address future
program risk. The program's new strategy, as outlined in the
President's fiscal year 2012 budget, lengthens the development
schedule, increases development funding, and delays the production
decision by 1 year. However, while the program's new acquisition
strategy increases development time to mitigate risk, some testing and
production activities remain concurrent, which could result in costly
retrofits if problems are discovered during testing.
CH-53K Program Has Made Progress Addressing Earlier Difficulties:
The CH-53K program has taken several steps to address some of the
shortfalls that the program experienced early in development. For
example, the program has addressed its cost growth by revising its
cost estimate to align with the current schedule. The program's 2011
budget request fully funded the development program to its revised
estimate. The program addressed its early staffing issues by
increasing staffing levels beginning in January 2009 and maintained
those levels through completion of CDR. In addition, the program
delayed technical reviews until it was prepared to move forward,
thereby becoming more of an event-driven rather than a schedule-driven
program. An event-driven approach enables developers to be reasonably
certain that their products are more likely to meet established cost,
schedule, and performance baselines. For instance, the program delayed
CDR--a vehicle for making the determination that a product's design is
stable and capable of meeting its performance requirements--until all
subsystem design reviews were held and more than 90 percent of
engineering designs had been released.
In July 2010, the program completed system integration--a period when
individual components of a system are brought together--culminating
with the program's CDR. With completion of CDR, the program has
demonstrated that the CH-53K design is stable--an indication that it
is appropriate to proceed into fabrication, demonstration, and testing
and that it is expected that the program can meet stated performance
requirements within cost and schedule. At the time CDR was held, the
program had released 93 percent of its engineering drawings, exceeding
the best practice standard for the completion of system integration.
According to best practices, a high percentage of design drawings--at
least 90 percent--should be completed and released to manufacturing at
CDR. Additionally, the program office stated that all 29 major
subsystem design reviews were held prior to the start of CDR, and that
coded software delivery was ahead of schedule. In the end, the
Technical Review Board, the approving authority for CDR, determined
that the program was ready to transition to system demonstration--a
period when the system as a whole demonstrates its reliability as well
as its ability to work in the intended environment--and identified
seven action items, none of which were determined by the program
office to be critical.
CH-53K Program Has Taken Steps to Address Future Risk:
The program has also adopted several mitigation strategies to address
future program risk. The program has established weight improvement
plans to address risks associated with any potential weight increases
and has been able to locate areas where weight reductions can be made.
For example, the program worked with the subcontractor responsible for
designing and manufacturing the floor of the CH-53K to find areas to
reduce weight. The program has also created several working groups to
reduce risk to the overall capabilities of the CH-53K. For example,
the Capabilities Integrated Product Team, which meets on a monthly
basis, was developed to focus on risk relating to the program's
requirements. This team comprises officials from the program office;
Headquarters U.S. Marine Corps; Marine Corps Combat Development
Command; Chief of Naval Operations staff; the Navy's Commander,
Operational Test and Evaluation Force, staff; the operational testing
squadron; and the developmental testing squadron. Its members work
with the program office to identify, clarify, and resolve mission-
related issues and program requirements. In addition, the program
holds integrating design reviews every 6 months, freezing the working
design in order to hold a system-level review and manage design risk.
Future CH-53K Program Risk Remains:
The CH-53K program's schedule contains overlap, or concurrency,
between testing and production. The stated rationale for concurrency
is to introduce systems in a timelier manner or to fulfill an urgent
need, to avoid technology obsolescence, to maintain an efficient
industrial development/production workforce, or a combination of
these. While some concurrency may be beneficial to efficiently
transition from development to production, there is also risk in
concurrency. Any changes in design and manufacturing that require
modifications to delivered aircraft or to tooling and manufacturing
processes would result in increased costs and delays in getting
capabilities to the warfighter. In the past, we have reported a number
of examples of the adverse consequences of concurrent testing and
delivery of systems and how concurrency can place significant
investment at risk and increases the chances that costly design
changes will surface during later testing.
The CH-53K program's original schedule contained concurrency between
testing and aircraft production. In 2009, reflecting the early
difficulties experienced in development, the CH-53K program revised
its cost and schedule estimates. This revised schedule would have
reduced the program's level of concurrency. For example, while the
original program schedule called for developmental testing to be
ongoing during the production of all three lots of LRIP, the schedule
resulting from the 2009 adjustments called for developmental testing
to be ongoing during the first two lots of LRIP. However, the program
had concerns that this schedule's allowance of approximately 2 years
between final delivery of developmental test aircraft and the
beginning of LRIP would create a production gap that could be costly.
As a result, the program office was considering accelerating
procurement funds in an effort to begin production 1 year earlier than
planned and minimize breaks in production. This consideration was
negated, however, as a result of a funding cut that the program
sustained in the process of formulating the President's fiscal year
2012 budget.
In February 2011, the President's fiscal year 2012 budget was released
and outlined changes to the program's budget and schedule. According
to a program official, the program's requested budget was reduced by
approximately $30.5 million in fiscal year 2012 (and a total of $94.6
million between fiscal year 2010 and fiscal year 2015)--funds to be
applied to other DOD priorities. The President's budget reports that
while the CH-53K program was fully funded to the OSD Cost Assessment
and Program Evaluation Office estimate in the President's fiscal year
2011 budget, the funding adjustments made to the program in the
President's fiscal year 2012 budget would result in a net increase of
$69 million to the development cost estimate and a schedule delay of
approximately 7 months. The new schedule results in later delivery of
developmental test aircraft and delays some testing. As a result,
according to program officials, the production gap issue has been
addressed. Another result, though, is that the program's new schedule
maintains a level of concurrency similar to that of the original
schedule. Program officials have conceded that concurrency exists
within their program, but state that this concurrency will reduce the
operational risk of further delaying IOC. In commenting on the risks
of concurrency, Marine Corps officials noted that the time allotted
prior to the start of production and the small quantity of LRIP
planned reduces the risks of costly retrofits resulting from issues
identified during developmental test. Figure 3 compares the CH-53K
program's original and new schedules.
Figure 3: Comparison of the CH-53K's Original and New Schedules:
[Refer to PDF for image: time line]
Original schedule:
FY06: Milestone B;
FY07: Preliminary design review;
FY09: Critical design review;
FY09-FY12: Test articles production and delivery;
FY11-FY16: Testing;
FY12: Milestone C;
FY13-14: LRIP Lot 1 (6);
FY14-16: LRIP Lot 2 (9);
FY14-17: LRIP Lot 3 (14);
FY16: Initial operational capacity;
FY16-FY20 and beyond: Full rate production (FRP) Lots 4-9 (127).
New schedule:
FY06: Milestone B;
FY09: Preliminary design review;
FY10: Critical design review;
FY11-FY14: Test articles production and delivery;
FY13: First flight;
FY13-FY19: Testing;
FY15: Milestone C;
FY16-19: LRIP Lot 1 (6);
FY18-19: LRIP Lot 2 (9);
FY19-20: LRIP Lot 3 (14);
FY19: Initial operational capacity;
FY16-FY20 and beyond: Full rate production (FRP) Lots 4-9 (171).
Source: GAO analysis of United States Marine Corps data.
[End of figure]
As the CH-53K program moves forward, it is important that further cost
growth and schedule delays are mitigated. The CH-53K program's new
acquisition strategy addresses previous programmatic issues that led
to early development cost growth and schedule delays.
Agency Comments:
DOD provided technical comments on the information in this report,
which GAO incorporated as appropriate, but declined to provide
additional comments.
We are sending copies of this report to the Secretary of Defense; the
Under Secretary of Defense for Acquisition, Technology and Logistics;
the Secretary of the Navy; the Commandant of the Marine Corps; and the
Director of the Office of Management and Budget. The report also is
available at no charge on the GAO Web site at [hyperlink,
http://www.gao.gov].
If you or your staff have any questions concerning this report, please
contact me at (202) 512-4841 or sullivanm@gao.gov. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. Staff members who made key
contributions to this report are listed in appendix II.
Sincerely yours,
Signed by:
Michael J. Sullivan:
Director Acquisition and Sourcing Management:
[End of section]
Appendix I: Scope and Methodology:
To determine how the CH-53K's estimates of cost, schedule, and
quantity have changed since the program began development, we received
briefings by program and contractor officials and reviewed budget
documents, annual Selected Acquisition Reports, monthly status
reports, performance indicators, and other data. We compared reported
progress with the program of record and previous years' data,
identified changes in cost and schedule, and obtained officials'
reasons for these changes. We interviewed officials from the CH-53K
program and the Department of Defense (DOD) to obtain their views on
progress, ongoing concerns, and actions taken to address them.
To identify the CH-53K's current acquisition strategy and determine
how this strategy will meet current program targets as well as the
warfighter's needs, we reviewed the program's acquisition schedule and
other program documents, such as Selected Acquisition Reports and test
plans. We analyzed the retirement schedule of the legacy CH-53E fleet
and discussed the impact of these retirements on the Marine Corps's
heavy-lift requirement with appropriate officials. To identify the CH-
53K program's current acquisition strategy and to determine how the
program plans to meet its new targets and still meet the needs of the
warfighter, we obtained from the program--through program documents--
the program's revised acquisition plans.
In performing our work, we obtained documents, data, and other
information and met with CH-53K program officials at Patuxent River,
Maryland, and the prime contractor, Sikorsky Aircraft Corporation, at
Stratford, Connecticut. We met with officials from Headquarters Marine
Corps, the Office of the Chief of Naval Operations, and the Office of
the Secretary of Defense's Cost Assessment and Program Evaluation
Office at the Pentagon, Arlington, Virginia. We interviewed officials
from the Office of Director of Defense Research and Engineering and
the Office of the Under Secretary of Defense for Acquisition,
Technology and Logistics, Office of Developmental Testing and
Evaluation, in Arlington, Virginia. We also met with officials from
the Defense Contract Management Agency who were responsible for the CH-
53K program at Stratford, Connecticut. We drew on prior GAO work
related to acquisition best practices and reviewed analyses and
assessments done by DOD.
To assess the reliability of DOD's cost, schedule, and performance
data for the CH-53K program, we talked with knowledgeable agency
officials about the processes and practices used to generate the data.
We determined that the data we used were sufficiently reliable for the
purpose of this report.
We conducted this performance audit from February 2010 through March
2011 in accordance with generally accepted government auditing
standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives.
We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our audit objectives.
[End of section]
Appendix II: GAO Contact and Staff Acknowledgments:
GAO Contact:
Michael Sullivan (202) 512-4841 or sullivanm@gao.gov:
Staff Acknowledgments:
In addition to the contact named above, the following staff members
made key contributions to this report: Bruce Thomas, Assistant
Director; Noah Bleicher; Marvin Bonner; Laura Greifner; Laura
Jezewski; and Robert Miller.
[End of section]
Footnotes:
[1] Section 2433 of title 10, U.S. Code, requires the Department of
Defense (DOD) to perform unit cost reports on major defense
acquisition programs or designated major defense subprograms. Two
measures are tracked: "procurement unit cost" (total funds programmed
for procurement divided by the total number of fully configured items
to be procured) and "program acquisition unit cost" (total cost of
development, procurement, and system-specific military construction
divided by the number of fully configured end items to be procured).
To eliminate the effects of inflation, costs are expressed in constant
base year dollars. If a program exceeds specified cost growth
thresholds specified in the law, commonly referred to as a Nunn-
McCurdy breach, DOD is required to report to Congress. In certain
circumstances, DOD is required to reassess the program and submit a
certification to Congress in order to continue the program, in
accordance with 10 U.S.C. § 2433a.
[2] The CH-53K program was initiated under the laws and regulations in
existence in 2005. DOD's acquisition policy at that time did not
require a preliminary design review prior to the start of development.
DOD's current acquisition policy (Department of Defense Instruction
5000.02, Operation of the Defense Acquisition System (Dec. 8, 2008))
now encourages the completion of a preliminary design review prior to
the start of development (during the technology development phase of
DOD's acquisition process).
[3] GAO, Defense Acquisitions: Assessments of Selected Weapon
Programs, [hyperlink, http://www.gao.gov/products/GAO-09-326SP]
(Washington, D.C.: Mar. 30, 2009).
[4] The Avionics Management System includes the cockpit and mission
management system with integrated flight and navigation displays and
provides the crew with communication, navigation, surveillance, and
air traffic management.
[5] Key performance parameters are those capabilities or
characteristics considered most essential for successful mission
accomplishment. Failure to meet an Operational Requirements Document
key performance parameter threshold can be cause for the concept or
system selection to be reevaluated or the program to be reassessed or
terminated.
[6] Mean Time To Repair is the average elapsed corrective maintenance
time needed to repair all chargeable failures and is measured from the
time that the maintenance event begins until the item is ready for
operational use.
[7] Mean Corrective Maintenance Time for Operational Mission Failures
is the average elapsed corrective maintenance time needed to repair
all operational mission hardware failures and is measured from the
time that the maintenance event begins until the item is ready for
operational use.
[8] Operating and support costs are those program costs necessary to
operate and maintain the capability. These costs include military
personnel and operations and maintenance costs.
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: