Nuclear Weapons
DOD and NNSA Need to Better Manage Scope of Future Refurbishments and Risks to Maintaining U.S. Commitments to NATO
Gao ID: GAO-11-387 May 2, 2011
U.S. nuclear weapons are aging, with key components reaching the end of their service life. In September 2008, the Department of Defense (DOD) and the National Nuclear Security Administration (NNSA) began a study of military requirements and design options for extending the B61 bomb's service life. The B61 is used to support the U.S. strategic deterrent and the North Atlantic Treaty Organization (NATO). GAO was asked to assess the extent to which DOD and NNSA have (1) considered the time available to begin producing refurbished bombs when determining the scope of the study; and (2) taken actions to avoid operational gaps in U.S. nuclear weapons commitments to NATO during the life extension program. To evaluate these objectives, GAO analyzed DOD and NNSA policies, guidance, and reports on life extension programs, and interviewed officials responsible for B61 operations, life extension program planning, management, and oversight. This is the unclassified version of a classified report issued in December 2010.
DOD and NNSA have made progress in studying and updating the military's performance requirements for the B61 bomb and have ruled out some design options, but the broad scope of the study has complicated the effort, given the time available to begin producing refurbished bombs. Key components of the B61 bombs need to be replaced or they will begin reaching the end of their service life. However, the time and effort required to evaluate the broad scope, and other factors identified by DOD and NNSA officials, have prolonged the study by 1 year. Unlike prior life extension programs, the ongoing B61 study was broadly scoped to accomplish a variety of goals--such as considering previously untried design options and concepts--in addition to replacing the bomb's aging components. GAO's prior work on designing evaluative studies has shown that tailoring a study's scope to reflect relevant time constraints is a critical and well-established practice. However, the guidance for conducting life extension programs does not require DOD and NNSA to consider the available time when setting the scope for a life extension study. Because they have until September 2011 to complete the study, DOD and NNSA officials told GAO that it was premature to assess whether the study's broad scope put the life extension program at risk. However, future life extension programs are also likely to occur against the end of the existing warhead's service life. Unless DOD and NNSA clarify their procedures to require that future studies are properly scoped for the available time, they risk setting unrealistic goals and delaying future life extensions. Although DOD and NNSA believe the B61 study will be completed by September 2011, they have not yet prepared a long-term risk management plan to help avoid operational gaps and ensure that the United States will be able to maintain the capability to support its NATO commitments if the B61 life extension program is delayed or canceled. The United States has pledged to support its nuclear weapons commitments to NATO while the B61 life extension program is under way. In light of this pledge, NNSA and DOD plan to perform just-in-time maintenance on the affected bombs to ensure they remain operational until NNSA can deliver refurbished bombs to DOD. However, avoiding an operational capability gap over the long term may prove challenging, as previous nuclear weapons life extension programs have experienced schedule delays for a variety of reasons. GAO's prior work has shown that a risk management plan is a useful tool for identifying and measuring risks, developing and implementing risk handling options, and assessing risk reduction measures. DOD and NNSA have identified potential steps that could be taken to mitigate operational risks if the B61 life extension program is delayed, but they have not prepared a plan to offer options for managing these risks. Developing such a plan would help ensure that DOD and NNSA are prepared to implement necessary measures to preserve U.S. commitments to NATO. Furthermore, without guidance requiring that DOD and NNSA prepare such risk management plans, operational requirements for other weapons could also be at risk as they go through future life extension programs. GAO is making recommendations that address the need to scope future requirements and design studies to reflect the time available to complete the program and prepare risk management plans to address operational concerns caused by potential life extension program delays. DOD and NNSA agreed with the recommendations.
Recommendations
Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.
Director:
John H. Pendleton
Team:
Government Accountability Office: Defense Capabilities and Management
Phone:
(404) 679-1816
GAO-11-387, Nuclear Weapons: DOD and NNSA Need to Better Manage Scope of Future Refurbishments and Risks to Maintaining U.S. Commitments to NATO
This is the accessible text file for GAO report number GAO-11-387
entitled 'Nuclear Weapons: DOD and NNSA Need to Better Manage Scope of
Future Refurbishments and Risks to Maintaining U.S. Commitments to
NATO' which was released on May 2, 2011.
This text file was formatted by the U.S. Government Accountability
Office (GAO) to be accessible to users with visual impairments, as
part of a longer term project to improve GAO products' accessibility.
Every attempt has been made to maintain the structural and data
integrity of the original printed product. Accessibility features,
such as text descriptions of tables, consecutively numbered footnotes
placed at the end of the file, and the text of agency comment letters,
are provided but may not exactly duplicate the presentation or format
of the printed version. The portable document format (PDF) file is an
exact electronic replica of the printed version. We welcome your
feedback. Please E-mail your comments regarding the contents or
accessibility features of this document to Webmaster@gao.gov.
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed
in its entirety without further permission from GAO. Because this work
may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this
material separately.
United States Government Accountability Office:
GAO:
Report to Congressional Requesters:
May 2011:
Nuclear Weapons:
DOD and NNSA Need to Better Manage Scope of Future Refurbishments and
Risks to Maintaining U.S. Commitments to NATO:
GAO-11-387:
GAO Highlights:
Highlights of GAO-11-387, a report to congressional requesters.
Why GAO Did This Study:
U.S. nuclear weapons are aging, with key components reaching the end
of their service life. In September 2008, the Department of Defense
(DOD) and the National Nuclear Security Administration (NNSA) began a
study of military requirements and design options for extending the
B61 bomb‘s service life. The B61 is used to support the U.S. strategic
deterrent and the North Atlantic Treaty Organization (NATO). GAO was
asked to assess the extent to which DOD and NNSA have (1) considered
the time available to begin producing refurbished bombs when
determining the scope of the study; and (2) taken actions to avoid
operational gaps in U.S. nuclear weapons commitments to NATO during
the life extension program. To evaluate these objectives, GAO analyzed
DOD and NNSA policies, guidance, and reports on life extension
programs, and interviewed officials responsible for B61 operations,
life extension program planning, management, and oversight. This is
the unclassified version of a classified report issued in December
2010.
What GAO Found:
DOD and NNSA have made progress in studying and updating the
military‘s performance requirements for the B61 bomb and have ruled
out some design options, but the broad scope of the study has
complicated the effort, given the time available to begin producing
refurbished bombs. Key components of the B61 bombs need to be replaced
or they will begin reaching the end of their service life. However,
the time and effort required to evaluate the broad scope, and other
factors identified by DOD and NNSA officials, have prolonged the study
by 1 year. Unlike prior life extension programs, the ongoing B61 study
was broadly scoped to accomplish a variety of goals”such as
considering previously untried design options and concepts”in addition
to replacing the bomb‘s aging components. GAO‘s prior work on
designing evaluative studies has shown that tailoring a study‘s scope
to reflect relevant time constraints is a critical and well-
established practice. However, the guidance for conducting life
extension programs does not require DOD and NNSA to consider the
available time when setting the scope for a life extension study.
Because they have until September 2011 to complete the study, DOD and
NNSA officials told GAO that it was premature to assess whether the
study‘s broad scope put the life extension program at risk. However,
future life extension programs are also likely to occur against the
end of the existing warhead‘s service life. Unless DOD and NNSA
clarify their procedures to require that future studies are properly
scoped for the available time, they risk setting unrealistic goals and
delaying future life extensions.
Although DOD and NNSA believe the B61 study will be completed by
September 2011, they have not yet prepared a long-term risk management
plan to help avoid operational gaps and ensure that the United States
will be able to maintain the capability to support its NATO
commitments if the B61 life extension program is delayed or canceled.
The United States has pledged to support its nuclear weapons
commitments to NATO while the B61 life extension program is under way.
In light of this pledge, NNSA and DOD plan to perform just-in-time
maintenance on the affected bombs to ensure they remain operational
until NNSA can deliver refurbished bombs to DOD. However, avoiding an
operational capability gap over the long term may prove challenging,
as previous nuclear weapons life extension programs have experienced
schedule delays for a variety of reasons. GAO‘s prior work has shown
that a risk management plan is a useful tool for identifying and
measuring risks, developing and implementing risk handling options,
and assessing risk reduction measures. DOD and NNSA have identified
potential steps that could be taken to mitigate operational risks if
the B61 life extension program is delayed, but they have not prepared
a plan to offer options for managing these risks. Developing such a
plan would help ensure that DOD and NNSA are prepared to implement
necessary measures to preserve U.S. commitments to NATO. Furthermore,
without guidance requiring that DOD and NNSA prepare such risk
management plans, operational requirements for other weapons could
also be at risk as they go through future life extension programs.
What GAO Recommends:
GAO is making recommendations that address the need to scope future
requirements and design studies to reflect the time available to
complete the program and prepare risk management plans to address
operational concerns caused by potential life extension program
delays. DOD and NNSA agreed with the recommendations.
View [hyperlink, http://www.gao.gov/products/GAO-11-387] or key
components. For more information, contact John Pendleton at (202) 512-
3489 or pendletonj@gao.gov or Gene Aloise at (202) 512-3841 or
aloisee@gao.gov. [End of section]
Contents:
Letter:
Background:
The DOD-NNSA Review of B61 Performance Requirements and Design Options
Is Progressing but the Review's Broad Scope Complicated the Study
Efforts, Given the Available Time:
DOD and NNSA Have Not Planned for Maintaining Operational Nuclear
Weapons Commitments to NATO if the B61 Life Extension Program Is
Delayed:
Conclusions:
Recommendations for Executive Action:
Agency Comments and Our Evaluation:
Appendix I: Scope and Methodology:
Appendix II: Comments from the Department of Defense:
Appendix III: Comments from the National Nuclear Security
Administration:
Appendix IV: GAO Contacts and Staff Acknowledgments:
Tables:
Table 1: Scope of B61 Phase 6.2 Study Compared to Prior Nuclear Weapon
Life Extension Programs and Major Refurbishments:
Table 2: Status of Potential Design Options for the B61 Life Extension
Program as of September 2010:
Table 3: Options for Mitigating a Gap in U.S. Commitments to NATO:
Figures:
Figure 1: Notional Life Extension Program Schedule, May 2010:
Figure 2: DOD-DOE Phase 6.X Process for Managing Nuclear Weapons
Refurbishments and Life Extension Programs:
Figure 3: Key Dates in the Planning and Execution of the B61 Life
Extension Program:
Figure 4: Bomb Design Consolidation in the B61 Life Extension Program:
Figure 5: Key Operational Dates for the B61 Bombs during the Life
Extension Program:
Abbreviations:
DOD: Department of Defense:
DOE: Department of Energy:
ICBM: Intercontinental Ballistic Missile:
NATO: North Atlantic Treaty Organization:
NNSA: National Nuclear Security Administration:
SHAPE: Supreme Headquarters Allied Powers Europe:
SLBM: Submarine-Launched Ballistic Missile:
USAFE: United States Air Forces in Europe:
USEUCOM: United States European Command:
[End of section]
United States Government Accountability Office:
Washington, DC 20548:
May 2, 2011:
The Honorable Michael R. Turner:
Chairman:
Subcommittee on Strategic Forces:
Committee on Armed Services:
House of Representatives:
The Honorable James R. Langevin:
House of Representatives:
Nuclear weapons have long been a cornerstone of the nation's defense
strategy. These weapons--deployed on intercontinental ballistic
missiles (ICBM), submarine-launched ballistic missiles (SLBM), heavy
bombers, and fighter aircraft capable of performing nuclear missions--
have played an essential role in deterring a nuclear attack on the
United States and its allies and partners, including the North
Atlantic Treaty Organization (NATO). At the same time, arms control
agreements and other policies since the 1960s have led the United
States to maintain its nuclear deterrent with decreasing numbers of
weapons. In the April 2010 Nuclear Posture Review Report,[Footnote 1]
the current administration declared its commitment to further reducing
U.S. nuclear forces, while maintaining a safe, secure, and effective
nuclear deterrent for the United States and its allies, even as the
weapons in the nuclear stockpile continue to age and weapon components
reach the end of their operational life. Further, recognizing that
NATO was undertaking a review of its Strategic Concept, which
expresses the alliance's fundamental security tasks, the
administration pledged in April 2010 not to prejudge NATO's review,
even as it committed to retain the capability to forward deploy
nuclear bombs.[Footnote 2]
The Department of Defense (DOD) and the National Nuclear Security
Administration (NNSA), a separately organized agency within the
Department of Energy (DOE), are currently in the process of planning a
life extension affecting four of the five versions of the B61 bomb.
[Footnote 3] The B61 bomb is one of seven types of nuclear weapons
that remain in the U.S. stockpile. The bomb is used to support U.S.
nuclear commitments to NATO, where, as part of NATO's forces, it is
intended to signal cohesion among NATO members, and when deployed,
versions of the bomb could be carried on U.S. and NATO fighter
aircraft during conflict. DOD and NNSA have stated that the B61 life
extension program is necessary because key bomb components will soon
need replacement or the bombs would become nonoperational. Although
Congress initially limited the scope and funding for the B61 life
extension study to the bomb's nonnuclear components during fiscal year
2010, the April 2010 Nuclear Posture Review Report endorsed completing
a "fullscope" life extension of the B61 bomb's nuclear and nonnuclear
components.[Footnote 4] In May 2010, as directed by Congress, DOE
requested approval from the House and Senate Committees on
Appropriations to study options for a fullscope life extension;
[Footnote 5] the fullscope life extension study was approved in August
2010.
The administration's continued commitment to extending the life of
nuclear weapons is accompanied by requirements for significant
investment in DOD delivery platforms and NNSA nuclear weapons
production infrastructure. In a May 2010 report to Congress,[Footnote
6] the administration identified a 10-year cost estimate of over $100
billion to sustain and modernize strategic delivery systems and U.S.
dual-capable fighter aircraft. Additionally, NNSA has identified $80
billion in nuclear weapons stockpile and infrastructure costs over the
same period to maintain the safety and reliability of the nuclear
weapons stockpile without nuclear testing. Among other things, these
infrastructure investments are to support not only the B61 life
extension, but future life extension programs for ICBM, SLBM, and
bomber-delivered cruise missile warheads.
Our prior work has shown that nuclear weapons life extension programs
can be complicated and risky endeavors that require disciplined
management and effective collaboration among all the participating DOD
and NNSA organizations. Although DOD and NNSA have improved management
practices since our first report on NNSA's life extension programs was
issued in 2000,[Footnote 7] in March 2009, we reported that DOD and
NNSA have continued to experience problems carrying out life
extensions within the agreed-upon schedule, and within estimated
costs.[Footnote 8]
In March 2008 the Nuclear Weapons Council--a statutorily authorized
joint activity composed of DOD and DOE officials--approved an Air
Force request for a study of military performance requirements and
potential design options for the B61 life extension program. As
requested, we have reviewed the extent to which DOD and NNSA have (1)
considered the time available to begin producing refurbished bombs
when determining the scope of the study; and (2) taken actions to
avoid operational gaps in U.S. nuclear weapons commitments to NATO
during the B61 life extension program. In December 2010, we reported
to you on the results of our work in a classified report. This is the
unclassified version of that classified report. To prepare this
unclassified version, we removed certain references to nuclear weapons
quantities, storage locations, designs, and performance
characteristics.
To evaluate our objectives, we analyzed DOD, DOE, and Nuclear Weapons
Council policies and guidance on planning and carrying out nuclear
stockpile life extension programs; and reviewed DOD and NNSA reports
and B61 Project Officers Group status briefings on the B61 life
extension program. We also interviewed DOD and NNSA officials
responsible for coordinating the joint DOD-NNSA study of requirements
and design options for the planned B61 life extension program, and
other officials from the Office of the Secretary of Defense, Air
Force, and NNSA, including the former NNSA manager for nuclear weapons
stockpile sustainment, the current NNSA manager for the B61 weapon
system, and NNSA managers for ICBM, SLBM, and cruise missile weapon
systems. We analyzed documents from the Office of the Secretary of
Defense, NNSA, U.S. Strategic Command, U.S. European Command, and NATO
and met with officials from these organizations. Our scope and
methodology are described in more detail in appendix I.
We conducted this performance audit from October 2009 to December 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
Background:
Most modern nuclear weapons consist of three sets of components--a
primary, a secondary, and a set of nonnuclear components enclosed in a
case. When detonated, the primary and secondary components, which
together are referred to as the weapon's "nuclear explosive package,"
produce the weapon's explosive force, or "yield." The array of
nonnuclear components surrounding the nuclear explosive package serves
to control the detonation sequence and helps ensure the weapon's
safety and security from human tampering and accidental detonation.
Some of these nonnuclear components--collectively called "limited-life
components"--have shorter service lives than the weapon itself, and
therefore must be periodically replaced.
The U.S. stockpile includes more than 5,000 nuclear weapons, the vast
majority of which are either operationally deployed in the United
States or on submarines at sea, or held in storage.[Footnote 9] Based
on guidance and direction provided by the President, Secretary of
Defense, and Chairman of the Joint Chiefs of Staff, the Commander of
U.S. Strategic Command is responsible for developing an operational
plan and identifying targets for an arsenal that includes 1,700 to
2,200 operationally deployed strategic nuclear weapons. The Air Force
maintains and operates nuclear-armed ICBMs, cruise missiles, and
gravity bombs, whereas the Navy maintains and operates nuclear-armed
SLBMs. The Commander of U.S. Strategic Command has operational command
and control over these nuclear forces but only the President is
authorized to direct the use of nuclear weapons.
In addition to the nuclear forces under U.S. Strategic Command's
operational control, the United States retains a limited number of
nonstrategic, or "tactical" B61 bombs in the nuclear weapons stockpile
to support NATO commitments. These bombs are maintained in an
operational configuration, and can be delivered by both U.S. fighter
aircraft and aircraft of predesignated, trained, and certified NATO
allies. The Commander of U.S. European Command also serves as the
Supreme Allied Commander of European forces, and would exercise
command and control of these weapons during a conflict. The Air Force
exercises day-to-day custody of the B61 bombs used to support NATO
commitments. As is the case for the employment of nuclear weapons
under U.S. Strategic Command's control, only the President of the
United States can authorize the NATO Supreme Allied Commander to
employ the B61 bomb.
While U.S. Strategic Command has prepared an operational plan for
employing nuclear weapons, neither NATO nor U.S. European Command, in
accordance with the NATO Strategic Concept, have prepared standing
peacetime nuclear contingency plans or identified targets involving
nuclear weapons. The B61 bombs assigned to support NATO are intended
to provide for the collective security of all its members. According
to U.S. European Command officials, the B61 bombs couple U.S. and NATO
security, and tangibly assure the members of NATO that the United
States is committed to their national security. The April 2010 Nuclear
Posture Review Report recognizes that the risk of nuclear attack
against NATO members is at a historic low. However, the Nuclear
Posture Review Report emphasized that NATO's unique arrangements, in
which nonnuclear members participate in nuclear planning and possess
specially configured aircraft capable of delivering nuclear weapons,
[Footnote 10] contribute to alliance cohesion and provide reassurance
to allies and partners who feel exposed to regional threats.
The U.S. stockpile includes five different versions of the B61 bomb,
which first entered the stockpile in the late 1970s and is the oldest
weapon in the U.S. stockpile. Two of the five versions, considered
"strategic" versions, would be carried into combat by B-52 and B-2
bomber aircraft, whereas the other three "nonstrategic" versions would
be carried into combat by U.S. or NATO allied fighter aircraft. The
five versions have different military characteristics, which identify
key military performance requirements, such as safety requirements or
explosive yield, for a given nuclear bomb or warhead. Furthermore, to
protect against access by unauthorized persons, the nonstrategic
versions were designed with advanced security systems.
To sustain the nuclear deterrent as weapons age, the current
administration has endorsed a policy--also followed by prior
administrations--to perform life extension programs on existing
stockpiled weapons, rather than design, test, and produce new weapons.
DOD and DOE both play crucial roles in planning and executing nuclear
weapons life extension programs. DOE formally initiated the Stockpile
Life Extension Program in 1996; NNSA has administered the program
since fiscal year 2000. DOD and NNSA (or its predecessor DOE
organizations) have previously planned and executed several nuclear
weapons life extension programs and refurbishments, including life
extensions of the W87 warhead, which is deployed on ICBMs, and the W76
warhead, which is deployed on SLBMs. NNSA also performed a significant
refurbishment to the secondary component of the strategic versions of
the B61 in the mid-2000s.[Footnote 11] NNSA, due to limited production
capacity, has conducted these life extension programs consecutively,
rather than concurrently. Although their durations have varied, life
extension programs can take nearly a decade or more from the start of
the planning phases until refurbished weapons are delivered to DOD for
reintroduction into the stockpile. The B61 life extension program and
other planned life extension programs also are expected to occur
sequentially, as shown in figure 1.
Figure 1: Notional Life Extension Program Schedule, May 2010:
[Refer to PDF for image: time line]
Production dates:
W76: Current to end of 2017.
B61: 2017 through end of 2021.
W78: 2021 through end of 2025.
W88: 20206 through 2030 and beyond.
Study and Design dates:
W80-1: 2021-2030: Study, design and engineering activities; production
to start after 2030.
B83/B61-11 and W87: Startup of design activities for one of these
systems is anticipated in mid-2020s.
Source: NNSA.
[End of figure]
NNSA and DOD use the "Phase 6.X" process to manage all nuclear weapons
refurbishments, including not only alterations to fix or replace aging
nuclear weapons components, but also fullscope life extension
programs. The Procedural Guideline for the Phase 6.X Process
establishes the joint process for nuclear weapons refurbishments.
[Footnote 12] After the Nuclear Weapons Council--the joint DOD and
NNSA activity responsible for executive-level management of the
nuclear weapons stockpile[Footnote 13]--formally authorizes the
beginning of a Phase 6.2 feasibility study for a life extension
program, [Footnote 14] a Service-led project officers group manages
the study of design options for the weapon.[Footnote 15] The steps for
the Phase 6.X process are described in figure 2.
Figure 2: DOD-DOE Phase 6.X Process for Managing Nuclear Weapons
Refurbishments and Life Extension Programs:
[Refer to PDF for image: illustration]
Phase 6.X Weapon Production, Maintenance, and Evaluation:
The illustration depicts an interlocking circular pattern: 6.1 to 6.6
and recycling.
6.1: DOD, NNSA, or the responsible project officers group conducts
studies to determine if a weapon in the stockpile needs refurbishment
or to investigate refurbishment concepts.
6.2: For a weapon needing refurbishment, the project officers group
coordinates DOD and NNSA efforts to update the weapon‘s military
requirements, develop feasible design options to meet the
requirements, and identify a preferred design option(s).
6.2A: The project officers group coordinates further DOD and NNSA
investigation of a preferred design option(s) and the expected
refurbishment costs.
6.3: NNSA-led tests and experiments to validate the design option(s)
in consultation with DOD.
6.4: NNSA-led activities to adapt the design for production and
prepare its production facilities.
6.5: Refurbishment of a limited number of weapons for analysis and
production process qualification.
6.6: Full-scale production at NNSA‘s facilities.
Source: Nuclear Weapons Council.
[End of figure]
In March 2008, the Nuclear Weapons Council approved the Air Force's
request for a study, under Phases 6.2 and 6.2A, to explore the
feasibility and costs of conducting a fullscope life extension program
of the B61 bomb.[Footnote 16] In June 2008, the council directed the
study to begin no later than September 2008 and be completed within 24
months; however, the study's completion has been extended by 1 year.
[Footnote 17] As shown in figure 3, DOD and NNSA plan to deliver the
first refurbished B61 bomb[Footnote 18]--Phase 6.5 in the 6.X process--
in 2017. According to the Air Force lead project officer for the B61
bomb, NNSA plans to produce enough refurbished bombs by the end of
fiscal year 2022 to meet both U.S. Strategic Command's requirements
and U.S. European Command's requirements to support NATO. The project
officers group is seeking to extend the bomb's service life for
another 30 years. According to the NNSA program manager for the B61
bomb, the preliminary cost estimate for the life extension program is
about $4 billion through 2022, when the program would be completed.
Figure 3: Key Dates in the Planning and Execution of the B61 Life
Extension Program:
[Refer to PDF for image: illustration]
2008-2011: Study:
June 2008: Nuclear Weapons Council directs start of B61 life extension
program.
September 2008: Start of B61 life extension program Phase 6.2/6.2A
study.
September 2011 (estimated): Nuclear Weapons Council decision on design
options for the B61 life extension program and approval to move to
Phase 6.3.
2011-2017: Development and production engineering:
2017-2022: Production and delivery:
September 2017 (estimated): NNSA to deliver first production unit to
DOD.
September 2022 (estimated): completion of full-scale production.
Source: GAO analysis of DOD information.
[End of figure]
NNSA's Office of Defense Programs is primarily responsible for the B61
life extension program. This office plans and coordinates NNSA
activities to maintain the nuclear stockpile, including the
manufacture, maintenance, refurbishment, surveillance, and
dismantlement of weapons; annual assessment of the weapons' safety and
reliability; and research, development, and nonnuclear testing to
support these activities. A national complex of three national nuclear
weapons design laboratories, four production plants, and the Nevada
National Security Site (formerly the Nevada Test Site) carries out the
Office of Defense Programs' mission. For the B61 life extension
program, Los Alamos National Laboratory, in New Mexico, and Sandia
National Laboratory, in New Mexico and California, are directly
involved in designing the refurbished B61; while Lawrence Livermore
National Laboratory, in California, will peer-review the design. Once
production has begun, NNSA's Pantex Plant, in Texas, will assemble key
subcomponents of the refurbished bomb, including many of the
nonnuclear components, manufactured at the Kansas City Plant, in
Missouri, and, for a fullscope life extension, any nuclear components
refurbished at other sites in the complex.
The DOD-NNSA Review of B61 Performance Requirements and Design Options
Is Progressing but the Review's Broad Scope Complicated the Study
Efforts, Given the Available Time:
Since initiating the joint study for the B61 life extension program at
the request of the Nuclear Weapons Council in September 2008, DOD and
NNSA have made progress evaluating the military's performance
requirements for the refurbished B61 bomb and have ruled out key
design options, but the broad scope of the council's request has
complicated the joint study effort, given the time available to begin
producing refurbished weapons. For example, the Nuclear Weapons
Council, in its June 2008 letter, scoped the study to include options
for incorporating previously untried technologies and design concepts
into the refurbished bomb, in addition to replacing its aging
components. As a result of the broad scope and other factors
identified by DOD and NNSA officials, the study is expected to take
until September 2011--1 year longer than initially planned. Our prior
work on designing evaluative studies has shown that tailoring a
study's scope to reflect the time constraints for conducting the study
is a critical and well-established research practice.[Footnote 19]
Because the B61 Project Officers Group has made progress in the study,
NNSA and DOD officials told us it was premature to assess whether the
broad scope will affect their ability to begin producing refurbished
B61 bombs by 2017. However, the complications raised by the B61
study's broad scope and limited time frame have implications for
future life extension programs, because those programs also are likely
to occur against the approaching end of the existing weapon's service
life. Unless DOD and NNSA clarify their procedures to require that
future life extension studies are properly scoped for the available
time, they risk setting unrealistic goals and delaying future life
extension programs.
DOD and NNSA Have Made Progress Identifying Military Performance
Requirements and Design Options for the B61 Life Extension Program:
DOD and NNSA have reached a tentative agreement to consolidate several
older versions of the B61 bomb into a single design. According to U.S.
Strategic Command and NNSA officials, consolidating the versions could
reduce the risks and costs of maintaining the bomb, improve the safety
and security of the weapon, eliminate the need to conduct a life
extension on multiple B61 versions, and reduce expenses by prolonging
the interval for replacing key limited-life components. As a result of
this agreement, as shown in figure 4, DOD plans to retire four
versions of the B61 and replace them with a refurbished weapon based
generally around the design of one of those versions, the B61-4.
Because the B61-4 has the lowest yield among the different versions,
consolidating the versions in this manner would also remove
significant quantities of nuclear material from the deployed B61 bombs.
Figure 4: Bomb Design Consolidation in the B61 Life Extension Program:
[Refer to PDF for image: illustration]
4 Bomb types:
B61-3;
B61-4;
B61-7;
B61-10.
Consolidated to 1 bomb design:
B61 Life Extension.
Source: U.S. Strategic Command.
Note: Figure is for illustrative purposes and does not accurately
convey weapons design information or characterize differences among
the B61-3/4/7/10 versions of the bomb. The B61-11 is not included as
part of the scope of the B61 life extension program.
[End of figure]
In agreeing to consolidate the B61 stockpile around a single design,
DOD components--including U.S. Strategic Command, U.S. European
Command, and the Air Force--reached agreement on some of the key
performance requirements, or military characteristics, for the
refurbished bomb. A nuclear weapon's military characteristics describe
DOD's official requirements for the weapon's size, weight, and other
physical attributes; performance characteristics, such as nuclear
yields or heights-of-burst; safety and security standards, such as
minimizing military personnel's radiation exposure; and other factors
that affect nuclear weapons design. When conducting a Phase 6.2 study,
NNSA officials told us that its design laboratories need DOD to reach
agreement on its requirements early in the process so that they are
able to assess the extent to which various design options for the life-
extended weapon meet the military's needs.
The agreements reached to date have come about only through
significant effort and time. For example, DOD required about 18 months
from the beginning of the study to confirm NATO's requirements for the
weapon. NATO's Supreme Headquarters, Allied Powers Europe (SHAPE),
[Footnote 20] originally submitted requirements for the refurbished
B61 bomb in March 2009, 6 months after the study began. However, the
Air Force lead project officer, and officials from U.S. European
Command and SHAPE, told us that the original submission did not
provide the B61 Project Officers Group with the specific requirements
that it needed to conduct the Phase 6.2 study. In October 2009, the
group asked DOD to clarify NATO requirements, and U.S. European
Command led a DOD-wide effort throughout early 2010 to resolve key
issues with certain NATO allies. In April 2010, DOD and the NATO
allies reached agreement on key military characteristics of the bomb,
including the yield, that it be capable of freefall (rather than
parachute-retarded) delivery,[Footnote 21] its accuracy requirements
when used on modern aircraft and that it employ a guided tailkit
section,[Footnote 22] and that it have both midair and ground
detonation options. They further agreed that the weapon should be
capable of being carried by both existing and modernized fighter
aircraft, including the F-35,[Footnote 23] and be compatible with
current weapon storage vaults abroad. Subsequently, after U.S.
Strategic Command expressed a requirement for a different yield, U.S.
European Command and SHAPE agreed to the proposal.
According to Air Force and NNSA officials, DOD's ability to reach
agreement with the allies on these issues was a significant
achievement. For example, had the allies opposed the guided tailkit,
then the strategy to consolidate the different versions of the bomb
may have been in jeopardy.
Broad Scope and Tight Time Frames Have Complicated the Joint B61
Refurbishment Study:
Although DOD and NNSA have made progress defining requirements and
identifying design options for the B61, the Nuclear Weapons Council's
June 2008 request was considerably broader than prior life extension
programs and has complicated the agencies' effort, given the tight
time frames for completing the study. Our prior work on designing
evaluative studies has shown that tailoring a study's scope to reflect
the time constraints for conducting the study is a critical and well-
established research practice. Furthermore, the failure to align a
study's scope with the time available can adversely affect the quality
of the study.
The scope of the B61 study--which includes studying new features and
designs, in addition to replacing aging components--is considerably
broader than previous life extension programs. For example, the
Nuclear Weapons Council requested the joint Navy and NNSA project
officers group to only develop design options and cost estimates for
refurbishing the W76 SLBM warhead,[Footnote 24] which the Navy and
NNSA concluded could be best accomplished by adhering as closely as
possible to the weapon's original specifications.[Footnote 25]
Similarly, during the life extension of the W87 ICBM warhead, which
was begun before DOD and DOE formalized the Phase 6.X process and
completed in 2005, NNSA's actions were limited and not based on
changes to the warhead's military requirements. However, for the
current B61 life extension program, the Nuclear Weapons Council
instructed the joint Air Force and NNSA project officers group that it
should pursue not only the complete refurbishment of the bomb, but
also opportunities to improve other characteristics affecting the
bomb's safety, security, and performance, as well as investigate
alternative design concepts untried during prior life extension
programs. Table 1 compares the scope of the current B61 study with the
scope of prior life extension programs and major refurbishments.
Table 1: Scope of B61 Phase 6.2 Study Compared to Prior Nuclear Weapon
Life Extension Programs and Major Refurbishments:
Life extension program or refurbishment:
Current life extension program: B61 bomb, strategic and nonstrategic
versions (B61-3, -4, -7, -10);
Service: Air Force;
Scope: Refurbishment of aging components: Yes, many;
Scope: Safety and security enhancements: Yes, many;
Scope: Other enhancements or design changes: Yes, many.
Prior life extensions or major refurbishments: B61 bomb, strategic
versions (B61-7, -11)[A];
Service: Air Force;
Scope: Refurbishment of aging components: Yes;
Scope: Safety and security enhancements: None;
Scope: Other enhancements or design changes: None.
Prior life extensions or major refurbishments: W80-1 cruise missile
warhead[B];
Service: Air Force;
Scope: Refurbishment of aging components: Yes;
Scope: Safety and security enhancements: Yes;
Scope: Other enhancements or design changes: None.
Prior life extensions or major refurbishments: W76 SLBM warhead;
Service: Navy;
Scope: Refurbishment of aging components: Yes;
Scope: Safety and security enhancements: None;
Scope: Other enhancements or design changes: None.
Prior life extensions or major refurbishments: W87 ICBM warhead[C];
Service: Air Force;
Scope: Refurbishment of aging components: None;
Scope: Safety and security enhancements: None;
Scope: Other enhancements or design changes: Yes.
Source: GAO analysis of DOD and NNSA data.
[A] The scope of this refurbishment included only the replacement of
the nuclear secondary component in the strategic versions of the bomb.
[B] Safety and security enhancements were not originally part of the
scope of the Phase 6.2 study for the W80-1 cruise missile warhead's
life extension program. The W80 Project Officers Group first
considered enhancements to the weapon's safety and security features
after the Phase 6.2 study was under way, in response to a joint DOD
and NNSA requirement that the W80 Project Officers Group consider
opportunities for such enhancements. The life extension program,
however, was canceled in May 2006 after DOD re-evaluated its cruise
missile force structure requirements. According to a senior official
from the Office of the Secretary of Defense, the life extension
program may be resumed for the warhead after the Air Force assesses
the requirements for long-range strike capabilities.
[C] The W87 refurbishment was initiated before DOD and DOE established
the Phase 6.X process.
[End of table]
The broad scope of the B61 life extension program study also differs
from prior life extension program studies in how it instructed the B61
Project Officers Group to review and address the weapon's key military
performance requirements. Unlike the ongoing B61 life extension
program study, prior programs did not require significant changes to
the military performance requirements for the weapon being refurbished
because these requirements were generally fixed by the type of
delivery systems that carried them. For example, the W76 SLBM warhead
and W80 cruise missile warhead life extension programs were intended
to result in refurbished weapons carried by SLBMs and cruise missiles,
respectively, and therefore the programs largely adhered to the
military characteristics associated with the original weapon.[Footnote
26] In contrast, the Nuclear Weapons Council's June 2008 request
letter instructed the B61 Project Officers Group to consider revisions
to the bomb's military performance requirements in line with the
aforementioned strategy to consolidate multiple B61 versions. As a
result, the group has been working to consolidate the requirements for
strategic and nonstrategic versions of the bomb, which currently have
different requirements based on their mission. Also unlike prior
programs, the B61 Project Officers Group also has been reviewing
design options to ensure that the refurbished weapon will be able to
be employed on existing and yet-to-be fielded aircraft--particularly
the F-35. According to the Air Force official leading the requirements
subgroup, consolidating the military performance requirements for the
various versions of the bomb required considerably more time than
previous life extension programs had taken to establish the
refurbished weapons' military characteristics.
The B61 life extension program is also unique in that the stockpiled
B61 bombs are approaching the end of their service lives, thus
constraining the amount of time available to complete the study and
the subsequent phases of the life extension program. The Nuclear
Weapons Council recognized this urgency, when it emphasized, in the
June 2008 letter, that the target date for production must ensure no
capability gaps with respect to preserving U.S. nuclear weapons
commitments to NATO, which would require NNSA to achieve Phase 6.5
(first production) no later than 2017. According to Air Force and NNSA
officials, meeting this schedule will require the Air Force to perform
maintenance on the existing weapons in order to give NNSA time to
complete the life extension program before the weapons begin reaching
the end of their service life. In contrast, prior life extension
programs have not faced firm deadlines driven by end-of-life issues.
For example, a senior Navy official told us that the Nuclear Weapons
Council tasked the Navy and NNSA to begin the W76 life extension
program study well before that weapon was expected to reach the end of
its service life.
In addition to improving the bomb's safety and performance and reduce
maintenance costs, the Nuclear Weapons Council had various other goals
in mind when it requested a broad scope for the B61 refurbishment
study, according to DOD and NNSA officials. According to DOD
officials, the B61 life extension offers a unique opportunity to
implement national policy on safety and security of nuclear weapons.
[Footnote 27] In particular, Office of the Secretary of Defense
officials told us that the council scoped the study broadly to provide
opportunities to broaden the range of weapons-design and production
activities being performed at the NNSA weapons complex. The council
also wanted to potentially make use of the design innovations being
developed at NNSA's nuclear design laboratories to improve the safety,
security, and performance of aging weapons. Furthermore, in
preparation for future life extension programs, the council wanted to
take advantage of the B61 study to explore novel and innovative
concepts that could be applied when conducting future life extension
programs. As of September 2010, the B61 Project Officers Group had not
yet reached agreement on some of the design options that were included
in the scope of the study. The status of the review is summarized in
table 2.
Table 2: Status of Potential Design Options for the B61 Life Extension
Program as of September 2010:
Potential design option: Multipoint safety technology[A];
Description: The June 2008 letter instructed the B61 Project Officers
Group that it should explore options for enhancing the bomb's safety
and security;
Risk: Has not been used in existing stockpiled weapons;
Status: The B61 Project Officers Group is continuing its evaluation of
costs and benefits of different multipoint safety technologies,
including the potential impacts of different approaches on how the Air
Force maintains and operates the weapons.
Potential design option: Alternative power supply components;
Description: Although the B61 bombs currently use a well-proven
technology for power supplies, the B61 Project Officers Group studied
alternative power supply technologies in order to potentially lower
the bomb's overall costs;
Risk: The alternative technologies have not been used in the
stockpile. NNSA estimates that the initial development and production
costs of one of the technologies would be significantly greater than
using the existing technology;
Status: The B61 Project Officers Group ruled out one technology in
August 2009. However, according to senior Air Force officials, the
group had not yet determined whether the existing power supply
technology is the most cost-effective approach for the refurbished
bomb.
Potential design option: Alternative bomb shapes;
Description: To create space for more safety and security features
inside the tightly packed B61 bomb case, the council asked the B61
Project Officers Group to study alternative bomb bodies. In response,
the group investigated the Mark-84 bomb shape and the Joint Standoff
Weapon[B];
Risk: Significant programmatic and design risks to incorporate
alternative bomb shapes; did not meet the military's performance
requirements;
Status: The Joint Standoff Weapon was ruled out as a design option in
April 2009, and the Mark-84 was ruled out in August 2009.
Potential design option: Alternative nuclear explosive components;
Description: Due to limitations in NNSA's capacity to manufacture new
nuclear components, the council asked the B61 Project Officers Group
to study options for reusing nuclear components from other weapons, in
addition to reusing the B61 bomb's components. In particular, the
group investigated reusing components from the W84 ground-launched
cruise missile warhead[C];
Risk: Significant programmatic and performance risks to adapt these
components to a new weapon; did not meet the military's performance
requirements; insufficient quantities to meet expected production
requirements;
Status: Ruled out as a design option in April 2009.
Source: GAO analysis of DOD and NNSA data.
[A] "Multipoint safety" means that the probability is no greater than
1 in 1 million that a weapon will detonate with a yield of greater
than 4 pounds of TNT if more than one point on the weapon's high
explosive is accidentally detonated. Currently, all nuclear weapons in
the U.S. stockpile are judged to be one-point safe.
[B] The Mark-84 is a 2,000-pound, unguided, conventional bomb. The
Joint Standoff Weapon is a precision-guided, 1,000-pound air-to-
surface conventional missile.
[C] Ground-launched cruise missiles were withdrawn from Europe
beginning in the late 1980s. The W84 warheads, while not in the
current U.S. stockpile, remain in a "managed retirement" status.
Because they are a modern design, the warheads could be used as
replacements for existing weapons, should those weapons develop
performance problems.
[End of table]
Another factor complicating the B61 study is that the B61 Project
Officers Group lacked the time to perform a formal concept assessment
during Phase 6.1 of the Phase 6.X process. DOD and NNSA officials
agreed that exploring novel design concepts would ideally occur before
starting a Phase 6.2 study, consistent with the joint guidelines.
Under the guidelines, either DOD or NNSA can begin a formal Phase 6.1
assessment to address a requirement change, or to study refurbishment
options. Our prior work reviewing life extension programs also has
concluded that, had NNSA taken the time needed to follow the Phase 6.X
process during the earlier effort to refurbish components for the
strategic versions of the B61 bomb, then the agency might have been
better prepared to develop and test key materials that it had not
manufactured in decades. However, in preparing for the ongoing B61
study, the B61 Project Officers Group lacked the time to perform a
Phase 6.1 concept assessment, where requirements and design options
could be more thoroughly explored, according to DOD and NNSA
officials. As a result, the group required about 6 months to work
through issues that might have been addressed during a Phase 6.1
study, added the NNSA program manager for the B61 bomb.
Broad Scope among the Factors That Prolonged the B61 Study:
According to DOD and NNSA officials, the broad scope of the B61 study
is one of several factors that have lengthened the time for completing
the study. According to DOD and NNSA officials, the final study report
is expected to be completed in September 2011, or 1 year later than
the Nuclear Weapons Council's original deadline. DOD and NNSA
officials told us that, while investigating these options, they were
initially concerned that the broad scope would leave the B61 Project
Officers Group without sufficient time or resources to select a
preferred design option and develop more detailed cost information
about that option. Prior GAO work on best practices for managing
program costs has shown that poorly defining a program at the outset
increases the risk that the program will fail to meet its cost,
schedule, or operational goals.[Footnote 28] According to DOD and NNSA
members of the B61 Project Officers Group, absent the ability to
rigorously define the military performance requirements and design
options during the Phase 6.2 study, the later phases of the life
extension program could be at risk. According to a March 2009 progress
report from the B61 Project Officers Group, the scope of the study and
progress made up to that point in time, among other factors, had put
the study at risk of not meeting its deadline to produce the first
refurbished B61 bombs in 2017. In August 2009, according to DOD and
NNSA officials, the group was still considering multiple design
options because of the broad scope, which made it difficult for it to
investigate any particular option in greater detail.
Despite these delaying factors, members of the B61 Project Officers
Group and other DOD and NNSA officials told us that they believe there
is enough time remaining to complete the study and deliver the first
refurbished bomb in fiscal year 2017, as noted by the Nuclear Weapons
Council. Moreover, the officials added that factors aside from the
Nuclear Weapons Council's broad scope also delayed progress in
completing the study. First, according to DOD and NNSA officials, the
B61 study was not fully funded during fiscal years 2009 and 2010. For
example, the NNSA program manager for the B61 bomb stated that NNSA's
fiscal year 2009 budget had already been submitted to Congress when
the Nuclear Weapons Council authorized the B61 study; as a result, the
NNSA had only about $28 million of a required $60 million for the
study in fiscal year 2009. Additionally, the officials told us that
Congress's prohibiting NNSA to obligate or expend funds during fiscal
year 2010 for nuclear components for the refurbished B61 bomb without
prior approval also delayed progress on the study.[Footnote 29] For
example, the NNSA program manager told us that the B61 Project
Officers Group would have begun an investigation of the extent to
which nuclear components from some versions of the bomb could be
reused, had the congressional prohibitions not been in place. In its
committee report accompanying the Energy and Water Development
Appropriations Bill, 2010, the House of Representatives Committee on
Appropriations recommended that no funds be appropriated for the B61
6.2/6.2A study in the absence of a clearly articulated strategy for
the bomb.[Footnote 30] With the lifting of this restriction and
reprogramming of about $53.7 million to the program in August 2010,
[Footnote 31] however, an NNSA official told us that NNSA has
developed a recovery plan to put the life extension program back on
track to meet the 2017 deadline.
According to DOD and NNSA officials, the B61 Project Officers Group is
responsible for completing the study and assessing the cost, schedule,
and performance risk of the recommended design options to completing a
fullscope life extension program and producing the initial refurbished
weapons in 2017. The officials told us that, until the group completes
its study and recommends particular design options to the Nuclear
Weapons Council for approval, it would be premature to judge whether
the scope of the study or other factors have placed the future phases
of the life extension program at risk. However, the officials do
acknowledge that, at the outset of the study, the scope of the effort
was highly ambitious given the time that was originally allowed for
completing the review.
Future Life Extension Programs Could Be at Risk If Scope and Schedule
Are Not Reconciled:
The complications raised by the B61 study's broad scope and narrow
time frames have implications for future life extension programs.
Future life extension programs are likely to be increasingly complex.
According to the April 2010 Nuclear Posture Review Report, every
weapon currently in the stockpile will require some level of technical
attention over the next 30 years to extend its service life. The
Nuclear Posture Review Report also declared the administration's
intention to study options for ensuring the safety, security, and
reliability of the weapons on a case-by-case basis when planning
future life extension programs, including whether to refurbish weapons
components, reuse nuclear components from previously tested weapons or
designs, or replace nuclear components with newly manufactured
components. Adding to the complexity, the report added further the
administration's intent, beginning with the planned W78 ICBM life
extension program, to reduce the number of warhead types in the
stockpile by considering the possibility of using refurbished warheads
on multiple platforms.
Moreover, like the B61 life extension program, future life extension
programs also are likely to occur against the approaching end of the
existing warhead's service life. The W80-1 cruise missile warhead, for
example, is expected to begin becoming nonoperable in about 2017
unless the Air Force replaces key limited-life components in the
stockpiled weapons, according to the Air Force lead project officer
for that weapon. Although NNSA expects to begin studying options for
the W80-1 warhead life extension in the early 2020s, the Nuclear
Weapons Council has not yet decided whether to authorize a life
extension program for the warhead. Additionally, the Air Force is now
leading a concept assessment for the W78 ICBM warhead so that the life
extension program for the warhead could begin production as early as
fiscal year 2020.[Footnote 32] According to the Air Force, the W78
warhead life extension program is needed to meet ICBM operational
requirements through 2030.
When faced with the approaching end of the B61 bomb's service life,
the Nuclear Weapons Council was able to broadly scope the B61 study
without fully reconciling it to the available time because it was not
required to do so. In particular, the DOD-DOE Procedural Guideline for
the Phase 6.X Process does not require the council to consider time
constraints when requesting a refurbishment study. Officials from the
Office of the Secretary of Defense, the Air Force, and NNSA agreed
that the joint Phase 6.X process guidelines should be updated to
require that the scope of future Phase 6.2 studies reflect time
constraints for conducting the study. For example, DOD officials told
us that although the planned concept assessment for the W78 ICBM life
extension program is expected to help clarify and narrow the scope of
the requirements and design options that would be evaluated during the
subsequent Phase 6.2 review, the underlying guidance for implementing
the Phase 6.X process gives the Nuclear Weapons Council the
flexibility to scope the Phase 6.2 study as its members see fit.
Unless DOD and DOE clarify their procedures to require that future
life extension studies are properly scoped given available time, they
may set unrealistic goals for future life extension programs and raise
the risk of delay.
DOD and NNSA Have Not Planned for Maintaining Operational Nuclear
Weapons Commitments to NATO if the B61 Life Extension Program Is
Delayed:
Although DOD and NNSA expect the B61 study to be completed by
September 2011, a life extension program delay could affect the U.S.
pledge to maintain operational nuclear weapons to support its NATO
commitments. However, DOD and NNSA have not yet prepared a long-term
risk management plan to help ensure that the United States will be
able to maintain these commitments should such delays occur. In the
Nuclear Posture Review Report and in remarks to NATO allies, DOD has
committed to avoid a gap in its nuclear weapons capability for NATO
while the B61 bomb's fullscope life extension is under way. However,
meeting this commitment may prove challenging, as previous nuclear
weapons life extension programs have experienced schedule delays for a
variety of reasons. Our prior work has shown that developing a risk
management plan is a useful program management tool for identifying
and measuring risks, developing and implementing risk handling
options, and assessing risk reduction measures.[Footnote 33] NNSA has
developed a risk management plan designed to keep the life extension
program on schedule, and NNSA and DOD have developed some risk
management measures that address near-term operational capability
risks. However, they have not developed a long-term plan to offer
options for preserving the ability to maintain the U.S. commitments to
NATO if the life extension program is delayed or canceled. Developing
such a plan would help ensure that DOD and NNSA are prepared to take
the measures necessary to maintain these commitments during the B61
life extension. Furthermore, without guidance requiring that DOD and
NNSA prepare such risk management plans, operational requirements for
other weapons could also be at risk as they go through life extension
programs, because these weapons are also reaching the end of their
operational life.
The United States Has Pledged to Avoid a Capability Gap in Its NATO
Commitments:
Recognizing the B61 bomb's importance to NATO security, United States
officials have stated they will complete the B61 life extension
program while maintaining the U.S. commitment to NATO. Under National
Security Presidential Directive 35, the President establishes the
number and type of weapons the U.S. commits to NATO. The United States
has demonstrated its commitment to preserving this capability in a
variety of ways. In 2008, the Nuclear Weapon Council stated that the
first production target date for the B61 life extension--Phase 6.5 in
the Phase 6.X process--must ensure that no gap in capability occurs
with respect to this commitment. In the unclassified April 2010
Nuclear Posture Review Report, DOD pledged that the B61 life extension
program would ensure the U.S. capability to deploy these weapons in
support of NATO commitments, and that the program would enhance the
bomb's safety and security features in order to maintain the allies'
confidence in the U.S. deterrent. Further, in June 2010, the Secretary
of Defense stated to NATO's senior nuclear decision-making body that
the United States was committed to supporting the current and future
NATO nuclear weapons requirements during the B61 life extension
program. Given these commitments, a senior official from the Office of
the Secretary of Defense told us that failing to perform the B61 life
extension on schedule could create significant doubt among some NATO
allies regarding the U.S. intentions to preserve its nuclear security
guarantees.
While NATO is currently reviewing its reliance on nuclear weapons,
officials from DOD and NATO do not expect the alliance to change its
nuclear weapons requirements in the short term.[Footnote 34] U.S.
policy emphasizes that change to NATO's nuclear weapons requirements
should be made based on a thorough review by the alliance and by
consensus among NATO's 28 members. In November 2010, the NATO
Secretary General is expected to provide NATO leaders with a revision
to The Alliance's Strategic Concept, which was last published in 1999.
[Footnote 35] Given their expectation that NATO members will approve
the revised Strategic Concept only by consensus, DOD and NATO
officials told us that they believe the alliance will continue to rely
on U.S. nuclear weapons commitments to maintain alliance cohesion for
several reasons. First, the U.S. Secretary of State said in April
2010, shortly after the Nuclear Posture Review Report's publication,
that NATO's review should be guided by the principles that NATO will
remain a nuclear alliance for as long as nuclear weapons exist and, as
a nuclear alliance, sharing nuclear risks and responsibilities widely
among members is fundamental.[Footnote 36] Second, the officials told
us they believed that some NATO members, who joined the alliance since
the Strategic Concept was last updated, were unlikely to seek changes
to NATO's nuclear requirements, because they joined the alliance
specifically because of strong U.S. security guarantees. Third, like
the U.S. Secretary of State, a group of experts from 12 NATO members--
convened by NATO to help revise the Strategic Concept[Footnote 37]--
recommended that NATO should continue to maintain secure and reliable
nuclear weapons capabilities with widely shared responsibility at the
minimum level required by the prevailing security environment.
Although officials from DOD and NATO told us that they believed that
NATO could consider altering specifics about its nuclear posture after
the Strategic Concept was completed, they stated that the basic
requirement for the United States to retain the capability to deploy
nuclear weapons in support of NATO was likely to endure, even if NATO
changes its policy.
DOD and NNSA Have Plans to Preserve Operational Requirements over the
Short Term:
In light of these commitments, both DOD and NNSA plan to take steps to
ensure that the nuclear weapons committed to NATO remain operational
while the B61 life extension program progresses. These steps include
just-in-time maintenance actions on the existing bombs because
critical components are expected to soon begin reaching the end of
their service lives.[Footnote 38] As shown in figure 5, DOD requires
NNSA to deliver refurbished B61 bombs to meet its NATO commitments in
2018. To extend the operational life of the bombs committed to NATO
for a few years while the life extension program is ongoing, the Air
Force plans to replace key components--neutron generators and power
supplies--with newer components removed from bombs that are no longer
in the active stockpile. NNSA is supporting this effort by inspecting
the components that are to be reintroduced to the weapons and by
designing and manufacturing the containers, tooling, and related
hardware needed to retrofit the deployed bombs.
Figure 5: Key Operational Dates for the B61 Bombs during the Life
Extension Program:
[Refer to PDF for image: timeline]
2008-2011: Study:
2011-2017: Development and production engineering:
2011-2015: The Air Force plans to replace limited-life components in
the B61 bombs committed to NATO to prevent them from becoming
nonoperational. This action temporarily extends the life of the bombs
during the planned life extension program.
2018-2022: Production and delivery:
2018-2022: DOD requires NNSA to deliver the refurbished B61 bombs that
are intended to meet NATO commitments.
Source: GAO analysis of DOD information.
[End of figure]
In addition to these planned maintenance actions, NNSA has drafted a
risk management plan to help ensure that the life extension program
meets its milestones.[Footnote 39] The plan, which includes the
generally accepted elements of a risk management approach,[Footnote
40] is focused on managing the cost, schedule, and performance risks
to help ensure that the program is completed on time and within
expected costs. The NNSA project manager for the B61 bomb told us that
the plan will be updated as the B61 life extension program moves
through the Phase 6.X process. Successfully executing this risk
management plan is intended to avoid the operational consequences
caused by delays to the life extension program, according to the B61
bomb's project manager, because the NNSA plan would minimize these
delays.
NNSA also may design the refurbished B61 bomb so that some types of
limited-life components could be used both on the existing weapons and
on the newer version. In particular, the Air Force lead project
officer and NNSA program manager for the B61 bomb stated that NNSA
could produce neutron generators that could be used in both the
existing versions that support NATO, and in the refurbished B61 bomb.
According to NNSA's project manager for SLBM warheads, NNSA followed a
similar strategy when it was unable to meet the Navy's production
requirements during the W76 life extension program; in that instance,
NNSA produced new neutron generators and took another nonnuclear
component out of its reserve inventory for the Navy to install in
existing W76 SLBM warheads. Similarly, if appropriate neutron
generators are produced and available during the B61 life extension
program, then they could be installed in the older bombs before the
existing components reach the end of their service life. However, the
B61 project manager also told us that the B61 Project Officers Group
has yet to determine whether power supply requirements for the
refurbished weapon will be significantly different from the existing
weapons' requirements; such requirements would depend on other weapons-
design issues that have yet to be settled, according to the official.
Moreover, NNSA would have to initiate a new production line for the
power supply components used in the older bombs, because unlike
neutron generators, NNSA currently is not manufacturing these
components. Given the complexity of the B61 life extension program
compared to the W76 life extension program, it is not clear that NNSA
will design components that could be easily used in both the new and
old weapons.
Key Factors Challenge the Commitment to Preserve Operational Nuclear
Weapons Capability during the Life Extension Program:
Even as DOD has plans to preserve the U.S. operational capability
while the life extension program moves forward, preserving this
capability in the event that the B61 life extension program is delayed
could prove challenging, given the complexity of the task and the
tight time lines for completing the program. Nuclear weapons life
extensions are by their nature complex technical endeavors, and the
B61 life extension program has a broader scope than prior life
extensions. According to DOD and NNSA officials, the B61 life
extension is the most complex life extension effort undertaken by NNSA
to date. The effort involves replacing three times as many aging
components as the W76 SLBM warhead life extension program, and NNSA
has less time to complete the program, according to DOD and NNSA
officials. The B61 life extension program is expected to produce far
fewer weapons than did the W76 life extension program; however, NNSA
has less time--8 years--from the start of the Phase 6.2 study to
produce the first refurbished B61 bomb, than the 10 years that NNSA
required to produce the first refurbished W76 SLBM warhead. According
to the B61 Project Officers Group, this development schedule is
aggressive.
Potentially, the B61 life extension program will face key challenges,
several of which have delayed prior life extension programs. These
include potential challenges in manufacturing critical materials and
components; difficulties in meeting production requirements; problems
with the quality of finished weapons; and coordinating the production
of bomb components with the Air Force. Because the B61 bomb is
approaching the end of its operational life during its life extension
program, the consequences of delays caused by these or other
challenges could have a greater impact on the weapons' operational
availability than they had during prior life extension programs.
* Challenges in manufacturing critical materials and components: NNSA
could experience challenges in producing key materials and components,
as it has in prior life extension programs. The W76 SLBM warhead life
extension program experienced a yearlong delay when NNSA determined
that it lacked the knowledge, expertise, and facilities to produce a
key material required for the refurbished warhead. Also, as we found
in our prior work,[Footnote 41] NNSA experienced significant technical
challenges when refurbishing secondary components in the strategic
models of the B61, when testing revealed that NNSA was unable to reuse
a critical material as planned because it did not function under
certain conditions. Similar infrastructure-related issues could affect
the B61 life extension program as well, according to NNSA officials.
In particular, NNSA's construction of a new Kansas City Plant could
present challenges for certain production activities in support of the
B61 life extension program. The current Kansas City Plant, which was
built in 1943, supplies about 85 percent of the nonnuclear components
that compose a typical nuclear weapon, including those used in the
B61. The transition from the old plant to the modern facility is
scheduled to occur during fiscal years 2013 and 2014 at the same time
the B61 life extension program will be conducting preproduction
activities that support the life extension program. According to NNSA
program officials, this means that some of the preproduction
activities may have to be conducted at the old plant, then continued
after the new plant is operating. In 2009, we reported that the
program to replace the Kansas City Plant had already been delayed by 1
year.[Footnote 42] If the plant's modernization schedule is delayed
further, then there could be a risk to completing the first
refurbished B61 bomb in 2017, according to NNSA officials. However,
the NNSA officials added that the risks can be managed by thorough
planning.
* Difficulties in meeting production requirements: As it has in past
life extension programs, NNSA may have difficulty meeting production
requirements to deliver refurbished B61 bombs to DOD on time. For
example, NNSA and Navy officials involved in the W76 SLBM warhead life
extension program told us that NNSA was unable to meet the Navy's
production requirements for refurbished W76 warheads; the Navy
official explained that funding shortfalls left NNSA unable to
purchase certain components, obtain necessary tooling, or hire more
technical personnel needed to increase production rates. Regarding the
B61 life extension program, after NNSA achieves first production in
2017--Phase 6.5 in the Phase 6.X process--the agency will require
additional time to increase its weapons production rate in order to
produce enough weapons suitable for delivery to DOD beginning in
fiscal year 2018. However, as of August 2010 DOD and NNSA officials
were uncertain that NNSA could meet the production rate required to
meet NATO commitments given the time available to do so. Principally,
NNSA has not determined how long it will take to achieve a full rate
of production after reaching Phase 6.5, because the agency has not yet
finalized the designs for key components that it would have to
produce, according to NNSA and Air Force officials. Additionally, the
NNSA program manager for the B61 bomb told us that he did not yet know
whether NNSA was capable of producing enough weapons in time to meet
not only DOD's operational requirements, but also NNSA's requirement
to produce additional weapons for surveillance testing. The NNSA
official added that DOD established its operational requirements and
deadlines without considering NNSA's need to produce such weapons.
However, DOD officials told us simply that DOD and NNSA have not been
able to come to an agreement on projected out-year production
requirements.
* Problems with the quality of finished weapons: Even as the need to
produce weapons for quality assurance testing could pose challenges,
the B61 life extension program also could face delays because of
problems with the finished weapons that are discovered when NNSA
performs surveillance tests. DOD officials have emphasized the
importance of a surveillance testing program to ensure that newly
refurbished bombs and warheads are reliable. In the past, NNSA has
detected problems resulting from NNSA's manufacturing processes in
finished warheads resulting in delivery delays to DOD.
* Coordinating the production of bomb components between NNSA and the
Air Force: Uncertainty exists that the B61 life extension program will
be completed on time because doing so will require NNSA and the Air
Force to synchronize the production of different components of the
bomb. While NNSA is responsible for refurbishing the bomb's nuclear
and many of its nonnuclear components, the Air Force is responsible
for acquiring a new guided tailkit section for the refurbished B61.
The new bomb tail section is estimated to cost $800 million and is
designed to increase accuracy, enabling the military to achieve the
same effects as the older bomb, but with lower nuclear yield. The
addition of the new tail section also allows NNSA to consolidate the
different versions of the B61 bomb into a single version. Delivery of
the refurbished B61 bombs with the new tail section is essential to
meeting DOD's initial operating requirements to support NATO
commitments. The Air Force is studying the requirements for the new
tail section concurrently with the B61 study, and officials told us
that the Air Force included funding in its budget request for fiscal
year 2011. However, if the Air Force does not receive adequate funds,
or the program is canceled altogether, NNSA would have to use a less
sophisticated tail design in order to produce the first refurbished
weapon in 2017. If the new tail is only delayed, and not canceled,
then it could be fitted to the already-refurbished bombs at a later
time, according to NNSA officials; however, this would involve
increased cost and logistics efforts.
DOD and NNSA Have Not Established a Long-Term Plan to Avoid
Operational Capability Gaps If the B61 Life Extension Program Is
Delayed:
Although Air Force and NNSA officials told us that DOD's planned
measures should mitigate the risk of a capability gap in the U.S.
commitments to NATO during the B61 life extension program, DOD and
NNSA have not established a plan to mitigate the long-term operational
risks to these commitments, should the program be delayed. Our prior
work shows that risk management is a useful tool that integrates a
systematic concern for risk into the cycles of decision making.
[Footnote 43] Risk management principles help organizations to manage
risk by assessing current threats and vulnerabilities; evaluating,
selecting, and implementing risk reduction actions; and monitoring
their implementation.
DOD and NNSA officials told us that there are several options that
could be taken to manage the long-term risks to U.S. operational
commitments. As of September 2010, the official program of record was
for NNSA to develop options for a fullscope, 30-year life extension of
the B61 bomb's nuclear and nonnuclear components, as requested by the
Nuclear Weapons Council in June 2008. However, if the B61 Project
Officers Group determines that the fullscope life extension is too
high risk, it could recommend a more limited refurbishment, involving
the bomb's nonnuclear components and communications systems, according
to the Air Force's B61 lead project officer and other DOD and NNSA
officials. The officials told us that while this option would extend
the operational life of the B61 for several years, it would involve
significant drawbacks. According to the Air Force lead project officer
for the B61 bomb, the bomb would require continued patchwork
maintenance to ensure the bomb's performance, safety, and security,
even after NNSA completed the more limited refurbishment.
Additionally, the NNSA would be unable to address the enhanced safety
and security goals established for the program without making more
extensive changes to the weapon's design than the limited
refurbishment would allow. Moreover, according to NNSA, the bomb would
require a second life extension program beginning in the mid 2020s;
together, NNSA estimates that performing two life extension programs
would cost roughly $2 billion more than the currently planned program.
Moreover, because other nuclear weapons are expected to require
refurbishment throughout the 2020s, NNSA officials told us that NNSA's
limited production capacity would make it impractical to perform a
second life extension effort on the B61 bomb at that time.
Regardless of the approach that NNSA undertakes for the life extension
program, DOD and NNSA officials told us that there are options that
could be taken to mitigate gaps in the U.S. commitments to NATO that
are caused by delays to the program. These options include changing
the refurbished weapon's required delivery schedules; allowing the
bomb's power supply to expire, which reduces the reliability of the
weapon; and changing the quantity of U.S. nuclear weapons committed to
NATO. However, as shown in table 3, each of these options has
considerable drawbacks.
Table 3: Options for Mitigating a Gap in U.S. Commitments to NATO:
Option: Change required delivery schedules;
Description: Currently, DOD requires the delivery of strategic
versions of the refurbished bombs about 6 months earlier than those
committed to support NATO. This option reverses these schedules, so
that the initially refurbished bombs are used to meet U.S. NATO
commitments if production schedules are delayed. Alternatively, NNSA
produces and replaces limited-life components for the strategic
versions of the bomb;
Principal drawbacks:
* U.S. Strategic Command would be required to offset lost capabilities
with other nuclear weapons;
* Added cost to NNSA for producing and replacing limited life
components.
Option: Existing weapons allowed to operate with reduced reliability;
Description: Power supplies allowed to reach the end of their life;
Principal drawbacks:
* According to officials from the Office of the Deputy Assistant
Secretary of Defense for Nuclear and Missile Defense Policy, this
option would require "unacceptable" changes to U.S. and NATO policy.
Option: Change U.S. nuclear weapons posture;
Description: The U.S. President reduces the number of weapons
authorized to be committed to support NATO;
Principal drawbacks:
* Would require United States to alter the capability to deploy
weapons to NATO during a crisis;
* Could reduce opportunities for NATO allies to actively take part in
the nuclear mission;
* Could be unsettling to NATO allies.
Source: GAO analysis of DOD information.
[End of table]
Although DOD officials told us that such options could be available to
DOD as the B61 life extension program moves forward, they added that
DOD and NNSA have not prepared a long-term risk management plan to
preserve operational capability. DOD and NNSA have not developed such
a plan because there is no such requirement in the Procedural
Guideline for the Phase 6.X Process, the principal document that
establishes the joint DOD-DOE process for nuclear weapons
refurbishments. Such a plan would describe the measures that NNSA and
DOD could take at different points in time to preserve U.S.
commitments to NATO, should the B61 life extension program be delayed.
A risk management plan also would identify the resources required to
manage and mitigate risk, according to the risk management principles
identified in our prior work. Moreover, according to these principles,
DOD and NNSA would continuously monitor and update the plan as
circumstances changed. Lacking a long-term risk management plan, DOD
may be unprepared to weigh the costs and benefits of potential risk
management actions.
DOD and NNSA officials agreed that the B61 Project Officers Group
should be responsible for preparing a long-term plan to address
potential operational risks, but they added that the group has not
done so because it is focused instead on developing the plans and
approaches for refurbishing the weapon within required time frames.
According to the NNSA program manager for the B61 bomb, because the
B61 Project Officers Group is responsible for overseeing activities to
sustain the B61 bomb as an operational weapon, the group should
develop a long-term plan for sustaining the weapon's capability as the
life extension program moves forward. DOD officials agreed that a long-
term risk management plan would help DOD identify how to move forward
and prepare for potential schedule slippages in the B61 life extension
program, and begin thinking about options before they were required.
U.S. European Command officials stated that developing such a plan in
advance of the life extension program's execution could help DOD and
NNSA identify steps to be taken--and when to take them--to preserve
the U.S. nuclear weapons commitments to NATO.
According to the Risk Management Guide for DOD Acquisition,[Footnote
44] the alternative to risk management is crisis management, which
usually involves increased resources and a restricted set of available
options. An operational risk management plan would help the United
States to be better prepared to take the steps needed to maintain its
nuclear weapons commitments to NATO with no gaps in operational
capability during the B61 life extension program. Moreover, like the
B61 life extension program, future life extension programs are also
expected to increasingly be scheduled against rapidly approaching
service-life deadlines, leaving DOD with fewer options to draw upon in
order to cover contingencies. Officials from the Office of the
Secretary of Defense and NNSA agreed that the relevant project
officers group responsible for preparing the Phase 6.2 study should
also be responsible for developing plans during that study to manage
potential operational risks in order to avoid crisis management. An
Air Force official told us that, unless DOD and NNSA prepare plans to
mitigate operational risks as they plan and execute future life
extension programs, the programs could end up adversely affecting
other nuclear weapons maintenance and sustainment actions as resources
are reprioritized to meet operational requirements on an emergency
basis. Unless the Procedural Guideline for the Phase 6.X Process is
updated to require the preparation of an operational risk mitigation
plan, operational capability gaps could arise during future life
extension programs if they experience schedule delays.
Conclusions:
Given that future nuclear weapons life extension programs are expected
to increasingly be scheduled against rapidly approaching service-life
deadlines, DOD and NNSA will likely face increased risk to their
ability to complete the programs within available time frames and
without operational ramifications. We have identified two areas where
DOD and NNSA can take steps to reduce or manage such risk. First, DOD
and NNSA may incur undue risk unless the time available to complete a
life extension program is considered when setting the scope of
activities to be considered during the program. The joint DOD-DOE
guidance governing the performance of life extension programs does not
require the Nuclear Weapons Council to factor in time available to
complete life extension programs. For example, the Nuclear Weapons
Council requested an ambitious scope for the study that will be used
as the basis for the B61 life extension program, in spite of a
compressed time schedule and potentially significant risk to U.S.
commitments to its NATO allies. The reasons for this ambitious scope
were many and included desires to improve nuclear weapons safety,
minimize maintenance requirements, and exercise NNSA's nuclear weapons
design and production capabilities. These goals should have been
weighed against the reality that the B61 life extension program will
be conducted within very tight time frames to ensure completion before
the existing weapons begin to become nonoperational. However, the
Nuclear Weapons Council may not have fully accounted for the time
available to plan for and complete the life extension program when it
laid out the broad scope. The B61 Project Officers Group has until
September 2011 to complete the study and assess the risk of different
design options. Although we are not making a recommendation that the
Nuclear Weapons Council revise the scope of this effort to better
reflect the available time, it is important to note that these actions
have implications for future life extension programs, which are also
expected to face highly constrained time lines. Without a requirement
to factor in the time available to complete future life extension
programs, the Nuclear Weapons Council may increase the risk that the
programs will not be properly scoped.
Second, similar to the B61 life extension program, future nuclear
weapons life extension programs, including those for weapons deployed
on ICBMs and submarines, will have their own complexities and
challenges to overcome. The operational consequences of failing to
complete these programs on time could be significant, given the
purposes for which these weapons are deployed. However, the joint DOD-
DOE guidance governing the performance of life extension programs does
not require DOD and NNSA to prepare a plan for managing operational
risks that may occur if a life extension program is delayed. As a
result, DOD and NNSA have not prepared a long-term risk management
plan for ensuring operationally capable B61 bombs to support NATO
commitments throughout the life extension program. Such a plan would
help ensure that the weapons remain operational throughout the life
extension program, thus helping preserve the commitment to NATO.
Looking ahead, unless DOD and DOE take steps to update their guidance
to reflect the need for such a plan, DOD and NNSA may be required to
take difficult policy and programmatic actions to preserve operational
requirements during the execution of the B61 life extension and future
life extension programs.
Recommendations for Executive Action:
We are recommending that the Secretaries of Defense and Energy direct
the Nuclear Weapons Council to take the following three actions:
To reduce the risk that future Phase 6.2 studies for nuclear weapons
life extension programs are not properly scoped given available time
for completing a life extension, revise the Procedural Guideline for
the Phase 6.X Process to require that the council factor in the time
available for completing a life extension program when establishing
the scope of a Phase 6.2 feasibility study of military performance
requirements and design options.
To mitigate the risk that U.S. operational commitments will be
affected by life extension program schedule delays:
* Direct the appropriate DOD components, in coordination with NNSA, to
prepare an operational risk management plan identifying the measures
that would be required to ensure that the United States is able to
maintain its commitments to NATO with no gaps in operational
capability while the B61 life extension program is being carried out.
* Revise the Procedural Guideline for the Phase 6.X Process to require
the council to direct the preparation of operational risk management
plans during the planning and execution of future life extension
programs.
Agency Comments and Our Evaluation:
We provided DOD and NNSA with copies of our draft classified report
for their review and comment. DOD concurred with all three of the
recommendations, and identified actions that it would take toward
implementing each one. NNSA also generally concurred with our report
and recommendations, but did not comment on specific findings or
recommendations in the draft report. DOD's comments appear in their
entirety in appendix II, and NNSA's in appendix III. Both agencies
also provided technical comments, which we have incorporated into the
draft as appropriate.
DOD concurred with our recommendation that the Secretaries of Defense
and Energy direct the Nuclear Weapons Council to revise the Procedural
Guideline for the Phase 6.X Process to require that the council factor
in time available for completing a life extension program when
establishing the scope of a Phase 6.2 feasibility study. In its
comments, DOD stated that the Under Secretary of Defense for
Acquisition, Technology, and Logistics will recommend that the Nuclear
Weapons Council revise these guidelines to take into consideration the
available time. However, DOD also commented that while working within
established time constraints is important, the time available to
complete a life extension program is one of many competing factors
that the Nuclear Weapons Council must consider when scoping a Phase
6.2 study. DOD also commented that the Nuclear Weapons Council should
avoid placing unnecessary restrictions on exploring the design options
identified by technical experts early in the study. While we agree
that the time available to carry out a life extension program is one
of many competing factors to consider when scoping a Phase 6.2 study,
and that prudent exploration of design options should not be
restricted, scoping the study to meet the available time has become
critical to the success of life extension programs. As we stated in
our draft report, the broad scope of the B61 Phase 6.2 study
complicated the study effort, given the limited time for NNSA to
produce refurbished weapons before the currently deployed B61 bombs
begin reaching the end of their service life. While it is too soon to
tell what effect the broad scope will have on the B61 life extension
program overall, future life extension programs will face similar time
constraints, as other weapons in the stockpile approach the end of
their service life. We believe that if the procedural guideline is
revised and the Nuclear Weapons Council factors time constraints into
setting the scope of Phase 6.2 studies for future life extension
programs, the likelihood of success will be improved.
DOD also concurred with our two recommendations that are intended to
mitigate the risk that U.S. operational commitments will be affected
by life extension program schedule delays. First, DOD concurred with
our recommendation that the Secretaries of Defense and Energy direct
the appropriate DOD components, in cooperation with NNSA, to prepare
an operational risk management plan to ensure no gaps in operational
capability while the B61 life extension program is being carried out.
In response to this recommendation, DOD stated that the Under
Secretary of Defense for Acquisition, Technology, and Logistics will
recommend that the Nuclear Weapons Council formally task the "B61 Life
Extension Group"[Footnote 45] to provide an operational risk
assessment plan and mitigation scenarios ensuring there is no gap in
supporting the NATO nuclear deterrent mission. DOD also concurred with
our recommendation that the Secretaries of Defense and Energy direct
the Nuclear Weapons Council to revise the Procedural Guideline for the
Phase 6.X Process to direct the preparation of operational risk
management plans during future life extension programs. In its
comments DOD stated that the Under Secretary for Defense for
Acquisition, Technology, and Logistics will request that the council
revise the guideline to require operational risk management plans as
part of the Phase 6.X process. We agree that DOD's proposed actions to
provide an operational risk management plan for the B61 life extension
program as well revise the procedural guideline to require such plans,
will meet the intent of our recommendations once they are implemented.
We are sending copies of this report to the appropriate congressional
committees; the Secretary of Defense; the Secretary of the U.S. Air
Force; the Chairman, Joint Chiefs of Staff; the Commander, U.S.
Strategic Command; the Commander, U.S. European Command, and NATO
Supreme Allied Commander Europe; the Secretary of Energy; and the
Administrator of the National Nuclear Security Administration. In
addition, the report will be available at no charge on our Web site at
[hyperlink, http://www.gao.gov].
If you or your staffs have any questions about this report, please
contact Gene Aloise at (202) 512-3841 aloisee@gao.gov or John
Pendleton at (202) 512-3489 or pendletonj@gao.gov. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. Key contributors to this report are
listed in appendix IV.
Signed by:
Gene Aloise:
Director, Natural Resources and Environment:
Signed by:
John Pendleton:
Director, Defense Capabilities and Management:
[End of section]
Appendix I: Scope and Methodology:
For this review we addressed the extent to which the Department of
Defense (DOD) and the National Nuclear Security Agency (NNSA) have (1)
considered the time available to begin producing refurbished bombs
when determining the scope of military performance requirements and
design options for the B61 life extension program; and (2) taken
actions to avoid operational gaps in U.S. nuclear weapons commitments
to NATO during the B61 life extension program. For our review of these
two objectives, we obtained and reviewed key DOD and Department of
Energy (DOE) documentation for implementing the Phase 6.X process in
order to understand the roles of the DOD, DOE, Nuclear Weapons
Council, B61 Project Officers Group, and other organizations
throughout the B61 life extension process. This documentation
included: the Joint DOD-DOE Procedural Guideline for Implementing the
Phase 6.X Process, dated April 2000; DOE's Procedural Guidelines for
the Phase 6.X Process, dated October 2000, and DOD Instruction
5030.55, DOD Procedures for Joint DOD-DOE Nuclear Weapons Life Cycle
Activities, dated January 2001. We obtained and reviewed briefings
from the Office of the Deputy Assistant to the Secretary of Defense
for Nuclear Matters, Office of the Deputy Assistant Secretary of
Defense for Nuclear and Missile Defense Policy, U.S. Strategic
Command, U.S. European Command, and the Air Force Nuclear Weapons
Center to understand their roles and responsibilities in the
management and oversight of the U.S. stockpile, including the Phase
6.X process. We also reviewed briefings from the NNSA Office of the
Deputy Administrator for Defense Programs to understand NNSA's role in
the day-to-day activities of managing the U.S. stockpile and executing
the B61 life extension program. To provide us with an understanding of
the role that the B61 bomb plays in U.S. national security, we
obtained and reviewed briefings from U.S. Strategic Command, U.S.
European Command, and the North Atlantic Treaty Organization (NATO).
We also met with the Deputy Assistant Secretary of Defense for Nuclear
and Missile Defense Policy to discuss how DOD determines requirements
for nuclear weapons capabilities and force structure, and reviewed
briefings outlining the roles played by the President, Secretary of
Defense, and Chairman of the Joint Chiefs of Staff, to prepare
operational direction and guidance for the employment of nuclear
weapons. To put the B61 life extension program in a broader
programmatic context, we reviewed the administration's Nuclear Posture
Review Report, dated April 2010; the May 2010 Report in Response to
National Defense Authorization Act Fiscal Year 2010 Section 1251 New
START Treaty Framework and Nuclear Force Structure Plans; and the
NNSA's Fiscal Year 2011 Stockpile Stewardship and Management Plan
Summary, also published in May 2010.[Footnote 46] To provide context
on the challenges of implementing life extension programs on nuclear
weapons, we reviewed prior GAO reports, and reviewed the Nuclear
Weapons Council's annual Report on Stockpile Assessments, which
include reports by the directors of Sandia, Los Alamos, and Livermore
National Laboratories on the status of the U.S. stockpile. We also
obtained and reviewed reports and briefings prepared by the U.S.
Strategic Command Strategic Advisory Group, and reports prepared by
the JASON group.[Footnote 47]
To determine the extent to which DOD and NNSA considered the time
available to begin producing refurbished B61 bombs when determining
the scope of the on-going study of military performance requirements
and design options, we examined both the scope of the study and the
time frames for performing the B61 life extension program by reviewing
documents and interviewing officials from both DOD and NNSA. In
particular, we analyzed the June 2008 memorandum to the Members of the
Nuclear Weapons Council's Standing and Safety Committee, requesting
that the B61 Project Officers Group conduct a Phase 6.2/6.2A study,
evaluate military performance requirements, and recommend design
options for the B61 life extension program. We reviewed documentation
for the B61 life extension program from the Office of the Secretary of
Defense, U.S. Strategic Command, U.S. European Command, U.S. Air
Forces in Europe, and NATO. To track the B61 Project Officers Group's
progress in evaluating military performance requirements, we compared
successive revisions to the refurbished B61 bomb's draft military
characteristics, and discussed how they have changed with key NNSA and
Air Force officials, including the official responsible for managing
the changes to the B61 bomb's requirements. We reviewed relevant
documents and discussed the challenges of reconciling requirements
with officials from the Air Force, U.S. European Command, NATO, and
the NNSA. We also reviewed the Air Force's requirements documentation
prepared to support the acquisition of a tailkit for the refurbished
B61 bomb, and determined the linkage of this design option to key DOD
requirements by obtaining and reviewing documentation from U.S.
Strategic Command, U.S. European Command, NNSA, and the B61 Project
Officers Group. We identified and reviewed key NNSA and Air Force
briefings that evaluated design options for the life extension
program, and tracked the B61 Project Officers Group's progress in
narrowing the scope of design options by obtaining and analyzing
status briefings that the B61 Project Officers Group prepared
throughout the 6.2/6.2A study for the Nuclear Weapons Council's
Standing and Safety Committee. We compared the scope of the ongoing
B61 6.2/6.2A study with the scope of the life extension programs for
the W87 intercontinental ballistic missile warhead, the W76 submarine-
launched ballistic missile warhead, the W80 cruise missile warhead,
and the refurbishment of the secondary components of the strategic
versions of the B61 bomb. We identified the scope of these prior life
extension programs and refurbishments by obtaining the Nuclear Weapons
Council's direction to establish the life extension programs and other
key documentation. We identified criteria for assessing the scope of
the B61 life extension program study, given available time, by
reviewing our prior work on best practices for designing evaluations
and conducting studies.[Footnote 48] To understand the challenges of
evaluating requirements and design options for the B61 study, we
traveled to the Air Force Nuclear Weapons Center in Albuquerque, New
Mexico, to interview the lead project officer of the B61 Project
Officers Group, and other key officials involved in the preparing the
B61 bomb's requirements. We interviewed NNSA officials involved in the
management and oversight of the B61 stockpile, both in NNSA
headquarters and at the NNSA Service Center in Albuquerque, New
Mexico. These officials included the NNSA program manager for the B61
bomb and other officials from NNSA's Office of the Deputy
Administrator for Defense Programs. We met with senior DOD officials,
including officials from the Office of the Deputy Assistant to the
Secretary of Defense for Nuclear Matters; the Office of the Deputy
Assistant Secretary of Defense for Nuclear and Missile Defense Policy;
U.S. Strategic Command; U.S. European Command; U.S. Air Forces in
Europe; and NATO. We visited U.S. Strategic Command in Omaha,
Nebraska, and met with the U.S. Strategic Command Chief of Staff and
other senior military officers and civilian officials from the
command. We also interviewed other DOD officials throughout our work,
including officials from: the Deputy Director for Strategy and Policy
(J5), Joint Staff; Defense Threat Reduction Agency; Office of the
Assistant Chief of Staff of the Air Force for Strategic Deterrence and
Nuclear Integration. We also analyzed briefings from, and met with,
the Air Force lead project officers for the B83, W78, W80, and W87
Project Officers Groups; the Navy lead project officer for the W76 and
W88 Project Officers Group; the U.S. Army Nuclear and Combating
Weapons of Mass Destruction Agency, and the NNSA program managers for
the W76, W78, W80, B83, W87, and W88 nuclear weapon systems.
To determine the extent to which DOD and NNSA have taken actions to
avoid operational gaps in U.S. nuclear weapons commitments to NATO
during the B61 life extension program, we identified U.S. nuclear
weapons commitments for NATO by reviewing National Security
Presidential Directive 35, the presidential guidance that establishes
the required number of nuclear weapons to be committed to NATO; and by
obtaining and reviewing DOD's requirements for declaring an initial
operating capability for both strategic and nonstrategic B61 bombs.
Further, we reviewed key NATO documentation, including The Alliance's
Strategic Concept, the Nuclear Planning Group's Political Principles
for Nuclear Planning and Consultation, and High Level Group reports,
and received briefings from the U.S. European Command and NATO
outlining these operational requirements. We determined the
commitments made by the United States to preserve this operational
capability by reviewing the June 2008 memorandum requesting the start
of the B61 life extension program study; the April 2010 Nuclear
Posture Review Report; and the June 2010 speech by the Secretary of
Defense to NATO. We clarified that we fully understood these
commitments by interviewing the Deputy Assistant Secretary of Defense
for Nuclear and Missile Defense Policy and other DOD officials. To
obtain operational perspectives on these commitments, we traveled to
Stuttgart, Germany, and Kaiserslautern, Germany, where we met with
officials from U.S. European Command and U.S. Air Forces in Europe,
respectively, and visited NATO in Brussels, Belgium, to meet with
officials from the U.S. Mission to NATO, with an official from NATO's
Supreme Headquarters, Allied Powers Europe, the NATO Deputy Assistant
Secretary General for Weapons of Mass Destruction Policy, and a member
of the NATO International Military Staff. We identified potential
challenges to the B61 life extension program by reviewing our prior
work on nuclear weapons life extension programs and by interviewing
NNSA nuclear weapons program managers, Navy and Air Force lead project
officers, officials from the Office of the Deputy Assistant to the
Secretary of Defense for Nuclear Matters, and other DOD officials. To
identify risk management criteria and the key elements of a risk
management approach, we used prior GAO work and the Defense
Acquisition University's August 2006 Risk Management Guide for DOD
Acquisition. We obtained information on the B61 Project Officers
Group's overall risk management approach by reviewing the December
2008 B61 Life Extension Project Risk Management Plan and interviewing
the NNSA program manager and Air Force lead project officer for the
B61 bomb. We discussed possible risk mitigation steps in light of the
potential challenges to the B61 life extension program with officials
from the Office of the Deputy Assistant to the Secretary of Defense
for Nuclear Matters; Office of the Deputy Assistant to the Secretary
of Defense for Nuclear and Missile Defense Policy; U.S. European
Command; and both DOD and NNSA members of the B61 Project Officers
Group, including the Air Force lead project officer and the NNSA
program manager for the B61 bomb.
We conducted this performance audit from October 2009 to December 2010
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe
that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.
[End of section]
Appendix II: Comments from the Department of Defense:
[Redacted]
Assistant To The Secretary Of Defense:
Nuclear And Chemical And Biological Defense Programs:
3050 Defense Pentagon:
Washington, DC 20301-3050:
November 17, 2010:
Mr. John Pendleton:
Director, Defense Capabilities and Management:
U.S. Government Accountability Office:
441 G Street, N.W.
Washington, D.C. 20548:
Dear Mr. Pendleton:
This is the Department of Defense (DoD) response to the Government
Accountability Office (GAO) draft report [redacted] "Nuclear Weapons:
DoD and NNSA Need To Better Manage Scope of Future Refurbishments and
Risks to Maintaining U.S. Commitments to NATO," dated October 4, 2010
(GAO Code 351404). The DoD concurs with all GAO recommendations
contained in the draft report. We have provided specific comments to
each recommendation in the enclosed Department of Defense Comments to
the GAO Recommendations.
Technical corrections suggested to further enhance the report were
forwarded under separate cover. If you have any questions, please call
me at 703-697-1771. The point of contact for this issue is Mr. David
Court, 703-693-4304, david.eourt@osd.smil.mil or david.court@osd.mil.
Sincerely,
Signed by:
Andrew Weber:
Enclosure: As stated:
Unclassified when separated from enclosure.
[End of letter]
GAO Draft Report Dated October 4, 2010:
Nuclear Weapons:
DOD and NNSA Need to Better Manage Scope of Future Refurbishments and
Risks to Maintaining U.S. Commitments to NATO:
Department of Defense Comments to the GAO Recommendations:
Recommendation 1: The GAO recommends that the Secretaries of Defense
and Energy direct the Nuclear Weapons Council to revise Procedural
Guideline for the Phase 6.X Process to require the Council factor in
the time available for completing a life extension program when
establishing the scope of a Phase 6.2 feasibility study of military
performance requirements and design options. (See page 40 of the Draft
report)
DOD Response: The Department concurs with the recommendation but
recognizes that the time available for completing a life extension
program is one of many competing factors that the Nuclear Weapons
Council (NWC) must consider when establishing the scope of a Phase 6.2
feasibility study. The Department considers it important to work
within established time constraints, but must also avoid unnecessary
restrictions on design options that are identified by the technical
experts during the initial study phases. The USD (AT&L) will recommend
that the NWC revise the Procedural Guideline for the Phase 6.X Process
to take into consideration the amount of time available for completion
of the life extension program when assigning the scope of the 6.2
study. The Department recognizes that the Phase 6.X Process must
maintain the ability to document deviations with acknowledgment that
changes within contingency are allowed.
Recommendation 2: The GAO recommends that the Secretaries of Defense
and Energy direct the Nuclear Weapons Council to direct the
appropriate DoD components, in coordination with NNSA, to prepare an
operational risk management plan identifying the measures that would
be required to insure that the United States is able to maintain its
commitments to NATO [redacted] with no gaps in its operational
capability while the B61 life extension program is being carried out.
(See page 40 of the Draft report).
Dod Response: The Department concurs with the recommendation and the
USD (AT&L) will recommend the NWC formally task the B61 Life Extension
Group to provide an operational risk assessment plan and mitigation
scenarios ensuring there is no gap in supporting [redacted].
Recommendation 3: The GAO recommends that the Secretaries of Defense
and Energy direct the Nuclear Weapons Council to revise the Procedural
Guideline for the Phase 6.X Process to require the Council to direct
the preparation of operational risk management plans [illegible] the
planning and execution of future life extension programs. (See page 40
of the Draft report).
Dod Response: The Department concurs with the recommendation and the
USD (AT&L) will request the NWC revise the Procedural Guideline for
the Phase 6.X Process to require operational risk management plans as
a part of the Phase 6.X process for the planning and execution of
future life extension programs.
[End of section]
Appendix III: Comments from the National Nuclear Security
Administration:
Department of Energy:
National Nuclear Security Administration:
Washington, DC 20585:
November 4, 2010:
Mr. Gene Aloise:
Director:
Natural Resources and Environment:
Government Accountability Office:
Washington, DC 20548:
Dear Mr. Aloise:
The National Nuclear Security Administration (NNSA) appreciates the
opportunity to review the Government Accountability Office's (GAO)
draft report, [redacted] Nuclear Weapons: DOD and NNSA Need to Better
Manage Scope of Future Refurbishments and Risks to Maintaining U.S.
Commitments to NATO. We understand that this work was done at the
request of the Subcommittee on Strategic Forces, Committee on Armed
Services, House of Representatives, to review the Department of
Defense's military requirements for nuclear weapons and force
structure.
NNSA generally agrees with the report and the recommendations. NNSA
recognizes that a life extension Phase 6.2 Study is the single
opportunity to determine a weapon's optimal balance of performance,
surety, and life-cycle cost over its next 30 to 40 years of stockpile
service. Hence, we believe it to be the best course of action to
consider all viable enhancements consistent with schedule, funding and
acceptable risk as part of the Phase 6.1/6.2 Study.
Under separate cover we will send technical comments to help clarify
and improve the report in areas that may be confusing or misleading.
If you have any questions related to this response, please contact
JoAnne Parker, Director, Office of Internal Controls, at 202-586-1913.
Sincerely,
Signed by:
Gerald L. Talbot, Jr.
Associate Administrator for Management and Administration:
cc: Deputy Administrator for Defense Programs:
[End of section]
Appendix IV: GAO Contacts and Staff Acknowledgments:
GAO Contacts:
Gene Aloise (202) 512-3841 or aloisee@gao.gov:
John H. Pendleton (202) 512-3489 or pendletonj@gao.gov:
Staff Acknowledgments:
In addition to the contacts named above, Jonathan M. Gill, Assistant
Director; Penney Harwell Caramia, Assistant Director; Colin L.
Chambers; Grace A. Coleman; David G. Hubbell; Katherine S. Lenane;
Gregory A. Marchand; Kevin L. O'Neill, Analyst in Charge; Timothy M.
Persons; Steven R. Putansu; Robert Robinson; Jeff R. Rueckhaus; and
Rebecca Shea also made key contributions to this report.
[End of section]
Footnotes:
[1] Section 1070 of the National Defense Authorization Act for Fiscal
Year 2008, Pub. L. No. 110-181 (2008), required the Secretary of
Defense, in consultation with the Secretary of Energy and Secretary of
State, to conduct a comprehensive review of the nuclear posture of the
United States for the next 5 to 10 years. DOD published the
conclusions and recommendations from that review in the April 2010
Nuclear Posture Review Report.
[2] On November 19, 2010, shortly after we received comments on our
draft report, NATO members completed this review and adopted a new
Strategic Concept.
[3] The planned life extension program covers the B61-3, B61-4, B61-7,
and B61-10 versions, but does not cover the B61-11 version.
[4] A fullscope life extension would include the refurbishment of the
bomb's nuclear components and nonnuclear components, whereas a limited
life extension would include only the nonnuclear components.
[5] The Energy and Water Development and Related Agencies
Appropriations Act, 2010, restricted NNSA from obligating or expending
funds for "B61-12" nuclear components without prior approval of the
Appropriations Committees. Pub. L. No. 111-85, 123 Stat. 2866 (2009).
[6] White House, Report in Response to Fiscal Year 2010 National
Defense Authorization Act Section 1251 New START Treaty Framework and
Nuclear Force Structure Plans, May 13, 2010.
[7] GAO, Nuclear Weapons: Improved Management Needed to Implement
Stockpile Stewardship Program Effectively, [hyperlink,
http://www.gao.gov/products/GAO-01-48] (Washington, D.C.: Dec. 14,
2000).
[8] GAO, Nuclear Weapons: NNSA and DOD Need to More Effectively Manage
the Stockpile Life Extension Program, [hyperlink,
http://www.gao.gov/products/GAO-09-385] (Washington, D.C.: Mar. 2,
2009).
[9] As of September 30, 2009, the U.S. stockpile totaled 5,113
warheads, including deployed weapons, spares, and warheads kept in
reserve for operational crises or to replace weapons that have become
unreliable due to aging or other defects. "Operationally deployed"
weapons are those that are deployed on either ICBMs in their launchers
or on SLBMs onboard submarines, and nuclear armaments loaded on
bombers, or stored in weapons storage areas on bomber bases.
[10] Although NATO has no standing operational plans for the use of
nuclear weapons, the United States and certain NATO allies provide
forces and are required to maintain the ability to be on alert for
nuclear operations within a 30-day, 180-day, or 365-day period.
[11] We reviewed this refurbishment in our prior work. See GAO-09-385.
[12] Department of Defense and Department of Energy, Procedural
Guideline for the Phase 6.X Process (Washington, D.C.: Apr. 19, 2000).
[13] The Nuclear Weapons Council membership includes the Under
Secretary of Defense for Acquisition, Technology and Logistics
(chair), the Under Secretary of Defense for Policy, the Vice Chairman
of the Joint Chiefs of Staff, the Commander of U.S. Strategic Command,
and the Under Secretary for Nuclear Security of the Department of
Energy (dual-hatted as the Administrator of the National Nuclear
Security Administration). 10 U.S.C. § 179.
[14] Although the Phase 6.X process begins with activities under Phase
6.1, DOD officials told us that life extension programs formally begin
with a Phase 6.2 study authorization from the Nuclear Weapons Council,
after weapons needing a life extension have been identified in Phase
6.1.
[15] A "project officers group" is a group of DOD and DOE personnel
assigned to coordinate the development and compatibility assurance of
a designated nuclear weapon system and its associated interfaces.
[16] The B61-11 entered the stockpile in the 1990s and was not
included as part of the scope of the life extension program.
[17] According to the B61 Project Officers Group, the congressional
direction to initially limit the scope of the study extended the time
required to complete the study for a fullscope life extension program.
In August 2010, the project officers group informed the Standing and
Safety Committee that the study would be completed by September 2011.
[18] Although we recognize the distinctions among different life
extension approaches that would "refurbish," "reuse," or "replace"
nuclear weapons components, we use the expression "refurbished B61
bomb" throughout this report in a generalized way to distinguish the
resulting B61 weapon from the existing versions currently in the
stockpile, and the term "refurbishment" to refer to the B61 life
extension program itself.
[19] GAO, Designing Evaluations, [hyperlink,
http://www.gao.gov/products/GAO/PEMD-10.1.4] (Washington, D.C.: May
1991).
[20] The Supreme Headquarters, Allied Powers Europe, is the
Headquarters of Allied Command Operations, one of NATO's two military
commands, and is responsible for all alliance military operations.
[21] The currently deployed B61 bombs use a parachute to slow the bomb
in midair and allow time for delivery aircraft to exit the targeted
area before the bomb detonates.
[22] The guided tailkit section is a nonnuclear component that will
replace the existing parachute and is intended to allow for increased
aircraft survivability, safer delivery profiles, and more space for
additional components, such as safety and security enhancements.
[23] The F-35 is the U.S. Air Force's next-generation fighter
aircraft. The United States and other NATO allies are currently
planning to use the F-35 for nuclear operations when it becomes
available later this decade.
[24] Nuclear Weapons Council Standing and Safety Committee, Memorandum
for Director, Strategic Systems Program Office, Subject: W76/MK4 RBA
Phase 6.2/6.2A Life Extension Study, August 6, 1998.
[25] According to a Navy official, some improvements to the W76
warhead's safety and security features were also made during the
refurbishment.
[26] In the late 1990s, DOD and NNSA initiated a life extension
program for the W80-1 cruise missile, which is designed for employment
on air-launched cruise missiles. Although the W80 Project Officers
Group completed the Phase 6.2 study for the life extension, and NNSA
was preparing for production, the Nuclear Weapons Council canceled the
effort in May 2006 after DOD re-evaluated its cruise missile force
structure requirements.
[27] National Security Presidential Directive 28, issued in 2003,
called for upgrading, where appropriate, safety and use control
capabilities for all nuclear warheads during their refurbishment.
[28] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for
Developing and Managing Capital Program Costs, [hyperlink,
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2009).
[29] Pub. L. No. 111-85, 123 Stat. 2866 (2009).
[30] H.R. Rep. No. 111-203, at 129 (2009).
[31] Of this amount about, $39.6 million will support the B61 life
extension study, and about $14.1 million will be used to replenish the
stockpile systems account that was used to support the nonnuclear
portions of the study.
[32] Associate Air Force Chief of Staff for Strategic Deterrence and
Nuclear Integration, Memorandum for Chairman, Nuclear Weapons Council
Standing and Safety Committee, Subject: W78 Life Extension Program
Phase 6.1 Study, August 18, 2010.
[33] GAO, Homeland Defense: Greater Focus on Analysis of Alternatives
and Threats Needed to Improve DOD's Strategic Nuclear Weapons
Security, [hyperlink, http://www.gao.gov/products/GAO-09-828]
(Washington, D.C.: Sept. 18, 2009).
[34] In November 2010, as we were preparing to publish the classified
version of this report, NATO completed its review and published a new
Strategic Concept. Regarding NATO's nuclear posture, the revised
strategic concept states that deterrence, based on an appropriate mix
of nuclear and conventional capabilities, remains a core element of
NATO's overall strategy and that as long as nuclear weapons exist,
NATO will remain a nuclear alliance. See NATO, Active Engagement,
Modern Defense: Strategic Concept for the Defense and Security of the
Members of the North Atlantic Treaty Organization, Adopted by the
Heads of State and Government in Lisbon (Nov. 2010).
[35] NATO, The Alliance's Strategic Concept, Approved by the Heads of
State and Government participating in the meeting of the North
Atlantic Council in Washington, D.C. (Apr. 1999).
[36] Five Points on NATO Nuclear for the Secretary's Intervention at
Tallinn, Apr. 22, 2010, Tallinn, Estonia.
[37] NATO, NATO 2020: Assured Security; Dynamic Engagement, Analysis
and Recommendations of the Group of Experts on a New Strategic Concept
for NATO, May 17, 2010.
[38] In contrast, the strategic B61-7 version of the bomb faces end-of-
life issues later.
[39] NNSA, B61 Life Extension Project Risk Management Plan
(Albuquerque, New Mexico: Dec. 10, 2008).
[40] The five elements of a risk management approach are: setting
strategic goals, objectives, and determining constraints; assessing
risk; evaluating alternatives for addressing risks; selecting
alternatives; and implementation and monitoring. See [hyperlink,
http://www.gao.gov/products/GAO-09-828].
[41] [hyperlink, http://www.gao.gov/products/GAO-09-385].
[42] GAO, Nuclear Weapons: National Nuclear Security Administration
Needs to Better Manage Risks Associated with Modernization of Its
Kansas City Plant, [hyperlink, http://www.gao.gov/products/GAO-10-115]
(Washington, D.C.: Oct. 23, 2009).
[43] [hyperlink, http://www.gao.gov/products/GAO-09-828].
[44] Department of Defense, Defense Acquisition University, Risk
Management Guide for DOD Acquisition, Sixth Edition, Version 1.0 (Fort
Belvoir, Va.: Aug. 2006).
[45] The B61 Life Extension Group is a subgroup of the B61 Project
Officers Group, according to the Air Force lead project officer of the
B61 bomb.
[46] Department of Energy, National Nuclear Security Administration,
Fiscal Year 2011 Stockpile Stewardship and Management Plan Summary
(Washington, D.C.: May 2010).
[47] JASON is an independent group of accomplished scientists that
advises the U.S. government on matters of science and technology. The
name "JASON" is not an acronym. Its sponsors include DOD, DOE, and the
U.S. Intelligence Community.
[48] GAO, Designing Evaluations, [hyperlink,
http://www.gao.gov/products/GAO-PEMD-10.1.4 (Washington, D.C.: May
1991).
[End of section]
GAO's Mission:
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting
its constitutional responsibilities and to help improve the performance
and accountability of the federal government for the American people.
GAO examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding
decisions. GAO's commitment to good government is reflected in its core
values of accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony:
The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each
weekday, GAO posts newly released reports, testimony, and
correspondence on its Web site. To have GAO e-mail you a list of newly
posted products every afternoon, go to [hyperlink, http://www.gao.gov]
and select "E-mail Updates."
Order by Phone:
The price of each GAO publication reflects GAO‘s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO‘s Web site,
[hyperlink, http://www.gao.gov/ordering.htm].
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
To Report Fraud, Waste, and Abuse in Federal Programs:
Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]:
E-mail: fraudnet@gao.gov:
Automated answering system: (800) 424-5454 or (202) 512-7470:
Congressional Relations:
Ralph Dawn, Managing Director, dawnr@gao.gov:
(202) 512-4400:
U.S. Government Accountability Office:
441 G Street NW, Room 7125:
Washington, D.C. 20548:
Public Affairs:
Chuck Young, Managing Director, youngc1@gao.gov:
(202) 512-4800:
U.S. Government Accountability Office:
441 G Street NW, Room 7149:
Washington, D.C. 20548: